This document provides guidance on substantiating a claim for additional time or compensation due to changes in the scope, timing, or resources required for a contract. It outlines key information to include: (1) what changed to require additional work, (2) when and where the change occurred, (3) how the works were affected, (4) why additional compensation is needed, (5) who instructed the change, (6) applicable contract clauses, (7) records to substantiate the change and its effects, (8) a measurement of associated costs and time impacts, and (9) any measures taken to mitigate the effects of the change. Graphical representations, like updated schedules, should also identify how events disrupted the original