SlideShare a Scribd company logo
1 of 3
Download to read offline
The Beetham landmark is the tallest
concrete frame ever constructed in the
UK. The project is a mixed-use
development consisting of a 279-bed
Hilton hotel, public bar and 219
apartments, all housed within its 47
storeys. The building itself is over 170m
in height above ground level.
The lower levels of the Beetham Hilton Tower are made
up of a two-storey basement car park, the ground floor
reception area and hotel restaurant, the Level 1 ballroom
and bar. At Level 2 there is a health spa with swimming
pool.The hotel rooms are situated over Levels 4 to 22 inclu-
sive. The public bar is situated at Level 23, with the apart-
ments above on Levels 25 to 47 inclusive.
The structure of the building is made up of two vertical
cores, with post-tensioned slabs being used to maintain
minimal slab depths and give greater spans between
columns. Concrete was used to construct the frame due to
its superb acoustic resistance and good fire protection.
The tower is founded on a 2.5m-thick raft slab, which
sits directly upon the sandstone strata approximately 9m
below existing ground level; there are no piles supporting
the tower. The first post-tensioned slab is at Level -1 within
the basement. All other slabs on the tower are post-ten-
sioned with the exception of Level 49, the roof slab, which
is a conventional metal deck construction.
There are five elliptical reinforced concrete columns
(1800 × 900mm) that are situated within the reception area,
rising up through the building to Level 2, where the internal
columns become shear walls that run up through the tower
to full height. The elliptical columns are rectangular
through Levels -2 to 00, so these columns were reinforced
elliptically, while maintaining a rectangular shape.
Of the five elliptical columns, the western feature
columns are 10m high and were constructed in one pour.
These columns were to have no additional finish on them,
so a very high standard of finish as cast was required. At
Level 3 the building cantilevers out approximately 1.8m at
the top of the western elliptical columns, requiring a com-
plex transfer structure to be constructed at the top of each
column. These transfers contain over 2000 bars in each.
These transfer structures are tied back to the main core via
the post-tensioned slab, at Levels 3 and 4, thus reducing the
amount of reinforcement required at these locations.
At Level 23, the cantilever level, the building cantilevers
out to the north by approximately 4m. A transfer load sys-
tem was devised using a combination of two-storey ‘walk-
ing columns’along the two sides and four 2m-long concrete
cantilever beams projecting from the concrete shear walls.
The cantilevered beams work together with a 300mm-thick
post-tensioned slab, with the tendons running north to south
to support the extended cantilever slab from the core face,
providing the stiffness required. This slab required design-
ing to ensure the deflections were tightly controlled.
The reinforced concrete frame had to be constructed to
NOVEMBER 2007 CONCRETE12
THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE
Building
Category
WINNER
Beetham Hilton Tower, Manchester
Figure 1: Level 31 crane height 150m. Figure 2: Level 18 hotel section. Figure 3: Level 26 with 4m cantilever
from Level 23.
Figure 4: View from
below.
CONCRETE NOVEMBER 2007 13
THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE
Figure 5 above: Level 21 and Level 3 external swimming
pool structure.
Figure 7 below: Beetham Hilton Manchester.
Figure 6 above: 11m in-situ elliptical concrete columns in the Reception.
Figure 8 below: Exposed elliptical columns.
close tolerances due to the glazing system, which is fixed to
the slab by means of cast-in Halfen channels. The tolerance
onthesechannelswas5mm,andwasrequiredtoensurethat
glazing units maintained their design joint of 14mm
between the panels in their vertical joint.As the deflections
of slab edges could impact on the curtain wall, a slab with
minimal deflections had to be designed. The post-tension-
ing system was considered the best solution to this problem.
As there are also residential lifts running from Level -2
up to 47, the verticality of the shafts was critical in order for
the lifts to be installed. The building is also subject to axial
shortening, requiring the cores and slab edge columns to be
super-elevated at construction stage. This means in effect
that the slab edges had to be installed at a higher level than
designed, with the edges coming down to level once the
shortening had taken place.
Efficient use of concrete
Concealed beneath the glass façade are the twin concrete
cores and post-tensioned floor slabs, delivering a very effi-
cient use of horizontal and vertical space. The design deliv-
ered 200mm-thick concrete floor slabs without the need for
supporting columns, which would have restricted the floor
layout. The tower was built using a self-climbing jump
form technique achieving 3.5m height per lift and at one lift
perweek.Astrikingfeatureofthebuildingisthe4.5mover-
sail at the Sky bar on Level 23, with windows set into the
floor to show the street below.
Concrete made the building possible in many ways,
even though the design is based on concealing how it is
done:
• 200mm post-tensioned slabs minimise storey heights
and give big bays; they also allow apartment owners to
cut through and join floors
• oval columns in the base are fair-faced concrete and
sleekly done
• cladding to the podium block is in a precast polished
concrete with a dark, terrazzo-like finish, matching the
glazing in sophistication.
The construction process used pump-placed high-
strength concrete (80 and 60MPa) for all floors.An innova-
tive idea, with over 2m3
in the pump line, was to discharge
the concrete at the end of the day’s pour into formwork to
make precast stairs for the works, which avoided waste.
Regarding the design, the building seeks to be sensa-
tional in several ways:
• its slender profile and asymmetrical widening part-
way up (the apartments have a deeper floor plate than
the hotel) makes it highly memorable and noticeable
• its publicly accessible, double-storey Sky bar in the
cantilever Level 23 draws crowds
• its height, glamorous finish and style are attracting
celebrity buyers. ■
NOVEMBER 2007 CONCRETE14
THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE
Beetham Hilton Tower, Manchester
Owner: Beetham Organisation
Architect: Ian Simpson Architects
Consulting engineer: WSP Group
Contractor: Carillion Building
Concrete contractor: MPB Structures Limited
Reinforcement supplier: BRC
Concrete supplier: Tarmac Concrete
Judges’ comments
The Beetham Hilton Tower lives up to its billing as an
excellent example of concrete construction. It has
become the latest in a line of new buildings to raise
the architectural and commercial level of the centre of
Manchester. By putting a high-ambition building on a
low-cost but strategic site, the city’s commercial
geography has been shifted decisively.
While much of the concrete is now concealed
behind the glass cladding, concrete is used to good
effect in the lobby and conference reception on Level
1, with exposed elliptical concrete columns lining the
lobby area. The tower structure proved efficient, with
great design and construction skill used to achieve the
step-out at the 23rd floor. Floor windows in the Sky
Bar are typical of the design’s gymnastics. The tower
is more in harmony with its surroundings than
indicated by the submission photos, given the
redevelopments underway, and the tower uses the
flexibility and high strength of concrete in the design
and construction, particularly the modifications
following Building Control changes. Overall, the
Beetham Tower is a great example of integrated
design and construction skills.
Figure 9 above:
Beetham Hilton
nightshift.
Figure 10 right: View of
elliptical columns.
Figure 11: The
completed Beetham
Hilton Tower on the
Manchester
landscape.

More Related Content

What's hot

Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studiesSoumitra Smart
 
Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsasalsa moyara
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyDinesh Kumar
 
High rise building case study
High rise building case study High rise building case study
High rise building case study VISHAKA BOTHRA
 
A presentation on high rise
A presentation on high riseA presentation on high rise
A presentation on high riseAnamikaAntora
 
highrise report bangladesh (city center)
highrise report bangladesh (city center)highrise report bangladesh (city center)
highrise report bangladesh (city center)iftekhar rafat
 
Vertical cities presentation
Vertical cities presentationVertical cities presentation
Vertical cities presentationravindransandhya
 
Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.Mayur Waghulde
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.Shabarinath R
 
Planning and locating service cores.
Planning and locating service cores.Planning and locating service cores.
Planning and locating service cores.Danish Ryan
 
Triangle Group, Dover St, Mayfair
Triangle Group, Dover St, MayfairTriangle Group, Dover St, Mayfair
Triangle Group, Dover St, Mayfairclive yorath
 
World trade centre,bahrain
World trade centre,bahrainWorld trade centre,bahrain
World trade centre,bahrainDishant Rautela
 

What's hot (20)

Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsa
 
Al Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, KuwaitAl Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, Kuwait
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case Study
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
 
Tower
TowerTower
Tower
 
A presentation on high rise
A presentation on high riseA presentation on high rise
A presentation on high rise
 
High rise construction
High rise constructionHigh rise construction
High rise construction
 
highrise report bangladesh (city center)
highrise report bangladesh (city center)highrise report bangladesh (city center)
highrise report bangladesh (city center)
 
Vertical cities presentation
Vertical cities presentationVertical cities presentation
Vertical cities presentation
 
Shard tower
Shard towerShard tower
Shard tower
 
Petronas Towers
Petronas TowersPetronas Towers
Petronas Towers
 
Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.
 
Petronas tower
Petronas towerPetronas tower
Petronas tower
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Planning and locating service cores.
Planning and locating service cores.Planning and locating service cores.
Planning and locating service cores.
 
Triangle Group, Dover St, Mayfair
Triangle Group, Dover St, MayfairTriangle Group, Dover St, Mayfair
Triangle Group, Dover St, Mayfair
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
World trade centre,bahrain
World trade centre,bahrainWorld trade centre,bahrain
World trade centre,bahrain
 

Similar to Concrete society award 2007 -Hilton hotel

foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
High rise archive research
High rise archive researchHigh rise archive research
High rise archive researchdenverdieza
 
Selecting one single type of building and covering
Selecting one single type of building and coveringSelecting one single type of building and covering
Selecting one single type of building and coveringHREAT
 
JohnHancockCenter.pdf_20230809_123220_0000.pdf
JohnHancockCenter.pdf_20230809_123220_0000.pdfJohnHancockCenter.pdf_20230809_123220_0000.pdf
JohnHancockCenter.pdf_20230809_123220_0000.pdfYashawantSastikar
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal reportConor Meaney
 
Lecture 8 s.s.iii Steel Structures
Lecture 8  s.s.iii Steel Structures Lecture 8  s.s.iii Steel Structures
Lecture 8 s.s.iii Steel Structures Ursachi Răzvan
 
HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxgoreshsaini2
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabRajat Nainwal
 
Highrise buildings....
Highrise buildings....Highrise buildings....
Highrise buildings....MSulmanSarwar
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherifBian Bian
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherifhlksd
 

Similar to Concrete society award 2007 -Hilton hotel (20)

foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
High rise archive research
High rise archive researchHigh rise archive research
High rise archive research
 
Selecting one single type of building and covering
Selecting one single type of building and coveringSelecting one single type of building and covering
Selecting one single type of building and covering
 
JohnHancockCenter.pdf_20230809_123220_0000.pdf
JohnHancockCenter.pdf_20230809_123220_0000.pdfJohnHancockCenter.pdf_20230809_123220_0000.pdf
JohnHancockCenter.pdf_20230809_123220_0000.pdf
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
Car park 02
Car park 02Car park 02
Car park 02
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
Lecture 8 s.s.iii Steel Structures
Lecture 8  s.s.iii Steel Structures Lecture 8  s.s.iii Steel Structures
Lecture 8 s.s.iii Steel Structures
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Trump Tower Chicago
Trump Tower ChicagoTrump Tower Chicago
Trump Tower Chicago
 
HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptx
 
Kohinoor Square BTECH.pptx
Kohinoor Square BTECH.pptxKohinoor Square BTECH.pptx
Kohinoor Square BTECH.pptx
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Bulk active
Bulk activeBulk active
Bulk active
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arab
 
Highrise buildings....
Highrise buildings....Highrise buildings....
Highrise buildings....
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 

Concrete society award 2007 -Hilton hotel

  • 1. The Beetham landmark is the tallest concrete frame ever constructed in the UK. The project is a mixed-use development consisting of a 279-bed Hilton hotel, public bar and 219 apartments, all housed within its 47 storeys. The building itself is over 170m in height above ground level. The lower levels of the Beetham Hilton Tower are made up of a two-storey basement car park, the ground floor reception area and hotel restaurant, the Level 1 ballroom and bar. At Level 2 there is a health spa with swimming pool.The hotel rooms are situated over Levels 4 to 22 inclu- sive. The public bar is situated at Level 23, with the apart- ments above on Levels 25 to 47 inclusive. The structure of the building is made up of two vertical cores, with post-tensioned slabs being used to maintain minimal slab depths and give greater spans between columns. Concrete was used to construct the frame due to its superb acoustic resistance and good fire protection. The tower is founded on a 2.5m-thick raft slab, which sits directly upon the sandstone strata approximately 9m below existing ground level; there are no piles supporting the tower. The first post-tensioned slab is at Level -1 within the basement. All other slabs on the tower are post-ten- sioned with the exception of Level 49, the roof slab, which is a conventional metal deck construction. There are five elliptical reinforced concrete columns (1800 × 900mm) that are situated within the reception area, rising up through the building to Level 2, where the internal columns become shear walls that run up through the tower to full height. The elliptical columns are rectangular through Levels -2 to 00, so these columns were reinforced elliptically, while maintaining a rectangular shape. Of the five elliptical columns, the western feature columns are 10m high and were constructed in one pour. These columns were to have no additional finish on them, so a very high standard of finish as cast was required. At Level 3 the building cantilevers out approximately 1.8m at the top of the western elliptical columns, requiring a com- plex transfer structure to be constructed at the top of each column. These transfers contain over 2000 bars in each. These transfer structures are tied back to the main core via the post-tensioned slab, at Levels 3 and 4, thus reducing the amount of reinforcement required at these locations. At Level 23, the cantilever level, the building cantilevers out to the north by approximately 4m. A transfer load sys- tem was devised using a combination of two-storey ‘walk- ing columns’along the two sides and four 2m-long concrete cantilever beams projecting from the concrete shear walls. The cantilevered beams work together with a 300mm-thick post-tensioned slab, with the tendons running north to south to support the extended cantilever slab from the core face, providing the stiffness required. This slab required design- ing to ensure the deflections were tightly controlled. The reinforced concrete frame had to be constructed to NOVEMBER 2007 CONCRETE12 THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE Building Category WINNER Beetham Hilton Tower, Manchester Figure 1: Level 31 crane height 150m. Figure 2: Level 18 hotel section. Figure 3: Level 26 with 4m cantilever from Level 23. Figure 4: View from below.
  • 2. CONCRETE NOVEMBER 2007 13 THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE Figure 5 above: Level 21 and Level 3 external swimming pool structure. Figure 7 below: Beetham Hilton Manchester. Figure 6 above: 11m in-situ elliptical concrete columns in the Reception. Figure 8 below: Exposed elliptical columns.
  • 3. close tolerances due to the glazing system, which is fixed to the slab by means of cast-in Halfen channels. The tolerance onthesechannelswas5mm,andwasrequiredtoensurethat glazing units maintained their design joint of 14mm between the panels in their vertical joint.As the deflections of slab edges could impact on the curtain wall, a slab with minimal deflections had to be designed. The post-tension- ing system was considered the best solution to this problem. As there are also residential lifts running from Level -2 up to 47, the verticality of the shafts was critical in order for the lifts to be installed. The building is also subject to axial shortening, requiring the cores and slab edge columns to be super-elevated at construction stage. This means in effect that the slab edges had to be installed at a higher level than designed, with the edges coming down to level once the shortening had taken place. Efficient use of concrete Concealed beneath the glass façade are the twin concrete cores and post-tensioned floor slabs, delivering a very effi- cient use of horizontal and vertical space. The design deliv- ered 200mm-thick concrete floor slabs without the need for supporting columns, which would have restricted the floor layout. The tower was built using a self-climbing jump form technique achieving 3.5m height per lift and at one lift perweek.Astrikingfeatureofthebuildingisthe4.5mover- sail at the Sky bar on Level 23, with windows set into the floor to show the street below. Concrete made the building possible in many ways, even though the design is based on concealing how it is done: • 200mm post-tensioned slabs minimise storey heights and give big bays; they also allow apartment owners to cut through and join floors • oval columns in the base are fair-faced concrete and sleekly done • cladding to the podium block is in a precast polished concrete with a dark, terrazzo-like finish, matching the glazing in sophistication. The construction process used pump-placed high- strength concrete (80 and 60MPa) for all floors.An innova- tive idea, with over 2m3 in the pump line, was to discharge the concrete at the end of the day’s pour into formwork to make precast stairs for the works, which avoided waste. Regarding the design, the building seeks to be sensa- tional in several ways: • its slender profile and asymmetrical widening part- way up (the apartments have a deeper floor plate than the hotel) makes it highly memorable and noticeable • its publicly accessible, double-storey Sky bar in the cantilever Level 23 draws crowds • its height, glamorous finish and style are attracting celebrity buyers. ■ NOVEMBER 2007 CONCRETE14 THE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETETHE CONCRETE SOCIETY Awards EXCELLENCE IN CONCRETE Beetham Hilton Tower, Manchester Owner: Beetham Organisation Architect: Ian Simpson Architects Consulting engineer: WSP Group Contractor: Carillion Building Concrete contractor: MPB Structures Limited Reinforcement supplier: BRC Concrete supplier: Tarmac Concrete Judges’ comments The Beetham Hilton Tower lives up to its billing as an excellent example of concrete construction. It has become the latest in a line of new buildings to raise the architectural and commercial level of the centre of Manchester. By putting a high-ambition building on a low-cost but strategic site, the city’s commercial geography has been shifted decisively. While much of the concrete is now concealed behind the glass cladding, concrete is used to good effect in the lobby and conference reception on Level 1, with exposed elliptical concrete columns lining the lobby area. The tower structure proved efficient, with great design and construction skill used to achieve the step-out at the 23rd floor. Floor windows in the Sky Bar are typical of the design’s gymnastics. The tower is more in harmony with its surroundings than indicated by the submission photos, given the redevelopments underway, and the tower uses the flexibility and high strength of concrete in the design and construction, particularly the modifications following Building Control changes. Overall, the Beetham Tower is a great example of integrated design and construction skills. Figure 9 above: Beetham Hilton nightshift. Figure 10 right: View of elliptical columns. Figure 11: The completed Beetham Hilton Tower on the Manchester landscape.