This document discusses a construction project scheduling problem that was initially planned using Microsoft Project software. The client requested shortening the schedule, which Microsoft Project could not accommodate. The authors combined traditional precedence diagramming with a linear programming time/cost tradeoff model to resolve the scheduling issues. They identified a plan to accelerate project completion that compressed the schedule from 56 to 48 days at an additional cost of $175 by adjusting activity durations. This demonstrated how combining contemporary and traditional project management tools can successfully address scheduling problems.
PRACTICUM REPORT ON Monitoring the Construction Process of Superstructure ...Rubel Rana
A Practicum Report Submitted to Practicum & Placement Committee, Department of Civil Engineering, College of Engineering & Technology (CEAT), IUBAT for the Partial Fulfillment of the Requirement for the
Bachelor of Science in Civil Engineering (BSCE) Degree
PRACTICUM REPORT ON Monitoring the Construction Process of Superstructure ...Rubel Rana
A Practicum Report Submitted to Practicum & Placement Committee, Department of Civil Engineering, College of Engineering & Technology (CEAT), IUBAT for the Partial Fulfillment of the Requirement for the
Bachelor of Science in Civil Engineering (BSCE) Degree
Question 1 A project manager has received the following probab.docxIRESH3
Question 1
A project manager has received the following probabilistic estimates for the duration of an activity: optimistic duration is 7 workdays, most likely duration is 8 workdays and pessimistic duration is 15 workdays. What is the PERT weighted average for this activity?
a.
11 workdays
b.
10 workdays
c.
9 workdays
d.
8 workdays
Question 2
Successful project managers employ certain tactics to reduce late stage changes to scope. Which of the following is one such tactic?
a.
Route scope change requests through the project sponsor
b.
Connect scope change requests to cost and schedule changes
c.
Refuse to entertain any scope change requests
d.
Assign change requests to future projects
Question 3
As a project manager you understand that you can choose from multiple approaches to generate a work breakdown structure (WBS). Which approach must you check first?
a.
Analogy
b.
Top-down
c.
Guidelines
d.
Mind-mapping
Question 4
Project scope management is a set of processes that are used to describe, control and validate the work to be done in a project. What is a purpose of project scope management?
a.
To ensure common understanding among stakeholders of the project’s products
b.
To convince the customers of the importance and quality of the project’s products
c.
To persuade top management of the necessity of the project’s products
d.
To protect the project manager from any liability arising from the project’s products
Question 5
Project time management involves 7 main processes to ensure that the project is completed on time. Which of the following processes does not work with the project schedule network diagrams?
a.
Estimating activity resources
b.
Estimating activity durations
c.
Defining activities
d.
Sequencing activities
Question 6
The government has mandated a new regulation. Your company has made you the project manager responsible to implement the systems to support this regulation. You have been given the discretion to choose a legal team. You contacted three legal teams and are waiting for proposals from them. What dependency of project activities is this?
a.
External dependency
b.
Legal dependency
c.
Discretionary dependency
d.
Mandatory dependency
Question 7
Requirements of a project can be collected using many different methods. Which method collects requirements through a comparative study?
a.
Observation
b.
Survey
c.
Benchmarking
d.
Interviewing
Question 8
A work breakdown structure (WBS) lists in an organized manner all the tasks of a project. What is the main tool used to create a WBS?
a.
Decomposition
b.
Template
c.
Project management software
d.
Brainstorming
Question 9
Which of the following statements about project milestones is not true?
a.
Milestones are the most important events
b.
Milestones are useful for monitoring progress
c.
Milestones are sometimes deliverables
d.
Milestones are always without any duration
Question 10
While reviewing the work breakdown stru ...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...Kuldeep Kumar
No Need Thankx! Very Helpful in Software Mange Tools, Software Project Management, I cover all things of MS Project, like History, Purpose Critical Path. Scheduling & Competitors.
Starts with the basic learning in Critical Path Method and continued with the the use of MS Project software. Even though the software is upgraded to teh latest version, the basic fundamentals in using the software does not change
Question 1 A project manager has received the following probab.docxIRESH3
Question 1
A project manager has received the following probabilistic estimates for the duration of an activity: optimistic duration is 7 workdays, most likely duration is 8 workdays and pessimistic duration is 15 workdays. What is the PERT weighted average for this activity?
a.
11 workdays
b.
10 workdays
c.
9 workdays
d.
8 workdays
Question 2
Successful project managers employ certain tactics to reduce late stage changes to scope. Which of the following is one such tactic?
a.
Route scope change requests through the project sponsor
b.
Connect scope change requests to cost and schedule changes
c.
Refuse to entertain any scope change requests
d.
Assign change requests to future projects
Question 3
As a project manager you understand that you can choose from multiple approaches to generate a work breakdown structure (WBS). Which approach must you check first?
a.
Analogy
b.
Top-down
c.
Guidelines
d.
Mind-mapping
Question 4
Project scope management is a set of processes that are used to describe, control and validate the work to be done in a project. What is a purpose of project scope management?
a.
To ensure common understanding among stakeholders of the project’s products
b.
To convince the customers of the importance and quality of the project’s products
c.
To persuade top management of the necessity of the project’s products
d.
To protect the project manager from any liability arising from the project’s products
Question 5
Project time management involves 7 main processes to ensure that the project is completed on time. Which of the following processes does not work with the project schedule network diagrams?
a.
Estimating activity resources
b.
Estimating activity durations
c.
Defining activities
d.
Sequencing activities
Question 6
The government has mandated a new regulation. Your company has made you the project manager responsible to implement the systems to support this regulation. You have been given the discretion to choose a legal team. You contacted three legal teams and are waiting for proposals from them. What dependency of project activities is this?
a.
External dependency
b.
Legal dependency
c.
Discretionary dependency
d.
Mandatory dependency
Question 7
Requirements of a project can be collected using many different methods. Which method collects requirements through a comparative study?
a.
Observation
b.
Survey
c.
Benchmarking
d.
Interviewing
Question 8
A work breakdown structure (WBS) lists in an organized manner all the tasks of a project. What is the main tool used to create a WBS?
a.
Decomposition
b.
Template
c.
Project management software
d.
Brainstorming
Question 9
Which of the following statements about project milestones is not true?
a.
Milestones are the most important events
b.
Milestones are useful for monitoring progress
c.
Milestones are sometimes deliverables
d.
Milestones are always without any duration
Question 10
While reviewing the work breakdown stru ...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...Kuldeep Kumar
No Need Thankx! Very Helpful in Software Mange Tools, Software Project Management, I cover all things of MS Project, like History, Purpose Critical Path. Scheduling & Competitors.
Starts with the basic learning in Critical Path Method and continued with the the use of MS Project software. Even though the software is upgraded to teh latest version, the basic fundamentals in using the software does not change
Combining Contemporary and Traditional Project Management Tools to Resolve a Project Scheduling Problem
1. Combining Contemporary and
Traditional Project Management
Tools to Resolve a Project
Scheduling Problem
Authors:
John E.Hebert
University of Akron,USA
RichardF.Deckro
Air Force Institute of Technology, USA
Computers & Operations Research
Presented By: Mohammad Rabay’ah
ByM
oham
m
ad
Rabay'ah
4. Abstract
• In this presentation we will examine a construction
project.
• Initial project schedule prepared using Microsoft
Project.
• The client ask to shorten the schedule.
• Manually validate the results using the precedence
diagramming method (PDM) procedure.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
5. • The problem involves a construction project, which
require the building of three large adjacent concrete
slabs for three buildings in an office park complex.
• There are five activities associated with construction
of each slab.
• Non Working Days are:
▫ Saturday and Sunday (week end)
▫ 28th May (memorial day)
Introduction
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
6. • Revers Critical Activity:
▫ Anomalous effect of FF followed by SS
precedence relationships:
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
7. Solving a Problem
• At the beginning a manually-drawn diagram drawn
diagram of the 15 project activities, which has been
‘‘marked-up’’ to include (and display) the
precedence relationships among the project
activities.
• Activities and precedence information depicted in
the precedence diagram was transcribed into a
project activity list.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
10. • GANTT chart by MSP
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
11. • Critical Paths (TCD=56)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
12. • The client reject the schedule and state that the project
must be completed by end of fiscal year (30th June)
• The subcontractor indicates that:
▫ they can not start the project before Monday, April 23,
2007 due to prior commitment.
▫ Cannot work on Saturdays, Sundays, or holidays because
of contractual obligations.
▫ Also indicates that the planning should include one
additional day for ‘‘site clean-up’’ and ‘‘other
contingencies’By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
13. • MSP does not have the capability for resolving our
particular time/cost tradeoff issues as it does not
have a feature that will compress a project by X
days at minimum cost.
• Manually, an original time/cost trade-off model for
projects modelled in the precedence diagramming
format is developed.
• Goal: reschedule the project so that it is completed
by June 28, 2007, leaving Friday, June 29, 2007 for
site clean-up. (48 working days)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
14. • Slab Construction Project/ Accelerated Solution
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
15. • Project example was solved using the EXCEL Solver
tool .
• In order to accelerate the completion of the slab
construction project from 56 to 48 days the least
expensive plan is to:
▫ Reduce the duration of activities (1) and (14) by 2 d.
▫ Reduce the duration of activity (12) by 3 d.
▫ Increase the duration of activities (3) and (8) by 4 d.
▫ Increase the duration of activity (13) by 1 d.
• This project acceleration (time compression) plan is
estimated to cost an additional $175.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
16. • Modified GANTT chart by MSP
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
17. • Original Critical Paths (TCD=48)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
18. • New Critical Paths (TCD=48)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
19. Conclusion
• By combining contemporary (MSP) and traditional
(a linear programming time/cost tradeoff model)
project management tools we are able to successfully
resolve the scheduling issues associated with the
slab construction project.
• In some Anomalous cases like “Revers Critical
Activity”, lengthen an activity duration will result in
shorten the project time.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
20. Critiques
• The title
• Using appendices for formulas details.
• All related details are explained within the paper
• Referring to old references
• Did not mention any thing about other
contemporary tools (i.e. softwares rather than MSP)
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah
21. Critiques
• Did not clarify the Non-working days at the
beginning of explaining the example problem.
• Repeating information about the project in the
abstract, introduction, example problem and
summary.
By Mohammad Rabay'ah
ByM
oham
m
ad
Rabay'ah