MAIN POINTS
• BACKGROUND AND DESCRIPTION OF THE PROBLEM
• DESIGN LIMITATIONS AND METHODOLOGIES
• COVERAGE DESIGN
• COMPONENT CALCULATIONS
• LINK BUDGET CALCULATIONS
• OPTIMIZATION STAGE
BACKGROUND AND DESCRIPTION OF
THE PROBLEM
MAIN RESEARCH OBJECTIVE (PROJECT
SCOPE)
TECHNICAL NEED FOR THIS PROJECT
• LACK OF COVERAGE IN THE MALL (SPECIALLY 3G COVERAGE)
• WE NEED MORE AND MORE CAPACITY INDOOR
• THE MACRO SITES MUST BE SUPPORTED WITH MICRO AND PICO SITES IN THE MALL
• THE DESIGN MUST BE OPTIMUM AND FLEXIBLE FOR FUTURE NEEDS (DATA RATES, NEW SERVICES AND
MORE CAPACITY) AND IT MUST KEEP UP WITH EXTENSIONS
BUSINESS NEEDS FOR THIS PROJECT
• 70-80% OF CALLS ORIGINATE IN THE INDOOR AREA
• THIS INVESTMENT MUST MAKE A POSITIVE BUSINESS CASE AND A GOOD AND FAST ROI
• COST REDUCTION OF UP TO 65% CAN BE ACHIEVED BY COVERING THE 3G (AND 4G IF NEEDED ALSO)
USERS FROM INSIDE THE BUILDING WITH INDOOR COVERAGE SYSTEMS
THE PROJECT METHODOLOGY AND
LIMITATION (CHALLENGES)
THE 3G CHALLENGE
• POWER LOAD PER USER WILL INCREASE IN THE INDOOR (POWER IS A VERY IMPORTANT RESOURCE IN 3G)
• MANY SOFT HAND OVERS ARE EXPECTED
• PILOT POLLUTION IS EXPECTED DUE TO SMALL AREA AND THE MACRO SITES EFFECT
BASIC INDOOR METHODOLOGIES COMMON
FOR 2G AND 3G
• ISOLATION
• HIGH RISE PROBLEM
• THE ZONE PLANNING CONCEPT
ISOLATION
HIGH RISE PROBLEM
THE ZONE PLANNING CONCEPT
FREQUENCY SELECTION
• SELECTING 3 FREQUENCIES FROM 1800 BAND TO INCREASE PENETRATION
• SELECTING 1 FREQUENCY 2100 AND USE THREE CODES
• ALL VOICE CALLS WILL BE ORIGINATED ON 2G AND USE 3G FOR DATA ONLY TO MAXIMIZE THROUGHPUT
REUSE AREA CALCULATIONS
REUSE AREA CALCULATIONS
• FOR 24 TIME SLOTS AND 2% GOS, I WIIL HAVE 16.63 E
• AS THE GIVEN DATA IS 150 USERS EVERY 100 M SO I CALCULATED THE AREA AS 100*100= 10,000 M2
WITH 30ME FOR EVERY USER
• THEN I WILL HAVE 4.5 E FOR EVERY 10,000 M2 (ACCORDING TO THE GIVEN DATA)
REUSE AREA CALCULATIONS
4.5------10,000M2
16.63------AREA TO BE REUSED
• AREA= (16.63*10,000)/4.5=36,900 M2
• I WILL REUSE EVERY 36,900 M2 (OR EVERY ONE CELL)
FOOD COURT (1 CELL 2G AND 1 CELL 3G)
CARREFOUR AND THE CORRIDOR IN FRONT
OF IT (1 SECTOR)
CENTER POINT AREA (1 SECTOR)
GARAGE (REPEATERS FROM CENTER POINT
AREA)
THE FOUNTAIN AREA AND BUILDINGS
AROUND IT (1 CELL)
THE MAIN CORRIDOR OF THE MALL IN THE 3
FLOORS
• 2 SECTORS IN EVERY FLOOR EXCEPT FLOOR 1 BECAUSE IT IS SMALLER
FLOOR 1
FLOOR 2
FLOOR 3
PARKING 1 AND 2 AND STREETS NEAR TO
THEM
PARKING 3 AND STREETS NEAR TO IT
DAS DISTRIBUTION
ANTENNAS
• 5 STREET LEVEL-DIRECTIONAL ANTENNAS
• 10 OMNIDIRECTIONAL ANTENNAS
• 1 MICROWAVE ANTENNA IN THE SITE TO TRANSMIT ALL THE TRAFFIC TO THE BSC
REPEATERS
• 7 REPEATERS AND MAY BE INCREASED AFTER OPTIMIZATION
SPLITTERS
• NO. OF 1:3 SPLITTER = 3
• NO. OF 1:2 SPLITTER = 1
RRU (ONE FOR EVERY AREA)
• FOUNTAIN AREA
• FOOD COURT AREA
• FLOOR 3 AREA (CARREFOUR AND THE MAIN CORRIDOR)
• FLOOR 1 AND 2 TOGETHER
MASTER UNIT
• ONE MASTER UNIT WILL BE PLACED IN THE TELECOM ROOM
SHELTER, ACS AND CABLES
• 1 SHELTER TO PROTECT THE MASTER UNIT
• 3 KM OF COAXIAL CABLES
LINK BUDGET CALCULATIONS
• COAXIAL LOSSES
• SPLITTER LOSSES
• ANTENNA AND AMPLIFIERS GAINS
• AIR LOSSES
• WALL AND BODY LOSSES
WALK TEST
• SIGNAL REACH IN THE MALL
• SIGNAL QUALITY
• GOS
• MEASURING ANY KPI
FINAL PLANNING STAGE
• IT IS EXPECTED TO FIND SOME PROBLEMS
• A MAXIMUM DEVIATION +VE OR –VE 10 % IS ACCEPTED FINALLY.
• IMPROVING ANY KPI UNDER THE EXPECTED PERFORMANCE
HOW MANY SITES YOU NEED TO COVER
YOUR SOLUTION?
• I WILL USE ACTIVE DAS SOLUTION SO I USE ONE MASTER UNIT AND DISTRIBUTE USING MULTIPLE RRUS
IN DIFFERENT AREAS AND FINALLY ALL TRAFFIC WILL BE TRANSMITTED BY ONE MICROWAVE LINK.
WHAT ARE THE TYPES OF SITES OF SITES
YOU WILL USE AT YOUR DESIGN?
• ALL INDOOR RRUS AND ANTENNAS ARE INDOOR SITES.
• THE PARKING AREA AND THE FOUNTAIN ARE STREET LEVEL SITES.
IF WE HAVE A TRAFFIC OF 20E UNDER
GOS=2%, IS IT BETTER TO USE ONE CELL OR
TO SPLIT THE TRAFFIC BETWEEN TWO
CELLS EACH CARRY 10E?
• FOR 2G CALCULATIONS ONLY I HAVE 16.63E SO I CANNOT USE ONE CELL TO COVER 20E WITH FULL RATE
BUT I CAN USE HALF RATE TECHNIQUE TO COVER ALL THE 20E IN ONE CELL.
• IF I SPLIT THE CELL I CAN COVER 32E AND IT WILL BE WASTE OF RESOURCES
NOTE
• I DID NOT USE THE HALF RATE TECHNIQUE IN MY CALCULATIONS BECAUSE THE TRAFFIC IN THE MALL WILL
INCREASE GRADUALLY AND I WANT THE DESIGN TO LAST LONGEST TIME IN THE FUTURE TO ACCEPT NEW
USERS, MORE CAPACITY, NEW SERVICES AND MORE DATA RATES
NOTE
• I DID NOT USE BACK TO BACK ANTENNA TECHNIQUE DUE TO MALL STRUCTURE (CORRIDORS AND
SQUARES)
NOTE
• I MAY USE OPTICAL FIBER TO TRANSMIT SIGNAL TO THE FOUNTAIN AREA OR I MAY CONNECT THEM BY A
MICROWAVE LINK

CFC Planning presentation

  • 3.
    MAIN POINTS • BACKGROUNDAND DESCRIPTION OF THE PROBLEM • DESIGN LIMITATIONS AND METHODOLOGIES • COVERAGE DESIGN • COMPONENT CALCULATIONS • LINK BUDGET CALCULATIONS • OPTIMIZATION STAGE
  • 4.
  • 5.
    MAIN RESEARCH OBJECTIVE(PROJECT SCOPE)
  • 6.
    TECHNICAL NEED FORTHIS PROJECT • LACK OF COVERAGE IN THE MALL (SPECIALLY 3G COVERAGE) • WE NEED MORE AND MORE CAPACITY INDOOR • THE MACRO SITES MUST BE SUPPORTED WITH MICRO AND PICO SITES IN THE MALL • THE DESIGN MUST BE OPTIMUM AND FLEXIBLE FOR FUTURE NEEDS (DATA RATES, NEW SERVICES AND MORE CAPACITY) AND IT MUST KEEP UP WITH EXTENSIONS
  • 7.
    BUSINESS NEEDS FORTHIS PROJECT • 70-80% OF CALLS ORIGINATE IN THE INDOOR AREA • THIS INVESTMENT MUST MAKE A POSITIVE BUSINESS CASE AND A GOOD AND FAST ROI • COST REDUCTION OF UP TO 65% CAN BE ACHIEVED BY COVERING THE 3G (AND 4G IF NEEDED ALSO) USERS FROM INSIDE THE BUILDING WITH INDOOR COVERAGE SYSTEMS
  • 8.
    THE PROJECT METHODOLOGYAND LIMITATION (CHALLENGES)
  • 9.
    THE 3G CHALLENGE •POWER LOAD PER USER WILL INCREASE IN THE INDOOR (POWER IS A VERY IMPORTANT RESOURCE IN 3G) • MANY SOFT HAND OVERS ARE EXPECTED • PILOT POLLUTION IS EXPECTED DUE TO SMALL AREA AND THE MACRO SITES EFFECT
  • 10.
    BASIC INDOOR METHODOLOGIESCOMMON FOR 2G AND 3G • ISOLATION • HIGH RISE PROBLEM • THE ZONE PLANNING CONCEPT
  • 11.
  • 12.
  • 13.
  • 15.
    FREQUENCY SELECTION • SELECTING3 FREQUENCIES FROM 1800 BAND TO INCREASE PENETRATION • SELECTING 1 FREQUENCY 2100 AND USE THREE CODES • ALL VOICE CALLS WILL BE ORIGINATED ON 2G AND USE 3G FOR DATA ONLY TO MAXIMIZE THROUGHPUT
  • 17.
  • 18.
    REUSE AREA CALCULATIONS •FOR 24 TIME SLOTS AND 2% GOS, I WIIL HAVE 16.63 E • AS THE GIVEN DATA IS 150 USERS EVERY 100 M SO I CALCULATED THE AREA AS 100*100= 10,000 M2 WITH 30ME FOR EVERY USER • THEN I WILL HAVE 4.5 E FOR EVERY 10,000 M2 (ACCORDING TO THE GIVEN DATA)
  • 19.
    REUSE AREA CALCULATIONS 4.5------10,000M2 16.63------AREATO BE REUSED • AREA= (16.63*10,000)/4.5=36,900 M2 • I WILL REUSE EVERY 36,900 M2 (OR EVERY ONE CELL)
  • 21.
    FOOD COURT (1CELL 2G AND 1 CELL 3G)
  • 22.
    CARREFOUR AND THECORRIDOR IN FRONT OF IT (1 SECTOR)
  • 23.
  • 24.
    GARAGE (REPEATERS FROMCENTER POINT AREA)
  • 25.
    THE FOUNTAIN AREAAND BUILDINGS AROUND IT (1 CELL)
  • 26.
    THE MAIN CORRIDOROF THE MALL IN THE 3 FLOORS • 2 SECTORS IN EVERY FLOOR EXCEPT FLOOR 1 BECAUSE IT IS SMALLER
  • 27.
  • 28.
  • 29.
  • 30.
    PARKING 1 AND2 AND STREETS NEAR TO THEM
  • 31.
    PARKING 3 ANDSTREETS NEAR TO IT
  • 33.
  • 35.
    ANTENNAS • 5 STREETLEVEL-DIRECTIONAL ANTENNAS • 10 OMNIDIRECTIONAL ANTENNAS • 1 MICROWAVE ANTENNA IN THE SITE TO TRANSMIT ALL THE TRAFFIC TO THE BSC
  • 36.
    REPEATERS • 7 REPEATERSAND MAY BE INCREASED AFTER OPTIMIZATION
  • 37.
    SPLITTERS • NO. OF1:3 SPLITTER = 3 • NO. OF 1:2 SPLITTER = 1
  • 38.
    RRU (ONE FOREVERY AREA) • FOUNTAIN AREA • FOOD COURT AREA • FLOOR 3 AREA (CARREFOUR AND THE MAIN CORRIDOR) • FLOOR 1 AND 2 TOGETHER
  • 39.
    MASTER UNIT • ONEMASTER UNIT WILL BE PLACED IN THE TELECOM ROOM
  • 40.
    SHELTER, ACS ANDCABLES • 1 SHELTER TO PROTECT THE MASTER UNIT • 3 KM OF COAXIAL CABLES
  • 42.
    LINK BUDGET CALCULATIONS •COAXIAL LOSSES • SPLITTER LOSSES • ANTENNA AND AMPLIFIERS GAINS • AIR LOSSES • WALL AND BODY LOSSES
  • 44.
    WALK TEST • SIGNALREACH IN THE MALL • SIGNAL QUALITY • GOS • MEASURING ANY KPI
  • 45.
    FINAL PLANNING STAGE •IT IS EXPECTED TO FIND SOME PROBLEMS • A MAXIMUM DEVIATION +VE OR –VE 10 % IS ACCEPTED FINALLY. • IMPROVING ANY KPI UNDER THE EXPECTED PERFORMANCE
  • 47.
    HOW MANY SITESYOU NEED TO COVER YOUR SOLUTION? • I WILL USE ACTIVE DAS SOLUTION SO I USE ONE MASTER UNIT AND DISTRIBUTE USING MULTIPLE RRUS IN DIFFERENT AREAS AND FINALLY ALL TRAFFIC WILL BE TRANSMITTED BY ONE MICROWAVE LINK.
  • 48.
    WHAT ARE THETYPES OF SITES OF SITES YOU WILL USE AT YOUR DESIGN? • ALL INDOOR RRUS AND ANTENNAS ARE INDOOR SITES. • THE PARKING AREA AND THE FOUNTAIN ARE STREET LEVEL SITES.
  • 49.
    IF WE HAVEA TRAFFIC OF 20E UNDER GOS=2%, IS IT BETTER TO USE ONE CELL OR TO SPLIT THE TRAFFIC BETWEEN TWO CELLS EACH CARRY 10E? • FOR 2G CALCULATIONS ONLY I HAVE 16.63E SO I CANNOT USE ONE CELL TO COVER 20E WITH FULL RATE BUT I CAN USE HALF RATE TECHNIQUE TO COVER ALL THE 20E IN ONE CELL. • IF I SPLIT THE CELL I CAN COVER 32E AND IT WILL BE WASTE OF RESOURCES
  • 50.
    NOTE • I DIDNOT USE THE HALF RATE TECHNIQUE IN MY CALCULATIONS BECAUSE THE TRAFFIC IN THE MALL WILL INCREASE GRADUALLY AND I WANT THE DESIGN TO LAST LONGEST TIME IN THE FUTURE TO ACCEPT NEW USERS, MORE CAPACITY, NEW SERVICES AND MORE DATA RATES
  • 51.
    NOTE • I DIDNOT USE BACK TO BACK ANTENNA TECHNIQUE DUE TO MALL STRUCTURE (CORRIDORS AND SQUARES)
  • 52.
    NOTE • I MAYUSE OPTICAL FIBER TO TRANSMIT SIGNAL TO THE FOUNTAIN AREA OR I MAY CONNECT THEM BY A MICROWAVE LINK