Abstract
Do you have a handle on investment
management but not sure how to manage your
resources effectively? All you need are Straight
As - four (4) of them to be precise; Availability,
Allocation, Assignment and Actuals. Attending
this session will give you a solid view of the
"what and the how" the 4 As relate and you will
be well on your way to becoming a Resource
Management Rock Star!
Kismet
Silva-Smith
CA Technologies
Instructor
4 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Agenda
WHAT IS RESOURCE MANAGEMENT?
AVAILABILITY
RESOURCE PLANNING ROCK STAR VIEWS
ALLOCATION
ASSIGNMENTS
ACTUALS
1
2
3
4
5
6
5 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Summary
A Few Words to Describe Resource Management
Results
Resource management is the efficient and effective deployment of an organization's resources when they
are needed
Organizations manage all their resources: employees, contractors, partners, and suppliers
Organizations interact with many partners and suppliers on a daily basis, with intertwined business
processes
CA Product and Portfolio Management
(PPM) 4 As
7 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Let’s Define Them!
 Availability – The state of being able to be obtained or used
 Allocation – The state of being designated for a
special purpose
 Assignment – The state of being appointed to perform a
specific duty
 Actual – The state of completed work
8 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Availability
 When a resource is present and ready for use;
at hand; accessible
 When a resource is capable of being attained
 When a resource is willing to serve or assist
9 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Demo
 Resource Properties
 Calendar
– Standard Calendar
– Resource Calendar
– Shifts
– Non-Working Time
10 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Availability
 This is the percentage of time a resource is booked to an
investment, determined by the:
– Start and end date of the resource on the investment
– Hours that the resource works in a day
– Percentage allocation of the resource on the investment
– Non-working time of the resource
Allocation may be Formal
 Hard Book
 Resource Requisition
Allocation may be Informal
 Soft Book
11 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Demo
 Team
— Default
— Allocation Segments
— Allocation Detail
— Capitalization %
— Cost Plan based on
Investment Team
 Resource
— Allocation Summary
— Allocation Detail
 Resource Requisition
— Project Manager requests
— Resource Manager fills request
12 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Assignment
 This is when you associate a resource to a task to complete
the work.
 Estimate to Complete (ETC)
– This is the number of hours planned to complete each task,
determined by:
 A resource’s assignment to a specific task
 The resource's allocation percent to the project
13 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Demo
 Task
– Effort Task
– WBS
– ETC
– Cost Type
– Cost Plan based on Task Assignments
14 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Actuals
 This is the work that has been completed by resources
on tasks.
15 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Demo
 Timesheets
– Actual work
– Save
– Proposed ETC
– Pending Actuals
– Submit/Approve/Post
 Portlets
– Team Member Task Summary
– Task Assignment
– Timesheet Overview
16 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Resource Management Portlets
 Resource Planning
– Workloads
– Allocations
– Unfilled Allocations
– Bookings
– Top Down Planning
– Organizational Demand
– Capacity
– Scenarios
17 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
Q & A
18 © 2015 CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD
For More Information
To learn more, please visit:
http://cainc.to/Nv2VOe
CA World ’15

CA Project and Portfolio Management v14.x: Get Straight A's in Managing Resources Effectively

  • 1.
    Pre-Con Education: CAProject and Portfolio Management v14.x Get Straight As in Managing Resources Effectively Kismet Silva-Smith Agile Management CA Technologies Instructor AMX04E @CAPPM #CAWorld
  • 2.
    3 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Abstract Do you have a handle on investment management but not sure how to manage your resources effectively? All you need are Straight As - four (4) of them to be precise; Availability, Allocation, Assignment and Actuals. Attending this session will give you a solid view of the "what and the how" the 4 As relate and you will be well on your way to becoming a Resource Management Rock Star! Kismet Silva-Smith CA Technologies Instructor
  • 3.
    4 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Agenda WHAT IS RESOURCE MANAGEMENT? AVAILABILITY RESOURCE PLANNING ROCK STAR VIEWS ALLOCATION ASSIGNMENTS ACTUALS 1 2 3 4 5 6
  • 4.
    5 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Summary A Few Words to Describe Resource Management Results Resource management is the efficient and effective deployment of an organization's resources when they are needed Organizations manage all their resources: employees, contractors, partners, and suppliers Organizations interact with many partners and suppliers on a daily basis, with intertwined business processes
  • 5.
    CA Product andPortfolio Management (PPM) 4 As
  • 6.
    7 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Let’s Define Them!  Availability – The state of being able to be obtained or used  Allocation – The state of being designated for a special purpose  Assignment – The state of being appointed to perform a specific duty  Actual – The state of completed work
  • 7.
    8 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Availability  When a resource is present and ready for use; at hand; accessible  When a resource is capable of being attained  When a resource is willing to serve or assist
  • 8.
    9 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Demo  Resource Properties  Calendar – Standard Calendar – Resource Calendar – Shifts – Non-Working Time
  • 9.
    10 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Availability  This is the percentage of time a resource is booked to an investment, determined by the: – Start and end date of the resource on the investment – Hours that the resource works in a day – Percentage allocation of the resource on the investment – Non-working time of the resource Allocation may be Formal  Hard Book  Resource Requisition Allocation may be Informal  Soft Book
  • 10.
    11 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Demo  Team — Default — Allocation Segments — Allocation Detail — Capitalization % — Cost Plan based on Investment Team  Resource — Allocation Summary — Allocation Detail  Resource Requisition — Project Manager requests — Resource Manager fills request
  • 11.
    12 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Assignment  This is when you associate a resource to a task to complete the work.  Estimate to Complete (ETC) – This is the number of hours planned to complete each task, determined by:  A resource’s assignment to a specific task  The resource's allocation percent to the project
  • 12.
    13 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Demo  Task – Effort Task – WBS – ETC – Cost Type – Cost Plan based on Task Assignments
  • 13.
    14 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Actuals  This is the work that has been completed by resources on tasks.
  • 14.
    15 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Demo  Timesheets – Actual work – Save – Proposed ETC – Pending Actuals – Submit/Approve/Post  Portlets – Team Member Task Summary – Task Assignment – Timesheet Overview
  • 15.
    16 © 2015CA. ALL RIGHTS RESERVED.@CAWORLD #CAWORLD Resource Management Portlets  Resource Planning – Workloads – Allocations – Unfilled Allocations – Bookings – Top Down Planning – Organizational Demand – Capacity – Scenarios
  • 16.