SlideShare a Scribd company logo
1 of 5
Download to read offline
Page 1 / 5
Case Study
Borkum Riffgrund 1 OWF (2014) – 43 ICC cables
This task was the first project in German waters for CT Offshore. The company’s cable installation vessel SIA
was supported by survey vessel MV SANDER 2, also owned and operated by CT Offshore, installing a total
number of 43 cables at DONG Energy’s 277MW wind farm project.
1. Scope of Work
Installation and burial of 43 inter-array cables, using CPS system Seaproof.
 Cable load-out
 Pre-lay Multibeam survey (MBES)
 Pre-lay grapnel run (PLGR)
 Rigging of towers and messenger wire work
 Array cable installation
 Post-lay inspection (PLI)
 Optical time delay reflection (OTDR) test
 Post-lay burial (PLB)
 Post-burial inspection (PLI)
 ROV post-burial survey
Additional works (1 cable)
 1 cable to be installed at DONG Energy’s test suction bucket foundation
 Recovery and replacement of 1 PCC cable
Vessels and equipment utilized
Cable Installation: CLV SIA
MBES / TSS Survey: MV SANDER 2
Trenching vessel: VOS SYMPATHY
Trencher ROV: CTO 103
Crew Transfer Vessels: Njord Skua, Njord Avocet, Marineco Stingray, Fob Lady
Execution period, free surface cable laid
Start-up 4 July 2014
Completed 2 September 2014
Preparing for cable load out at harbour
“Client says…
DONG Energy – Sam Gardner, Offshore Client Representative, Cable Installation,
Borkum Riffgrund 1…
“Throughout the project your team on board the Sia showed good
knowledge, experience and confidence in cable installation. They
maintained a professional attitude at all times and successfully
surface laid 44 cables without incident. This is a huge achievement
and one you should all be very proud of. Congratulations on a job
well done and I look forward to working with you all in the future.
Good luck with the burial campaign.”
Page 2 / 5
2. Cable load out – self designed harbour set up
For this project the cables protection system Seaproof was chosen.
To ensure an optimum cable load and handling, CT Offshore designed our own load out arrangement, which
allowed us to mount the Seaproof onshore and load it onto the CLV SIA in a quick and safe way.
Nordenham in Germany was chosen for cable load out.
3. Raw Installation Time
It was the first time for CT Offshore to install cables with the CPS system Seaproof. Despite the limited practical
knowledge with this specific type, the learning curve improved satisfactory.
3.1 raw installation time of 43 inter-array cables (green = Raw Installation Time)
Page 3 / 5
3.2 Min. / Average installation time (hrs.) of 43 cable 3.3. Duration of time vs. number of cables
Page 4 / 5
Cable Protection System Seaproof
The experienced team on board CLV SIA at work on the Bridge.
Page 5 / 5
Beautiful sun set while MV SANDER 2 is running a pre-lay MBES survey.

More Related Content

Similar to Case study_BKR1_rev1

Case study_GYM_rev1
Case study_GYM_rev1Case study_GYM_rev1
Case study_GYM_rev1Rune Kaltoft
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Jerry Brown
 
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...Allen Gibson
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptxAbdalmoedAlaiashy2
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Jerry Brown
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
DeesideSeaways MPSS Presentation Ver 3
DeesideSeaways MPSS  Presentation Ver 3DeesideSeaways MPSS  Presentation Ver 3
DeesideSeaways MPSS Presentation Ver 3Craig Lang
 
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment SystemOffshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment SystemJay Nowlin
 
[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution Monitoring[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution MonitoringLeo Santana
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1robinking277
 
Abfad ltd Company Profile November 2014
Abfad ltd Company Profile November 2014Abfad ltd Company Profile November 2014
Abfad ltd Company Profile November 2014Chris Haritou
 
Abfad ltd company profile november 2014
Abfad ltd company profile november 2014Abfad ltd company profile november 2014
Abfad ltd company profile november 2014Chris Haritou
 
CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016Dave Bryant
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
Abfad Ltd General Services Presentation
Abfad Ltd General Services PresentationAbfad Ltd General Services Presentation
Abfad Ltd General Services PresentationAbfad Limited
 
Aberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyAberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyPurdicom
 

Similar to Case study_BKR1_rev1 (20)

Case study_GYM_rev1
Case study_GYM_rev1Case study_GYM_rev1
Case study_GYM_rev1
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
DeesideSeaways MPSS Presentation Ver 3
DeesideSeaways MPSS  Presentation Ver 3DeesideSeaways MPSS  Presentation Ver 3
DeesideSeaways MPSS Presentation Ver 3
 
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment SystemOffshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
 
Ap112 lcm4670 heavy lift load distribution monitoring
Ap112   lcm4670 heavy lift load distribution monitoringAp112   lcm4670 heavy lift load distribution monitoring
Ap112 lcm4670 heavy lift load distribution monitoring
 
[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution Monitoring[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution Monitoring
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1
 
Abfad ltd Company Profile November 2014
Abfad ltd Company Profile November 2014Abfad ltd Company Profile November 2014
Abfad ltd Company Profile November 2014
 
Abfad ltd company profile november 2014
Abfad ltd company profile november 2014Abfad ltd company profile november 2014
Abfad ltd company profile november 2014
 
CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
Work Term Overview
Work Term OverviewWork Term Overview
Work Term Overview
 
Abfad Ltd General Services Presentation
Abfad Ltd General Services PresentationAbfad Ltd General Services Presentation
Abfad Ltd General Services Presentation
 
Aberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyAberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case Study
 

Case study_BKR1_rev1

  • 1. Page 1 / 5 Case Study Borkum Riffgrund 1 OWF (2014) – 43 ICC cables This task was the first project in German waters for CT Offshore. The company’s cable installation vessel SIA was supported by survey vessel MV SANDER 2, also owned and operated by CT Offshore, installing a total number of 43 cables at DONG Energy’s 277MW wind farm project. 1. Scope of Work Installation and burial of 43 inter-array cables, using CPS system Seaproof.  Cable load-out  Pre-lay Multibeam survey (MBES)  Pre-lay grapnel run (PLGR)  Rigging of towers and messenger wire work  Array cable installation  Post-lay inspection (PLI)  Optical time delay reflection (OTDR) test  Post-lay burial (PLB)  Post-burial inspection (PLI)  ROV post-burial survey Additional works (1 cable)  1 cable to be installed at DONG Energy’s test suction bucket foundation  Recovery and replacement of 1 PCC cable Vessels and equipment utilized Cable Installation: CLV SIA MBES / TSS Survey: MV SANDER 2 Trenching vessel: VOS SYMPATHY Trencher ROV: CTO 103 Crew Transfer Vessels: Njord Skua, Njord Avocet, Marineco Stingray, Fob Lady Execution period, free surface cable laid Start-up 4 July 2014 Completed 2 September 2014 Preparing for cable load out at harbour “Client says… DONG Energy – Sam Gardner, Offshore Client Representative, Cable Installation, Borkum Riffgrund 1… “Throughout the project your team on board the Sia showed good knowledge, experience and confidence in cable installation. They maintained a professional attitude at all times and successfully surface laid 44 cables without incident. This is a huge achievement and one you should all be very proud of. Congratulations on a job well done and I look forward to working with you all in the future. Good luck with the burial campaign.”
  • 2. Page 2 / 5 2. Cable load out – self designed harbour set up For this project the cables protection system Seaproof was chosen. To ensure an optimum cable load and handling, CT Offshore designed our own load out arrangement, which allowed us to mount the Seaproof onshore and load it onto the CLV SIA in a quick and safe way. Nordenham in Germany was chosen for cable load out. 3. Raw Installation Time It was the first time for CT Offshore to install cables with the CPS system Seaproof. Despite the limited practical knowledge with this specific type, the learning curve improved satisfactory. 3.1 raw installation time of 43 inter-array cables (green = Raw Installation Time)
  • 3. Page 3 / 5 3.2 Min. / Average installation time (hrs.) of 43 cable 3.3. Duration of time vs. number of cables
  • 4. Page 4 / 5 Cable Protection System Seaproof The experienced team on board CLV SIA at work on the Bridge.
  • 5. Page 5 / 5 Beautiful sun set while MV SANDER 2 is running a pre-lay MBES survey.