Guidance notes
Extended Dry Dockings
The potential for greater flexibility
Overview
Lloyd’s Register has been exploring the potential for greater flexibility which may be achieved by extending the
five-yearly docking survey cycle to 7.5 years.
For five years, we have been carrying out a pilot scheme for Extended Dry Dockings with a major containership operator.
Under the scheme, certain dry dockings are replaced by in-water surveys (IWS) carried out by approved diving companies.
The procedures agreed with the operator and with the Danish Maritime Authority, as well as other flags, have been
carefully thought through and are in no way a reduction of the controls provided by the special survey regime. The scheme
is predicated on a number of factors to secure class and flag state approval. Safety is always the paramount concern. To
date, the combination of our procedures, the involvement of a first-class operator and experienced flag states, is providing
appropriate oversight with respect to safety.
7.5 Year Extended Dry Docking
Year 0 Year 5 Year 10 Year 15 Year 20
CSH/SS CSH/SS CSH/SS CSH/SS CSH/SS
^ ^ ^ ^ ^ ^ ^
DS IWS IWS DS IWS IWS DS
Renewal
survey afloat
Renewal
survey afloat
Renewal
survey in
dock
Potential benefits
The benefits to operators are increased flexibility in choosing a dry docking window and, with proper maintenance
programmes in place, the potential for the hull to stay in water for up to 7.5 years increasing the availability of the vessel.
Some operators may be able to realise benefits and, potentially, cost savings but those considering the scheme need to
carefully consider the implications – on operating costs and maintenance planning – of pushing the docking cycle out to
7.5 years.
Extended Dry Dockings
© Lloyd's Register 2013
Eligibility
Extended docking survey cycles will not be appropriate or possible for all types of ship. The pilot scheme has been focused
on larger container ships, but smaller container ships, LNG carriers and general cargo ships may qualify. Bulk carriers and
tankers are excluded from consideration due to the Enhanced Survey requirements under which a docking survey is
required at each Special Survey.
The operators of ships involved must take a demonstrable and sophisticated approach to the maintenance and
management of ship operations. Requirements while in water include the arrangements for examination, testing and
maintenance that would normally be required during a dry docking. Coatings must be of a high quality suitable
for extended docking cycles and in line with the manufacturer's guidelines and an impressed current cathodic protection
system should be fitted Ships should ideally have been operated by the Company from new, and operated by a company
with a proven track record. They should also have a good record of flag and port state control inspection.
Requirements and technical considerations
The following are the requirements which must be met and the issues that must be considered before acceptance into the
pilot EDD scheme:
1. Ship type
In accordance with IMO resolution A744 (18), the scheme cannot be applied to Enhanced Survey Programme vessels –
most bulk carriers and tankers – and under the SOLAS Convention it cannot be applied to passenger vessels. Due to
trading patterns, current owner-planned maintenance and original design, it is currently only being considered
applicable to internationally trading container ships. However, other ship types (including short sea trade container
ships and LNG carriers) could possibly be considered.
2. Flag administration acceptance
As the method of the inspection of the outside of the ship’s bottom is a statutory requirement, the flag administration
will need to agree to the inclusion of a specified vessel and owner on the scheme. The UK, Danish, Cyprus, Liberia,
Hong Kong, Marshall Islands, Panama and Singapore flags have already agreed to consider the scheme for individual
vessels. It is understood that the German and Antigua & Bermuda flag administrations have agreed schemes and USCG,
USA Authorities are considering the scheme.
3. Age of ship
The ideal age for commencement of EDD is for ships between 0-5 years of age. However, older vessels may be considered
dependent upon both Flag and Classification Group evaluation/acceptance on case by case basis.
4. Notations and historical classification
Vessels must have been classed from construction with an IACS society and have been assigned the class notation
IWS* and the descriptive note ShipRight SCM, or meet the rule/regulation requirements for the notations.
MPMS (Machinery Planned Maintenance Scheme), CSM (Continuous Survey Machinery) and CSH (Continuous Survey
Hull) are not considered by Lloyd’s Register to be mandatory requirements for EDD.
Extended Dry Dockings
© Lloyd's Register 2013
5. External coatings
The documented service experience of the hull high-quality paint system is to be submitted for review.
The paint manufacturer will need to provide the specific criteria against which the coating will be valid for a 7.5 year
period. Paint Manufacturer recommendation for the vessel utilisation, average speed and idle time etc. are to be
complied with.
One coating manufacturer has already advised that the coating is only valid for 7.5 years if the vessel utilisation is 70%,
at an average speed of 22 knots and an idle time of a maximum of 14 days. Note: this implies that a vessel will not be
eligible for the scheme after lengthy lay-up.
Ships should, as far as is practicable, avoid operation in ice. Where this is unavoidable, hull and paint coatings shall be
inspected and restored soon afterwards. Records of such paint or other damage shall be maintained.
6. Other corrosion protection
All bolted sacrificial anodes to the hull are to be capable for renewal in water.
Monitoring of the impressed current corrosion protection system for effectiveness is to be a part of the company’s
managed maintenance programme. Records must be available for review by Lloyd’s Register annually.
The ballast tank coatings are to be maintained in good condition
7. Access arrangements
The sea valves are to be fully accessible when afloat (for examination by using external blanking pieces, for example).
Access to take rudder and pintle clearances while afloat should be verified as per IWS* Notation.
8. Special Survey
Special Surveys are to be carried out in full and therefore chain cables will need to be ranged after 10 years, and
thereafter every five years. This should be taken into consideration for older vessels or vessels on the scheme for the
long term.
9. Planning and IWS
A survey planning document will need to be submitted well in advance of each IWS survey. A copy of the plan will also
need to be submitted to the flag administration for review and agreement at each IWS survey for EDD.
A pre-survey meeting is to be held at the survey location with all involved parties: the EDD planning questionnaire,
details of hull markings and appropriate drawings are to be made available for guidance.
The diving company and location of in-water surveys are to be specially considered by class and flag administration at
each survey.
The scope of IWS surveys is to be as specified in Lloyd’s Register’s regulations, with a Lloyd’s Register surveyor in
attendance.
In cases where an in-water survey is unsatisfactory, the owner is to book a dry dock within one month of the IWS.
A comprehensive written report of each in-water survey and any work undertaken is to be submitted to Lloyd’s
Register and the flag administration, including good quality CCTV images.
Extended Dry Dockings
© Lloyd's Register 2013
10. Memo
If a Lloyd’s Register classed vessel is agreed for EDD, a memo will be assigned to it. This is to enable the EDD scheme to
continue and to be reviewed during change of owners and change of Flag.
11. Descriptive Note - EDD
The vessel will be eligible for the Owners/ Operators to apply to the Flag Administration for the vessel to be placed on a
pilot Extended Dry-Docking regime. The relevant Flag Administration may elect to impose requirements additional to
those defined as this descriptive note.
Summary
EDD may be appropriate for prudent owners, offering them a greater degree of flexibility for their Dry Docking Schedules
and allowing them to carry out continuous surveys and use in-water surveys to monitor underwater areas.
The future use of EDD looks promising on the evidence of performance to date. It requires a pro-active approach by
shipmanagers to move beyond the current mainstream prescriptive requirements. It is in an operator's best interests to
avoid the risk of unscheduled, and costly, dockings by prioritising well documented maintenance and inspections in support
of safety.
Members of the Lloyd’s Register Group will work closely with owners who qualify for, and wish to apply, the scheme.
Operators should fully investigate the requirements and the realities of extended docking cycles. The potential of this
scheme is in complementing a sophisticated approach to operational maintenance.
Lloyd’s Register Client Facing Office dealing with vessels on EDD Scheme should nominate a technical person in
consultation with relevant Classification Ship Type Section to co-ordinate and manage the scheme.
For further information, contact: dcg-class@lr.org
Extended Dry Dockings
© Lloyd's Register 2013

More Related Content

What's hot

PP_CERTIFICATES& DOCS List_Ver.056
PP_CERTIFICATES& DOCS List_Ver.056PP_CERTIFICATES& DOCS List_Ver.056
PP_CERTIFICATES& DOCS List_Ver.056
Stavrianidis Stavros
 
Maintenance guide checklist_(rev1)
Maintenance guide checklist_(rev1)Maintenance guide checklist_(rev1)
Maintenance guide checklist_(rev1)
diegocely700615
 
Guidelines for periodic servicing and maintenance of lifeboats
Guidelines for periodic servicing and maintenance of lifeboatsGuidelines for periodic servicing and maintenance of lifeboats
Guidelines for periodic servicing and maintenance of lifeboats
Ana Vicente
 
Psc pocket checklist
Psc pocket checklistPsc pocket checklist
Psc pocket checklist
Tevay Sayha
 
Panaich Oilfield - Company & Trg Profile
Panaich Oilfield - Company & Trg ProfilePanaich Oilfield - Company & Trg Profile
Panaich Oilfield - Company & Trg Profile
pots canada
 

What's hot (20)

2 gap-analysis-in-detail
2 gap-analysis-in-detail2 gap-analysis-in-detail
2 gap-analysis-in-detail
 
PD189 Management Of Charterparty For Oil Tankers
PD189 Management Of Charterparty For Oil TankersPD189 Management Of Charterparty For Oil Tankers
PD189 Management Of Charterparty For Oil Tankers
 
Class notation
Class notationClass notation
Class notation
 
2010 4.1
2010 4.12010 4.1
2010 4.1
 
Imcam149 -issue_8
Imcam149  -issue_8Imcam149  -issue_8
Imcam149 -issue_8
 
Psc
PscPsc
Psc
 
Erb navadmin update fa qs (8 jun)
Erb navadmin update fa qs (8 jun)Erb navadmin update fa qs (8 jun)
Erb navadmin update fa qs (8 jun)
 
PP_CERTIFICATES& DOCS List_Ver.056
PP_CERTIFICATES& DOCS List_Ver.056PP_CERTIFICATES& DOCS List_Ver.056
PP_CERTIFICATES& DOCS List_Ver.056
 
Maintenance guide checklist_(rev1)
Maintenance guide checklist_(rev1)Maintenance guide checklist_(rev1)
Maintenance guide checklist_(rev1)
 
Rk singh
Rk singhRk singh
Rk singh
 
Guidelines for periodic servicing and maintenance of lifeboats
Guidelines for periodic servicing and maintenance of lifeboatsGuidelines for periodic servicing and maintenance of lifeboats
Guidelines for periodic servicing and maintenance of lifeboats
 
Psc pocket checklist
Psc pocket checklistPsc pocket checklist
Psc pocket checklist
 
Panaich Oilfield - Company & Trg Profile
Panaich Oilfield - Company & Trg ProfilePanaich Oilfield - Company & Trg Profile
Panaich Oilfield - Company & Trg Profile
 
Teekay Offshore Second Quarter 2014 Earnings Presentation
Teekay Offshore Second Quarter 2014 Earnings PresentationTeekay Offshore Second Quarter 2014 Earnings Presentation
Teekay Offshore Second Quarter 2014 Earnings Presentation
 
Imsbc code pocket guide
Imsbc code pocket guideImsbc code pocket guide
Imsbc code pocket guide
 
Vessel General Permit
Vessel General PermitVessel General Permit
Vessel General Permit
 
PD221 Charterparty Management For Liquefied Petroleum Gas (LPG) Tankers
PD221 Charterparty Management For Liquefied Petroleum Gas (LPG) Tankers PD221 Charterparty Management For Liquefied Petroleum Gas (LPG) Tankers
PD221 Charterparty Management For Liquefied Petroleum Gas (LPG) Tankers
 
Imsbc
ImsbcImsbc
Imsbc
 
Management of Charterparty for Oil Tankers
Management of Charterparty for Oil TankersManagement of Charterparty for Oil Tankers
Management of Charterparty for Oil Tankers
 
Towingrecomends
TowingrecomendsTowingrecomends
Towingrecomends
 

Similar to Edd guidance 13 tcm155-198278

SAI Lay Up Service
SAI Lay Up ServiceSAI Lay Up Service
SAI Lay Up Service
Ayu Anira
 
Classification societes. presentation
Classification societes. presentationClassification societes. presentation
Classification societes. presentation
jabbar2002pk200
 
PRM37_16-18_Cover story
PRM37_16-18_Cover storyPRM37_16-18_Cover story
PRM37_16-18_Cover story
Aftab Hasan
 
Classification societes. presentation mariner
Classification societes. presentation marinerClassification societes. presentation mariner
Classification societes. presentation mariner
jabbar2002pk200
 
D1 mc s & m topic 3 loadline
D1 mc s & m topic 3 loadlineD1 mc s & m topic 3 loadline
D1 mc s & m topic 3 loadline
jabbar2002pk200
 
Rayomand Munchershaw Mistry_original12
Rayomand Munchershaw Mistry_original12Rayomand Munchershaw Mistry_original12
Rayomand Munchershaw Mistry_original12
raymond mistry
 

Similar to Edd guidance 13 tcm155-198278 (20)

Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361
 
Laid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of EnglandLaid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of England
 
SAI Lay Up Service
SAI Lay Up ServiceSAI Lay Up Service
SAI Lay Up Service
 
Ship conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptxShip conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptx
 
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
 
BWC-White-Paper-Rev-01
BWC-White-Paper-Rev-01BWC-White-Paper-Rev-01
BWC-White-Paper-Rev-01
 
CESA project on servicing ships for offshore wind farms - Challenges with pur...
CESA project on servicing ships for offshore wind farms - Challenges with pur...CESA project on servicing ships for offshore wind farms - Challenges with pur...
CESA project on servicing ships for offshore wind farms - Challenges with pur...
 
Towingrecomends.pdf
Towingrecomends.pdfTowingrecomends.pdf
Towingrecomends.pdf
 
Classification societes. presentation
Classification societes. presentationClassification societes. presentation
Classification societes. presentation
 
PRM37_16-18_Cover story
PRM37_16-18_Cover storyPRM37_16-18_Cover story
PRM37_16-18_Cover story
 
Classification societes. presentation mariner
Classification societes. presentation marinerClassification societes. presentation mariner
Classification societes. presentation mariner
 
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
 
Decommissioning of Offshore Installations
Decommissioning of Offshore InstallationsDecommissioning of Offshore Installations
Decommissioning of Offshore Installations
 
DNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseDNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects Showcase
 
Ship design rules han
Ship design rules hanShip design rules han
Ship design rules han
 
FSRU procurement for Oil and Gas Upstream Business (clauses and legal concern...
FSRU procurement for Oil and Gas Upstream Business (clauses and legal concern...FSRU procurement for Oil and Gas Upstream Business (clauses and legal concern...
FSRU procurement for Oil and Gas Upstream Business (clauses and legal concern...
 
Work n rest hours & olb
Work n rest hours  & olbWork n rest hours  & olb
Work n rest hours & olb
 
D1 mc s & m topic 3 loadline
D1 mc s & m topic 3 loadlineD1 mc s & m topic 3 loadline
D1 mc s & m topic 3 loadline
 
Rayomand Munchershaw Mistry_original12
Rayomand Munchershaw Mistry_original12Rayomand Munchershaw Mistry_original12
Rayomand Munchershaw Mistry_original12
 
MEC401 Directed Studies In Mechanical Engineering.docx
MEC401 Directed Studies In Mechanical Engineering.docxMEC401 Directed Studies In Mechanical Engineering.docx
MEC401 Directed Studies In Mechanical Engineering.docx
 

Recently uploaded

Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Recently uploaded (20)

Solan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Solan Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableSolan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Solan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
ALWAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
ALWAR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowALWAR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
ALWAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTSJHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
KOLKATA 💋 Call Girl 9827461493 Call Girls in Escort service book now
KOLKATA 💋 Call Girl 9827461493 Call Girls in  Escort service book nowKOLKATA 💋 Call Girl 9827461493 Call Girls in  Escort service book now
KOLKATA 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableNanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowSRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 

Edd guidance 13 tcm155-198278

  • 1. Guidance notes Extended Dry Dockings The potential for greater flexibility Overview Lloyd’s Register has been exploring the potential for greater flexibility which may be achieved by extending the five-yearly docking survey cycle to 7.5 years. For five years, we have been carrying out a pilot scheme for Extended Dry Dockings with a major containership operator. Under the scheme, certain dry dockings are replaced by in-water surveys (IWS) carried out by approved diving companies. The procedures agreed with the operator and with the Danish Maritime Authority, as well as other flags, have been carefully thought through and are in no way a reduction of the controls provided by the special survey regime. The scheme is predicated on a number of factors to secure class and flag state approval. Safety is always the paramount concern. To date, the combination of our procedures, the involvement of a first-class operator and experienced flag states, is providing appropriate oversight with respect to safety. 7.5 Year Extended Dry Docking Year 0 Year 5 Year 10 Year 15 Year 20 CSH/SS CSH/SS CSH/SS CSH/SS CSH/SS ^ ^ ^ ^ ^ ^ ^ DS IWS IWS DS IWS IWS DS Renewal survey afloat Renewal survey afloat Renewal survey in dock Potential benefits The benefits to operators are increased flexibility in choosing a dry docking window and, with proper maintenance programmes in place, the potential for the hull to stay in water for up to 7.5 years increasing the availability of the vessel. Some operators may be able to realise benefits and, potentially, cost savings but those considering the scheme need to carefully consider the implications – on operating costs and maintenance planning – of pushing the docking cycle out to 7.5 years. Extended Dry Dockings © Lloyd's Register 2013
  • 2. Eligibility Extended docking survey cycles will not be appropriate or possible for all types of ship. The pilot scheme has been focused on larger container ships, but smaller container ships, LNG carriers and general cargo ships may qualify. Bulk carriers and tankers are excluded from consideration due to the Enhanced Survey requirements under which a docking survey is required at each Special Survey. The operators of ships involved must take a demonstrable and sophisticated approach to the maintenance and management of ship operations. Requirements while in water include the arrangements for examination, testing and maintenance that would normally be required during a dry docking. Coatings must be of a high quality suitable for extended docking cycles and in line with the manufacturer's guidelines and an impressed current cathodic protection system should be fitted Ships should ideally have been operated by the Company from new, and operated by a company with a proven track record. They should also have a good record of flag and port state control inspection. Requirements and technical considerations The following are the requirements which must be met and the issues that must be considered before acceptance into the pilot EDD scheme: 1. Ship type In accordance with IMO resolution A744 (18), the scheme cannot be applied to Enhanced Survey Programme vessels – most bulk carriers and tankers – and under the SOLAS Convention it cannot be applied to passenger vessels. Due to trading patterns, current owner-planned maintenance and original design, it is currently only being considered applicable to internationally trading container ships. However, other ship types (including short sea trade container ships and LNG carriers) could possibly be considered. 2. Flag administration acceptance As the method of the inspection of the outside of the ship’s bottom is a statutory requirement, the flag administration will need to agree to the inclusion of a specified vessel and owner on the scheme. The UK, Danish, Cyprus, Liberia, Hong Kong, Marshall Islands, Panama and Singapore flags have already agreed to consider the scheme for individual vessels. It is understood that the German and Antigua & Bermuda flag administrations have agreed schemes and USCG, USA Authorities are considering the scheme. 3. Age of ship The ideal age for commencement of EDD is for ships between 0-5 years of age. However, older vessels may be considered dependent upon both Flag and Classification Group evaluation/acceptance on case by case basis. 4. Notations and historical classification Vessels must have been classed from construction with an IACS society and have been assigned the class notation IWS* and the descriptive note ShipRight SCM, or meet the rule/regulation requirements for the notations. MPMS (Machinery Planned Maintenance Scheme), CSM (Continuous Survey Machinery) and CSH (Continuous Survey Hull) are not considered by Lloyd’s Register to be mandatory requirements for EDD. Extended Dry Dockings © Lloyd's Register 2013
  • 3. 5. External coatings The documented service experience of the hull high-quality paint system is to be submitted for review. The paint manufacturer will need to provide the specific criteria against which the coating will be valid for a 7.5 year period. Paint Manufacturer recommendation for the vessel utilisation, average speed and idle time etc. are to be complied with. One coating manufacturer has already advised that the coating is only valid for 7.5 years if the vessel utilisation is 70%, at an average speed of 22 knots and an idle time of a maximum of 14 days. Note: this implies that a vessel will not be eligible for the scheme after lengthy lay-up. Ships should, as far as is practicable, avoid operation in ice. Where this is unavoidable, hull and paint coatings shall be inspected and restored soon afterwards. Records of such paint or other damage shall be maintained. 6. Other corrosion protection All bolted sacrificial anodes to the hull are to be capable for renewal in water. Monitoring of the impressed current corrosion protection system for effectiveness is to be a part of the company’s managed maintenance programme. Records must be available for review by Lloyd’s Register annually. The ballast tank coatings are to be maintained in good condition 7. Access arrangements The sea valves are to be fully accessible when afloat (for examination by using external blanking pieces, for example). Access to take rudder and pintle clearances while afloat should be verified as per IWS* Notation. 8. Special Survey Special Surveys are to be carried out in full and therefore chain cables will need to be ranged after 10 years, and thereafter every five years. This should be taken into consideration for older vessels or vessels on the scheme for the long term. 9. Planning and IWS A survey planning document will need to be submitted well in advance of each IWS survey. A copy of the plan will also need to be submitted to the flag administration for review and agreement at each IWS survey for EDD. A pre-survey meeting is to be held at the survey location with all involved parties: the EDD planning questionnaire, details of hull markings and appropriate drawings are to be made available for guidance. The diving company and location of in-water surveys are to be specially considered by class and flag administration at each survey. The scope of IWS surveys is to be as specified in Lloyd’s Register’s regulations, with a Lloyd’s Register surveyor in attendance. In cases where an in-water survey is unsatisfactory, the owner is to book a dry dock within one month of the IWS. A comprehensive written report of each in-water survey and any work undertaken is to be submitted to Lloyd’s Register and the flag administration, including good quality CCTV images. Extended Dry Dockings © Lloyd's Register 2013
  • 4. 10. Memo If a Lloyd’s Register classed vessel is agreed for EDD, a memo will be assigned to it. This is to enable the EDD scheme to continue and to be reviewed during change of owners and change of Flag. 11. Descriptive Note - EDD The vessel will be eligible for the Owners/ Operators to apply to the Flag Administration for the vessel to be placed on a pilot Extended Dry-Docking regime. The relevant Flag Administration may elect to impose requirements additional to those defined as this descriptive note. Summary EDD may be appropriate for prudent owners, offering them a greater degree of flexibility for their Dry Docking Schedules and allowing them to carry out continuous surveys and use in-water surveys to monitor underwater areas. The future use of EDD looks promising on the evidence of performance to date. It requires a pro-active approach by shipmanagers to move beyond the current mainstream prescriptive requirements. It is in an operator's best interests to avoid the risk of unscheduled, and costly, dockings by prioritising well documented maintenance and inspections in support of safety. Members of the Lloyd’s Register Group will work closely with owners who qualify for, and wish to apply, the scheme. Operators should fully investigate the requirements and the realities of extended docking cycles. The potential of this scheme is in complementing a sophisticated approach to operational maintenance. Lloyd’s Register Client Facing Office dealing with vessels on EDD Scheme should nominate a technical person in consultation with relevant Classification Ship Type Section to co-ordinate and manage the scheme. For further information, contact: dcg-class@lr.org Extended Dry Dockings © Lloyd's Register 2013