The document discusses a process improvement project to reduce the waiting time to energize high bay lighting in pot rooms from 6 months to 3 months. Currently, there is a 6 month delay between needing the lighting and its availability. The project aims to reduce this to 100 days by April 2012, saving $408k by avoiding temporary lighting costs. Key activities contributing to delays include material availability, construction implementation, and receiving permanent power. The document outlines the problem statement, objectives, metrics, process mapping, data analysis, improvement recommendations and team involved.