GROUP MEMBERS
1. Arni B. Hj. Morshidi P14D461P
2. Anisah Bt Ismail P14D389P
3. Syarifah Rohaya Bt Wan Idris P14D397P
4. Dayang Adelina Bt Hj Abang Muan P14D394P
5. Norhana Aini Bt Saini P14D398P
INTRODUCTION
1. Handles electrical water and waste disposable for a city of Austin, Texas and
surrounding counties
2. Serving more 1 million residents
3. Publicity owned company and an arm of city government and returns its profits to the
community each year
4. Has provided $1.5 billion in dividends back to Austin since 1976 which help fund city
services such as fire, police, emergency medical services, parks and libraries
5. Has one of the largest renewable energy program in the country
PROBLEM
PROBLEM
Billing system did not
integrate with smart
meters and other newer
technologiest
It also lacked newer
customer assistance
options, like ability to
choose the time of the
month that the customer
prefers to pay bills.
SOLUTION
CONTRACTED WITH IBM
In 2009 to create a
centralized billing
system and to run
the system for 5 year
COST
Agreed to pay IBM
$38 mill for building
and installing the
new billing system
and $17 mill for
operating the system
for 5 years after it
completion
NEW SYSTEM
Was slated to handle
electricity, water,
trash and recycling
Q1. THE AUSTIN ENERGY PROJECT A FAILURE? EXPLAIN YOUR
ANSWER
 Yes, the old billing system did not integrate with smart meters and other newer
technologies. It also lacked newer customer assistance option like ability to choose
the time of the month customer prefers to pay bill.
 The new billing system (contracted with IBM) – also failure due to the following
reason.
a) The system was supposed to go alive in early 2011, but it not fully
operational.
b) The software bugs have led to errors in thousands of bills. Over 65,000
customer never received a bill and another 35,000 have received
inaccurate bills. E,g one business that owed Austin $3,000 was instead
charged $300,000.
c) Austin was able to identify affected accounts and work with customers
individually to correct the problems, the company was ill-prepared to
handle the outpouring of customer service department was in danger of
being overrun.
d) Continuous to give the costly impact to their business and customer.
Q2. DESCRIBE THE BUSINESS IMPACT OF THE FALTERING AUSTIN
ENERGY PROJECT
 Instability which caused by the poor and inefficiency system
that continues to have serious and costly impacts to their
business and customer.
 Lack of application of related knowledge, skills tools and
techniques. Eg. Not using internet facilities – lack options to
customer to pay such as smart billing or e-payment system.
 High rise of complaints received when they actually
modernized the billing system. E.g software buds leads to
errors, system is not user friendly.
 Continuous mistake by IBM which caused disappointment to
Austin and the customers.
 Blaming game between Austin and IBM officers – unclear roles
and responsibility.
Q3. TO DEGREE WAS IBM RESPONSIBLE FOR THE PROBLEMS
COUNTERED BY THE AUSTIN ENERGY BILLING PROJECT?
 IBM was responsible for the problems countered by the Austin
are as follow:
a) Delay to complete the system.
b) The system not fully operational.
c) Persistent system errors prevented Austin from billing
apartment residents for water, balancing its books
and filing audit report.
d) Austin losing revenue due to unability the system to
bill for utility properly.
e) Lack quality of services.
Q3. WAS AUSTIN ENERGY BILLING AT FAULT FOR THE PROBLEM?
EXPLAIN YOUR ANSWER.
 Yes, Austin also at fault for the problem.
 Austin should clearly stated what is the project management
involved between Austin and IBM.
 Project management to develop billing system must deal with 5
major variables such as scope, time, cost, quality and risk.
 The role and responsibility of the both party should clearly
define.
 Austin also should monitor the progress of the project.
Q4. WHAT WERE THE SPECIFIC ORGANIZATIONAL OR TECHNICAL
FACTORS AS WELL AS MANAGEMENT FACTORS INVOLVED IN THIS
PROJECT FAILURE?
ORGANIZATIONAL TECHNICAL MANAGEMENT
No realignment internally
and externally
No specific infrastructure No planning and strategy
which cause time slippage
Involved a lot of budget –
exceed the budget
Unreliable systems caused
money loss
No business solution
Fail to meet customer
satisfaction
Inter related with man
power
Lost trust – Customers
away
SOLUTION / LOOKING AHEAD
 Planning the implementation of the project/contract
 Monitor the progress based on the milestone and
achievement
 Clearly stated the objective or output should deliver from the
project
 Risk analysis and how to mitigate the risk
Q5. DESCRIBE THE STEPS AUSTIN ENERGY AND IBM SHOULD HAVE
TAKEN TO BETTER MANAGE THIS PROJECT
Planning the
work
Assessing
the risk
Estimating
and
acquired of
resources to
accomplish
the work
Organization
the work
Directing
execution
Analysis the
result
5 MAJOR VARIABLES IN PROJECT MANAGEMENT FOR IS
PROJECT
MANAGEMENTTime
Scope
Cost
Quality
Risk

More Related Content

Viewers also liked

Albassmi's Job is Not Feasible without IT
Albassmi's Job is Not Feasible without ITAlbassmi's Job is Not Feasible without IT
Albassmi's Job is Not Feasible without IT
nhainisaini
 
What does IT take to go Mobile
What does IT take to go MobileWhat does IT take to go Mobile
What does IT take to go Mobile
nhainisaini
 
What does it take to go mobile
What does it take to go mobileWhat does it take to go mobile
What does it take to go mobile
niz73
 
Designing Drug Virtually
Designing Drug VirtuallyDesigning Drug Virtually
Designing Drug Virtually
nhainisaini
 
Honam Petrochemical's Quest for better Management Reports
Honam Petrochemical's Quest for better Management ReportsHonam Petrochemical's Quest for better Management Reports
Honam Petrochemical's Quest for better Management Reports
nhainisaini
 
Week 6 power point slide -1-case study 1- what does it take to go mobile -ca...
Week 6  power point slide -1-case study 1- what does it take to go mobile -ca...Week 6  power point slide -1-case study 1- what does it take to go mobile -ca...
Week 6 power point slide -1-case study 1- what does it take to go mobile -ca...
Zulkifflee Sofee
 
Knowledge Management and Collaboration at TATA Consulting Services
Knowledge Management and Collaboration at TATA Consulting ServicesKnowledge Management and Collaboration at TATA Consulting Services
Knowledge Management and Collaboration at TATA Consulting Services
nhainisaini
 

Viewers also liked (7)

Albassmi's Job is Not Feasible without IT
Albassmi's Job is Not Feasible without ITAlbassmi's Job is Not Feasible without IT
Albassmi's Job is Not Feasible without IT
 
What does IT take to go Mobile
What does IT take to go MobileWhat does IT take to go Mobile
What does IT take to go Mobile
 
What does it take to go mobile
What does it take to go mobileWhat does it take to go mobile
What does it take to go mobile
 
Designing Drug Virtually
Designing Drug VirtuallyDesigning Drug Virtually
Designing Drug Virtually
 
Honam Petrochemical's Quest for better Management Reports
Honam Petrochemical's Quest for better Management ReportsHonam Petrochemical's Quest for better Management Reports
Honam Petrochemical's Quest for better Management Reports
 
Week 6 power point slide -1-case study 1- what does it take to go mobile -ca...
Week 6  power point slide -1-case study 1- what does it take to go mobile -ca...Week 6  power point slide -1-case study 1- what does it take to go mobile -ca...
Week 6 power point slide -1-case study 1- what does it take to go mobile -ca...
 
Knowledge Management and Collaboration at TATA Consulting Services
Knowledge Management and Collaboration at TATA Consulting ServicesKnowledge Management and Collaboration at TATA Consulting Services
Knowledge Management and Collaboration at TATA Consulting Services
 

Similar to Austin's Energy's Billing System Can't Light Up

Case 6 austin's energy's billing system can't light up
Case 6 austin's energy's billing system can't light upCase 6 austin's energy's billing system can't light up
Case 6 austin's energy's billing system can't light up
dyadelm
 
Austin's energy's billing system can't light up
Austin's energy's billing system can't light upAustin's energy's billing system can't light up
Austin's energy's billing system can't light up
myteratak
 
Austin energy's billing system can't light up
Austin energy's billing system can't light upAustin energy's billing system can't light up
Austin energy's billing system can't light up
niz73
 
Austin's meeting 6
Austin's meeting 6Austin's meeting 6
Austin's meeting 6
szarinammd
 
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Week 6  power point slide -3-case study 3- austin's energy's billing system c...Week 6  power point slide -3-case study 3- austin's energy's billing system c...
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Zulkifflee Sofee
 
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Week 6  power point slide -3-case study 3- austin's energy's billing system c...Week 6  power point slide -3-case study 3- austin's energy's billing system c...
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Zulkifflee Sofee
 
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
Cognizant
 
North American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling SystemNorth American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling System
Cognizant
 
North American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling SystemNorth American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling System
Cognizant
 
Unit 5 Assignment TemplateUse the table below to input your sele.docx
Unit 5 Assignment TemplateUse the table below to input your sele.docxUnit 5 Assignment TemplateUse the table below to input your sele.docx
Unit 5 Assignment TemplateUse the table below to input your sele.docx
marilucorr
 
Direct Insite Presentation December 2013
Direct Insite Presentation December 2013Direct Insite Presentation December 2013
Direct Insite Presentation December 2013Company Spotlight
 
Modernization of ntuc income
Modernization of ntuc incomeModernization of ntuc income
Modernization of ntuc income
niz73
 
Direct Insite Presentation - October 2013
Direct Insite Presentation - October 2013Direct Insite Presentation - October 2013
Direct Insite Presentation - October 2013Company Spotlight
 
Salesforce
Salesforce Salesforce
Salesforce
Sonali Gupta
 
MODERNIZATION OF NTUC INCOME
MODERNIZATION OF NTUC INCOMEMODERNIZATION OF NTUC INCOME
MODERNIZATION OF NTUC INCOME
myteratak
 
Case 1 modernization of ntuc income 2
Case 1 modernization of ntuc income 2Case 1 modernization of ntuc income 2
Case 1 modernization of ntuc income 2
dyadelm
 
Capgemini ses - smart analytics for the utility sector (gr)
Capgemini   ses - smart analytics for the utility sector (gr)Capgemini   ses - smart analytics for the utility sector (gr)
Capgemini ses - smart analytics for the utility sector (gr)
Gord Reynolds
 
2.02 MBA NF110 Student Activities.doc
2.02 MBA NF110 Student Activities.doc2.02 MBA NF110 Student Activities.doc
2.02 MBA NF110 Student Activities.doc
René Huisa
 
electronic governance and digital signature.pptx
electronic governance and digital signature.pptxelectronic governance and digital signature.pptx
electronic governance and digital signature.pptx
VikasThakur122972
 

Similar to Austin's Energy's Billing System Can't Light Up (20)

Case 6 austin's energy's billing system can't light up
Case 6 austin's energy's billing system can't light upCase 6 austin's energy's billing system can't light up
Case 6 austin's energy's billing system can't light up
 
Austin's energy's billing system can't light up
Austin's energy's billing system can't light upAustin's energy's billing system can't light up
Austin's energy's billing system can't light up
 
Austin energy's billing system can't light up
Austin energy's billing system can't light upAustin energy's billing system can't light up
Austin energy's billing system can't light up
 
Austin's meeting 6
Austin's meeting 6Austin's meeting 6
Austin's meeting 6
 
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Week 6  power point slide -3-case study 3- austin's energy's billing system c...Week 6  power point slide -3-case study 3- austin's energy's billing system c...
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
 
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
Week 6  power point slide -3-case study 3- austin's energy's billing system c...Week 6  power point slide -3-case study 3- austin's energy's billing system c...
Week 6 power point slide -3-case study 3- austin's energy's billing system c...
 
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
CIS Transformation: Unlocking the Value of Utilities' Customer Information Sy...
 
North American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling SystemNorth American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling System
 
North American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling SystemNorth American Utility Sparks Up its Complaint Handling System
North American Utility Sparks Up its Complaint Handling System
 
Unit 5 Assignment TemplateUse the table below to input your sele.docx
Unit 5 Assignment TemplateUse the table below to input your sele.docxUnit 5 Assignment TemplateUse the table below to input your sele.docx
Unit 5 Assignment TemplateUse the table below to input your sele.docx
 
Direct Insite Presentation December 2013
Direct Insite Presentation December 2013Direct Insite Presentation December 2013
Direct Insite Presentation December 2013
 
Modernization of ntuc income
Modernization of ntuc incomeModernization of ntuc income
Modernization of ntuc income
 
logistics powerpoint
logistics powerpointlogistics powerpoint
logistics powerpoint
 
Direct Insite Presentation - October 2013
Direct Insite Presentation - October 2013Direct Insite Presentation - October 2013
Direct Insite Presentation - October 2013
 
Salesforce
Salesforce Salesforce
Salesforce
 
MODERNIZATION OF NTUC INCOME
MODERNIZATION OF NTUC INCOMEMODERNIZATION OF NTUC INCOME
MODERNIZATION OF NTUC INCOME
 
Case 1 modernization of ntuc income 2
Case 1 modernization of ntuc income 2Case 1 modernization of ntuc income 2
Case 1 modernization of ntuc income 2
 
Capgemini ses - smart analytics for the utility sector (gr)
Capgemini   ses - smart analytics for the utility sector (gr)Capgemini   ses - smart analytics for the utility sector (gr)
Capgemini ses - smart analytics for the utility sector (gr)
 
2.02 MBA NF110 Student Activities.doc
2.02 MBA NF110 Student Activities.doc2.02 MBA NF110 Student Activities.doc
2.02 MBA NF110 Student Activities.doc
 
electronic governance and digital signature.pptx
electronic governance and digital signature.pptxelectronic governance and digital signature.pptx
electronic governance and digital signature.pptx
 

More from nhainisaini

Summit Electric Light Up with a New ERP system
Summit Electric Light Up with a New ERP systemSummit Electric Light Up with a New ERP system
Summit Electric Light Up with a New ERP system
nhainisaini
 
Apple, Google and Microsoft: Battle for your Internet Experience
Apple, Google and Microsoft:  Battle for your Internet ExperienceApple, Google and Microsoft:  Battle for your Internet Experience
Apple, Google and Microsoft: Battle for your Internet Experience
nhainisaini
 
The Battle Over Net Neutrality
The Battle Over Net NeutralityThe Battle Over Net Neutrality
The Battle Over Net Neutrality
nhainisaini
 
Big Data, Big Rewards
Big Data, Big RewardsBig Data, Big Rewards
Big Data, Big Rewards
nhainisaini
 
Should Businesses Move to the Cloud
Should Businesses Move to the CloudShould Businesses Move to the Cloud
Should Businesses Move to the Cloud
nhainisaini
 
Facebook: It's About the Money
Facebook:  It's About the MoneyFacebook:  It's About the Money
Facebook: It's About the Money
nhainisaini
 
Modernization of NTUC Income
Modernization of NTUC IncomeModernization of NTUC Income
Modernization of NTUC Income
nhainisaini
 
Schiphol International Hub
Schiphol International HubSchiphol International Hub
Schiphol International Hub
nhainisaini
 
Mashaweer
MashaweerMashaweer
Mashaweer
nhainisaini
 

More from nhainisaini (9)

Summit Electric Light Up with a New ERP system
Summit Electric Light Up with a New ERP systemSummit Electric Light Up with a New ERP system
Summit Electric Light Up with a New ERP system
 
Apple, Google and Microsoft: Battle for your Internet Experience
Apple, Google and Microsoft:  Battle for your Internet ExperienceApple, Google and Microsoft:  Battle for your Internet Experience
Apple, Google and Microsoft: Battle for your Internet Experience
 
The Battle Over Net Neutrality
The Battle Over Net NeutralityThe Battle Over Net Neutrality
The Battle Over Net Neutrality
 
Big Data, Big Rewards
Big Data, Big RewardsBig Data, Big Rewards
Big Data, Big Rewards
 
Should Businesses Move to the Cloud
Should Businesses Move to the CloudShould Businesses Move to the Cloud
Should Businesses Move to the Cloud
 
Facebook: It's About the Money
Facebook:  It's About the MoneyFacebook:  It's About the Money
Facebook: It's About the Money
 
Modernization of NTUC Income
Modernization of NTUC IncomeModernization of NTUC Income
Modernization of NTUC Income
 
Schiphol International Hub
Schiphol International HubSchiphol International Hub
Schiphol International Hub
 
Mashaweer
MashaweerMashaweer
Mashaweer
 

Recently uploaded

UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 

Recently uploaded (20)

UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 

Austin's Energy's Billing System Can't Light Up

  • 1. GROUP MEMBERS 1. Arni B. Hj. Morshidi P14D461P 2. Anisah Bt Ismail P14D389P 3. Syarifah Rohaya Bt Wan Idris P14D397P 4. Dayang Adelina Bt Hj Abang Muan P14D394P 5. Norhana Aini Bt Saini P14D398P
  • 2. INTRODUCTION 1. Handles electrical water and waste disposable for a city of Austin, Texas and surrounding counties 2. Serving more 1 million residents 3. Publicity owned company and an arm of city government and returns its profits to the community each year 4. Has provided $1.5 billion in dividends back to Austin since 1976 which help fund city services such as fire, police, emergency medical services, parks and libraries 5. Has one of the largest renewable energy program in the country
  • 3. PROBLEM PROBLEM Billing system did not integrate with smart meters and other newer technologiest It also lacked newer customer assistance options, like ability to choose the time of the month that the customer prefers to pay bills.
  • 4. SOLUTION CONTRACTED WITH IBM In 2009 to create a centralized billing system and to run the system for 5 year COST Agreed to pay IBM $38 mill for building and installing the new billing system and $17 mill for operating the system for 5 years after it completion NEW SYSTEM Was slated to handle electricity, water, trash and recycling
  • 5. Q1. THE AUSTIN ENERGY PROJECT A FAILURE? EXPLAIN YOUR ANSWER  Yes, the old billing system did not integrate with smart meters and other newer technologies. It also lacked newer customer assistance option like ability to choose the time of the month customer prefers to pay bill.  The new billing system (contracted with IBM) – also failure due to the following reason. a) The system was supposed to go alive in early 2011, but it not fully operational. b) The software bugs have led to errors in thousands of bills. Over 65,000 customer never received a bill and another 35,000 have received inaccurate bills. E,g one business that owed Austin $3,000 was instead charged $300,000. c) Austin was able to identify affected accounts and work with customers individually to correct the problems, the company was ill-prepared to handle the outpouring of customer service department was in danger of being overrun. d) Continuous to give the costly impact to their business and customer.
  • 6. Q2. DESCRIBE THE BUSINESS IMPACT OF THE FALTERING AUSTIN ENERGY PROJECT  Instability which caused by the poor and inefficiency system that continues to have serious and costly impacts to their business and customer.  Lack of application of related knowledge, skills tools and techniques. Eg. Not using internet facilities – lack options to customer to pay such as smart billing or e-payment system.  High rise of complaints received when they actually modernized the billing system. E.g software buds leads to errors, system is not user friendly.  Continuous mistake by IBM which caused disappointment to Austin and the customers.  Blaming game between Austin and IBM officers – unclear roles and responsibility.
  • 7. Q3. TO DEGREE WAS IBM RESPONSIBLE FOR THE PROBLEMS COUNTERED BY THE AUSTIN ENERGY BILLING PROJECT?  IBM was responsible for the problems countered by the Austin are as follow: a) Delay to complete the system. b) The system not fully operational. c) Persistent system errors prevented Austin from billing apartment residents for water, balancing its books and filing audit report. d) Austin losing revenue due to unability the system to bill for utility properly. e) Lack quality of services.
  • 8. Q3. WAS AUSTIN ENERGY BILLING AT FAULT FOR THE PROBLEM? EXPLAIN YOUR ANSWER.  Yes, Austin also at fault for the problem.  Austin should clearly stated what is the project management involved between Austin and IBM.  Project management to develop billing system must deal with 5 major variables such as scope, time, cost, quality and risk.  The role and responsibility of the both party should clearly define.  Austin also should monitor the progress of the project.
  • 9. Q4. WHAT WERE THE SPECIFIC ORGANIZATIONAL OR TECHNICAL FACTORS AS WELL AS MANAGEMENT FACTORS INVOLVED IN THIS PROJECT FAILURE? ORGANIZATIONAL TECHNICAL MANAGEMENT No realignment internally and externally No specific infrastructure No planning and strategy which cause time slippage Involved a lot of budget – exceed the budget Unreliable systems caused money loss No business solution Fail to meet customer satisfaction Inter related with man power Lost trust – Customers away
  • 10. SOLUTION / LOOKING AHEAD  Planning the implementation of the project/contract  Monitor the progress based on the milestone and achievement  Clearly stated the objective or output should deliver from the project  Risk analysis and how to mitigate the risk
  • 11. Q5. DESCRIBE THE STEPS AUSTIN ENERGY AND IBM SHOULD HAVE TAKEN TO BETTER MANAGE THIS PROJECT Planning the work Assessing the risk Estimating and acquired of resources to accomplish the work Organization the work Directing execution Analysis the result
  • 12. 5 MAJOR VARIABLES IN PROJECT MANAGEMENT FOR IS PROJECT MANAGEMENTTime Scope Cost Quality Risk