Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Business Needs
     Benefits & Objectives




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Business Needs  
                  – Track submittal reviews and determine the
                    impact on the schedule
                 – Manage design changes and distribute
                   contract drawing revisions to contractor
                 – Review change orders for financial and
                   technical impact and make recommendations
                – Forecast project Budget

                – Communicate up to date project details to your
                  project team

Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Contract Manager Workflow
              ISSUES
                                               Submittal
                                                       s     Deliveries
                                 Drawings




                                               Contracts
            Transmittal No. 10

                                 Transmittal                      Daily
                 TO:

                                                PO's           Reports
                                           s
            FROM:




                                                  Meetings
                                 RFI’s/Chang
                                                               Requisitions
                                          es




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Tracking  Project Budget  (Cost Worksheet)
               Budget Cost              (Owner & Main Contractor)



               Committed Cost (Main Contractor & Subcontractors)

               Actual Cost (ALL)
        Analyze budgets , review commitment documents and record
        requisitions and invoices as they are received.
        The Cost Worksheet automatically collects and summarizes
        detailed cost elements from contracts, requisitions, changes and
        purchase orders and dynamically displays them so you can forecast
        project costs and simplify contract control.
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Payment
                                                      Requests
                                                    (Requisitions)




                          Project Cost Worksheet

                      Budget            Committed     Actual


                                                                     Invoices
       Budget
       Changes                             Contracts or P.O.
                                               Changes
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Tracks submittals
               Reviews and approvals .
               Ensures materials are perfectly to spec.

          Controls changes
               From the estimate phase to final approval for both budgeted and 
               committed costs. 
               Identifies impacts on project costs and schedule.
               According to the nature of the change and the company’s process for 
               recording and tracking changes, the Change Management module 
               enables you to create a customized workflow to meet your company’s 
               change management needs. 

Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
• Track Submittals :-

            Submittals include contract drawings, Sample
            materials, and Permits that need approval. this
            Submittals module helps to ensure contract
            compliance by tracking who received what and
            when they received it.




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
SUBMITTAL FLOW

                                        Review/Approval
Received                  Sent                            Returned    Forward

                                                   If DAYS HELD
                                                    GT Planned
                                                                     Transmittal
                 Transmittal
                                              Dunning
                                               letter

                   Correspondence
                        Sent



Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Project Changes

        After project parties accept a contract or
        purchase order and work begins, any changes
        resulting from changed specifications, scope of
        work, site conditions, or project schedule affect
        the initial contract. The process of formally
        changing a contract requires several steps, each
        of which should be fully documented


Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Subcontractor                            Change
                                                                         Order
                                        CO

                                  Contractor
                 Owner                  CO                              CHANGE ORDER



                                        COR                         CHANGE ORDER REQUEST


    Subcontractor                             Contractor
                                        PCO
                                                                   PROPOSED CHANGE ORDER



                                         RFP                        REQUEST FOR PROPOSAL
                                                  Contractor
 Designer
                                        ANS
                                                                           ANSWER



                                         RFI                       REQUEST FOR INFORMATION

                                                      Contractor
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Contract Drawings
          The drawing log ensures that everyone is building
         using the latest drawings and specifications.
          Contract Manager helps you to use the drawings log to
         manage your drawings, keep on top of the latest
         revision, and ensure the distribution to all project
         participants.




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Design Review
                          Drawing Rev. A
                                                              Drawing Rev. B


                             Civil
                                                                 Civil
                           DWG C1-C10                          DWG C1-C15

                                           30% Complete                        60% Complete
  15% Complete                                                                 (Review Meeting)
                                           (Review Meeting)

                              Elect                              Elect
                            DWG E1-E8                          DWG E1-E10

      Concept                                 Design
     Schematic                              Development                          Progress


                             MECH                                MECH
                           DWG M1-M20                          DWG M1-M20




                             STRUCT                             STRUCT
                                                               DWG S1-S20
                            DWG S1-S15



Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Design Review
                                Drawing Rev. C                      Drawing Rev. D


                                  Civil                                Civil
                                DWG C1-C20                           DWG C1-C20
           60%
           Complete                              95% Complete
           (Review                               (Review Meeting)
           Meeting)               Elect                                Elect
                                DWG E1-E12                           DWG E1-E12


             Progress                              Progress

                                  MECH                                 MECH
                                DWG M1-M20                           DWG M1-M20




                                 STRUCT                               STRUCT
                                DWG S1-S20                           DWG S1-S20



Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Distribution
                                                                 Drawing Rev. 1

           AFC                                         ADD            IFC
                                        IFB
    (Approved for                                    (Addendum    (Issued for
                                  (Issued for Bid)
    Construction)                                      Issued)   Construction)
    100% Complete                 (Drawing Bid Set                   (Contract
          (Final)                     to GCs)                    awarded: Cons.
                                                                    distributes
                                                                 drawings to GC)




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Tracking Contract Drawings
        Compress the drawing approval cycle
        Maintain an accurate history of revisions
        Create and maintain distribution lists
           Identify copies sent and paper size
        Relate drawing changes to financial changes
        Create transmittals for each drawing set sent for review or
        distribution




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Steps for Managing Drawings
         1.  Establish standard dictionaries
         2.  Define distribution lists
         3. Create multiple drawings for each discipline
         4. Package a group of drawings as a set 
         5. Log issued drawing revisions
         6. Forward the drawing set for review or distribution
         7. Update drawings by reviewer




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Defining Distribution Lists
         Create distribution lists for project participants 
         involved in the transmittal, submittal, or contract 
         drawing processes
         Contain individuals who should receive drawings
              Review or approval
              Copies of the drawing




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Link Contract Manager to
                         Primavera Schedule




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Connect a primavera schedule to Contract Manager
         Track submittal and delivery activities
         View contractors activities in daily reports
         Add change order activities when they occur
         Drawing sets
                   Monitor key design reviews
                   How will the impact your schedule
          Link requisition line items to activities
          Export Contract Manager data to P3


Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Note:
      You can link specific P3ec activities to documents 
        throughout Contract Manager.




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Staying on Top of  Issues 
         Benefit statement

              Keeps all documents organized to allow you to quickly 
              retrieve them in order to make informed decisions




Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
Questions?

Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC

Contract Manager Presentation

  • 1.
  • 2.
    Business Needs Benefits & Objectives Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 3.
    Business Needs   – Track submittal reviews and determine the impact on the schedule – Manage design changes and distribute contract drawing revisions to contractor – Review change orders for financial and technical impact and make recommendations – Forecast project Budget – Communicate up to date project details to your project team Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 4.
    Contract Manager Workflow ISSUES Submittal s Deliveries Drawings Contracts Transmittal No. 10 Transmittal Daily TO: PO's Reports s FROM: Meetings RFI’s/Chang Requisitions es Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 5.
  • 6.
    Tracking  Project Budget  (Cost Worksheet) Budget Cost (Owner & Main Contractor) Committed Cost (Main Contractor & Subcontractors) Actual Cost (ALL) Analyze budgets , review commitment documents and record requisitions and invoices as they are received. The Cost Worksheet automatically collects and summarizes detailed cost elements from contracts, requisitions, changes and purchase orders and dynamically displays them so you can forecast project costs and simplify contract control. Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 7.
    Payment Requests (Requisitions) Project Cost Worksheet Budget Committed Actual Invoices Budget Changes Contracts or P.O. Changes Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 8.
  • 9.
    Tracks submittals Reviews and approvals . Ensures materials are perfectly to spec. Controls changes From the estimate phase to final approval for both budgeted and  committed costs.  Identifies impacts on project costs and schedule. According to the nature of the change and the company’s process for  recording and tracking changes, the Change Management module  enables you to create a customized workflow to meet your company’s  change management needs.  Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 10.
    • Track Submittals:- Submittals include contract drawings, Sample materials, and Permits that need approval. this Submittals module helps to ensure contract compliance by tracking who received what and when they received it. Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 11.
    SUBMITTAL FLOW Review/Approval Received Sent Returned Forward If DAYS HELD GT Planned Transmittal Transmittal Dunning letter Correspondence Sent Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 12.
    Project Changes After project parties accept a contract or purchase order and work begins, any changes resulting from changed specifications, scope of work, site conditions, or project schedule affect the initial contract. The process of formally changing a contract requires several steps, each of which should be fully documented Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 13.
    Subcontractor Change Order CO Contractor Owner CO CHANGE ORDER COR CHANGE ORDER REQUEST Subcontractor Contractor PCO PROPOSED CHANGE ORDER RFP REQUEST FOR PROPOSAL Contractor Designer ANS ANSWER RFI REQUEST FOR INFORMATION Contractor Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 14.
  • 15.
    Contract Drawings The drawing log ensures that everyone is building using the latest drawings and specifications. Contract Manager helps you to use the drawings log to manage your drawings, keep on top of the latest revision, and ensure the distribution to all project participants. Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 16.
    Design Review Drawing Rev. A Drawing Rev. B Civil Civil DWG C1-C10 DWG C1-C15 30% Complete 60% Complete 15% Complete (Review Meeting) (Review Meeting) Elect Elect DWG E1-E8 DWG E1-E10 Concept Design Schematic Development Progress MECH MECH DWG M1-M20 DWG M1-M20 STRUCT STRUCT DWG S1-S20 DWG S1-S15 Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 17.
    Design Review Drawing Rev. C Drawing Rev. D Civil Civil DWG C1-C20 DWG C1-C20 60% Complete 95% Complete (Review (Review Meeting) Meeting) Elect Elect DWG E1-E12 DWG E1-E12 Progress Progress MECH MECH DWG M1-M20 DWG M1-M20 STRUCT STRUCT DWG S1-S20 DWG S1-S20 Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 18.
    Distribution Drawing Rev. 1 AFC ADD IFC IFB (Approved for (Addendum (Issued for (Issued for Bid) Construction) Issued) Construction) 100% Complete (Drawing Bid Set (Contract (Final) to GCs) awarded: Cons. distributes drawings to GC) Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 19.
    Tracking Contract Drawings Compress the drawing approval cycle Maintain an accurate history of revisions Create and maintain distribution lists Identify copies sent and paper size Relate drawing changes to financial changes Create transmittals for each drawing set sent for review or distribution Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 20.
    Steps for Managing Drawings 1.  Establish standard dictionaries 2.  Define distribution lists 3. Create multiple drawings for each discipline 4. Package a group of drawings as a set  5. Log issued drawing revisions 6. Forward the drawing set for review or distribution 7. Update drawings by reviewer Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 21.
    Defining Distribution Lists Create distribution lists for project participants  involved in the transmittal, submittal, or contract  drawing processes Contain individuals who should receive drawings Review or approval Copies of the drawing Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 22.
  • 23.
    Link Contract Managerto Primavera Schedule Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 24.
    Connect a primavera schedule to Contract Manager Track submittal and delivery activities View contractors activities in daily reports Add change order activities when they occur Drawing sets Monitor key design reviews How will the impact your schedule Link requisition line items to activities Export Contract Manager data to P3 Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 25.
    Note: You can link specific P3ec activities to documents  throughout Contract Manager. Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 26.
    Staying on Top of  Issues  Benefit statement Keeps all documents organized to allow you to quickly  retrieve them in order to make informed decisions Eng: Anas El-Wahdan,PMP,Who'sWho,CPMC
  • 27.