Ashok Kumar Verma is seeking a challenging position as a Deputy Manager where he can utilize his 28 years of experience, particularly his analytical abilities. He currently works as a Deputy Manager at Punj Loyd and has a B.Tech in Mechanical Engineering. His responsibilities have included managing fabrication, erection, and inspection of large steel structures for power plants. He has extensive experience overseeing projects in India and abroad with companies like Punj Loyd, UB Engineering, and Reliance Industries.
Strengthening Health Systems through the application of Wireless TechnologyOPS Colombia
Presentación realizada por el Dr. Trishan Panch, de Harvard School of Public Health, el 20 de Septiembre en OPS Colombia, en el espacio de intercambio sobre e-health.
El Dr. Panch, participa, con el auspicio de esta Representación, como conferencista en el IV Congreso Colombiano de Bioingeniería e Ingeniería Biomédica que se realizará en Barranquilla del 21 al 24 de septiembre del 2011.
Strengthening Health Systems through the application of Wireless TechnologyOPS Colombia
Presentación realizada por el Dr. Trishan Panch, de Harvard School of Public Health, el 20 de Septiembre en OPS Colombia, en el espacio de intercambio sobre e-health.
El Dr. Panch, participa, con el auspicio de esta Representación, como conferencista en el IV Congreso Colombiano de Bioingeniería e Ingeniería Biomédica que se realizará en Barranquilla del 21 al 24 de septiembre del 2011.
New Mortgage Fraud Scheme and Highest and Best Use Issue By Dave TowneBill Cobb, Appraiser
New Mortgage Fraud Scheme and Highest and Best Use Issue By Dave Towne
"Appraisers………
This may not affect you directly, but you should be aware of this new fraud situation. I decided to send this after talking with another appraiser about a potential assignment that might fall into the category the article below describes.
The appraiser was asked to appraise a SFR rental. Upon arriving at the property, doing the inspection, and observing the neighborhood, plus analyzing ownership of the undeveloped adjacent property owned by the same entity as the SFR, it became evident that the H&BU was actually more appropriately financially feasible and legally permissible, plus physically possible and maximally productive as a Multi-Family property. This is because properties to either side of the SFR are already MF per area zoning, as the changes to the area have been made over prior years.
When this situation was discussed with the client – prior to starting the report, the attempt was made to ‘force’ the appraiser to just accept the SFR assignment and ignore the completed H&BU analysis – as is required under USPAP and per the 1004 (and other) Form. The appraiser ultimately declined the assignment due to the client’s intimidation and coercion, and found out it was just given to another appraiser - probably to be done as a SFR.
Will the new appraiser do a thorough H&BU analysis or just ignore that aspect of responsibility? Who knows.
Will this property be part of the ‘Reverse Occupancy’ scheme as the Mortgage News Daily article explains? Also…who knows."
The Joint Learning Network in Action: Spotlight on GhanaHFG Project
More and more countries are implementing complex health systems reforms to achieve universal health coverage. The Joint Learning Network (JLN) is a country-driven network of practitioners and policymakers who together develop knowledge products to bridge the gap between theory and practice, with the goal of extending health care coverage to more than 3 billion people.
The JLN community is comprised of leaders from ministries of health, national health financing agencies, and other key government institutions in 27 Asian, African, European, Latin American, and Middle Eastern countries as well as a diverse group of international, regional, and local partners.
On Thursday, September 22, the HFG Project hosted a technical briefing session on the JLN's work on the ground, and about Ghana’s National Health Insurance Authority (NHIA) on their collaboration with the JLN and the HFG project. Speakers included: Amanda Folsom (JLN Program Director, Results for Development), Nathaniel Otoo, (Chief Executive, Ghana NHIA), Dr. Lydia Dsane-Selby (Director, Claims, NHIA), and Chris Lovelace (Principal Associate, International Health, Abt Associates).
Essential Package of Health Services Country Snapshot: NepalHFG Project
This country snapshot is one in a series of 24 snapshots as part of an activity looking at the Governance Dimensions of Essential Packages of Health Services in the Ending Preventable Child and Maternal Death priority countries. The snapshot explores several important dimensions of the EPHS in the country, such as how government policies contribute to the service coverage, population coverage, and financial coverage of the package. Each country snapshot includes annexes that contain further information about the EPHS.
PROFESSIONAL SUMMARY
As a Diploma Mechanical Engineer Obtained, Over 21 Years of Experience in the Areas of fabrication and erection of Steel Structures, Having Experience in Fabrication and Erection of Steel Structures and Piping in Refineries, Oil and Gas, , Power plants, Civil Construction, Industrial projects, Metro Water Pipe Line , AirPort Projects, and Metro Rail Projects. Fabrication and erection of Main pipe rack, Sub-pipe rack, Compressor shelter, Pipe Bridge, Technical structure, Roof structure, Platforms, Grating, Handrail, and other steel fabrication and erection works. pipeline, laying (1200 to 1300mm), an inspection of pipe fit-up and welding works, Refineries projects (SRU and PFCCU), and Shutdown Maintenance, and Supervising the pipe Truss, Walkway Bridge, Atrium, and Hollow Section Truss. Monorail, Gantry grider fabrication and erection work.
“Construction and Contracts Engineering Professional with more than10 years of hands on experience in Mega Multi-discipline Energy Sector and Building Utilities projects, having key Skills of Supervision, QA/QC, FATs, Erection of; Hydropower Plant, Hydraulic Gates, Cranes, Tunnel Steel Lining, Mechanical Equipment (Static, Rotating, Piping) & Allied Steel Structures, HVAC System and MEP Works. Acquainted with FIDIC, Preparation and Evaluation of Contract / Tender Documents, Claims and Variation Orders.
Worked with renowned lenders including World Bank - WB, Asian Development Bank - ADB, Islamic Development Bank – IDB, International Finance Corporation – IFC and Commonwealth Development Corporation - CDC.”
1. Ashok kumar Verma
E-Mail:ashokkumarverma149@gmail.com
Contact: +91-09430101139, 07043132773
Career Objective:
Seeking a challenging position and working as a Deputy Manager in a company where my analytical
ability and analyzing quest are used maximum for growth of the organization and that offers
professional growth and ample opportunity to learn and enrich competencies in carrier path.
Summary:
Having total 28 years of experience, currently working as Deputy Manager in Punj Loyd.
Educational Qualification—B.Tech (Mechanical)—State Council for Engineering and Technical
Government College of West Bengal.
Software Skills—
Operating System, MS Office, Windows
Jobs And Responsibilities
Total looking after inspections of structural steel like Material Inspection, fabrication,
alignment and final SSSSinspection of Power house, Mill Bunker.
Preparing Monthly and weekly planning for Fabrication and Erection work of steel structure
as per priority of work sequence.
Managing and looking after activities related to fabrication and erection with Staff/Engineers.
Managing time to time records of raw material requirement of fabrication work.
Discussing with staff related to updated shop and scope drawings.
Looking after heavy erection work like erection of bunker structure (Approx 62 m height).
Maintaining monthly material reconciliation statement like RA bill of sub-contractors and
own organization RA bill to client.
Co-ordinating with Civil Clients, department, third party inspection to enhance the
productivity.
Discussing with staff to resolve some critical problems at site ,some time discuss with the
Designers to resolve the site issues.
Looking after monthly loading of sub-contractors for fabrication and erection work.
Certifying sub-contractor’ RA bills and maintains the control register for certified bills.
Preparing the SKETCH/DETAIL drawing from scope drawing in the absence of detail
drawing at site.
Attending weekly/monthly meeting with the Client.
2. Maintaining QA/QC and HSE Standard in the work site.
Work Experience—
Total Experience of 25 years in Fabrication and Erection of Structural Work in India& Onsite
(Dubai, Kuwait) with different Multi National Companies.
Project Details—
Project 1 Reliance IndustriesLimited Gujarat
Client: Reliance Industries Limited
Organization: Punj Lloyd Limited
Period: 1-Jan-2014---Till date
Responsibility: Erection of cryogenic (liquid oxygen& liquid nitrogen) storage tank.
Project 2 2*270 MWThermal Power Plant
Client: GVK Power Limited
Organization: Punj Lloyd Limited
Period: 1-March-2012---December 2013
Responsibility: Fabrication and Erection of 2* 250 Mill Bunker Building.
Project 3: Chabra Thermal Power Plant
Client: Rajasthan Rajya Vidyut Utpadan Nigam Limited
Organization: Punj Lloyd Limited
Period: 1-April-2007---February 2012
Responsibility: Fabrication and Erection of 2* 250 MW Power house Building &Mill Bunker Build.
Project 4: 4*250,Jindal Power Plant
Client: Jindal Power Plant Limited
Organization: Punj Lloyd Limited
Period: 1-January-2006---March 2007
Responsibility: Fabrication and Erection of 2* 250 MW Power house Building.
Project 5: 2*250,Guru Har Govind Thermal Power Project
Client: BHEL
Organization: UB Engineering
Period: 1-April-2005---March 2006
Designation: Assistant Resident Engineer
Responsibility: Pre Assembly & Erection of 250 MW Boiler.
Project 6: Metro Rail NewDelhi
Client: IMCC
Organization: UB Engineering
Period: 1-April-2002---March 2005
Designation: Senior Engineer
Responsibility: Fabrication& Erection.
Project 7: Erection ofCross Country Pipeline
Client: Nirma Limited Pipeline
Organization: UB Engineering
Period: 1-April-2000---April 2002
Designation: Senior Engineer
Responsibility: Erection of Cross Country Pipeline
3. Project 8: Kuwait Cement Company(Onsite Shore)
Client: Kuwait Cement Company
Organization: UB Engineering
Period: 1-April-1999---April 2000.
Designation: Senior Engineer
Responsibility: Fabrication and Erection of Row Mill Building.
Project 9: Reliance Petroleum Limited
Client: Reliance Petroleum Limited Gujarat
Organization: UB Engineering
Period: 1-April-1998---April 1999
Designation: Senior Engineer
Responsibility: Pre-Assembly and Erection of Steel Structure.
Project 10: Sabiya Power Plant Kuwait(Onsite)
Client: Hyundai Engineering and Construction Company Limited
Organization: UB Engineering
Period: 1-April-1996---April 1998
Designation: Senior Engineer
Responsibility: Pre-Assembly and Erection of 3*800 MW Main Turbine Building.
Project 11: Reliance Industries Limited Hazira Gujarat
Client: Reliance Industries Limited
Organization: UB Engineering
Period: 1-April-1994---December 1995
Designation: Senior Engineer
Responsibility: Pre-Assembly and Erection of Pipe Rack Structures, Compressor House Building
d Erection of CS Tank.
Project 12: 2*500MWNational Thermal Power Corporation,Bengal
Client: Ansaldo
Organization: UB Engineering
Period: 1-April-1989---April 1994
Designation: Assistant Engineer
Responsibility: Pre-Assembly and Erection of Boiler, Ducting, ESP.
Project 13: 2*500MWNational Thermal Power Corporation, Rihand Mirzapur
Client: Ansaldo
Organization: UB Engineering
Period: 1-April-1986---December 1988
Designation: Junior Engineer
Responsibility: Pre-Assembly and Erection of Boiler, Ducting, ESP.
Personal Profile:
Name : Ashok Kumar Verma
Date of Birth : 21 January1962
Gender : Male
Marital Status : Married
Nationality : Indian
4. I hereby declare that the above information furnished is true to the best of my knowledge and belief.
Ashok Kumar Verma