SlideShare a Scribd company logo
1 of 7
Download to read offline
Datasheet >                                                                                                      june
                                                                                                                 2006




              compaction of Concrete




              SCOPE                                                       Compaction of concrete is, therefore, a
              This data sheet discusses the benefits of compaction   two-stage process Figure 1. First the aggregate
  >




              of concrete and provides information on the            particles are set in motion and slump to fill the
              techniques for undertaking the process on site.        form giving a level top surface. In the second stage,
                                                                     entrapped air is expelled.
              INTRODUCTION                                                It is important to recognise the two stages in
              Compaction is the process which expels entrapped       the compaction process because, with vibration,
              air from freshly placed concrete and packs the         initial consolidation of the concrete can often be
              aggregate particles together so as to increase the     achieved relatively quickly. The concrete liquefies
              density of concrete. It increases significantly the    and the surface levels, giving the impression that
              ultimate strength of concrete and enhances the         the concrete is compacted. Entrapped air takes a
              bond with reinforcement. It also increases the         little longer to rise to the surface. Compaction must
              abrasion resistance and general durability of the      therefore be prolonged until this is accomplished,
              concrete, decreases the permeability and helps to      ie until air bubbles no longer appear on the surface.
              minimise its shrinkage-and-creep characteristics.
                                                                     >




                  Proper compaction also ensures that the
              formwork is completely filled – ie there are no
              pockets of honeycombed material – and that the
              required finish is obtained on vertical surfaces.
                  When first placed in the form, normal concretes,      Compaction is the process
              excluding those with very low or very high slumps,
              will contain between 5% and 20% by volume of              which expels entrapped air from
              entrapped air. The aggregate particles, although
              coated with mortar, tend to arch against one              freshly placed concrete and
              another and are prevented from slumping or
              consolidating by internal friction.                       packs the aggregate particles
                                                                        together so as to increase the
                                                                        density of concrete.
STAGE 1                           STAGE 2




                   PROCESS: Liquefaction of the      PROCESS: The expulsion of            METHODS AND EQUIPMENT
                            concrete which                    entrapped air               General
                            allows it to slump
                            and fill the form                                             Two types of vibrators are common on building
                   TIME:      3 to 5 seconds         TIME:         7 to 15 seconds        sites – immersion vibrators and surface vibrators.
                                                                                          Each has its own specific application, although on
                    TOTAL TIME (for both stages of the process): 10 to 20 seconds
                                                                                          floors and other flatwork it is not uncommon for
                  Figure 1: The process of compaction                                     one to complement the other. A third type, form
                                                                                          vibrators, are commonly used in precast work, and
                                                                                          sometimes on building sites.
                 RELATIVE STRENGTH (%)
                 100                                                                      Immersion Vibrators
                                                                                          Frequently referred to as ‘poker’ or ‘needle ’
                                                                                          vibrators, immersion vibrators consist essentially
                  80
                                                                                          of a tubular housing which contains a rotating
                                                                                          eccentric weight. The out-of-balance rotating
                  60
                                                                                          weight causes the casing to vibrate and, when
                                                                                          immersed in concrete, the concrete itself.
                  40                                                                      Depending on the diameter of the casing or head,
                                                                                          and on the frequency and the amplitude of the
                  20                                                                      vibration, an immersion vibrator may have a radius
                                                                                          of action between 100 and 600 mm Table 1.
                   0
                                                                                              Immersion vibrators may be driven by:
                       0         5        10        15        20           25        30   n	 a flexible shaft connected to a petrol, diesel, or
                       AIR VOIDS (%)                                                          electric motor;
                                                                                          n	 an electric motor situated within the tubular

                  Figure 2: Loss of strength through incomplete                               casing;
                  compaction                                                              n	 compressed air.

                                                                                              The effectiveness of an immersion vibrator is
                                                                                          dependent on its frequency and amplitude, the
                                                                                          latter being dependent on the size of the head, the
                  EFFECT ON HARDENED PROPERTIES                                           eccentric moment and the head weight – the larger
                  As may be seen from Figure 2, the effect of                             the head, the larger the amplitude.
                  compaction on compressive strength is dramatic.                             Table 1 summarises the characteristics and
                  For example, the strength of concrete containing                        applications of immersion vibrators. As a general
                  10% of entrapped air (air voids) may be as little as                    rule, the radius of action of a given vibrator not
                  50% that of the concrete when fully compacted.                          only increases with the workability of the concrete
                       Permeability may be similarly affected since                       (higher slump), but also with the diameter of the
                  compaction, in addition to expelling entrapped                          head. A good general rule is to use as large a
                  air, promotes a more even distribution of pores                         diameter head as practicable, bearing in mind that
                  within the concrete, causing them to become                             vibrators with diameters in excess of 100 mm will
                  discontinuous. This reduces the permeability of the                     probably require two men to handle them. Below
                  concrete and hence improves its durability.                             this diameter, the appropriate head size will be
                      The abrasion resistance of concrete surfaces                        dependent on the width of the formwork, the
                  is normally improved by adequate compaction.                            spacing of the reinforcement and the cover to it.
                  However, excessive vibration, or excessive working                          Immersion vibrators should be inserted
                  of the surface, can cause an excessive amount of                        vertically into concrete, as quickly as possible, and
                  mortar (and moisture) to collect at the surface,                        then held stationary until air bubbles cease to rise
                  thereby reducing its potential abrasion resistance.                     to the surface, usually in about 15–20 seconds
                  In flatwork therefore, a careful balance is required                    Figure 3. The vibrator should then be slowly
                  to expel entrapped air without bringing excessive                       withdrawn and reinserted vertically in a fresh
                  amounts of mortar to the surface of the concrete.                       position adjacent to the first. These movements
                                                                                          should be repeated in a regular pattern until all the
                                                                                          concrete has been compacted Figure 4. Random
                                                                                          insertions are likely to leave areas of the concrete
                                                                                          uncompacted. The vibrator should not be used to
                                                                                          cause concrete to flow horizontally in the forms, as

Page  of 7  compaction of Concrete
Table 1 Characteristics and applications of immersion vibrators

      Diameter	     Recommended	       Average	       Radius of	     Rate of concrete
      of head	      frequency1	        amplitude 2	   action 3,5	    placement 4,5
      (mm)	         (Hz)	              (mm)	          (mm)	          (m3/h per vibrator)	   Application

      	 20–40	      150–250	           0.4–0.8	       75–150	         1–4	                  High slump concrete in very thin
                                                                                            members and confined places.
                                                                                            May be used to supplement larger
                                                                                            vibrators where reinforcement or
                                                                                            ducts cause congestion in forms.

      	 30–65	      140–210	           0.5–1.0	       125–250	        2–8	                  Concrete of 100–150 mm slump in
                                                                                            thin walls, columns, beams,
                                                                                            precast piles, thin slabs, and along
                                                                                            construction joints. May be used
                                                                                            to supplement larger vibrators in
                                                                                            confined areas.

      	 50–90	      130–200	           0.6–1.3	       175–350	        6–20	                 Concrete (less than 80 mm slump)
                                                                                            in normal construction, eg walls,
                                                                                            floors, beams and columns in
                                                                                            buildings.

      	75–150	      120–180	           0.8–1.5	       300–500	       11–31	Mass and structural concrete of
                                                                            0 to 50 mm slump deposited in
                                                                            quantities up to 3m3 in relatively
                                                                            open forms of heavy construction.

      1
      	 25–175	      90–140	           1.0–2.0	       400–600	       19–38	Mass concrete in gravity dams,
                                                                            large piers, massive walls, etc.

      Adapted from Table 5.1 ACI Committee Report: Guide for Consolidation of Concrete 309R-05 ACI Manual of Concrete
      Practice 2006 Part 2.

      1	 While vibrator is operating in concrete.
      2	 Computed or measured. This is peak amplitude (half the peak-to-peak value), operating in air. Reduced by 15–20%
         when operating in concrete.
      3	 Distance over which concrete is fully consolidated.
      4	 Assumes insertion spacing 1½ times the radius of action, and that vibrator operates two-thirds of time concrete is

         being placed.
      5	 Reflects not only the capability of the vibrator but also differences in workability of the mix, degree of de-aeration

         desired, and other conditions experienced in construction.




Page  of 7  compaction of Concrete
Radius of action      Immersion       SQUARE PATTERN
                                                                                                       vibrator
                                                                                                                       D1 = e √2
                                                                                      D1
                                                                                                                       See Table 1 for
                                                                                                                       values of e
                                                                             e
                                                                                                                       For range of immersion
                                                                                                           D1          vibrators used in
                                                                                                                       normal construction
                                                                                                                       e = 180 to 360 mm
                                                                                                                       D1 = 255 to 500 mm


                                                                                                                       OFFSET PATTERN
                                                                                         D2
                                                                                                                       D2 = e √3
                                                                             e                                         See Table 1 for
                                                                                                                       values of e
                                                                                                            D2
                  Figure 3: Use of an immersion vibrator
                                                                                                                       For range of immersion
                                                                                                                       vibrators used in
                                                                                                                       normal construction
                  this can lead to segregation. In addition, the vibrator                                              e = 180 to 360 mm
                  should not be dragged through the concrete as this                D2
                                                                                                                       D2 = 300 to 620 mm
                  leads to inadequate compaction and increases the                  2
                  risk of segregation.
                      In deep sections such as walls, footings and          Figure 4: Alternative patterns for use of immersion
                  large columns, the concrete should be placed in           vibrators
                  layers about 300 mm thick. The vibrator should
                  penetrate about 150 mm into the previous layer of
                  fresh concrete to meld the two layers together and                                                Place concrete
                  avoid ‘cold-pour’ lines on the finished surface. In                                               a little away
                                                                                                                    from the corner
                  small columns where concreting is continuous, the
                  vibrator may be slowly raised as the concrete is
                  placed. Care should be taken to avoid trapping air
                  at the form face and a means of lighting the interior                                             With immersion vibrator,
                  of the form while the concrete is being placed and                                                move concrete into the
                  vibrated should be considered.                                                                    corner and up the form face
                      The vibrator should not be allowed to touch the
                  forms as this can cause ‘burn’ marks which will           Figure 5: Compaction at stop ends and in inclined
                  be reflected on the finished surface. Generally, the      forms
                  vibrator should be kept about 50 mm clear of the
                  form face. Similarly, the vibrator should not be held
                                                                                               Void Form   First layer placed and compacted.
                  against the reinforcement as this may cause its
                                                                                                           Second and subsequent placements
                  displacement.                                                                            made from one side only.
                      Stop-ends, joints and, especially, inclined forms                                    Concrete induced to flow under
                  are prone to trapping air. To minimise this tendency,                                    the void former by action of
                                                                                                           immersion vibrator
                  the best technique is to place the concrete close
                  to, but away from the side of the form and insert
                  the immersion vibrator close to the leading edge                             Void Form
                  of the concrete, forcing it to properly fill the corner                                  When concrete reaches the same
                  Figure 5.                                                                                level on each side of the former,
                      Void-formers are also prone to trapping air on                                       concrete placement and compaction
                                                                                                           can proceed normally
                  their undersides if concrete is placed from both
                  sides and then compacted. Concrete should be
                  placed at one side and, maintaining a head, vibrated                                     Similar technique to that above,
                  until it appears at the other side. (Note that the                                       used for encasing steel beams.
                  void-former will need to be fixed so as to resist the                                    Concrete placed and compacted
                  pressure of the plastic concrete.)                                                       from one side until equalised
                                                                                                           either side of beam
                      When the top of the concrete is fully visible from
                  above, then placing can continue normally Figure 6.
                  This technique is used in other similar situations,
                  such as encasing steel beams.                             Figure 6: Compaction around void formers and
                                                                            encased members



Page  of 7  compaction of Concrete
Surface vibrator
                                                                           Edge                                                       Edge
                                                                           Form                                                       Form

                  Figure 7: Typical surface vibrator                                  Depth of            Depth of              Immersion
                                                                                      compaction          compaction            vibrators
                                                                                      decreases           (maximum              needed to
                  Surface Vibrators                                                   in vicinity of      200 mm)               supplement
                  Surface vibrators are applied to the top surface of                 edge forms                                compaction
                  concrete and act downwards from there. They are                                                               here
                  very useful for compacting slabs, industrial floors,
                  road pavements, and similar flat surfaces. They          Figure 8: Degree of compaction varies across width
                  also aid in levelling and finishing the surface.         when surface vibrators are used
                      There are a number of types of surface vibrators
                  including vibrating-roller screeds, vibrating-beam
                  screeds and pan-type vibrators which are used
                  mainly on very specialised equipment such as road                                                    Screed
                  paving plant. The most common type is the single or
                  double vibrating-beam screed.
                      A vibrating-beam screed consists of either one                                                   Height of required
                  or two beams, made from aluminium, steel or                                                          surcharge
                  timber, to which is attached a form of vibrating unit                                                Packing to screed
                  to allow the beams to impart adequate vibration to
                                                                                                                       Edge form
                  the concrete. This may be a single unit, mounted
                  centrally, or may consist of a series of eccentric
                  weights on a shaft driven from a motor on one end
                  and supported on a trussed frame. In general, the
                  centrally-mounted units have a maximum span of
                  about 6 m, but the trussed units may span up to          Figure 9: Method for providing a surchage to the
                  20 m. The small units are normally pulled forward        uncompacted concrete
                  by hand whereas the larger units may be winched,
                  towed or be self-propelled Figure 7.
                      The intensity of vibration, and hence the amount         In using vibrating-beam screeds to compact
                  of compaction achieved, decreases with depth             concrete, the uncompacted concrete should first
                  because surface vibrators act from the top down.         be roughly levelled to above the final level required,
                  Therefore, the slab thickness for which compaction       ie a surcharge should be provided to compensate
                  by surface vibrators is effective will vary (from        for the reduction in slab thickness caused by
                  100 to 200 mm) depending on the size and operation       the compaction of the concrete. The amount of
                  of the unit used. With slabs 200 mm or over in           surcharge should be such that, when the beam is
                  thickness, immersion vibrators should be used to         moved forward, a consistent ‘roll’ of concrete is
                  supplement the surface vibrations                        maintained ahead of the beam. The surcharge may
                      With centrally-mounted vibration units, the          be provided evenly on slabs of up to 4 m in width
                  degree of compaction achieved may vary across the        by the use of a ‘surcharge-beam’. This is simply a
                  width of the beam. When they rest on edge forms, the     straightedge, usually made of timber, with small
                  latter may tend to damp the vibration at the extrem-     packing pieces on the ends which ‘ride’ on the edge
                  ities of the beam Figure 8. It is generally desirable,   forms Figure 9.
                  therefore, to supplement vibrating-beam compaction           The surcharge beam is pulled over the
                  by using immersion vibrators alongside edge forms.       uncompacted concrete without any attempt being
                      The effectiveness of vibration, and hence degree     made to compact or finish it. The sole purpose is to
                  of compaction, increases with an increase in the         provide an even surcharge. The correct thickness
                  beam weight, the amplitude and the frequency,            for the packing pieces (and hence the surcharge)
                  and decreases with an increase in forward speed.         is soon found by observing the ‘roll’ of concrete.
                  Forward speed is critical in the correct use of          Providing an even surcharge has the advantage that
                  vibrating-beam screeds and should be limited to          one pass of the vibrating-beam screed is generally
                  between 0.5 and 1.0 m/min. The lower speed should        sufficient to compact, level and provide the initial
                  be used for thicker slabs and where reinforcement        finish. This is preferable to multiple passes, as a
                  is close to the top face. A second, faster pass may      slower single pass is more effective in compacting
                  be made as an aid to finishing.                          the concrete than two faster passes.

Page  of 7  compaction of Concrete
Form Vibrators                                                Situations in which revibration may be beneficial
                  Form vibrators (normally called ‘external’ vibrators)     include:
                  are useful with complicated members or where              n	 To bond layers of concrete into those preceding

                  the reinforcement is highly congested. They are               them. In elements such as walls, deep
                  clamped to the outside of the formwork and vibrate            beams and columns, which are being filled
                  it, thus compacting the concrete. The formwork will           in successive layers, the vibrator should just
                  need to be specifically designed to resist the forces         penetrate the previous layer.
                  imposed on it.                                            n	 To close plastic shrinkage and settlement

                                                                                cracks.
                  Under-Vibration and Over-Vibration                        	 These may form within the first few hours of
                  Normal-weight concretes that are well proportioned            concrete being placed and may be able to be
                  are not readily susceptible to defects caused by              closed by vibration, providing it is done early and
                  over-vibration. These result from segregation and             prior to the hardening of the concrete. However,
                  are characterised by an excessive thickness of                a reasonable level of energy input is required
                  mortar at the surface of the concrete. The surface            since mere reworking of the surface, may
                  may also have a frothy appearance. Over-vibration             simply close the cracks superficially. They may
                  may cause problems when grossly oversized                     then reopen as the concrete dries out.
                  equipment is operated for an excessive length of          n	 To improve the surface finish at the tops of

                  time, but is more likely to cause problems with               columns and walls by expelling the air which
                  poorly-proportioned mixes or those to which                   tends to congregate there as the concrete
                  excessive amounts of water have been added.                   settles in the formwork.
                       When signs of over-vibration are detected, the       n	 To improve the wear resistance of floors.

                  initial reaction may be to reduce the amount of           	 Revibration, coupled with a trowelling action,
                  vibration. The most appropriate solution may be to            helps to create a burnished wear-resistant
                  investigate if suitable changes to mix design are             surface layer.
                  warranted.
                       Under-vibration is far more common than              FURTHER INFORMATION
                  over‑vibration and, when it occurs, can cause             Further information on good concreting practices
                  serious defects. Invariably, the concrete is              can be downloaded from the Cement Concrete
                  incompletely compacted which reduces its strength          Aggregates Australia website at
                  (see Effect on Hardened Properties above), its            www.concrete.net.au.
                  durability and will possibly affect its surface finish.
                       Despite this, many specifications contain a
                  caution against the over-vibration – and even lay
                  down a maximum length of time for vibration –
                  whilst neglecting totally the question of
                  under‑vibration.

                  Revibration
                  Revibration of concrete is the intentional systematic
                  vibration of concrete which has been compacted
                  some time earlier. It should not be confused with
                  the double vibration which sometimes occurs
                  with the haphazard use of immersion vibrators or
                  multiple passes of a vibrating-beam screed.
                      Whilst it is generally agreed that revibration of
                  concrete can be beneficial to its strength, its bond
                  to reinforcement and its surface finish, the practice
                  is not widely used, partly due to the difficulty of
                  knowing just how late it can be applied. A good rule
                  of thumb is that revibration may be used as long
                  as the vibrator is capable of liquefying the concrete
                  and sinking into it under its own weight.




Page  of 7  compaction of Concrete
june                                   CCAA OFFICES
                                       SYDNEY OFFICE:

2006                                   Level 6, 504 Pacific Highway
                                       St Leonards NSW Australia 2065
                                       POSTAL ADDRESS:
                                       Locked Bag 2010
                                       St Leonards NSW 1590
                                       TELEPHONE: (61 2) 9437 9711
                                       FACSIMILE: (61 2) 9437 9470

                                       BRISBANE OFFICE:
                                       Level 14, IBM Building
                                       348 Edward Street
                                       Brisbane QLD 4000
                                       TELEPHONE: (61 7) 3831 3288
                                       FACSIMILE: (61 7) 3839 6005

                                       MELBOURNE OFFICE:
                                       2nd Floor, 1 Hobson Street
                                       South Yarra VIC 3141
                                       TELEPHONE: (61 3) 9825 0200
                                       FACSIMILE: (61 3) 9825 0222

                                       PERTH OFFICE:
                                       45 Ventnor Avenue
                                       West Perth WA 6005
                                       TELEPHONE: (61 8) 9389 4452
                                       FACSIMILE: (61 8) 9389 4451

                                       ADELAIDE OFFICE:
                                       Greenhill Executive Suites
                                       213 Greenhill Road
                                       Eastwood SA 5063
                                       POSTAL ADDRESS:
                                       PO Box 229
                                       Fullarton SA 5063
                                       TELEPHONE: (61 8) 8274 3758
                                       FACSIMILE: (61 8) 8373 7210
                                       EXTRACTIVE INDUSTRIES OFFICE
                                       PO Box 243
                                       Henley Beach SA 5022
                                       TELEPHONE: (61 8) 8353 8151
                                       FACSIMILE: (61 8) 8353 8151

                                       TASMANIAN OFFICE:
                                       EXTRACTIVE INDUSTRIES OFFICE
                                       PO Box 246
                                       Sheffield TAS 7306
                                       TELEPHONE: (61 3) 6491 2529
                                       FACSIMILE: (61 3) 6491 2529

                                       WEBSITE: www.concrete.net.au

                                       EMAIL: info@ccaa.com.au

                                       Layout: Helen Rix Design

                                       Disclaimer: Cement Concrete  Aggregates
                                       Australia is a not for profit organisation sponsored
                                       by the cement concrete and aggregate industries
                                       in Australia to provide information on the many
                                       uses of cement and concrete. This publication
                                       is produced by CCAA for that purpose. Since
                                       the information provided is intended for general
                                       guidance only and in no way replaces the services
                                       of professional consultants on particular projects, no
                                       legal liability can be accepted by CCAA for its use.

                                       CCAA respects your privacy. Your details have
                                       been collected to provide you with information on
                                       our activities, publications and services. From time
                                       to time your details may be made available to third
                                       party organisations who comply with the Privacy
                                       Act such as affiliated associations, sponsors of
                                       events and other reputable organisations whose
                                       services we think you may find of interest. If you do
                                       not wish to receive information from CCAA or wish
                                       to be taken off the database please write to the
                                       Privacy Officer, CCAA, Locked Bag 2010,
                                       St Leonards, NSW, 1590




Page  of 7  compaction of Concrete

More Related Content

What's hot

Compaction in different type of structure
Compaction  in different type of structure Compaction  in different type of structure
Compaction in different type of structure Dhaval Jalalpara
 
construction equipment(VIBRATOR)
construction equipment(VIBRATOR)construction equipment(VIBRATOR)
construction equipment(VIBRATOR)vikas verma
 
Hardened Concrete
Hardened ConcreteHardened Concrete
Hardened ConcreteDeviprasad
 
Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pileRizwan Khurram
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) laxman singh
 
Production of concrete
Production of concreteProduction of concrete
Production of concreteDarshil Vekaria
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and gunitingVipul Kerni
 
TYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETETYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETEJASHU JASWANTH
 
Fresh concrete
Fresh concreteFresh concrete
Fresh concretelaxman singh
 
A presentation on concrete-Concrete Technology
A presentation on concrete-Concrete TechnologyA presentation on concrete-Concrete Technology
A presentation on concrete-Concrete TechnologyAbdul Majid
 
Construction joints
Construction jointsConstruction joints
Construction jointsDaniia Roxio
 
Lecture 5, concrete-hmm
Lecture 5, concrete-hmmLecture 5, concrete-hmm
Lecture 5, concrete-hmmDr. H.M.A. Mahzuz
 
Concrete basicss for gem
Concrete basicss for gemConcrete basicss for gem
Concrete basicss for gemAbdel Zayed
 
Concrete Compressive Strength
Concrete Compressive Strength Concrete Compressive Strength
Concrete Compressive Strength Mahmoud Hassan
 
Fresh concrete for civil engineering
Fresh concrete for civil engineeringFresh concrete for civil engineering
Fresh concrete for civil engineeringlaxman singh
 

What's hot (20)

Compaction in different type of structure
Compaction  in different type of structure Compaction  in different type of structure
Compaction in different type of structure
 
Vibrators
VibratorsVibrators
Vibrators
 
construction equipment(VIBRATOR)
construction equipment(VIBRATOR)construction equipment(VIBRATOR)
construction equipment(VIBRATOR)
 
Hardened Concrete
Hardened ConcreteHardened Concrete
Hardened Concrete
 
Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pile
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering)
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 
Control joints
Control jointsControl joints
Control joints
 
TYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETETYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETE
 
Fresh concrete
Fresh concreteFresh concrete
Fresh concrete
 
A presentation on concrete-Concrete Technology
A presentation on concrete-Concrete TechnologyA presentation on concrete-Concrete Technology
A presentation on concrete-Concrete Technology
 
Concrete
ConcreteConcrete
Concrete
 
Construction joints
Construction jointsConstruction joints
Construction joints
 
Fresh concrete
Fresh concreteFresh concrete
Fresh concrete
 
Lecture 5, concrete-hmm
Lecture 5, concrete-hmmLecture 5, concrete-hmm
Lecture 5, concrete-hmm
 
Concrete basicss for gem
Concrete basicss for gemConcrete basicss for gem
Concrete basicss for gem
 
Fresh Concrete
Fresh ConcreteFresh Concrete
Fresh Concrete
 
Concrete Compressive Strength
Concrete Compressive Strength Concrete Compressive Strength
Concrete Compressive Strength
 
Fresh concrete for civil engineering
Fresh concrete for civil engineeringFresh concrete for civil engineering
Fresh concrete for civil engineering
 

Viewers also liked

Concrete Compaction
Concrete CompactionConcrete Compaction
Concrete CompactionRajesh Jindal
 
CDS Concrete Curing 2010
CDS Concrete Curing 2010CDS Concrete Curing 2010
CDS Concrete Curing 2010Andrew Hall
 
Making and curing concrete test specimens in the
Making and curing concrete test specimens in theMaking and curing concrete test specimens in the
Making and curing concrete test specimens in theFarrukh Khan
 
Curing Concrete Pavement
Curing Concrete PavementCuring Concrete Pavement
Curing Concrete PavementFritz Lejarso
 
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT NuzvidCuring & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvidhema3366
 
Heat of Hydration in Mass Concrete
Heat of Hydration in Mass ConcreteHeat of Hydration in Mass Concrete
Heat of Hydration in Mass ConcreteKhaldoon Slaiai
 
Batching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - ReportBatching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - ReportSarchia Khursheed
 
curing of concrete
curing of concrete curing of concrete
curing of concrete Rushabh shah
 
Handling of Concrete
Handling of ConcreteHandling of Concrete
Handling of ConcreteKezar Ali. Shah
 
Self curing concrete
Self curing concreteSelf curing concrete
Self curing concreteKoppolu Abishek
 
Ppt
PptPpt
Pptjirania
 
Detailed ppt on Curing of concrete
Detailed ppt on Curing of concreteDetailed ppt on Curing of concrete
Detailed ppt on Curing of concreteRushabh shah
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differencesscaffolddesign
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cementRizwan Samor
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 

Viewers also liked (19)

Concrete Compaction
Concrete CompactionConcrete Compaction
Concrete Compaction
 
CDS Concrete Curing 2010
CDS Concrete Curing 2010CDS Concrete Curing 2010
CDS Concrete Curing 2010
 
Making and curing concrete test specimens in the
Making and curing concrete test specimens in theMaking and curing concrete test specimens in the
Making and curing concrete test specimens in the
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cement
 
Curing Concrete Pavement
Curing Concrete PavementCuring Concrete Pavement
Curing Concrete Pavement
 
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT NuzvidCuring & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
 
Heat of Hydration in Mass Concrete
Heat of Hydration in Mass ConcreteHeat of Hydration in Mass Concrete
Heat of Hydration in Mass Concrete
 
Formwork & falsework
Formwork & falseworkFormwork & falsework
Formwork & falsework
 
Batching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - ReportBatching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - Report
 
curing of concrete
curing of concrete curing of concrete
curing of concrete
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cement
 
Handling of Concrete
Handling of ConcreteHandling of Concrete
Handling of Concrete
 
Methods of curing
Methods of curingMethods of curing
Methods of curing
 
Self curing concrete
Self curing concreteSelf curing concrete
Self curing concrete
 
Ppt
PptPpt
Ppt
 
Detailed ppt on Curing of concrete
Detailed ppt on Curing of concreteDetailed ppt on Curing of concrete
Detailed ppt on Curing of concrete
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cement
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 

Similar to Compaction

Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concreteJacobSabu2
 
Fresh Concrete Batching, Mixing.pptx
Fresh Concrete Batching, Mixing.pptxFresh Concrete Batching, Mixing.pptx
Fresh Concrete Batching, Mixing.pptxADCET, Ashta
 
Chapter 15 Of Rock Engineering
Chapter 15 Of  Rock  EngineeringChapter 15 Of  Rock  Engineering
Chapter 15 Of Rock EngineeringNgo Hung Long
 
02725 sewer manholes
02725 sewer manholes02725 sewer manholes
02725 sewer manholesAni Alikaj
 
Test of concrete
Test of concrete Test of concrete
Test of concrete kuntansourav
 
Under water concrete
Under water concreteUnder water concrete
Under water concreteMuftah Aljoat
 
Project complete
Project completeProject complete
Project completemantu verma
 
Concepts of Shotcrete Technology
Concepts of Shotcrete TechnologyConcepts of Shotcrete Technology
Concepts of Shotcrete TechnologyNADEEM AKHTAR
 
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdfPile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdfDharmPalJangra1
 
Understanding of concrete 28.june-08 (2) - copy
Understanding of concrete 28.june-08 (2) - copyUnderstanding of concrete 28.june-08 (2) - copy
Understanding of concrete 28.june-08 (2) - copyARIVU SUDAR
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concreteErankajKumar
 
CONCRETE TECHNOLOGY UNIT IV
CONCRETE TECHNOLOGY UNIT IVCONCRETE TECHNOLOGY UNIT IV
CONCRETE TECHNOLOGY UNIT IVcivilguna
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concreteBinay Shrestha
 
Advances in Concrete Technology
Advances in Concrete TechnologyAdvances in Concrete Technology
Advances in Concrete TechnologyJNTU
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
IRJET - Solid Flooring by using Tremix Method-Literature Review
IRJET - Solid Flooring by using Tremix Method-Literature ReviewIRJET - Solid Flooring by using Tremix Method-Literature Review
IRJET - Solid Flooring by using Tremix Method-Literature ReviewIRJET Journal
 
Ch 44 subsoil drainage
Ch 44   subsoil drainageCh 44   subsoil drainage
Ch 44 subsoil drainageVinod Kumar Nehta
 

Similar to Compaction (20)

Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concrete
 
Fresh Concrete Batching, Mixing.pptx
Fresh Concrete Batching, Mixing.pptxFresh Concrete Batching, Mixing.pptx
Fresh Concrete Batching, Mixing.pptx
 
Chapter 15 Of Rock Engineering
Chapter 15 Of  Rock  EngineeringChapter 15 Of  Rock  Engineering
Chapter 15 Of Rock Engineering
 
02725 sewer manholes
02725 sewer manholes02725 sewer manholes
02725 sewer manholes
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Test of concrete
Test of concrete Test of concrete
Test of concrete
 
Moisture Control for Masonry
Moisture Control for MasonryMoisture Control for Masonry
Moisture Control for Masonry
 
Under water concrete
Under water concreteUnder water concrete
Under water concrete
 
Project complete
Project completeProject complete
Project complete
 
Concepts of Shotcrete Technology
Concepts of Shotcrete TechnologyConcepts of Shotcrete Technology
Concepts of Shotcrete Technology
 
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdfPile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
 
Understanding of concrete 28.june-08 (2) - copy
Understanding of concrete 28.june-08 (2) - copyUnderstanding of concrete 28.june-08 (2) - copy
Understanding of concrete 28.june-08 (2) - copy
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
CONCRETE TECHNOLOGY UNIT IV
CONCRETE TECHNOLOGY UNIT IVCONCRETE TECHNOLOGY UNIT IV
CONCRETE TECHNOLOGY UNIT IV
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
 
Advances in Concrete Technology
Advances in Concrete TechnologyAdvances in Concrete Technology
Advances in Concrete Technology
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
Watershell Catalogue Specto Ct August 2009
Watershell Catalogue Specto Ct August 2009Watershell Catalogue Specto Ct August 2009
Watershell Catalogue Specto Ct August 2009
 
IRJET - Solid Flooring by using Tremix Method-Literature Review
IRJET - Solid Flooring by using Tremix Method-Literature ReviewIRJET - Solid Flooring by using Tremix Method-Literature Review
IRJET - Solid Flooring by using Tremix Method-Literature Review
 
Ch 44 subsoil drainage
Ch 44   subsoil drainageCh 44   subsoil drainage
Ch 44 subsoil drainage
 

Recently uploaded

JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Dr. Mazin Mohamed alkathiri
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...Pooja Nehwal
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 

Recently uploaded (20)

Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 

Compaction

  • 1. Datasheet > june 2006 compaction of Concrete SCOPE Compaction of concrete is, therefore, a This data sheet discusses the benefits of compaction two-stage process Figure 1. First the aggregate > of concrete and provides information on the particles are set in motion and slump to fill the techniques for undertaking the process on site. form giving a level top surface. In the second stage, entrapped air is expelled. INTRODUCTION It is important to recognise the two stages in Compaction is the process which expels entrapped the compaction process because, with vibration, air from freshly placed concrete and packs the initial consolidation of the concrete can often be aggregate particles together so as to increase the achieved relatively quickly. The concrete liquefies density of concrete. It increases significantly the and the surface levels, giving the impression that ultimate strength of concrete and enhances the the concrete is compacted. Entrapped air takes a bond with reinforcement. It also increases the little longer to rise to the surface. Compaction must abrasion resistance and general durability of the therefore be prolonged until this is accomplished, concrete, decreases the permeability and helps to ie until air bubbles no longer appear on the surface. minimise its shrinkage-and-creep characteristics. > Proper compaction also ensures that the formwork is completely filled – ie there are no pockets of honeycombed material – and that the required finish is obtained on vertical surfaces. When first placed in the form, normal concretes, Compaction is the process excluding those with very low or very high slumps, will contain between 5% and 20% by volume of which expels entrapped air from entrapped air. The aggregate particles, although coated with mortar, tend to arch against one freshly placed concrete and another and are prevented from slumping or consolidating by internal friction. packs the aggregate particles together so as to increase the density of concrete.
  • 2. STAGE 1 STAGE 2 PROCESS: Liquefaction of the PROCESS: The expulsion of METHODS AND EQUIPMENT concrete which entrapped air General allows it to slump and fill the form Two types of vibrators are common on building TIME: 3 to 5 seconds TIME: 7 to 15 seconds sites – immersion vibrators and surface vibrators. Each has its own specific application, although on TOTAL TIME (for both stages of the process): 10 to 20 seconds floors and other flatwork it is not uncommon for Figure 1: The process of compaction one to complement the other. A third type, form vibrators, are commonly used in precast work, and sometimes on building sites. RELATIVE STRENGTH (%) 100 Immersion Vibrators Frequently referred to as ‘poker’ or ‘needle ’ vibrators, immersion vibrators consist essentially 80 of a tubular housing which contains a rotating eccentric weight. The out-of-balance rotating 60 weight causes the casing to vibrate and, when immersed in concrete, the concrete itself. 40 Depending on the diameter of the casing or head, and on the frequency and the amplitude of the 20 vibration, an immersion vibrator may have a radius of action between 100 and 600 mm Table 1. 0 Immersion vibrators may be driven by: 0 5 10 15 20 25 30 n a flexible shaft connected to a petrol, diesel, or AIR VOIDS (%) electric motor; n an electric motor situated within the tubular Figure 2: Loss of strength through incomplete casing; compaction n compressed air. The effectiveness of an immersion vibrator is dependent on its frequency and amplitude, the latter being dependent on the size of the head, the EFFECT ON HARDENED PROPERTIES eccentric moment and the head weight – the larger As may be seen from Figure 2, the effect of the head, the larger the amplitude. compaction on compressive strength is dramatic. Table 1 summarises the characteristics and For example, the strength of concrete containing applications of immersion vibrators. As a general 10% of entrapped air (air voids) may be as little as rule, the radius of action of a given vibrator not 50% that of the concrete when fully compacted. only increases with the workability of the concrete Permeability may be similarly affected since (higher slump), but also with the diameter of the compaction, in addition to expelling entrapped head. A good general rule is to use as large a air, promotes a more even distribution of pores diameter head as practicable, bearing in mind that within the concrete, causing them to become vibrators with diameters in excess of 100 mm will discontinuous. This reduces the permeability of the probably require two men to handle them. Below concrete and hence improves its durability. this diameter, the appropriate head size will be The abrasion resistance of concrete surfaces dependent on the width of the formwork, the is normally improved by adequate compaction. spacing of the reinforcement and the cover to it. However, excessive vibration, or excessive working Immersion vibrators should be inserted of the surface, can cause an excessive amount of vertically into concrete, as quickly as possible, and mortar (and moisture) to collect at the surface, then held stationary until air bubbles cease to rise thereby reducing its potential abrasion resistance. to the surface, usually in about 15–20 seconds In flatwork therefore, a careful balance is required Figure 3. The vibrator should then be slowly to expel entrapped air without bringing excessive withdrawn and reinserted vertically in a fresh amounts of mortar to the surface of the concrete. position adjacent to the first. These movements should be repeated in a regular pattern until all the concrete has been compacted Figure 4. Random insertions are likely to leave areas of the concrete uncompacted. The vibrator should not be used to cause concrete to flow horizontally in the forms, as Page of 7 compaction of Concrete
  • 3. Table 1 Characteristics and applications of immersion vibrators Diameter Recommended Average Radius of Rate of concrete of head frequency1 amplitude 2 action 3,5 placement 4,5 (mm) (Hz) (mm) (mm) (m3/h per vibrator) Application 20–40 150–250 0.4–0.8 75–150 1–4 High slump concrete in very thin members and confined places. May be used to supplement larger vibrators where reinforcement or ducts cause congestion in forms. 30–65 140–210 0.5–1.0 125–250 2–8 Concrete of 100–150 mm slump in thin walls, columns, beams, precast piles, thin slabs, and along construction joints. May be used to supplement larger vibrators in confined areas. 50–90 130–200 0.6–1.3 175–350 6–20 Concrete (less than 80 mm slump) in normal construction, eg walls, floors, beams and columns in buildings. 75–150 120–180 0.8–1.5 300–500 11–31 Mass and structural concrete of 0 to 50 mm slump deposited in quantities up to 3m3 in relatively open forms of heavy construction. 1 25–175 90–140 1.0–2.0 400–600 19–38 Mass concrete in gravity dams, large piers, massive walls, etc. Adapted from Table 5.1 ACI Committee Report: Guide for Consolidation of Concrete 309R-05 ACI Manual of Concrete Practice 2006 Part 2. 1 While vibrator is operating in concrete. 2 Computed or measured. This is peak amplitude (half the peak-to-peak value), operating in air. Reduced by 15–20% when operating in concrete. 3 Distance over which concrete is fully consolidated. 4 Assumes insertion spacing 1½ times the radius of action, and that vibrator operates two-thirds of time concrete is being placed. 5 Reflects not only the capability of the vibrator but also differences in workability of the mix, degree of de-aeration desired, and other conditions experienced in construction. Page of 7 compaction of Concrete
  • 4. Radius of action Immersion SQUARE PATTERN vibrator D1 = e √2 D1 See Table 1 for values of e e For range of immersion D1 vibrators used in normal construction e = 180 to 360 mm D1 = 255 to 500 mm OFFSET PATTERN D2 D2 = e √3 e See Table 1 for values of e D2 Figure 3: Use of an immersion vibrator For range of immersion vibrators used in normal construction this can lead to segregation. In addition, the vibrator e = 180 to 360 mm should not be dragged through the concrete as this D2 D2 = 300 to 620 mm leads to inadequate compaction and increases the 2 risk of segregation. In deep sections such as walls, footings and Figure 4: Alternative patterns for use of immersion large columns, the concrete should be placed in vibrators layers about 300 mm thick. The vibrator should penetrate about 150 mm into the previous layer of fresh concrete to meld the two layers together and Place concrete avoid ‘cold-pour’ lines on the finished surface. In a little away from the corner small columns where concreting is continuous, the vibrator may be slowly raised as the concrete is placed. Care should be taken to avoid trapping air at the form face and a means of lighting the interior With immersion vibrator, of the form while the concrete is being placed and move concrete into the vibrated should be considered. corner and up the form face The vibrator should not be allowed to touch the forms as this can cause ‘burn’ marks which will Figure 5: Compaction at stop ends and in inclined be reflected on the finished surface. Generally, the forms vibrator should be kept about 50 mm clear of the form face. Similarly, the vibrator should not be held Void Form First layer placed and compacted. against the reinforcement as this may cause its Second and subsequent placements displacement. made from one side only. Stop-ends, joints and, especially, inclined forms Concrete induced to flow under are prone to trapping air. To minimise this tendency, the void former by action of immersion vibrator the best technique is to place the concrete close to, but away from the side of the form and insert the immersion vibrator close to the leading edge Void Form of the concrete, forcing it to properly fill the corner When concrete reaches the same Figure 5. level on each side of the former, Void-formers are also prone to trapping air on concrete placement and compaction can proceed normally their undersides if concrete is placed from both sides and then compacted. Concrete should be placed at one side and, maintaining a head, vibrated Similar technique to that above, until it appears at the other side. (Note that the used for encasing steel beams. void-former will need to be fixed so as to resist the Concrete placed and compacted pressure of the plastic concrete.) from one side until equalised either side of beam When the top of the concrete is fully visible from above, then placing can continue normally Figure 6. This technique is used in other similar situations, such as encasing steel beams. Figure 6: Compaction around void formers and encased members Page of 7 compaction of Concrete
  • 5. Surface vibrator Edge Edge Form Form Figure 7: Typical surface vibrator Depth of Depth of Immersion compaction compaction vibrators decreases (maximum needed to Surface Vibrators in vicinity of 200 mm) supplement Surface vibrators are applied to the top surface of edge forms compaction concrete and act downwards from there. They are here very useful for compacting slabs, industrial floors, road pavements, and similar flat surfaces. They Figure 8: Degree of compaction varies across width also aid in levelling and finishing the surface. when surface vibrators are used There are a number of types of surface vibrators including vibrating-roller screeds, vibrating-beam screeds and pan-type vibrators which are used mainly on very specialised equipment such as road Screed paving plant. The most common type is the single or double vibrating-beam screed. A vibrating-beam screed consists of either one Height of required or two beams, made from aluminium, steel or surcharge timber, to which is attached a form of vibrating unit Packing to screed to allow the beams to impart adequate vibration to Edge form the concrete. This may be a single unit, mounted centrally, or may consist of a series of eccentric weights on a shaft driven from a motor on one end and supported on a trussed frame. In general, the centrally-mounted units have a maximum span of about 6 m, but the trussed units may span up to Figure 9: Method for providing a surchage to the 20 m. The small units are normally pulled forward uncompacted concrete by hand whereas the larger units may be winched, towed or be self-propelled Figure 7. The intensity of vibration, and hence the amount In using vibrating-beam screeds to compact of compaction achieved, decreases with depth concrete, the uncompacted concrete should first because surface vibrators act from the top down. be roughly levelled to above the final level required, Therefore, the slab thickness for which compaction ie a surcharge should be provided to compensate by surface vibrators is effective will vary (from for the reduction in slab thickness caused by 100 to 200 mm) depending on the size and operation the compaction of the concrete. The amount of of the unit used. With slabs 200 mm or over in surcharge should be such that, when the beam is thickness, immersion vibrators should be used to moved forward, a consistent ‘roll’ of concrete is supplement the surface vibrations maintained ahead of the beam. The surcharge may With centrally-mounted vibration units, the be provided evenly on slabs of up to 4 m in width degree of compaction achieved may vary across the by the use of a ‘surcharge-beam’. This is simply a width of the beam. When they rest on edge forms, the straightedge, usually made of timber, with small latter may tend to damp the vibration at the extrem- packing pieces on the ends which ‘ride’ on the edge ities of the beam Figure 8. It is generally desirable, forms Figure 9. therefore, to supplement vibrating-beam compaction The surcharge beam is pulled over the by using immersion vibrators alongside edge forms. uncompacted concrete without any attempt being The effectiveness of vibration, and hence degree made to compact or finish it. The sole purpose is to of compaction, increases with an increase in the provide an even surcharge. The correct thickness beam weight, the amplitude and the frequency, for the packing pieces (and hence the surcharge) and decreases with an increase in forward speed. is soon found by observing the ‘roll’ of concrete. Forward speed is critical in the correct use of Providing an even surcharge has the advantage that vibrating-beam screeds and should be limited to one pass of the vibrating-beam screed is generally between 0.5 and 1.0 m/min. The lower speed should sufficient to compact, level and provide the initial be used for thicker slabs and where reinforcement finish. This is preferable to multiple passes, as a is close to the top face. A second, faster pass may slower single pass is more effective in compacting be made as an aid to finishing. the concrete than two faster passes. Page of 7 compaction of Concrete
  • 6. Form Vibrators Situations in which revibration may be beneficial Form vibrators (normally called ‘external’ vibrators) include: are useful with complicated members or where n To bond layers of concrete into those preceding the reinforcement is highly congested. They are them. In elements such as walls, deep clamped to the outside of the formwork and vibrate beams and columns, which are being filled it, thus compacting the concrete. The formwork will in successive layers, the vibrator should just need to be specifically designed to resist the forces penetrate the previous layer. imposed on it. n To close plastic shrinkage and settlement cracks. Under-Vibration and Over-Vibration These may form within the first few hours of Normal-weight concretes that are well proportioned concrete being placed and may be able to be are not readily susceptible to defects caused by closed by vibration, providing it is done early and over-vibration. These result from segregation and prior to the hardening of the concrete. However, are characterised by an excessive thickness of a reasonable level of energy input is required mortar at the surface of the concrete. The surface since mere reworking of the surface, may may also have a frothy appearance. Over-vibration simply close the cracks superficially. They may may cause problems when grossly oversized then reopen as the concrete dries out. equipment is operated for an excessive length of n To improve the surface finish at the tops of time, but is more likely to cause problems with columns and walls by expelling the air which poorly-proportioned mixes or those to which tends to congregate there as the concrete excessive amounts of water have been added. settles in the formwork. When signs of over-vibration are detected, the n To improve the wear resistance of floors. initial reaction may be to reduce the amount of Revibration, coupled with a trowelling action, vibration. The most appropriate solution may be to helps to create a burnished wear-resistant investigate if suitable changes to mix design are surface layer. warranted. Under-vibration is far more common than FURTHER INFORMATION over‑vibration and, when it occurs, can cause Further information on good concreting practices serious defects. Invariably, the concrete is can be downloaded from the Cement Concrete incompletely compacted which reduces its strength Aggregates Australia website at (see Effect on Hardened Properties above), its www.concrete.net.au. durability and will possibly affect its surface finish. Despite this, many specifications contain a caution against the over-vibration – and even lay down a maximum length of time for vibration – whilst neglecting totally the question of under‑vibration. Revibration Revibration of concrete is the intentional systematic vibration of concrete which has been compacted some time earlier. It should not be confused with the double vibration which sometimes occurs with the haphazard use of immersion vibrators or multiple passes of a vibrating-beam screed. Whilst it is generally agreed that revibration of concrete can be beneficial to its strength, its bond to reinforcement and its surface finish, the practice is not widely used, partly due to the difficulty of knowing just how late it can be applied. A good rule of thumb is that revibration may be used as long as the vibrator is capable of liquefying the concrete and sinking into it under its own weight. Page of 7 compaction of Concrete
  • 7. june CCAA OFFICES SYDNEY OFFICE: 2006 Level 6, 504 Pacific Highway St Leonards NSW Australia 2065 POSTAL ADDRESS: Locked Bag 2010 St Leonards NSW 1590 TELEPHONE: (61 2) 9437 9711 FACSIMILE: (61 2) 9437 9470 BRISBANE OFFICE: Level 14, IBM Building 348 Edward Street Brisbane QLD 4000 TELEPHONE: (61 7) 3831 3288 FACSIMILE: (61 7) 3839 6005 MELBOURNE OFFICE: 2nd Floor, 1 Hobson Street South Yarra VIC 3141 TELEPHONE: (61 3) 9825 0200 FACSIMILE: (61 3) 9825 0222 PERTH OFFICE: 45 Ventnor Avenue West Perth WA 6005 TELEPHONE: (61 8) 9389 4452 FACSIMILE: (61 8) 9389 4451 ADELAIDE OFFICE: Greenhill Executive Suites 213 Greenhill Road Eastwood SA 5063 POSTAL ADDRESS: PO Box 229 Fullarton SA 5063 TELEPHONE: (61 8) 8274 3758 FACSIMILE: (61 8) 8373 7210 EXTRACTIVE INDUSTRIES OFFICE PO Box 243 Henley Beach SA 5022 TELEPHONE: (61 8) 8353 8151 FACSIMILE: (61 8) 8353 8151 TASMANIAN OFFICE: EXTRACTIVE INDUSTRIES OFFICE PO Box 246 Sheffield TAS 7306 TELEPHONE: (61 3) 6491 2529 FACSIMILE: (61 3) 6491 2529 WEBSITE: www.concrete.net.au EMAIL: info@ccaa.com.au Layout: Helen Rix Design Disclaimer: Cement Concrete Aggregates Australia is a not for profit organisation sponsored by the cement concrete and aggregate industries in Australia to provide information on the many uses of cement and concrete. This publication is produced by CCAA for that purpose. Since the information provided is intended for general guidance only and in no way replaces the services of professional consultants on particular projects, no legal liability can be accepted by CCAA for its use. CCAA respects your privacy. Your details have been collected to provide you with information on our activities, publications and services. From time to time your details may be made available to third party organisations who comply with the Privacy Act such as affiliated associations, sponsors of events and other reputable organisations whose services we think you may find of interest. If you do not wish to receive information from CCAA or wish to be taken off the database please write to the Privacy Officer, CCAA, Locked Bag 2010, St Leonards, NSW, 1590 Page of 7 compaction of Concrete