PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 1 of 22
Complexity in Large Engineering & Construction Programs
By Bob Prieto
Chairman & CEO
Strategic Program Management LLC
Increasingly, today’s large projects are complex. While recognizing this property of
these projects we seemingly gloss over it, giving it much less attention than more
traditional project properties.
A review of even the best developed project
baseline documents will highlight efforts
placed on defining and quantifying scope;
delineating costs; and ascribing time to the
various means & methods we will employ to
deliver the project. But our focus on thorough
characterization goes further assessing and
addressing how risks will be provided for,
tracked and managed; how safety and quality
will be assured; and even how operational
stage considerations will be brought forward.
But throughout our robust stage setting and subsequent management efforts we
acknowledge complexity but do little to assess it, and maybe even less to manage it.
While we measure changes in cost and schedule and risk profile we lack even a metric
for measuring similar changes in complexity.
Complexity is not unique to the large engineering and construction projects we
undertake but is a property of all large systems. How can we learn from these analogs
and what strategies may help us better manage the complexity we face on these
projects?
This is the “century of complexity” according to Steven Hawkings, transcending the
domain of experts, taking us into a realm of emergence where the multi-finality of even
well-developed programs must be acknowledged and provided for. The complex may
even behave chaotically, amplifying the need for timely, responsive management
interventions on project paths not previously well traveled. Returning from chaos to
complexity requires leadership and broad engagement of the wisdom of the team.
But our traditional organization charts and their associated position descriptions
understate the management and leadership skills and attributes required to respond to
the complexity these programs will inevitably face. These skills include pattern
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 2 of 22
recognition, dealing with ambiguity, real time coaching and facilitation, and the ability to
manage transformations not just transitions.
Nature’s complex systems offer some hints we should heed. They reward modularity
and its ability to limit the effects of perturbations while at the same time recognizing that
excessive modularity exposes the system negatively to the effects of even stronger
perturbations. Here modules can be thought of “as a set of nodes densely connected
among themselves but loosely connected to other parts”i
.
But perturbations can spread even in highly modular systems with these stronger
perturbations occurring along couplings not readily apparent such as what we see with
constraint coupling (See Appendix 1) or other interlacing networks interacting with
multiple elements of our project, potentially amplifying otherwise more manageable
permutations.
Modularity in project design and management can also carry risks associated with
unintended impediments of delays in information flows and decision making.
I’ve touched on organizational skills and leadership aspects to be more strongly
considered when we undertake complex projects. I’ve also highlighted benefits of
modularity as a project design principle but also the risks associated with unrecognized
couplings. I’d like to turn now to the subject of measuring complexity. Again, here work
has been done in other fields in the form of cyclomatic complexity analysis in software
codes, the largest of which resemble the 50 – 100,000 activity schedules we see in
large complex programs. Cyclomatic complexity is focused on control flows or the
myriad of arrows we see in our project activity models and pay insufficient attention to. I
have discussed this previously.ii
In a project context both module and overall program complexity need to be considered
with overall program complexity considering only those connections (both apparent and
otherwise) between the densely coupled modules and the rest of the program network.
Application of an approach akin to cyclomatic analysis allows for a comparison of
execution strategies for complex projects where today we accept but don’t seek to
mitigate complexity and its threats to large complex projects.
Hawkings was right, this is the “century of complexity”, but our projects do not need to
be its victims.
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 3 of 22
Thoughts on Perturbations
In the previous section I looked at the relationship between complexity and modularity of
“systems”. I noted that Nature’s complex systems reward modularity and its ability to
limit the effects of perturbations while at the same time recognizing that excessive
modularity exposes the system negatively to the effects of even stronger perturbations.
In this section I further explore this
linkage between modularity and
complexity as well as begin to consider
ways of defining and measuring
complexity at least on a relative basis.
Let’s begin by considering two systems
in the engineering & construction
ecosystem. The first represents the
physical project to be designed and
constructed and the second represents
the project execution plan that may encompass as many as 100,000 discrete activities
on a large project.
We see from natural and other complex system analogs that the potential disruption
from perturbations declines with modularization, reaching some minimum potential after
which further increases in modularization increase the level of disruptions from
perturbations as shown in Figure 1.
% MODULARIZATION
POTENTIAL
DISRUPTION
FROM
PERTURBATIONS
Figure 1
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 4 of 22
This behavior in the impacts of perturbations can be understood by considering two
different classes of perturbations. The first is associated with purely random discrete
events. As we increase the modularization of the system, susceptibility to these random
perturbations are more localized and contained. Conversely as we increase the
modularization of the system susceptibility of the system to perturbations more systemic
in nature grows. In the second class of perturbations second and third order couplings,
including coupling through constraints, grows in scope and importance. We can see the
behavior of each of these classes of perturbations in Figure 2.
% MODULARIZATION
PERTURBATION
IMPACT
SYSTEMIC
PERTURBATIONS
RANDOM
PERTURBATIONS
Figure 2
The symmetrical behavior shown in Figures 1 and 2 is not intended to indicate that
these perturbation classes behave in similar manners and to the contrary we should
expect them to materialize and deteriorate at different rates.
The figures above represent a snapshot of the totality of the planned project and its
execution approach at project initiation. They can provide guidance in optimizing
modularity of both design and project execution to minimize the risks from various
perturbations.
It is important to recognize that perturbation risks, once a level of project modularization
has been established, are not constant throughout the project execution period. This
can be seen in Figure 3 where perturbation risk attenuates over time as various
precedences are realized and successfully transcended.
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 5 of 22
PERTURBATION
RISK
TIME
PERTURBATION RISK
DECLINES AS
PRECEDENCES
SATISFIED
Figure 3
It may be possible to define and measure precedence risk on at least a first order basis
by considering the number of paths through the project, where modules count as a
singular activity in the overall project network. We can see this in very simple terms in
Figure 4 where the precedence risk of each activity chain is the sum of the number of
precedences embedded in the activity chain.
In this example activity chain AB has a single precedence, A, which once completed
reduces the number of precedences in the chain to zero. Alternately, looking at the
three other activity chains, precedences are characterized as A plus C, and completing
A would reduce the precedence risk to that associated with C.
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 6 of 22
A B
C D
E
F
Precedence Risk (PR)
Chain PR
AB A
AD A+C
AE A+C
AF A+C
PRECEDENCE RISK
Figure 4
TIME
The above example treated each precedence equally in terms of its susceptibility to
disruption. While modules act to limit the effects of perturbations on the overall system
their aggregate system risk would reasonably be expected to be greater than one
average activity in the non-modularized part of the system. Similarly all activities are not
created equally in terms of their susceptibility to perturbations and as such it will be
important to create a weighting system reflecting activity susceptibility to disruption. This
may be accomplished through consideration of couplings discussed later in this paper.
In the example above we treated A and C equally. If the preponderance of perturbation
susceptibility lay with activity A, then completing activity A would remove a
disproportionate amount of precedence risk. Conversely if the susceptibility to
perturbation risk was much greater in C then completing A may not have significantly
improved our risk posture with respect to disruption.
In order to draw some insight into how to view susceptibility to perturbation risk, let us
look at the special case of an activity that represents a completed module. If we can
draw some insights around this special activity’s perturbation risk, we may be able to
generalize for a broader set of activities.
PM World Journal Complexity in Large Engineering &
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 7 of 22
Module Perturbation Risk
Let’s begin by defining some properties of a module:
Module Density (MD) – This may be considered to either represent the number of
connections (physical or activities) within the module or expressed more fully as the
number of perturbation “sites” which may better describe some of the coupling that
exists within the module itself.
Module Coupling (MC) – This represents the number of external module connections
or couplings of all kinds. The greater MC the less isolated from the broader system the
module is. These couplings include both incoming couplings (IC) and outgoing
couplings (OC) as shown in Figure 5. The potential for effectively bi-directional coupling
or feedback loops exist but have been treated as separate IC and OC components.
Figure 5
MODULE
IC –Incoming
Coupling
OC –Outgoing
Coupling
The disruption risk from a module to the overall system can be thought of as the sum of
two behaviors. The first looks at the risk the module itself has to disruption. This can be
thought of as being related to the overall internal susceptibility related to the Module
Density, MD, and the number of incoming couplings, IC. The greater IC, the less
insulated from disruption the module is. In this case effective modularity may be less
than apparent modularity.
The second behavior we must consider in looking at the module’s impact on overall
system disruption risk is associated with the number and strength of the outgoing
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 8 of 22
couplings, OC. Each OC feeds into one or more chains of subsequent activities which it
acts as a precedence for. Thus the greater OC, the more potential paths for disruption
from perturbations. This leads us to think carefully about where modules sit in the
overall project and execution plans. We should seek to minimize forward disruption risk
from disruptions to modules.
Thus the overall Disruption (or Perturbation) risk associated with a given module can be
described as:
𝑀𝑜𝑑𝑢𝑙𝑒 𝐷𝑖𝑠𝑟𝑢𝑝𝑡𝑖𝑜𝑛 𝑅𝑖𝑠𝑘 = 𝑓(𝑀𝐷: 𝐼𝐶) + 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝑂𝐶))
In plain English, the first term looks at the number of potential perturbation sites within
the module and the number of incoming couplings. These incoming couplings represent
potential disruption paths from more systemic type perturbations. The second term
looks at the ability of a disruption that effects the module to propagate through the
broader system, considering all possible outgoing couplings. This second term can be
generalized to apply to any activity in the overall system network.
Generalizing Activity Disruption Risk
As shown above for the special case of modules, an activity’s contribution to overall
perturbation risk can be described as 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝐶𝑜𝑛𝑛𝑒𝑐𝑡𝑒𝑑 𝑃𝑎𝑡ℎ𝑤𝑎𝑦)). Whether
such pathways should be further weighted to consider the broader connectivity of
individual activities such as was reflected in the special case of modules remains to be
answered.
Ignoring weighting we come to recognize that the more activities one activity is
connected to, the greater the perturbation risk and thus the greater complexity of the
system. This is analogous to what was determined in the IT industry and leads itself to
calculation of cyclomatic complexity.
In considering large complex projects in our industry it will be important to calculate not
only apparent complexity, associated with direct couplings, but also actual complexity
considering additional couplings which increase system exposure to systemic risks. I
will touch on these later in this paper.
Apparent Complexity of Large Complex Projects
Apparent complexity looks only at direct couplings or connected components as
described by graph theory. In Figure 6 we see one system representation consisting of
18 nodes, 22 couplings and 1 exit point (completed project).
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 9 of 22
In an assessment of complexity analogous to one formulation of cyclomatic complexity,
complexity would be assessed as Couplings – Nodes + Exit Pointsiii
(first Betti number).
In the Figure 6 example this would equate to 22-18 + 1 or 5. From a program
perspective, illustrated in Figure 7, where O, P, Q each represent independent projects
in the overall program we would have 17 Nodes, 19 Couplings and 3 exit points.
Complexity would be described as 19-17 +3 or 5. The complexity of the challenge at
hand is not affected by terminology when assessing apparent complexity.
In Figure 8 we have removed one of the couplings reducing complexity to 4.
Returning to Figure 7, we can define the number of independent pathways as 6
including:
A-B-G-L-O
A-C-D-H-L-O
A-C-E-I-M-L-O
A-C-E-I-M-P
A-C-F-j-N-P
A-C-F-K-Q
Whereas in Figure 8, the five independent pathways consist of:
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 10 of 22
A-B-G-L-O
A-C-D-H-L-O
A-C-E-I-M-P
A-C-F-j-N-P
A-C-F-K-Q
By contrast the simplified system described in Figure 9 has only 5 Nodes and 4
Couplings and 1 Exit Point and a complexity of zero (4-5+1). In the complexity
formulation just described the number of independent pathways is equal to apparent
complexity plus 1.
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 11 of 22
A B
C D
E
F
Figure 8
G
H
I
J
K
L O
M
N
Q
P
Apparent Complexity
Eliminating a Coupling
A B
Figure 9
G
L O
Apparent Complexity
Simple System
Recognizing that the level of detail reflected in design or management program details
can vary, affecting the magnitude of the overall complexity number, it may be useful to
construct a complexity index to provide guidance across project phases and to compare
alternative project execution strategies. This index can be described as:
Complexity Index =
𝑪𝒐𝒖𝒑𝒍𝒊𝒏𝒈𝒔+𝑬𝒙𝒊𝒕 𝑷𝒐𝒊𝒏𝒕𝒔
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝑵𝒐𝒅𝒆𝒔
Returning to the examples in the above Figures we would see Complexity Index values
of:
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 12 of 22
Complexity Index
Figure 6 =23/18 = 1.28
Figure 7 =22/17 = 1.29
Figure 8 =19/17 = 1.18
Figure 9 =5/5 = 1.00
Clearly the simpler networks reflected in Figures 8 and 9 are shown. The slight
difference between Figure 6 and 7 values associated with project vs program
perspective requires further examination when considering apparent complexity. As we
move towards considering actual complexity this difference may become less important.
Actual Complexity
Let’s turn our attention now to evaluating actual complexity. Actual complexity seeks to
assess second and third order couplings which are not readily apparent from a review of
the project execution plan and network. In effect the number of couplings grows while
the number of discrete nodes remains unchanged, concomitantly, complexity grows.
These hidden couplings are a characteristic of large complex programs and can result
in severely impactful perturbations.
There are several classes of second and third order coupling that may be considered.
These include assumption couplingiv
and perhaps more specifically a related form of
coupling, namely, constraint coupling. I have previously written about constraint
coupling and have included an example as Appendix 1. In this paper I will focus on
illustrating its effect on complexity.
Let’s consider one particular constraint which is availability of a particular skilled trade
such as a welder. In Figure 10 we illustrate the potential coupling created by this skilled
trade, recognizing that availability is both market and temporally driven. Activities G, H,
and K all rely on this constrained resource. Detailed project planning may have been
based on slightly staggering demand for this resource while assuming an overall pool
availability. If the pool contracts activities G, H, and K may all be adversely effected.
Figure 10 illustrates strong temporal coupling and as such changes in the overall welder
pool will be particularly important. Activities can be taken to minimize the probability of
such coupled constraints but if they occur they create strong perturbations and
significant project disruption. They most certainly add to project complexity and as such
must be modeled when considering actual complexity.
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 13 of 22
Let’s consider both apparent and actual complexity in Figure 10. We previously saw that
apparent complexity for this system was 4 (Figure 8) described by 18 Couplings – 17
Nodes + 3 Exit Points (O, P, Q). Actual complexity would consider these three added
couplings to G, H, and K and the added “Welder” node which is also an exit point since
the program itself acts to shape and size this constrained resource. This yields 21
Couplings – 18 Nodes + 4 Exit Points or a complexity value of 7. Actual complexity is
greater than apparent complexity.
In assessing actual complexity it is important to focus on the most impactful second and
third order couplings. Similarly, the treatment of the added coupling node as also an exit
point requires a judgement as to whether the program itself is a significant part of the
overall constraint. In the Figure 10 example I assumed this to be the case and added
one more Exit Point but in another setting the project demand may have represented a
much smaller part of the overall demand for the constrained resource.
Much in the same manner as we calculated an apparent complexity index of 1.18
(Figure 8) we can calculate an actual complexity index of 1.39 (Figure 10) here. The
ratio of actual to apparent complexity provides an additional measure of project
performance uncertainty as we manage based on the defined project execution network
but face risks from out of network perturbations. This uncertainty measure related to
complexity would have a value equal to 1.39/1.18 or Complexity Uncertainty = 1.18.
The greater the uncertainty the greater the susceptibility to “white space” and Black
Swan risk.
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 14 of 22
Recap on Complexity
Up to this point I have looked at the relationship between complexity and modularity of
“systems”. I explored the linkage between modularity and complexity and began to
consider ways of defining and measuring complexity at least on a relative basis.
I drew several inferences and posited several new measures related to complexity in
large complex projects. These include:
 Modularization reduces susceptibility to random perturbations but increases
susceptibility to systemic perturbations
 Perturbation risk, the sum of the number of precedences in the activity
chain, declines as precedences are satisfied
 Module Density (MD) representing the number of connections (physical or
activities) within the module or expressed more fully as the number of
perturbation “sites” that exists within the module.
 Module Coupling (MC) representing the number of external module connections
or couplings of all kinds. The greater MC the less isolated from the broader
system the module is. These couplings include both incoming couplings (IC) and
outgoing couplings (OC).
 𝑴𝒐𝒅𝒖𝒍𝒆 𝑫𝒊𝒔𝒓𝒖𝒑𝒕𝒊𝒐𝒏 𝑹𝒊𝒔𝒌 = 𝑓(𝑀𝐷: 𝐼𝐶) + 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝑂𝐶))
 Apparent Complexity = Couplings – Nodes + Exit Points
 Complexity Index =
𝐶𝑜𝑢𝑝𝑙𝑖𝑛𝑔𝑠+𝐸𝑥𝑖𝑡 𝑃𝑜𝑖𝑛𝑡𝑠
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑁𝑜𝑑𝑒𝑠
 Actual complexity seeks to assess second and third order couplings which are
not readily apparent from a review of the project execution plan and network. In
effect the number of couplings grows while the number of discrete nodes remains
largely unchanged, concomitantly, complexity grows
 Complexity Uncertainty - The ratio of actual to apparent complexity provides an
additional measure of project performance uncertainty as we manage based on
the defined project execution network but face risks from out of network
perturbations.
Several areas warrant future development including development of a simplified
weighting system for activity’s susceptibility to perturbation risk and modeling of
modules incorporated into a larger activity chain. Here the work above on Module
Disruption Risk represents a starting point. Classes of couplings are discussed in the
next section and warrant further development but it is important to note that these flows
are largely from external or stakeholder sources, represent the biggest source of
incremental complexity and their disruption effect is consistent with observation.
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 15 of 22
Classes of Coupling
Up to this point I have looked at the relationship between complexity and modularity of
“systems”. I noted that Nature’s complex systems reward modularity and its ability to
limit the effects of perturbations while at the same time recognizing that excessive
modularity exposes the system negatively to the effects of even stronger, more
systemic perturbations.
I further explored this linkage between
modularity and complexity as well as
considered ways of defining and measuring
both apparent and actual complexity at
least on a relative basis. A complexity
index was suggested and the subject of
coupling introduced. It was suggested that
coupling in large complex projects could be
classified. This section suggests one
possible classification system, recognizes the potential interaction between classes and
provides an initial ranking of these classes with respect to their potential to broadly
disrupt planned execution of the project.
Coupling refers to the interdependencies between activities where modules may be
considered as a special activity type. Nine classes of coupling in large complex projects
have been defined as follows:
Control Coupling – This is represented by the normal control flows that guide project
execution and work activities; those arrows on the Gantt chart or WBS is you will. The
control flow arrows are not dimensionless and a clear and comprehensive
understanding of the data, information and interfaces implicit in the control flow must be
made explicit for effective management. Data dictionaries and structures must be
coherent and comprehensive to achieve effective control flows. Additionally, Strategic
Business Objectives (SBOs) and associated kpi’s must cascade throughout the control
network.
Co-dependent Coupling – Interdependency between activities are such that a change
in the data, outputs or execution of one activity necessitates a change in the second.
For example, excavation and dewatering activities are linked where a change in
dewatering rates or volumes may influence excavation or ground stabilization and
improvement activities.
Assumption Coupling – Multiple activities share global assumptions, data or other
values. A change in assumptions, including through assumption migration, impacts
multiple, otherwise disparate, activities. Examples could include assumed labor
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 16 of 22
productivity improvement through the project; customs clearing times; or client approval
cycles.
Constraint Coupling – Also may be considered as shared resource coupling, where
temporal or more systemic constraints may occur in a resource common to execution of
multiple activities. Competition for resources with fixed supply rates (at least in the short
term) is exacerbated by ex-project changes in demand.
External Coupling – Multiple activities require externally imposed inputs, controlled
resources, approvals or other interfaces. Permits and inspections would be an example
of external couplings. Changes in the externally imposed requirements may impact
multiple activities.
Stakeholder Coupling – Different than External Coupling since flows from these
couplings are not imposed but carry the risk of being less manageable and potentially
more consequential. Stakeholder coupling impacts both activities as well as the
connecting flows.
Message Coupling – Messages, generally from management centers, are transmitted
formally or informally throughout the project execution network, including to portions for
which the message was never intended. This may cause unintended actions and
consequences.
Temporal Coupling – Simultaneous undertaking of two or more activities. Risk arises
as a result of any temporally based constraint coupling. Multiple projects, carefully
staged to spread out welder demand fail when project schedule slippages push demand
into the same time frame.
Uncoupling – Describes the lack of apparent couplings of any kind between modules.
Module to module coupling may occur as a result of any of the classes of coupling
described above.
The greater the coupling between activities, the greater the complexity and the
likelihood of propagating disruptions. It is likely the greater the number of classes of
couplings present the greater the management challenge and the greater the risk of
disruption. Additionally, classes of couplings that tend to forward changes from other
classes are more disruptive.
Table 1 shows the classes that a given class may impact. Table 2 synthesizes these
relationships to define those classes of couplings likely to most contribute to project
disruption. Here we note that stakeholder type couplings are likely to be the most
impactful from an overall disruption perspective. Instability measures reflect high
forward coupling by particular classes of couplings. In effect these are couplings which
themselves may be susceptible to the effects of other couplings and more likely to
translate those effects and pass them on. The ratio of stability to instability (I/O)
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 17 of 22
provides a relative measure of the contribution to disruption from various classes of
couplings.
Together with the Complexity Index and Complexity Uncertainty previously described,
I/O provides another measure of the contribution of coupling to disruption.
Cohesion, by contrast, looks at the range of actions that occur within a given activity
and makes a judgement to how related they are. For example if a given activity required
painting all east facing walls blue and changing washers in all 4” valves we would
describe its cohesion as low. By contrast an activity that required welding flanges and
making all connections in a particular fluid system would be viewed as having higher
cohesion.
By definition modules as previously described should be expected to have high
cohesion.
In my book, Theory of Management of Large Complex Projects, I suggest three areas
where current project management theory falls short at scale. In simple terms I suggest
the need for stronger foundations; a focus on flows, the arrows, not just the activities;
and recognize a need for a strengthened approach to stakeholder engagement. This
work on complexity is intended to begin to address the areas this new theory highlights
and to suggest another foundational activity to strengthen project performance through
its increased focus on flows and couplings, including most notably, stakeholder
coupling. Assessment of complexity is intended to help evaluate alternative execution
Control Co-dependent Assumption Constraint External Stakeholder Message Temporal Uncoupling
Control x x x x x
Co-dependent x x x
Assumption x x x x x x x
Constraint x x x x x x
External x x x x x x x x
Stakeholder x x x x x x x x x
Message x x x x x x x
Temporal x x x x x x x x x
Uncoupling x x x x x
SourceofInputs
Affected Classes
Table 1 Relationships Between Classes of Couplings
# Incoming # Outgoing Total Instability Stability I/O Least to Most Impactful
(I) (O) Outgoing/Total Incoming/Total
Control 9 5 14 0.36 0.64 1.80 2
Co-dependent 8 3 11 0.27 0.73 2.67 1
Assumption 6 7 13 0.54 0.46 0.86 6
Constraint 6 6 12 0.50 0.50 1.00 5
External 4 8 12 0.67 0.33 0.50 8
Stakeholder 4 9 13 0.69 0.31 0.44 9
Message 7 7 14 0.50 0.50 1.00 4
Temporal 7 9 16 0.56 0.44 0.78 7
Uncoupling 7 5 12 0.42 0.58 1.40 3
Ranking of Coupling Class Contribution to Disruption
Table 2
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 18 of 22
approaches and perhaps provide guidance on the confidence we should have in
planned or predicted results.
Improving large complex project execution remains a journey which I feel compelled to
continue.
Appendix 1
Constraint Coupling Example
Today, constraint identification is based on the original execution plan and rarely
updated. But, original program execution plans change and even impacts off the critical
path can have significant impacts on overall program performance because of
constraint coupling.
Let’s look at a simple example for a four project program:
 Project 1 is an enabling project, not on the critical path with a 12 month duration.
Its sequencing does not lend itself to acceleration.
 Project 2 is interdependent with Project 1 and cannot be initiated until Project 1
is substantively complete. The baseline plan shows it not starting until after
Project 1 complete but it could start 2 months earlier when Project 1
substantively complete.
 Project 3 represents the critical path effort and project labor is constrained at
600 as a condition of permitting.
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 19 of 22
 Project 4 is seasonal work which cannot be rescheduled but is generally
independent of other project linkages except constraints related to overall labor
availability.
Total labor available to program is capped at 1200 as labor is in short supply and multi-
owner labor agreements executed to eliminate poaching and an uncontrolled wage
spiral.
This is what the baseline program manpower loading looked like.
Like all programs, something changed in Project 1 that causes suspension of
construction and other activities at the end of month 4. The hiatus lasts for 2 months;
Project 1 not on critical path and the PM has indicated he can control costs so no cost
increase; no increased labor requirement; but project schedule is 2 months longer.
PM for Project 2 indicates he can accommodate 2 month slippage in Project 1 since
precedent work would be completed in time for him to begin.
0
200
400
600
800
1000
1200
Manpower
1 3 5 7 9 11 13 15 17 19 21 23
Time
Base Case Manpower
Project 4
Project 3
Project 2
Project 1
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 20 of 22
From a “direct” project interface perspective neither Projects 3 nor 4 were dependent on
Project 1.
The PM for project 1 submits a new manpower forecast and the other 3 PMs continue
without updating their forecasts since no direct impact.
Initial look shows the overall critical path end date maintained but manpower loading at
the program level is in excess of the overall 1200 constraint placed on the program.
Without such a programmatic viewpoint it may not be self evident that the change
proposed for Project 1 would cause the program to violate one of its constraints.
Attention now turns to executing the changed program while still meeting both the
overall program 1200 person constraint and Project 3’s 600 person constraint.
Program completion is delayed by 2 months despite the fact that Project 1 is not on the
critical path.
0
200
400
600
800
1000
1200
1400
1600
1800
Manpower
1 3 5 7 9 11 13 15 17 19 21 23
Time
Unconstrained Manpower Loading
Project 4
Project 3
Project 2
Project 1
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 21 of 22
Granted a simple example but others exist with respect to limited supply of key trades,
such as welding; limited camp accommodations; constrained import facility capacity and
so on. Each of those an example from a recent giga program.
References:
i. The importance of being modular; Marta Sales-Pardo; Science Vol 357, Issue 6347
ii. Theory of Management of Large Complex Projects; Bob Prieto; CMAA
iii. Cyclomatic complexity often states this as 2*exit points
iv. Management of Assumption Infatuation in Large Complex Projects; PM World Journal;
Volume V, Issue IV – April 2016
0
200
400
600
800
1000
1200
Manpower
1 4 7 10 13 16 19 22 25
Time
Manpower Loading Reflecting Labor Constraints
Project 4
Revised Project 3 Loading
Project 2
Project 1
PM World Journal Complexity in Large Engineering 
Vol. VI, Issue XI – November 2017 Construction Programs
www.pmworldjournal.net Featured Paper by Bob Prieto
© 2017 Bob Prieto www.pmworldlibrary.net Page 22 of 22
About the Author
Bob Prieto
Chairman  CEO
Strategic Program Management LLC
Jupiter, Florida, USA
Bob Prieto is a senior executive effective in shaping and
executing business strategy and a recognized leader within the infrastructure, engineering
and construction industries. Currently Bob heads his own management consulting practice,
Strategic Program Management LLC. He previously served as a senior vice president of
Fluor, one of the largest engineering and construction companies in the world. He focuses
on the development and delivery of large, complex projects worldwide and consults with
owners across all market sectors in the development of programmatic delivery strategies.
He is author of eight books including “Strategic Program Management”, “The Giga Factor:
Program Management in the Engineering and Construction Industry”, “Application of Life
Cycle Analysis in the Capital Assets Industry”, “Capital Efficiency: Pull All the Levers” and,
most recently, “Theory of Management of Large Complex Projects” published by the
Construction Management Association of America (CMAA) as well as over 600 other
papers and presentations.
Bob is a non-executive director of Cardno (ASX) and an Independent Member of the
Shareholder Committee of Mott MacDonald. He serves on the Millennium Challenge
Corporation Advisory Board and a member of the ASCE Industry Leaders Council, National
Academy of Construction, a Fellow of the Construction Management Association of America
and member of several university departmental and campus advisory boards. Bob served
until 2006 as a U.S. presidential appointee to the Asia Pacific Economic Cooperation
(APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business
leaders to shape the framework for trade and economic growth. He had previously served
as both as Chairman of the Engineering and Construction Governors of the World
Economic Forum and co-chair of the infrastructure task force formed after September 11th
by the New York City Chamber of Commerce. Previously, he served as Chairman at
Parsons Brinckerhoff (PB).
Bob can be contacted at rpstrategic@comcast.net.

More Related Content

What's hot

Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Reading week09 lechler_cc
Reading week09 lechler_ccReading week09 lechler_cc
Reading week09 lechler_cchenry KKK
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...IRJET Journal
 
Project risk management (1)
Project risk management (1)Project risk management (1)
Project risk management (1)Lezasmith
 
Is it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryIs it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryBob Prieto
 
Ibm acdemy of technology it complexity
Ibm acdemy of technology it complexityIbm acdemy of technology it complexity
Ibm acdemy of technology it complexitypsaravanan1985
 
Garro abarca, palos-sanchez y aguayo-camacho, 2021
Garro abarca, palos-sanchez y aguayo-camacho, 2021Garro abarca, palos-sanchez y aguayo-camacho, 2021
Garro abarca, palos-sanchez y aguayo-camacho, 2021ppalos68
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resumeguscaporusso
 
How to Effectively Manage IT Project Risks
How to Effectively Manage IT Project Risks How to Effectively Manage IT Project Risks
How to Effectively Manage IT Project Risks Bradley Susser
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
The problem of user designer relations in technolgy production, formatted
The problem of user designer relations in technolgy production, formattedThe problem of user designer relations in technolgy production, formatted
The problem of user designer relations in technolgy production, formattedPekka Muukkonen
 

What's hot (18)

Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Reading week09 lechler_cc
Reading week09 lechler_ccReading week09 lechler_cc
Reading week09 lechler_cc
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...
 
KHass Resume 2015 with CV
KHass Resume 2015 with CVKHass Resume 2015 with CV
KHass Resume 2015 with CV
 
Mega Project Support
Mega Project SupportMega Project Support
Mega Project Support
 
Project risk management (1)
Project risk management (1)Project risk management (1)
Project risk management (1)
 
Is it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryIs it time to rethink project managemnt theory
Is it time to rethink project managemnt theory
 
VDCL HICSS 2009
VDCL HICSS 2009VDCL HICSS 2009
VDCL HICSS 2009
 
Management Principles Associated with I.T. Project Success
Management Principles Associated with I.T. Project SuccessManagement Principles Associated with I.T. Project Success
Management Principles Associated with I.T. Project Success
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Ibm acdemy of technology it complexity
Ibm acdemy of technology it complexityIbm acdemy of technology it complexity
Ibm acdemy of technology it complexity
 
Garro abarca, palos-sanchez y aguayo-camacho, 2021
Garro abarca, palos-sanchez y aguayo-camacho, 2021Garro abarca, palos-sanchez y aguayo-camacho, 2021
Garro abarca, palos-sanchez y aguayo-camacho, 2021
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resume
 
Collaborative working
Collaborative workingCollaborative working
Collaborative working
 
How to Effectively Manage IT Project Risks
How to Effectively Manage IT Project Risks How to Effectively Manage IT Project Risks
How to Effectively Manage IT Project Risks
 
Evaluating Project Success
Evaluating Project SuccessEvaluating Project Success
Evaluating Project Success
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
The problem of user designer relations in technolgy production, formatted
The problem of user designer relations in technolgy production, formattedThe problem of user designer relations in technolgy production, formatted
The problem of user designer relations in technolgy production, formatted
 

Similar to Complexity in large engineering & construction programs

Classes of coupling in large complex engineering & construction projects
Classes of coupling in large complex engineering & construction projectsClasses of coupling in large complex engineering & construction projects
Classes of coupling in large complex engineering & construction projectsBob Prieto
 
**Exploring and Assessing Project Complexity-Dao;17.pdf
**Exploring and Assessing Project Complexity-Dao;17.pdf**Exploring and Assessing Project Complexity-Dao;17.pdf
**Exploring and Assessing Project Complexity-Dao;17.pdfDépartement de finance
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Bob Prieto
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET Journal
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule riskGlen Alleman
 
Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value BehaviorBob Prieto
 
Program tetrahedron further development
Program tetrahedron further developmentProgram tetrahedron further development
Program tetrahedron further developmentBob Prieto
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...ijccmsjournal
 
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)ijccmsjournal
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...ijccmsjournal
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...ijccmsjournal
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...ijccmsjournal
 
MarvinAndGarrett-SoS_ArchitectureModeling
MarvinAndGarrett-SoS_ArchitectureModelingMarvinAndGarrett-SoS_ArchitectureModeling
MarvinAndGarrett-SoS_ArchitectureModelingBob Garrett
 

Similar to Complexity in large engineering & construction programs (20)

Classes of coupling in large complex engineering & construction projects
Classes of coupling in large complex engineering & construction projectsClasses of coupling in large complex engineering & construction projects
Classes of coupling in large complex engineering & construction projects
 
**Exploring and Assessing Project Complexity-Dao;17.pdf
**Exploring and Assessing Project Complexity-Dao;17.pdf**Exploring and Assessing Project Complexity-Dao;17.pdf
**Exploring and Assessing Project Complexity-Dao;17.pdf
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
 
A review paper
A review paperA review paper
A review paper
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule risk
 
P070 a simple_view_of_complexity
P070 a simple_view_of_complexityP070 a simple_view_of_complexity
P070 a simple_view_of_complexity
 
Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value Behavior
 
Program tetrahedron further development
Program tetrahedron further developmentProgram tetrahedron further development
Program tetrahedron further development
 
9420ijccms01.pdf
9420ijccms01.pdf9420ijccms01.pdf
9420ijccms01.pdf
 
9420ijccms01.pdf
9420ijccms01.pdf9420ijccms01.pdf
9420ijccms01.pdf
 
9420ijccms01.pdf
9420ijccms01.pdf9420ijccms01.pdf
9420ijccms01.pdf
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
 
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)
International Journal of Chaos, Control, Modelling and Simulation (IJCCMS)
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE  PERFORMANCE AND UNDERDAMPED TRANSI...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSI...
 
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
SOCIO-ORGANO COMPLEXITY, PROJECT SCHEDULE PERFORMANCE AND UNDERDAMPED TRANSIE...
 
Zue2015Uncertainties
Zue2015UncertaintiesZue2015Uncertainties
Zue2015Uncertainties
 
MarvinAndGarrett-SoS_ArchitectureModeling
MarvinAndGarrett-SoS_ArchitectureModelingMarvinAndGarrett-SoS_ArchitectureModeling
MarvinAndGarrett-SoS_ArchitectureModeling
 

More from Bob Prieto

Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Bob Prieto
 
Theory of Management of Large Complex Projects - Introduction and Chapter 1
Theory of Management of Large Complex Projects - Introduction and Chapter 1Theory of Management of Large Complex Projects - Introduction and Chapter 1
Theory of Management of Large Complex Projects - Introduction and Chapter 1Bob Prieto
 
Sources of complexity
Sources of complexitySources of complexity
Sources of complexityBob Prieto
 
??? (Rutgers Innovation Key Note)
??? (Rutgers Innovation Key Note)??? (Rutgers Innovation Key Note)
??? (Rutgers Innovation Key Note)Bob Prieto
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklistBob Prieto
 
Suggestions to enhance infrastructure innovation
Suggestions to enhance infrastructure innovationSuggestions to enhance infrastructure innovation
Suggestions to enhance infrastructure innovationBob Prieto
 

More from Bob Prieto (18)

Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6
 
Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5
 
Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4
 
Theory of Management of Large Complex Projects - Introduction and Chapter 1
Theory of Management of Large Complex Projects - Introduction and Chapter 1Theory of Management of Large Complex Projects - Introduction and Chapter 1
Theory of Management of Large Complex Projects - Introduction and Chapter 1
 
Sources of complexity
Sources of complexitySources of complexity
Sources of complexity
 
??? (Rutgers Innovation Key Note)
??? (Rutgers Innovation Key Note)??? (Rutgers Innovation Key Note)
??? (Rutgers Innovation Key Note)
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
 
Suggestions to enhance infrastructure innovation
Suggestions to enhance infrastructure innovationSuggestions to enhance infrastructure innovation
Suggestions to enhance infrastructure innovation
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Complexity in large engineering & construction programs

  • 1. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 1 of 22 Complexity in Large Engineering & Construction Programs By Bob Prieto Chairman & CEO Strategic Program Management LLC Increasingly, today’s large projects are complex. While recognizing this property of these projects we seemingly gloss over it, giving it much less attention than more traditional project properties. A review of even the best developed project baseline documents will highlight efforts placed on defining and quantifying scope; delineating costs; and ascribing time to the various means & methods we will employ to deliver the project. But our focus on thorough characterization goes further assessing and addressing how risks will be provided for, tracked and managed; how safety and quality will be assured; and even how operational stage considerations will be brought forward. But throughout our robust stage setting and subsequent management efforts we acknowledge complexity but do little to assess it, and maybe even less to manage it. While we measure changes in cost and schedule and risk profile we lack even a metric for measuring similar changes in complexity. Complexity is not unique to the large engineering and construction projects we undertake but is a property of all large systems. How can we learn from these analogs and what strategies may help us better manage the complexity we face on these projects? This is the “century of complexity” according to Steven Hawkings, transcending the domain of experts, taking us into a realm of emergence where the multi-finality of even well-developed programs must be acknowledged and provided for. The complex may even behave chaotically, amplifying the need for timely, responsive management interventions on project paths not previously well traveled. Returning from chaos to complexity requires leadership and broad engagement of the wisdom of the team. But our traditional organization charts and their associated position descriptions understate the management and leadership skills and attributes required to respond to the complexity these programs will inevitably face. These skills include pattern
  • 2. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 2 of 22 recognition, dealing with ambiguity, real time coaching and facilitation, and the ability to manage transformations not just transitions. Nature’s complex systems offer some hints we should heed. They reward modularity and its ability to limit the effects of perturbations while at the same time recognizing that excessive modularity exposes the system negatively to the effects of even stronger perturbations. Here modules can be thought of “as a set of nodes densely connected among themselves but loosely connected to other parts”i . But perturbations can spread even in highly modular systems with these stronger perturbations occurring along couplings not readily apparent such as what we see with constraint coupling (See Appendix 1) or other interlacing networks interacting with multiple elements of our project, potentially amplifying otherwise more manageable permutations. Modularity in project design and management can also carry risks associated with unintended impediments of delays in information flows and decision making. I’ve touched on organizational skills and leadership aspects to be more strongly considered when we undertake complex projects. I’ve also highlighted benefits of modularity as a project design principle but also the risks associated with unrecognized couplings. I’d like to turn now to the subject of measuring complexity. Again, here work has been done in other fields in the form of cyclomatic complexity analysis in software codes, the largest of which resemble the 50 – 100,000 activity schedules we see in large complex programs. Cyclomatic complexity is focused on control flows or the myriad of arrows we see in our project activity models and pay insufficient attention to. I have discussed this previously.ii In a project context both module and overall program complexity need to be considered with overall program complexity considering only those connections (both apparent and otherwise) between the densely coupled modules and the rest of the program network. Application of an approach akin to cyclomatic analysis allows for a comparison of execution strategies for complex projects where today we accept but don’t seek to mitigate complexity and its threats to large complex projects. Hawkings was right, this is the “century of complexity”, but our projects do not need to be its victims.
  • 3. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 3 of 22 Thoughts on Perturbations In the previous section I looked at the relationship between complexity and modularity of “systems”. I noted that Nature’s complex systems reward modularity and its ability to limit the effects of perturbations while at the same time recognizing that excessive modularity exposes the system negatively to the effects of even stronger perturbations. In this section I further explore this linkage between modularity and complexity as well as begin to consider ways of defining and measuring complexity at least on a relative basis. Let’s begin by considering two systems in the engineering & construction ecosystem. The first represents the physical project to be designed and constructed and the second represents the project execution plan that may encompass as many as 100,000 discrete activities on a large project. We see from natural and other complex system analogs that the potential disruption from perturbations declines with modularization, reaching some minimum potential after which further increases in modularization increase the level of disruptions from perturbations as shown in Figure 1. % MODULARIZATION POTENTIAL DISRUPTION FROM PERTURBATIONS Figure 1
  • 4. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 4 of 22 This behavior in the impacts of perturbations can be understood by considering two different classes of perturbations. The first is associated with purely random discrete events. As we increase the modularization of the system, susceptibility to these random perturbations are more localized and contained. Conversely as we increase the modularization of the system susceptibility of the system to perturbations more systemic in nature grows. In the second class of perturbations second and third order couplings, including coupling through constraints, grows in scope and importance. We can see the behavior of each of these classes of perturbations in Figure 2. % MODULARIZATION PERTURBATION IMPACT SYSTEMIC PERTURBATIONS RANDOM PERTURBATIONS Figure 2 The symmetrical behavior shown in Figures 1 and 2 is not intended to indicate that these perturbation classes behave in similar manners and to the contrary we should expect them to materialize and deteriorate at different rates. The figures above represent a snapshot of the totality of the planned project and its execution approach at project initiation. They can provide guidance in optimizing modularity of both design and project execution to minimize the risks from various perturbations. It is important to recognize that perturbation risks, once a level of project modularization has been established, are not constant throughout the project execution period. This can be seen in Figure 3 where perturbation risk attenuates over time as various precedences are realized and successfully transcended.
  • 5. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 5 of 22 PERTURBATION RISK TIME PERTURBATION RISK DECLINES AS PRECEDENCES SATISFIED Figure 3 It may be possible to define and measure precedence risk on at least a first order basis by considering the number of paths through the project, where modules count as a singular activity in the overall project network. We can see this in very simple terms in Figure 4 where the precedence risk of each activity chain is the sum of the number of precedences embedded in the activity chain. In this example activity chain AB has a single precedence, A, which once completed reduces the number of precedences in the chain to zero. Alternately, looking at the three other activity chains, precedences are characterized as A plus C, and completing A would reduce the precedence risk to that associated with C.
  • 6. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 6 of 22 A B C D E F Precedence Risk (PR) Chain PR AB A AD A+C AE A+C AF A+C PRECEDENCE RISK Figure 4 TIME The above example treated each precedence equally in terms of its susceptibility to disruption. While modules act to limit the effects of perturbations on the overall system their aggregate system risk would reasonably be expected to be greater than one average activity in the non-modularized part of the system. Similarly all activities are not created equally in terms of their susceptibility to perturbations and as such it will be important to create a weighting system reflecting activity susceptibility to disruption. This may be accomplished through consideration of couplings discussed later in this paper. In the example above we treated A and C equally. If the preponderance of perturbation susceptibility lay with activity A, then completing activity A would remove a disproportionate amount of precedence risk. Conversely if the susceptibility to perturbation risk was much greater in C then completing A may not have significantly improved our risk posture with respect to disruption. In order to draw some insight into how to view susceptibility to perturbation risk, let us look at the special case of an activity that represents a completed module. If we can draw some insights around this special activity’s perturbation risk, we may be able to generalize for a broader set of activities.
  • 7. PM World Journal Complexity in Large Engineering & Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 7 of 22 Module Perturbation Risk Let’s begin by defining some properties of a module: Module Density (MD) – This may be considered to either represent the number of connections (physical or activities) within the module or expressed more fully as the number of perturbation “sites” which may better describe some of the coupling that exists within the module itself. Module Coupling (MC) – This represents the number of external module connections or couplings of all kinds. The greater MC the less isolated from the broader system the module is. These couplings include both incoming couplings (IC) and outgoing couplings (OC) as shown in Figure 5. The potential for effectively bi-directional coupling or feedback loops exist but have been treated as separate IC and OC components. Figure 5 MODULE IC –Incoming Coupling OC –Outgoing Coupling The disruption risk from a module to the overall system can be thought of as the sum of two behaviors. The first looks at the risk the module itself has to disruption. This can be thought of as being related to the overall internal susceptibility related to the Module Density, MD, and the number of incoming couplings, IC. The greater IC, the less insulated from disruption the module is. In this case effective modularity may be less than apparent modularity. The second behavior we must consider in looking at the module’s impact on overall system disruption risk is associated with the number and strength of the outgoing
  • 8. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 8 of 22 couplings, OC. Each OC feeds into one or more chains of subsequent activities which it acts as a precedence for. Thus the greater OC, the more potential paths for disruption from perturbations. This leads us to think carefully about where modules sit in the overall project and execution plans. We should seek to minimize forward disruption risk from disruptions to modules. Thus the overall Disruption (or Perturbation) risk associated with a given module can be described as: 𝑀𝑜𝑑𝑢𝑙𝑒 𝐷𝑖𝑠𝑟𝑢𝑝𝑡𝑖𝑜𝑛 𝑅𝑖𝑠𝑘 = 𝑓(𝑀𝐷: 𝐼𝐶) + 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝑂𝐶)) In plain English, the first term looks at the number of potential perturbation sites within the module and the number of incoming couplings. These incoming couplings represent potential disruption paths from more systemic type perturbations. The second term looks at the ability of a disruption that effects the module to propagate through the broader system, considering all possible outgoing couplings. This second term can be generalized to apply to any activity in the overall system network. Generalizing Activity Disruption Risk As shown above for the special case of modules, an activity’s contribution to overall perturbation risk can be described as 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝐶𝑜𝑛𝑛𝑒𝑐𝑡𝑒𝑑 𝑃𝑎𝑡ℎ𝑤𝑎𝑦)). Whether such pathways should be further weighted to consider the broader connectivity of individual activities such as was reflected in the special case of modules remains to be answered. Ignoring weighting we come to recognize that the more activities one activity is connected to, the greater the perturbation risk and thus the greater complexity of the system. This is analogous to what was determined in the IT industry and leads itself to calculation of cyclomatic complexity. In considering large complex projects in our industry it will be important to calculate not only apparent complexity, associated with direct couplings, but also actual complexity considering additional couplings which increase system exposure to systemic risks. I will touch on these later in this paper. Apparent Complexity of Large Complex Projects Apparent complexity looks only at direct couplings or connected components as described by graph theory. In Figure 6 we see one system representation consisting of 18 nodes, 22 couplings and 1 exit point (completed project).
  • 9. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 9 of 22 In an assessment of complexity analogous to one formulation of cyclomatic complexity, complexity would be assessed as Couplings – Nodes + Exit Pointsiii (first Betti number). In the Figure 6 example this would equate to 22-18 + 1 or 5. From a program perspective, illustrated in Figure 7, where O, P, Q each represent independent projects in the overall program we would have 17 Nodes, 19 Couplings and 3 exit points. Complexity would be described as 19-17 +3 or 5. The complexity of the challenge at hand is not affected by terminology when assessing apparent complexity. In Figure 8 we have removed one of the couplings reducing complexity to 4. Returning to Figure 7, we can define the number of independent pathways as 6 including: A-B-G-L-O A-C-D-H-L-O A-C-E-I-M-L-O A-C-E-I-M-P A-C-F-j-N-P A-C-F-K-Q Whereas in Figure 8, the five independent pathways consist of:
  • 10. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 10 of 22 A-B-G-L-O A-C-D-H-L-O A-C-E-I-M-P A-C-F-j-N-P A-C-F-K-Q By contrast the simplified system described in Figure 9 has only 5 Nodes and 4 Couplings and 1 Exit Point and a complexity of zero (4-5+1). In the complexity formulation just described the number of independent pathways is equal to apparent complexity plus 1.
  • 11. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 11 of 22 A B C D E F Figure 8 G H I J K L O M N Q P Apparent Complexity Eliminating a Coupling A B Figure 9 G L O Apparent Complexity Simple System Recognizing that the level of detail reflected in design or management program details can vary, affecting the magnitude of the overall complexity number, it may be useful to construct a complexity index to provide guidance across project phases and to compare alternative project execution strategies. This index can be described as: Complexity Index = 𝑪𝒐𝒖𝒑𝒍𝒊𝒏𝒈𝒔+𝑬𝒙𝒊𝒕 𝑷𝒐𝒊𝒏𝒕𝒔 𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝑵𝒐𝒅𝒆𝒔 Returning to the examples in the above Figures we would see Complexity Index values of:
  • 12. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 12 of 22 Complexity Index Figure 6 =23/18 = 1.28 Figure 7 =22/17 = 1.29 Figure 8 =19/17 = 1.18 Figure 9 =5/5 = 1.00 Clearly the simpler networks reflected in Figures 8 and 9 are shown. The slight difference between Figure 6 and 7 values associated with project vs program perspective requires further examination when considering apparent complexity. As we move towards considering actual complexity this difference may become less important. Actual Complexity Let’s turn our attention now to evaluating actual complexity. Actual complexity seeks to assess second and third order couplings which are not readily apparent from a review of the project execution plan and network. In effect the number of couplings grows while the number of discrete nodes remains unchanged, concomitantly, complexity grows. These hidden couplings are a characteristic of large complex programs and can result in severely impactful perturbations. There are several classes of second and third order coupling that may be considered. These include assumption couplingiv and perhaps more specifically a related form of coupling, namely, constraint coupling. I have previously written about constraint coupling and have included an example as Appendix 1. In this paper I will focus on illustrating its effect on complexity. Let’s consider one particular constraint which is availability of a particular skilled trade such as a welder. In Figure 10 we illustrate the potential coupling created by this skilled trade, recognizing that availability is both market and temporally driven. Activities G, H, and K all rely on this constrained resource. Detailed project planning may have been based on slightly staggering demand for this resource while assuming an overall pool availability. If the pool contracts activities G, H, and K may all be adversely effected. Figure 10 illustrates strong temporal coupling and as such changes in the overall welder pool will be particularly important. Activities can be taken to minimize the probability of such coupled constraints but if they occur they create strong perturbations and significant project disruption. They most certainly add to project complexity and as such must be modeled when considering actual complexity.
  • 13. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 13 of 22 Let’s consider both apparent and actual complexity in Figure 10. We previously saw that apparent complexity for this system was 4 (Figure 8) described by 18 Couplings – 17 Nodes + 3 Exit Points (O, P, Q). Actual complexity would consider these three added couplings to G, H, and K and the added “Welder” node which is also an exit point since the program itself acts to shape and size this constrained resource. This yields 21 Couplings – 18 Nodes + 4 Exit Points or a complexity value of 7. Actual complexity is greater than apparent complexity. In assessing actual complexity it is important to focus on the most impactful second and third order couplings. Similarly, the treatment of the added coupling node as also an exit point requires a judgement as to whether the program itself is a significant part of the overall constraint. In the Figure 10 example I assumed this to be the case and added one more Exit Point but in another setting the project demand may have represented a much smaller part of the overall demand for the constrained resource. Much in the same manner as we calculated an apparent complexity index of 1.18 (Figure 8) we can calculate an actual complexity index of 1.39 (Figure 10) here. The ratio of actual to apparent complexity provides an additional measure of project performance uncertainty as we manage based on the defined project execution network but face risks from out of network perturbations. This uncertainty measure related to complexity would have a value equal to 1.39/1.18 or Complexity Uncertainty = 1.18. The greater the uncertainty the greater the susceptibility to “white space” and Black Swan risk.
  • 14. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 14 of 22 Recap on Complexity Up to this point I have looked at the relationship between complexity and modularity of “systems”. I explored the linkage between modularity and complexity and began to consider ways of defining and measuring complexity at least on a relative basis. I drew several inferences and posited several new measures related to complexity in large complex projects. These include:  Modularization reduces susceptibility to random perturbations but increases susceptibility to systemic perturbations  Perturbation risk, the sum of the number of precedences in the activity chain, declines as precedences are satisfied  Module Density (MD) representing the number of connections (physical or activities) within the module or expressed more fully as the number of perturbation “sites” that exists within the module.  Module Coupling (MC) representing the number of external module connections or couplings of all kinds. The greater MC the less isolated from the broader system the module is. These couplings include both incoming couplings (IC) and outgoing couplings (OC).  𝑴𝒐𝒅𝒖𝒍𝒆 𝑫𝒊𝒔𝒓𝒖𝒑𝒕𝒊𝒐𝒏 𝑹𝒊𝒔𝒌 = 𝑓(𝑀𝐷: 𝐼𝐶) + 𝑓(∑𝐶ℎ𝑎𝑖𝑛 𝑅𝑖𝑠𝑘(𝑂𝐶))  Apparent Complexity = Couplings – Nodes + Exit Points  Complexity Index = 𝐶𝑜𝑢𝑝𝑙𝑖𝑛𝑔𝑠+𝐸𝑥𝑖𝑡 𝑃𝑜𝑖𝑛𝑡𝑠 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑁𝑜𝑑𝑒𝑠  Actual complexity seeks to assess second and third order couplings which are not readily apparent from a review of the project execution plan and network. In effect the number of couplings grows while the number of discrete nodes remains largely unchanged, concomitantly, complexity grows  Complexity Uncertainty - The ratio of actual to apparent complexity provides an additional measure of project performance uncertainty as we manage based on the defined project execution network but face risks from out of network perturbations. Several areas warrant future development including development of a simplified weighting system for activity’s susceptibility to perturbation risk and modeling of modules incorporated into a larger activity chain. Here the work above on Module Disruption Risk represents a starting point. Classes of couplings are discussed in the next section and warrant further development but it is important to note that these flows are largely from external or stakeholder sources, represent the biggest source of incremental complexity and their disruption effect is consistent with observation.
  • 15. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 15 of 22 Classes of Coupling Up to this point I have looked at the relationship between complexity and modularity of “systems”. I noted that Nature’s complex systems reward modularity and its ability to limit the effects of perturbations while at the same time recognizing that excessive modularity exposes the system negatively to the effects of even stronger, more systemic perturbations. I further explored this linkage between modularity and complexity as well as considered ways of defining and measuring both apparent and actual complexity at least on a relative basis. A complexity index was suggested and the subject of coupling introduced. It was suggested that coupling in large complex projects could be classified. This section suggests one possible classification system, recognizes the potential interaction between classes and provides an initial ranking of these classes with respect to their potential to broadly disrupt planned execution of the project. Coupling refers to the interdependencies between activities where modules may be considered as a special activity type. Nine classes of coupling in large complex projects have been defined as follows: Control Coupling – This is represented by the normal control flows that guide project execution and work activities; those arrows on the Gantt chart or WBS is you will. The control flow arrows are not dimensionless and a clear and comprehensive understanding of the data, information and interfaces implicit in the control flow must be made explicit for effective management. Data dictionaries and structures must be coherent and comprehensive to achieve effective control flows. Additionally, Strategic Business Objectives (SBOs) and associated kpi’s must cascade throughout the control network. Co-dependent Coupling – Interdependency between activities are such that a change in the data, outputs or execution of one activity necessitates a change in the second. For example, excavation and dewatering activities are linked where a change in dewatering rates or volumes may influence excavation or ground stabilization and improvement activities. Assumption Coupling – Multiple activities share global assumptions, data or other values. A change in assumptions, including through assumption migration, impacts multiple, otherwise disparate, activities. Examples could include assumed labor
  • 16. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 16 of 22 productivity improvement through the project; customs clearing times; or client approval cycles. Constraint Coupling – Also may be considered as shared resource coupling, where temporal or more systemic constraints may occur in a resource common to execution of multiple activities. Competition for resources with fixed supply rates (at least in the short term) is exacerbated by ex-project changes in demand. External Coupling – Multiple activities require externally imposed inputs, controlled resources, approvals or other interfaces. Permits and inspections would be an example of external couplings. Changes in the externally imposed requirements may impact multiple activities. Stakeholder Coupling – Different than External Coupling since flows from these couplings are not imposed but carry the risk of being less manageable and potentially more consequential. Stakeholder coupling impacts both activities as well as the connecting flows. Message Coupling – Messages, generally from management centers, are transmitted formally or informally throughout the project execution network, including to portions for which the message was never intended. This may cause unintended actions and consequences. Temporal Coupling – Simultaneous undertaking of two or more activities. Risk arises as a result of any temporally based constraint coupling. Multiple projects, carefully staged to spread out welder demand fail when project schedule slippages push demand into the same time frame. Uncoupling – Describes the lack of apparent couplings of any kind between modules. Module to module coupling may occur as a result of any of the classes of coupling described above. The greater the coupling between activities, the greater the complexity and the likelihood of propagating disruptions. It is likely the greater the number of classes of couplings present the greater the management challenge and the greater the risk of disruption. Additionally, classes of couplings that tend to forward changes from other classes are more disruptive. Table 1 shows the classes that a given class may impact. Table 2 synthesizes these relationships to define those classes of couplings likely to most contribute to project disruption. Here we note that stakeholder type couplings are likely to be the most impactful from an overall disruption perspective. Instability measures reflect high forward coupling by particular classes of couplings. In effect these are couplings which themselves may be susceptible to the effects of other couplings and more likely to translate those effects and pass them on. The ratio of stability to instability (I/O)
  • 17. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 17 of 22 provides a relative measure of the contribution to disruption from various classes of couplings. Together with the Complexity Index and Complexity Uncertainty previously described, I/O provides another measure of the contribution of coupling to disruption. Cohesion, by contrast, looks at the range of actions that occur within a given activity and makes a judgement to how related they are. For example if a given activity required painting all east facing walls blue and changing washers in all 4” valves we would describe its cohesion as low. By contrast an activity that required welding flanges and making all connections in a particular fluid system would be viewed as having higher cohesion. By definition modules as previously described should be expected to have high cohesion. In my book, Theory of Management of Large Complex Projects, I suggest three areas where current project management theory falls short at scale. In simple terms I suggest the need for stronger foundations; a focus on flows, the arrows, not just the activities; and recognize a need for a strengthened approach to stakeholder engagement. This work on complexity is intended to begin to address the areas this new theory highlights and to suggest another foundational activity to strengthen project performance through its increased focus on flows and couplings, including most notably, stakeholder coupling. Assessment of complexity is intended to help evaluate alternative execution Control Co-dependent Assumption Constraint External Stakeholder Message Temporal Uncoupling Control x x x x x Co-dependent x x x Assumption x x x x x x x Constraint x x x x x x External x x x x x x x x Stakeholder x x x x x x x x x Message x x x x x x x Temporal x x x x x x x x x Uncoupling x x x x x SourceofInputs Affected Classes Table 1 Relationships Between Classes of Couplings # Incoming # Outgoing Total Instability Stability I/O Least to Most Impactful (I) (O) Outgoing/Total Incoming/Total Control 9 5 14 0.36 0.64 1.80 2 Co-dependent 8 3 11 0.27 0.73 2.67 1 Assumption 6 7 13 0.54 0.46 0.86 6 Constraint 6 6 12 0.50 0.50 1.00 5 External 4 8 12 0.67 0.33 0.50 8 Stakeholder 4 9 13 0.69 0.31 0.44 9 Message 7 7 14 0.50 0.50 1.00 4 Temporal 7 9 16 0.56 0.44 0.78 7 Uncoupling 7 5 12 0.42 0.58 1.40 3 Ranking of Coupling Class Contribution to Disruption Table 2
  • 18. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 18 of 22 approaches and perhaps provide guidance on the confidence we should have in planned or predicted results. Improving large complex project execution remains a journey which I feel compelled to continue. Appendix 1 Constraint Coupling Example Today, constraint identification is based on the original execution plan and rarely updated. But, original program execution plans change and even impacts off the critical path can have significant impacts on overall program performance because of constraint coupling. Let’s look at a simple example for a four project program:  Project 1 is an enabling project, not on the critical path with a 12 month duration. Its sequencing does not lend itself to acceleration.  Project 2 is interdependent with Project 1 and cannot be initiated until Project 1 is substantively complete. The baseline plan shows it not starting until after Project 1 complete but it could start 2 months earlier when Project 1 substantively complete.  Project 3 represents the critical path effort and project labor is constrained at 600 as a condition of permitting.
  • 19. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 19 of 22  Project 4 is seasonal work which cannot be rescheduled but is generally independent of other project linkages except constraints related to overall labor availability. Total labor available to program is capped at 1200 as labor is in short supply and multi- owner labor agreements executed to eliminate poaching and an uncontrolled wage spiral. This is what the baseline program manpower loading looked like. Like all programs, something changed in Project 1 that causes suspension of construction and other activities at the end of month 4. The hiatus lasts for 2 months; Project 1 not on critical path and the PM has indicated he can control costs so no cost increase; no increased labor requirement; but project schedule is 2 months longer. PM for Project 2 indicates he can accommodate 2 month slippage in Project 1 since precedent work would be completed in time for him to begin. 0 200 400 600 800 1000 1200 Manpower 1 3 5 7 9 11 13 15 17 19 21 23 Time Base Case Manpower Project 4 Project 3 Project 2 Project 1
  • 20. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 20 of 22 From a “direct” project interface perspective neither Projects 3 nor 4 were dependent on Project 1. The PM for project 1 submits a new manpower forecast and the other 3 PMs continue without updating their forecasts since no direct impact. Initial look shows the overall critical path end date maintained but manpower loading at the program level is in excess of the overall 1200 constraint placed on the program. Without such a programmatic viewpoint it may not be self evident that the change proposed for Project 1 would cause the program to violate one of its constraints. Attention now turns to executing the changed program while still meeting both the overall program 1200 person constraint and Project 3’s 600 person constraint. Program completion is delayed by 2 months despite the fact that Project 1 is not on the critical path. 0 200 400 600 800 1000 1200 1400 1600 1800 Manpower 1 3 5 7 9 11 13 15 17 19 21 23 Time Unconstrained Manpower Loading Project 4 Project 3 Project 2 Project 1
  • 21. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 21 of 22 Granted a simple example but others exist with respect to limited supply of key trades, such as welding; limited camp accommodations; constrained import facility capacity and so on. Each of those an example from a recent giga program. References: i. The importance of being modular; Marta Sales-Pardo; Science Vol 357, Issue 6347 ii. Theory of Management of Large Complex Projects; Bob Prieto; CMAA iii. Cyclomatic complexity often states this as 2*exit points iv. Management of Assumption Infatuation in Large Complex Projects; PM World Journal; Volume V, Issue IV – April 2016 0 200 400 600 800 1000 1200 Manpower 1 4 7 10 13 16 19 22 25 Time Manpower Loading Reflecting Labor Constraints Project 4 Revised Project 3 Loading Project 2 Project 1
  • 22. PM World Journal Complexity in Large Engineering Vol. VI, Issue XI – November 2017 Construction Programs www.pmworldjournal.net Featured Paper by Bob Prieto © 2017 Bob Prieto www.pmworldlibrary.net Page 22 of 22 About the Author Bob Prieto Chairman CEO Strategic Program Management LLC Jupiter, Florida, USA Bob Prieto is a senior executive effective in shaping and executing business strategy and a recognized leader within the infrastructure, engineering and construction industries. Currently Bob heads his own management consulting practice, Strategic Program Management LLC. He previously served as a senior vice president of Fluor, one of the largest engineering and construction companies in the world. He focuses on the development and delivery of large, complex projects worldwide and consults with owners across all market sectors in the development of programmatic delivery strategies. He is author of eight books including “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry”, “Application of Life Cycle Analysis in the Capital Assets Industry”, “Capital Efficiency: Pull All the Levers” and, most recently, “Theory of Management of Large Complex Projects” published by the Construction Management Association of America (CMAA) as well as over 600 other papers and presentations. Bob is a non-executive director of Cardno (ASX) and an Independent Member of the Shareholder Committee of Mott MacDonald. He serves on the Millennium Challenge Corporation Advisory Board and a member of the ASCE Industry Leaders Council, National Academy of Construction, a Fellow of the Construction Management Association of America and member of several university departmental and campus advisory boards. Bob served until 2006 as a U.S. presidential appointee to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth. He had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB). Bob can be contacted at rpstrategic@comcast.net.