The project involves the construction of an LPG jetty including a trestle, loading platform, dolphins, loading arms, pipelines, and other systems. Construction is 80-100% complete for many components and is expected to be fully completed by mid-February. Resources include 51 staff members currently and various construction equipment. There are several outstanding variation orders for additional works including a firefighting water tank, pumps room, and electrical works. Overall progress is on schedule with most components nearing completion.
A professional portfolio of B2B and B2C marketing and communications work, crossing interactive, direct marketing, internal and marketing communications, branding, and publicity.
Gas Technology Institute, Boehlke Bottled Gas Corporation & AmeriGas - Statio...Wisconsin Clean Cities
Are you interested in the station installation guidelines for LPG? Learn about the basics guidelines, processes, and experiences of installing a LPG station.
A professional portfolio of B2B and B2C marketing and communications work, crossing interactive, direct marketing, internal and marketing communications, branding, and publicity.
Gas Technology Institute, Boehlke Bottled Gas Corporation & AmeriGas - Statio...Wisconsin Clean Cities
Are you interested in the station installation guidelines for LPG? Learn about the basics guidelines, processes, and experiences of installing a LPG station.
CTE WIND CIVIL ENGINEERING est une société d'ingénierie française spécialisée dans les fondations d'éoliennes et les systèmes photovoltaïques.Notre société est également implantée au Brésil, en Allemagne, au Vietnam, en Pologne et depuis peu au Portugal.CTE WIND travail dans l'éolien depuis 10 ans sur la base d'un savoir-faire acquis en Allemagne et opère dans une vingtaine de pays.Notre savoir-faire porte sur la conception des fondations pour un parc éolien déterminé, adaptées à la situation géotechnique du site concerné.
CTE WIND CIVIL ENGINEERING est une société d'ingénierie française spécialisée dans les fondations d'éoliennes et les systèmes photovoltaïques.Notre société est également implantée au Brésil, en Allemagne, au Vietnam, en Pologne et depuis peu au Portugal.CTE WIND travail dans l'éolien depuis 10 ans sur la base d'un savoir-faire acquis en Allemagne et opère dans une vingtaine de pays.Notre savoir-faire porte sur la conception des fondations pour un parc éolien déterminé, adaptées à la situation géotechnique du site concerné.
5. 5
Status Expected Completion Date
Trestle 100% Complete
Platform 100% Complete
Loading Arm 100% Complete
Pile Static Load Test 100% Complete
Pipe Line 80% 31-Jan-15
Mooring Dolphins 80% 25-Jan-15
Berthing Dolphins 75% 31-Jan-15
Catwalks 75% 5-Feb-15
Abutement & Access 50% 28-Jan-15
Electrical 30% 10-Feb-15
Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15
Commissioning 4-Feb to 18-Feb-15
Construction
6. 6
Front View
10” FF Pipe4” Vapour Pipe6” LPG Pipe
2.5” Water
Pipe
U-Channel
Pipe Support
Concrete Pipe
Support
Pipe 13-Jan-15
FireFighting 80%
Vapour 80%
LPG 80%
Water 80%
7. 7
Invoice
No.
Descripti
on
Initial Amount
(JOD)
Agreed Amount
(JOD)
Issue Date Due Date
Settleme
nt Date
Overdue
Period
(days)
Status
001
Advance
payment
10%
1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-14 8-Jun-14 94 Closed
002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14 48 Closed
003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed
004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed
005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14 35 Closed
006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14 9 Closed
007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14 Closed
008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14 30-Nov-14 Closed
009
IPC-8
1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open
010
IPC-9
1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not Yet
Open
Issued 14-Jan-2015
8. .1Steel Water Tank to feed the fire fighting system
•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%
.2Firefighting Pumps Room
•Issued on 17th 2014 (40,700.0) JD, Progress : 95%
.3LPG and Vapour Return Tie-In to Existing Networks
•Issued on 17th 2014 (64,509.61) JD, Progress : 100%
.4Design, Supply and Installation of Main Power cable
•Issued on Dec. 24th (18,246.99) JD, Progress : 80%
.5Design, Supply and Installation of a Standby Power Generator
•Issued on Dec. 24th (18,198.69) JD, Progress : 80%
8