SlideShare a Scribd company logo
Available % Target
3 1.69% 2.00% SS 19 8.88% 8.00%
3 1.69% 2.00% FS 186 86.92% 90.00% 1
0 0.00% 0.00% SF 0 0.00% 1.00%
4 2.26% 5.00% FF 9 4.21% 1.00%
167 94.35% 90.00% 1 0.56% 2.50% 1
0 0.00% 1.00% 4 2.26% 2.50%
0 0.00% 0.00% 1
Available % Target 17 9.60% 5.00% 0
30 16.95% -
29 16.38% - Long Lag > 44 Days 0 0.00% 2.50%
118 66.67% - High Duration > 44 Days 18 10.17% 5.00% 0
0 0.00% 2.00% Days 572 12.23% 7.00%
Large Free Float > 45 Days 6 3.39% 4.00% 1
0 0.00% 0.05% Days 3161 67.56% 10~12%
Large Total Float > 45 Days 33 18.64% 5.00%
1 0.56% 0.00% Negative Float 0 Days 0 0.0% 0.00% 1
0 0.00% 2.50% 1
3 1.69% 1.00% 0 0.00% 2.50%
0 0.00% 0.50%
1 0.56% 1.00% 0 0.00% 0.50%
1 0.56% 0.50%
0 0.00% 0.50% 0 0.00% 0.50%
0 0.00% 0.50%
1 0.56% 0.00% 0 0 0.00% 0.50%
0 0.00% 5.00% 1 0 0.00% 0.50%
QTY % Target Index Status Status
4 2.26% 1.00% 0 1. Logic Pass Fail
2. Lead Pass Fail
41,352 22.92% - 3. Lag Fail Fail
4,248 34.54% - 4. FS Relationship Pass Pass
1,744 42.54% - 5. Hard Constraint Pass Fail
6. High Float Pass Pass
7. Negative Float Pass Fail
Available % Target
5 2.82% 3~5% Critical Path Length 570
SS 0 0.00% 16.00% CP Total Float 0
FS 4 80.00% 80.00%
SF 0 0.00% 1.00% Tasks Complete: 118
FF 1 20.00% 3.00% Should be Complete: 177
Days 0 0.00% -
Large Free Float > 5 Days 0 0.00% 0.05% Narrative Report:
Days 0 0.00% 1.00%
Large Lead > -25 Days 0 0.00% 0.00%
Days 0 0.00% 2.50%
Large Lag > 9 Days 0 0.00% 1.00%
13. CPLI
14. BEI
Critical Path Length + Total Float
Critical Path Length
CPLI Calculator:
Please Insert the result Manually
9. Invalid Date
8. High Duration
10. Invalid Resources
11. Missed Activities
12. Critical Path Test
DCMA-14 Short Result
Remarks Index Remarks
Relasionship
Description
Description
Lead
Task Dependent Predessessor Free
Successor Free
Dangle Activities
Activity Status: Not Started
Activity Status: In Progress
Activity Status: Completed
Activity does not Available in BSL
Mandatory Start
Mandatory Finish
Finish On or After
Description
In progress Activity with 0% progress
In Progress Error - ACT > DD
Start Milestone
Finish Milestone
Resource Dependent
Activity Without Resource
Completed Activity without Finish Date
Description
Free Float
Resource Index
Labor
Nonlabor
Material
Critical Activities
Critical Path
Finish to Start (FS)
Start to Finish (SF)
Finish to Finish (FF)
In Progress Error - ACT = 00.0%
Missed Task
Completed Error - ACT > 00.0%
Start to Start
Invalid Date
= Fail
Start to Finish
Finish to Finish
Resource does not assigned to the activities
Not Started Error - Start > 0
Activity not started but the start included the date
Description
Update Index
Completed Error - ACT < 100%
Lag
Completed activity with less than 100% Progress
Actual Date is greater than Data Date
Start On
Finish On
Start On or After
Start On or Before
WBS Summary
Level Of Effort
Hard Constraint
As Late As Possible
Finish On or Before
Total Float
Free Float
Soft Constraint
Check the schedule quality based on DCMA-14
Relationships Lead
Relationships Lag
Prepared By: A.setayandeh
31-May-22
Data Date
Schedule Health Check Dashboard
Count if activitiess need to define in baseline
Activity Type
Available Available % Target
Lead is Negative Lag between relationships
Lag: delay between two activity relationships
Start to Start
Finish to Start
CPLI = Pass
BEI Calculator:
(Baseline Execution Index)
Total No of Tasks Complete
No of Tasks that should be Complete
BEI
0.00%
0.00%
0.00%
0.05%
0.00%
1.00%
0.00% 0.20% 0.40% 0.60% 0.80% 1.00% 1.20%
Large Free Float >
Large Lead >
Large Lag >
Critical Path Index Chart
Target Available %

More Related Content

Similar to Dashboard Schedule Healt

Factory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .pptFactory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .ppt
Nittamallik216
 
Factory Monthly Babylon.ppt
Factory Monthly Babylon.pptFactory Monthly Babylon.ppt
Factory Monthly Babylon.ppt
Nittamallik216
 
Webb Control Tollgate 15 DEC 14 Final Version
Webb Control Tollgate  15 DEC 14 Final VersionWebb Control Tollgate  15 DEC 14 Final Version
Webb Control Tollgate 15 DEC 14 Final Version
Justin Webb, MBA, PMP, LSSGB
 
Factory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.pptFactory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.ppt
Nittamallik216
 
Factory Monthly Marina.ppt
Factory Monthly Marina.pptFactory Monthly Marina.ppt
Factory Monthly Marina.ppt
Nittamallik216
 
Inventory stock reduction ultimatum
Inventory stock reduction ultimatumInventory stock reduction ultimatum
Inventory stock reduction ultimatum
Ghassan Kabbara
 
agilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptxagilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptx
ssuser1ecf25
 
Factory Monthly KSM- New.ppt
Factory Monthly KSM- New.pptFactory Monthly KSM- New.ppt
Factory Monthly KSM- New.ppt
Nittamallik216
 
Factory Monthly ALP.ppt
Factory Monthly ALP.pptFactory Monthly ALP.ppt
Factory Monthly ALP.ppt
Nittamallik216
 
Report May 16-Job Listing
Report May 16-Job ListingReport May 16-Job Listing
Report May 16-Job Listing
Angga .
 
Factory Monthly HAMZA.ppt
Factory Monthly HAMZA.pptFactory Monthly HAMZA.ppt
Factory Monthly HAMZA.ppt
Nittamallik216
 
Factory Monthly KSM- AZMERI.ppt
Factory Monthly KSM- AZMERI.pptFactory Monthly KSM- AZMERI.ppt
Factory Monthly KSM- AZMERI.ppt
Nittamallik216
 
Factory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.pptFactory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.ppt
Nittamallik216
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).ppt
Nittamallik216
 
Factory Monthly KRC (U-3&4).ppt
Factory Monthly KRC (U-3&4).pptFactory Monthly KRC (U-3&4).ppt
Factory Monthly KRC (U-3&4).ppt
Nittamallik216
 
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
CFG
 
Production Schedule Report 2016-rv
Production Schedule Report 2016-rvProduction Schedule Report 2016-rv
Production Schedule Report 2016-rv
James Thomas
 
RR - Technicals 1.pdf
RR - Technicals 1.pdfRR - Technicals 1.pdf
RR - Technicals 1.pdf
merag76668
 
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
John Barney
 
Estácio: 2Q13 Conference Call Presentation
Estácio: 2Q13 Conference Call PresentationEstácio: 2Q13 Conference Call Presentation
Estácio: 2Q13 Conference Call Presentation
Estácio Participações
 

Similar to Dashboard Schedule Healt (20)

Factory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .pptFactory Monthly KPI of DLPL .ppt
Factory Monthly KPI of DLPL .ppt
 
Factory Monthly Babylon.ppt
Factory Monthly Babylon.pptFactory Monthly Babylon.ppt
Factory Monthly Babylon.ppt
 
Webb Control Tollgate 15 DEC 14 Final Version
Webb Control Tollgate  15 DEC 14 Final VersionWebb Control Tollgate  15 DEC 14 Final Version
Webb Control Tollgate 15 DEC 14 Final Version
 
Factory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.pptFactory Monthly ACCL-1.ppt
Factory Monthly ACCL-1.ppt
 
Factory Monthly Marina.ppt
Factory Monthly Marina.pptFactory Monthly Marina.ppt
Factory Monthly Marina.ppt
 
Inventory stock reduction ultimatum
Inventory stock reduction ultimatumInventory stock reduction ultimatum
Inventory stock reduction ultimatum
 
agilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptxagilefinancenarrated-190414134302.pptx
agilefinancenarrated-190414134302.pptx
 
Factory Monthly KSM- New.ppt
Factory Monthly KSM- New.pptFactory Monthly KSM- New.ppt
Factory Monthly KSM- New.ppt
 
Factory Monthly ALP.ppt
Factory Monthly ALP.pptFactory Monthly ALP.ppt
Factory Monthly ALP.ppt
 
Report May 16-Job Listing
Report May 16-Job ListingReport May 16-Job Listing
Report May 16-Job Listing
 
Factory Monthly HAMZA.ppt
Factory Monthly HAMZA.pptFactory Monthly HAMZA.ppt
Factory Monthly HAMZA.ppt
 
Factory Monthly KSM- AZMERI.ppt
Factory Monthly KSM- AZMERI.pptFactory Monthly KSM- AZMERI.ppt
Factory Monthly KSM- AZMERI.ppt
 
Factory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.pptFactory Monthly SAFA-1.ppt
Factory Monthly SAFA-1.ppt
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).ppt
 
Factory Monthly KRC (U-3&4).ppt
Factory Monthly KRC (U-3&4).pptFactory Monthly KRC (U-3&4).ppt
Factory Monthly KRC (U-3&4).ppt
 
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
2D – BUILDING STRONGER CHARITIES THROUGH IMPROVED FINANCIAL MANAGEMENT
 
Production Schedule Report 2016-rv
Production Schedule Report 2016-rvProduction Schedule Report 2016-rv
Production Schedule Report 2016-rv
 
RR - Technicals 1.pdf
RR - Technicals 1.pdfRR - Technicals 1.pdf
RR - Technicals 1.pdf
 
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
STRATEGICALLY CHANGING TO SUPPORT-Team Version 11-2013
 
Estácio: 2Q13 Conference Call Presentation
Estácio: 2Q13 Conference Call PresentationEstácio: 2Q13 Conference Call Presentation
Estácio: 2Q13 Conference Call Presentation
 

Recently uploaded

Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
wafawafa52
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
Presentation on Food Delivery Systems
Presentation on Food Delivery SystemsPresentation on Food Delivery Systems
Presentation on Food Delivery Systems
Abdullah Al Noman
 
Digital Image Processing Unit -2 Notes complete
Digital Image Processing Unit -2 Notes completeDigital Image Processing Unit -2 Notes complete
Digital Image Processing Unit -2 Notes complete
shubhamsaraswat8740
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
drshikhapandey2022
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Balvir Singh
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptxEV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
nikshimanasa
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...
pvpriya2
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
Kamal Acharya
 

Recently uploaded (20)

Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
Presentation on Food Delivery Systems
Presentation on Food Delivery SystemsPresentation on Food Delivery Systems
Presentation on Food Delivery Systems
 
Digital Image Processing Unit -2 Notes complete
Digital Image Processing Unit -2 Notes completeDigital Image Processing Unit -2 Notes complete
Digital Image Processing Unit -2 Notes complete
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptxEV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
EV BMS WITH CHARGE MONITOR AND FIRE DETECTION.pptx
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
 

Dashboard Schedule Healt

  • 1. Available % Target 3 1.69% 2.00% SS 19 8.88% 8.00% 3 1.69% 2.00% FS 186 86.92% 90.00% 1 0 0.00% 0.00% SF 0 0.00% 1.00% 4 2.26% 5.00% FF 9 4.21% 1.00% 167 94.35% 90.00% 1 0.56% 2.50% 1 0 0.00% 1.00% 4 2.26% 2.50% 0 0.00% 0.00% 1 Available % Target 17 9.60% 5.00% 0 30 16.95% - 29 16.38% - Long Lag > 44 Days 0 0.00% 2.50% 118 66.67% - High Duration > 44 Days 18 10.17% 5.00% 0 0 0.00% 2.00% Days 572 12.23% 7.00% Large Free Float > 45 Days 6 3.39% 4.00% 1 0 0.00% 0.05% Days 3161 67.56% 10~12% Large Total Float > 45 Days 33 18.64% 5.00% 1 0.56% 0.00% Negative Float 0 Days 0 0.0% 0.00% 1 0 0.00% 2.50% 1 3 1.69% 1.00% 0 0.00% 2.50% 0 0.00% 0.50% 1 0.56% 1.00% 0 0.00% 0.50% 1 0.56% 0.50% 0 0.00% 0.50% 0 0.00% 0.50% 0 0.00% 0.50% 1 0.56% 0.00% 0 0 0.00% 0.50% 0 0.00% 5.00% 1 0 0.00% 0.50% QTY % Target Index Status Status 4 2.26% 1.00% 0 1. Logic Pass Fail 2. Lead Pass Fail 41,352 22.92% - 3. Lag Fail Fail 4,248 34.54% - 4. FS Relationship Pass Pass 1,744 42.54% - 5. Hard Constraint Pass Fail 6. High Float Pass Pass 7. Negative Float Pass Fail Available % Target 5 2.82% 3~5% Critical Path Length 570 SS 0 0.00% 16.00% CP Total Float 0 FS 4 80.00% 80.00% SF 0 0.00% 1.00% Tasks Complete: 118 FF 1 20.00% 3.00% Should be Complete: 177 Days 0 0.00% - Large Free Float > 5 Days 0 0.00% 0.05% Narrative Report: Days 0 0.00% 1.00% Large Lead > -25 Days 0 0.00% 0.00% Days 0 0.00% 2.50% Large Lag > 9 Days 0 0.00% 1.00% 13. CPLI 14. BEI Critical Path Length + Total Float Critical Path Length CPLI Calculator: Please Insert the result Manually 9. Invalid Date 8. High Duration 10. Invalid Resources 11. Missed Activities 12. Critical Path Test DCMA-14 Short Result Remarks Index Remarks Relasionship Description Description Lead Task Dependent Predessessor Free Successor Free Dangle Activities Activity Status: Not Started Activity Status: In Progress Activity Status: Completed Activity does not Available in BSL Mandatory Start Mandatory Finish Finish On or After Description In progress Activity with 0% progress In Progress Error - ACT > DD Start Milestone Finish Milestone Resource Dependent Activity Without Resource Completed Activity without Finish Date Description Free Float Resource Index Labor Nonlabor Material Critical Activities Critical Path Finish to Start (FS) Start to Finish (SF) Finish to Finish (FF) In Progress Error - ACT = 00.0% Missed Task Completed Error - ACT > 00.0% Start to Start Invalid Date = Fail Start to Finish Finish to Finish Resource does not assigned to the activities Not Started Error - Start > 0 Activity not started but the start included the date Description Update Index Completed Error - ACT < 100% Lag Completed activity with less than 100% Progress Actual Date is greater than Data Date Start On Finish On Start On or After Start On or Before WBS Summary Level Of Effort Hard Constraint As Late As Possible Finish On or Before Total Float Free Float Soft Constraint Check the schedule quality based on DCMA-14 Relationships Lead Relationships Lag Prepared By: A.setayandeh 31-May-22 Data Date Schedule Health Check Dashboard Count if activitiess need to define in baseline Activity Type Available Available % Target Lead is Negative Lag between relationships Lag: delay between two activity relationships Start to Start Finish to Start CPLI = Pass BEI Calculator: (Baseline Execution Index) Total No of Tasks Complete No of Tasks that should be Complete BEI 0.00% 0.00% 0.00% 0.05% 0.00% 1.00% 0.00% 0.20% 0.40% 0.60% 0.80% 1.00% 1.20% Large Free Float > Large Lead > Large Lag > Critical Path Index Chart Target Available %