SlideShare a Scribd company logo
Combining Contemporary and
Traditional Project Management
Tools to Resolve a Project
Scheduling Problem
Authors:
John E.Hebert
University of Akron,USA
RichardF.Deckro
Air Force Institute of Technology, USA
Computers & Operations Research
Presented By: Mohammad Rabay’ah
ByM
oham
m
ad
Rabay'ah
By Mohammad Rabay'ah
TRADITIONAL
CONTEMPORARY
ByM
oham
m
ad
Rabay'ah
Outline
• Abstract
• Introduction
• Solving a Problem
• Conclusion
• Critique
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
Abstract
• In this presentation we will examine a construction
project.
• Initial project schedule prepared using Microsoft
Project.
• The client ask to shorten the schedule.
• Manually validate the results using the precedence
diagramming method (PDM) procedure.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• The problem involves a construction project, which
require the building of three large adjacent concrete
slabs for three buildings in an office park complex.
• There are five activities associated with construction
of each slab.
• Non Working Days are:
▫ Saturday and Sunday (week end)
▫ 28th May (memorial day)
Introduction
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Revers Critical Activity:
▫ Anomalous effect of FF followed by SS
precedence relationships:
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
Solving a Problem
• At the beginning a manually-drawn diagram drawn
diagram of the 15 project activities, which has been
‘‘marked-up’’ to include (and display) the
precedence relationships among the project
activities.
• Activities and precedence information depicted in
the precedence diagram was transcribed into a
project activity list.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• PRECEDENCE DIAGRAM OF SLAB PROJECT
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Activity list
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• GANTT chart by MSP
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Critical Paths (TCD=56)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• The client reject the schedule and state that the project
must be completed by end of fiscal year (30th June)
• The subcontractor indicates that:
▫ they can not start the project before Monday, April 23,
2007 due to prior commitment.
▫ Cannot work on Saturdays, Sundays, or holidays because
of contractual obligations.
▫ Also indicates that the planning should include one
additional day for ‘‘site clean-up’’ and ‘‘other
contingencies’By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• MSP does not have the capability for resolving our
particular time/cost tradeoff issues as it does not
have a feature that will compress a project by X
days at minimum cost.
• Manually, an original time/cost trade-off model for
projects modelled in the precedence diagramming
format is developed.
• Goal: reschedule the project so that it is completed
by June 28, 2007, leaving Friday, June 29, 2007 for
site clean-up. (48 working days)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Slab Construction Project/ Accelerated Solution
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Project example was solved using the EXCEL Solver
tool .
• In order to accelerate the completion of the slab
construction project from 56 to 48 days the least
expensive plan is to:
▫ Reduce the duration of activities (1) and (14) by 2 d.
▫ Reduce the duration of activity (12) by 3 d.
▫ Increase the duration of activities (3) and (8) by 4 d.
▫ Increase the duration of activity (13) by 1 d.
• This project acceleration (time compression) plan is
estimated to cost an additional $175.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Modified GANTT chart by MSP
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• Original Critical Paths (TCD=48)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
• New Critical Paths (TCD=48)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
Conclusion
• By combining contemporary (MSP) and traditional
(a linear programming time/cost tradeoff model)
project management tools we are able to successfully
resolve the scheduling issues associated with the
slab construction project.
• In some Anomalous cases like “Revers Critical
Activity”, lengthen an activity duration will result in
shorten the project time.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
Critiques
• The title
• Using appendices for formulas details.
• All related details are explained within the paper
• Referring to old references
• Did not mention any thing about other
contemporary tools (i.e. softwares rather than MSP)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
Critiques
• Did not clarify the Non-working days at the
beginning of explaining the example problem.
• Repeating information about the project in the
abstract, introduction, example problem and
summary.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah

More Related Content

Similar to Combining Contemporary and Traditional Project Management Tools to Resolve a Project Scheduling Problem

06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
Eng.Ahmed Said Mohamed Refaei
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
Saqib Raza
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
IRESH3
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
Kuldeep Kumar
 
Lec#1
Lec#1Lec#1
Lec#1
Yasir Khan
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagementkaton808
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
PedadaSaikumar
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
Charles Cotter, PhD
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
Charles Cotter, PhD
 
Project time management
Project time managementProject time management
Project time management
Jack Pumpuni Frimpong-Manso
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
Isidro Sid Calayag
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)Jonathan Coleman
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
Galala University
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
MdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
MdSabujHossen2
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
Sampath Sredharran
 

Similar to Combining Contemporary and Traditional Project Management Tools to Resolve a Project Scheduling Problem (20)

06 project time management
06  project time management06  project time management
06 project time management
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
 
Lec#1
Lec#1Lec#1
Lec#1
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagement
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Bpp 3213 lecture 2
Bpp 3213 lecture 2Bpp 3213 lecture 2
Bpp 3213 lecture 2
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
 
Project time management
Project time managementProject time management
Project time management
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 

Combining Contemporary and Traditional Project Management Tools to Resolve a Project Scheduling Problem

  • 1. Combining Contemporary and Traditional Project Management Tools to Resolve a Project Scheduling Problem Authors: John E.Hebert University of Akron,USA RichardF.Deckro Air Force Institute of Technology, USA Computers & Operations Research Presented By: Mohammad Rabay’ah ByM oham m ad Rabay'ah
  • 3. Outline • Abstract • Introduction • Solving a Problem • Conclusion • Critique By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 4. Abstract • In this presentation we will examine a construction project. • Initial project schedule prepared using Microsoft Project. • The client ask to shorten the schedule. • Manually validate the results using the precedence diagramming method (PDM) procedure. By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 5. • The problem involves a construction project, which require the building of three large adjacent concrete slabs for three buildings in an office park complex. • There are five activities associated with construction of each slab. • Non Working Days are: ▫ Saturday and Sunday (week end) ▫ 28th May (memorial day) Introduction By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 6. • Revers Critical Activity: ▫ Anomalous effect of FF followed by SS precedence relationships: By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 7. Solving a Problem • At the beginning a manually-drawn diagram drawn diagram of the 15 project activities, which has been ‘‘marked-up’’ to include (and display) the precedence relationships among the project activities. • Activities and precedence information depicted in the precedence diagram was transcribed into a project activity list. By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 8. • PRECEDENCE DIAGRAM OF SLAB PROJECT By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 9. • Activity list By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 10. • GANTT chart by MSP By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 11. • Critical Paths (TCD=56) By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 12. • The client reject the schedule and state that the project must be completed by end of fiscal year (30th June) • The subcontractor indicates that: ▫ they can not start the project before Monday, April 23, 2007 due to prior commitment. ▫ Cannot work on Saturdays, Sundays, or holidays because of contractual obligations. ▫ Also indicates that the planning should include one additional day for ‘‘site clean-up’’ and ‘‘other contingencies’By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 13. • MSP does not have the capability for resolving our particular time/cost tradeoff issues as it does not have a feature that will compress a project by X days at minimum cost. • Manually, an original time/cost trade-off model for projects modelled in the precedence diagramming format is developed. • Goal: reschedule the project so that it is completed by June 28, 2007, leaving Friday, June 29, 2007 for site clean-up. (48 working days) By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 14. • Slab Construction Project/ Accelerated Solution By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 15. • Project example was solved using the EXCEL Solver tool . • In order to accelerate the completion of the slab construction project from 56 to 48 days the least expensive plan is to: ▫ Reduce the duration of activities (1) and (14) by 2 d. ▫ Reduce the duration of activity (12) by 3 d. ▫ Increase the duration of activities (3) and (8) by 4 d. ▫ Increase the duration of activity (13) by 1 d. • This project acceleration (time compression) plan is estimated to cost an additional $175. By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 16. • Modified GANTT chart by MSP By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 17. • Original Critical Paths (TCD=48) By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 18. • New Critical Paths (TCD=48) By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 19. Conclusion • By combining contemporary (MSP) and traditional (a linear programming time/cost tradeoff model) project management tools we are able to successfully resolve the scheduling issues associated with the slab construction project. • In some Anomalous cases like “Revers Critical Activity”, lengthen an activity duration will result in shorten the project time. By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 20. Critiques • The title • Using appendices for formulas details. • All related details are explained within the paper • Referring to old references • Did not mention any thing about other contemporary tools (i.e. softwares rather than MSP) By Mohammad Rabay'ah ByM oham m ad Rabay'ah
  • 21. Critiques • Did not clarify the Non-working days at the beginning of explaining the example problem. • Repeating information about the project in the abstract, introduction, example problem and summary. By Mohammad Rabay'ah ByM oham m ad Rabay'ah