SlideShare a Scribd company logo
Page 1 / 4
Case Study
West of Duddon Sands OWF (2013) – 108 cables / 118,000 m
After starting up the project in early June 2013, 164 days later CT Offshore could proudly announce that
a remarkable record in cable laying was set of ‘108 cables in 164 days’, where some days up to 3 cables
per day were installed, both 1st
and 2nd
end pull in and surface laid.
Introduction of Mini ROVs
This was also the project for CT Offshore to introduce the use of Mini ROVs, which significantly reduced
the time taken for preparing the messenger wire safely and efficiently, as the need to reduce divers Is
required.
CLV SIA deck
1. Scope of Work
Installation and burial of 11 PCC cables and 97 ICC cables, using the CPS system Tekmar.
 Cable transport by Freighter of cables in consecutive lengths
 Cable load-out
 Pre-lay Multibeam survey (MBES)
 Pre-lay grapnel run (PLGR)
 Rigging of towers and messenger wire work
 Array cable installation
 Post-lay inspection (PLI)
 Optical time delay reflection (OTDR) test
 Post-lay burial (PLB)
 Post-burial inspection (PLI)
 ROV post-burial survey
Vessels and equipment utilized
Cable Installation: CLV SIA
MBES / TSS Survey: MV LINE / MV SANDER 2
Trenching vessel: MV MAESK RESPONDER / MV VOS SYMPATHY
Trencher ROV: CTO 103
Execution period, surface laid cables
Start-up 5 June 2013
Completed 17 November 2013
“Statement from the client, half-way through project
DONG Energy - Lars Bruun, Installation Manager…
“During the still on-going array cable installation work, we have had
very good co-operation with CT Offshore.
Our WoDS project team is very content with CT Offshores’ cable
installation performance to date. They have been proactive, shown
initiative and professionalism in their performance which is reflected
in the quality of the cable installation work up to now.”
Page 2 / 4
Raw Installation Time – 108 ICC Cables (West of Duddon Sands)
1.1 Learning curve, 108 cables
2.1 Min. / Average installation time (hrs.) of 108 cables. 2.2. Duration of time vs. number of cables
2.3 Assigned in Project – Overall time consumption, according to DPR report structure
Page 3 / 4
2.4 Assigned in Project – Overall time consumption (DPR report in further details).
CLV SIA at West of Duddon Sands OWF
Cable transport by Freighter Cables at harbour site Cables being loaded at turntable
Page 4 / 4
Cables loaded at CLV SIA CLV SIA completing the 2nd end pull
Mini ROVs were introduced as an innovative way of reducing time for messenger wire set up and documentation for the pull ins.

More Related Content

Similar to Case study_WoDS_rev1

GM-casestudy-uninett
GM-casestudy-uninettGM-casestudy-uninett
GM-casestudy-uninettScott Miller
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1robinking277
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
Jerry Brown
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas PipelineBoudewijn Baan
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
jose bonifacio de souza leite cuadros
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
MEC Intelligence
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall Mine
Ulimella Siva Sankar
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
seifelsaie2
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Tahar Hajji
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
Stockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideStockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideThomas Ingrey
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Follow me on Twitter @Stockshaman
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15Greg Clifford
 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochure
Global Gravity
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000daniel cobar
 

Similar to Case study_WoDS_rev1 (20)

GM-casestudy-uninett
GM-casestudy-uninettGM-casestudy-uninett
GM-casestudy-uninett
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas Pipeline
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall Mine
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
Stockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideStockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with Pride
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
 
Dana Medway HR
Dana Medway HRDana Medway HR
Dana Medway HR
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
 
LMCV
LMCVLMCV
LMCV
 
RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochure
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 

Case study_WoDS_rev1

  • 1. Page 1 / 4 Case Study West of Duddon Sands OWF (2013) – 108 cables / 118,000 m After starting up the project in early June 2013, 164 days later CT Offshore could proudly announce that a remarkable record in cable laying was set of ‘108 cables in 164 days’, where some days up to 3 cables per day were installed, both 1st and 2nd end pull in and surface laid. Introduction of Mini ROVs This was also the project for CT Offshore to introduce the use of Mini ROVs, which significantly reduced the time taken for preparing the messenger wire safely and efficiently, as the need to reduce divers Is required. CLV SIA deck 1. Scope of Work Installation and burial of 11 PCC cables and 97 ICC cables, using the CPS system Tekmar.  Cable transport by Freighter of cables in consecutive lengths  Cable load-out  Pre-lay Multibeam survey (MBES)  Pre-lay grapnel run (PLGR)  Rigging of towers and messenger wire work  Array cable installation  Post-lay inspection (PLI)  Optical time delay reflection (OTDR) test  Post-lay burial (PLB)  Post-burial inspection (PLI)  ROV post-burial survey Vessels and equipment utilized Cable Installation: CLV SIA MBES / TSS Survey: MV LINE / MV SANDER 2 Trenching vessel: MV MAESK RESPONDER / MV VOS SYMPATHY Trencher ROV: CTO 103 Execution period, surface laid cables Start-up 5 June 2013 Completed 17 November 2013 “Statement from the client, half-way through project DONG Energy - Lars Bruun, Installation Manager… “During the still on-going array cable installation work, we have had very good co-operation with CT Offshore. Our WoDS project team is very content with CT Offshores’ cable installation performance to date. They have been proactive, shown initiative and professionalism in their performance which is reflected in the quality of the cable installation work up to now.”
  • 2. Page 2 / 4 Raw Installation Time – 108 ICC Cables (West of Duddon Sands) 1.1 Learning curve, 108 cables 2.1 Min. / Average installation time (hrs.) of 108 cables. 2.2. Duration of time vs. number of cables 2.3 Assigned in Project – Overall time consumption, according to DPR report structure
  • 3. Page 3 / 4 2.4 Assigned in Project – Overall time consumption (DPR report in further details). CLV SIA at West of Duddon Sands OWF Cable transport by Freighter Cables at harbour site Cables being loaded at turntable
  • 4. Page 4 / 4 Cables loaded at CLV SIA CLV SIA completing the 2nd end pull Mini ROVs were introduced as an innovative way of reducing time for messenger wire set up and documentation for the pull ins.