High Bay Lighting Energisation
Background
Work in the Pot Line area – Mc Connell Dowell & Brasco
Ferretti is critical to FHM. These contractors will need to
work in night shift in order to meet schedule. Currently
the high bay lighting will not be ready to support this night
shift work.
We need to help Kentz get permanent high bay lighting
operational in time to support this work in order to save
the cost of temporary lighting and gain the benefit of
better illuminated work environment.
Hence this PIP was selected to utilize the six sigma tools
to improve the process.
High bay Lighting Plan
for North Pot Line – 1
Problem Statement
Currently there will be a six months waiting period
between need date and availability date of High bay
Lighting Energisation in Pot Rooms.
Lighting Energisation
Y
Panel Board
Transformer Cables
X’s
Problem Objective
Reduce the waiting time from June 2012 (180 days)
to April 2012 (100 days) to achieve our target/desire
time schedule to energize the High Bay lightings in Pot
Rooms phase by phase.
COPQ for this process will be the cost avoidance of
Temporary Lighting arrangement cost approximately
US$ 408 K
High level Block Diagram
Primary Metric
Energisation duration
70
60
60
120
190
35
40
45
65
100
0 20 40 60 80 100 120 140 160 180 200
Cables
Distribution Boards
Lighting Transformers
Construction Work
Energisation
(Materials + construction )
MaterialsConstruction
No of Days
High Bay Lighting Energisation
Actual # of days Target # of days
Acitivities
Actual # of
days
Target # of
days
Cables 70 35
Distribution Boards 60 40
Lighting
Transformers 60 45
Construction Work 120 65
Energisation
(Materials +
construction ) 190 100
Secondary Metric - Job hours / month
0
2000
4000
6000
8000
10000
12000
14000
16000
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12
JOBHOURS
MONTHS
High bay Lighting Energisation
*SAMPLE DATA*
Process Map
Customer Identification
Internal External
Direct
Bechtel
Reduction Area
Manager
Brasco Ferretti - Pot lining
Mc Connell Dowell - Mechanical
Reduction Area contractors
Secondary
Bechtel
Reduction Area
Superintendent /FE
Ma'aden Area Manager
Indirect N/A KENTZ E&I contractor
RUMBA
RUMBA - Customer Valid Requirements Matrix
Customer
Perceived Valid
Requirements R U M B A Y/N
Reduction Area Manager
Sequential and
completion in time Y Y Y Y Y Y
Bechtel Area Superintendent &
Area Field Engineer
Meets standards and
specification Y Y Y Y Y Y
Fishbone
XY Matrix
Material
availability
Delay
Permanent
power
receiving
delay
Construction
Implementatio
n CT delay
Approved
documents &
Mobilization
CT delay
Equipments
Mobilization
delay
Schedule
delay
Rating 170 162 134 108 102 92
Cum % 22.14% 43.23% 60.68% 74.74% 88.02% 100.00%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
20
40
60
80
100
120
140
160
180
Rating
PARETO Chart - HB Lighting Energisation
Supply – Input – Process
Output - Customer
C – Controllable ( Inputs can be adjusted or controlled while process is in running)
SOP – Site Operating procedures
N – Noise ( Things that cannot be controlled or too expensive or too difficult)
Materials available
in time at site
Permanent power
Available in sub
station
Review for
Permanent
power
receiving
Document
Approval &
Mobilization
Review
CT for approval of
Documents &
Date for mobilization
Materials take off quantity
Material Approval documents
Intending for procurement
Expedite on time delivery
Preparation of required documents
Submission for approval
Manpower planning as scheduled
Equipment planning as scheduled
GIS Energisation
Main 34.5 KV SS Energisation
Cable work to Pot Room SS
MV/LV Testing and commissioning
C
C
C
C
C
C
C
C
C
SOP
C
C
Bechtel
Planner
Bechtel
Area
Supd.
Construction
Completion to
handover
Expedite
Material
availability
Analysis for
Construction
Implementation
Plan work schedule
Site clearance and access permit
Materials, Tools & Equipments
Skilled manpower
SOP
C
C
C
Bechtel
Field
Engineer
Bechtel
Area
Supd.
Specifications of Outputs & Inputs
Y's - Outputs Specification
High bay Lighting Energisation 180 Days
by Temporary Power 90 days
by Permanent Power 30 days
X's - Inputs Specification
C Materials take off quantity 25457-4200-SR2-E00Z-0001ee
C Material Approval documents MM/DD/YYYY
C Intending for procurement No of Materials
C Expedite on time delivery MM/DD/YYYY
C GIS Energisation MM/DD/YYYY
C Main 34.5 KV SS Energisation MM/DD/YYYY
C Cable work to Pot Room SS No of days
C MV/LV Testing and commissioning No of days
SOP Preparation of required documents No of documents & days
C Submission for approval MM/DD/YYYY
C Manpower planning as scheduled MM/DD/YYYY
C Equipment planning as scheduled MM/DD/YYYY
C Plan work schedule Number of Days
SOP Site clearance and access permit SWPP 4MP-T81-03303 TO 03305
C Materials, Tools & Equipments Quantity in Numbers
C Skilled manpower No of Man hours
Upstream & Outcome Indicators
Customer
Valid
Requirements
Customer
Specification(s)
Outcome (Y)
Indicators
Upstream (X) Indicator
Completion in
Time
90 days
Number of days
to High bay
Lighting
Energisation
X1 - Approved documents & Mobilization CT delay
X2 - Material availability CT Delay
X3- Construction Implémentation CT Delay
Meets
standards &
Specification
Zero
Deviation
Number of
Deviations
X4 – Number of Items in poor quality
X5- Number of items fails in Inspection checklist
Process Management System (PMS)
Conclusions & Recommendations
Improvements
Mobilize Manpower & Equipment on time – In Progress
Discuss the High Bay Lighting Materials availability issues in contractor weekly meetings
Develop a level 5 schedule of High bay Lighting activities from main schedule
Display High bay Lighting Energisation as a concern during Reduction Area Readiness
Review meetings.
Recommendations
Develop data collection methods for weekly job hours data (Secondary Metric)
Set up data collection methods for Xs and Ys and analyze
Project controls –Prioritize scope for this process from base line schedule
Contracts – Administrator to expedite FSR related issues.
Field Engineering – Expedite material approval, RFIs, ITPs, Method Statements.
Construction – Coordinate with contractor for site clearance.
Discuss access issues during regular POD meetings.
Contractor – Rigorously respect 3 week look ahead schedule preparation + adherence
A new PIP for Wait time reduction for permanent power availability.
Team involved – Thanks
Yellow Belt
Anandhajothi
Murugan
Reduction E&I
supervisor.
Black Belt
Mentor
Narayanan
Doraswamy
Lead six sigma
Engineer
Champion
Charles
(Mark)
Read
Reduction Area
Manager
Process
owner
Jeffrey
Reibel
Reduction Area
Superintendent
Others
Bassem
Semaan
Reduction
Area Planner
Others
Danilo
Molina
Reduction E&I
QC Inspector
Others
Bernard
Fogarty
KENTZ
Reduction E&I
Site Manager
Others
Michael
Fiorill
Reduction Area
E&I supervisor

More Related Content

What's hot

Resume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnamResume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnam
Rahul Laxman Iyer MSE Mech Eng, EIT, LSSBB/TPS/Kaizen
 
Decommissioning your offshore assets
Decommissioning your offshore assetsDecommissioning your offshore assets
Decommissioning your offshore assets
Advisian
 
Blackbeltpresentation
BlackbeltpresentationBlackbeltpresentation
Blackbeltpresentation
Robert Peth
 
cv 2016
cv 2016cv 2016
Technical audit- Position Available
Technical audit- Position AvailableTechnical audit- Position Available
Technical audit- Position Available
Erika Vanessa Rodriguez, M.A
 
KJGResume2015
KJGResume2015KJGResume2015
KJGResume2015
K Jeffrey (Jeff) Glenn
 
Paul brayman chronological
Paul brayman chronologicalPaul brayman chronological
Paul brayman chronological
Paul Brayman
 
Rocky Nash Resume A
Rocky Nash Resume ARocky Nash Resume A
Rocky Nash Resume A
Rocky Nash
 
Amanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast AnalyticsAmanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast Analytics
Amanda Alexander Spence
 
CV Jose F Gonzalez, P. Eng Mech & Process Project
CV Jose F Gonzalez, P. Eng Mech & Process ProjectCV Jose F Gonzalez, P. Eng Mech & Process Project
CV Jose F Gonzalez, P. Eng Mech & Process Project
Jose F. Gonzalez, P. Eng.
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
Toronto 2030 District
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACS
Leonardo ENERGY
 
Giles Greenwood CV
Giles Greenwood CVGiles Greenwood CV
Giles Greenwood CV
Giles Greenwood
 
Mesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling EngMesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling Eng
Mesbah Elazrig
 
Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
ignitetribes
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
Mario Fonseca
 
Internship for Honda of America Mfg., Inc.
Internship for Honda of America Mfg., Inc.Internship for Honda of America Mfg., Inc.
Internship for Honda of America Mfg., Inc.
Samin Ahmed, ASP, GSP
 

What's hot (17)

Resume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnamResume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnam
 
Decommissioning your offshore assets
Decommissioning your offshore assetsDecommissioning your offshore assets
Decommissioning your offshore assets
 
Blackbeltpresentation
BlackbeltpresentationBlackbeltpresentation
Blackbeltpresentation
 
cv 2016
cv 2016cv 2016
cv 2016
 
Technical audit- Position Available
Technical audit- Position AvailableTechnical audit- Position Available
Technical audit- Position Available
 
KJGResume2015
KJGResume2015KJGResume2015
KJGResume2015
 
Paul brayman chronological
Paul brayman chronologicalPaul brayman chronological
Paul brayman chronological
 
Rocky Nash Resume A
Rocky Nash Resume ARocky Nash Resume A
Rocky Nash Resume A
 
Amanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast AnalyticsAmanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast Analytics
 
CV Jose F Gonzalez, P. Eng Mech & Process Project
CV Jose F Gonzalez, P. Eng Mech & Process ProjectCV Jose F Gonzalez, P. Eng Mech & Process Project
CV Jose F Gonzalez, P. Eng Mech & Process Project
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACS
 
Giles Greenwood CV
Giles Greenwood CVGiles Greenwood CV
Giles Greenwood CV
 
Mesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling EngMesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling Eng
 
Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Internship for Honda of America Mfg., Inc.
Internship for Honda of America Mfg., Inc.Internship for Honda of America Mfg., Inc.
Internship for Honda of America Mfg., Inc.
 

Similar to As on 12 Jan 12 JOTHI Yellow Belt Presentation Template GFF-HXM-Y0001 [Repaired]

General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
Arun Jothilingam
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
Peter Scott
 
AK+CV
AK+CVAK+CV
Watlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxWatlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptx
ParabakaranBalasubra1
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
Nicholas Naing
 
Latest_resume_10.9.14
Latest_resume_10.9.14Latest_resume_10.9.14
Latest_resume_10.9.14
dnag12
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
maheshvkat1972
 
Drew Whitney Final Presentation
Drew Whitney Final PresentationDrew Whitney Final Presentation
Drew Whitney Final Presentation
Drew Whitney
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
Mostafa Ewees
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
TalebAlfihan
 
Resume 2016 - Product Scheduler
Resume 2016 - Product SchedulerResume 2016 - Product Scheduler
Resume 2016 - Product Scheduler
Tim Chau
 
Sathishkumar mechanical engineer - 2016
Sathishkumar   mechanical engineer - 2016Sathishkumar   mechanical engineer - 2016
Sathishkumar mechanical engineer - 2016
sathish kumar
 
Part one of project brown field for operational excellencies in scm integert...
Part one of project brown field for operational excellencies in scm  integert...Part one of project brown field for operational excellencies in scm  integert...
Part one of project brown field for operational excellencies in scm integert...
LT COLONEL VIKRAM BAKSHI ( RETD)
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
Guhan Visagan
 
DOUGLAS D 2
DOUGLAS D 2DOUGLAS D 2
DOUGLAS D 2
Doug Hill
 
Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010
Hayley Pallister
 
SAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-ExternalSAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-External
Andrew Si
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
University of Regina
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
sachin mohelay
 

Similar to As on 12 Jan 12 JOTHI Yellow Belt Presentation Template GFF-HXM-Y0001 [Repaired] (20)

General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
AK+CV
AK+CVAK+CV
AK+CV
 
Watlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxWatlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptx
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
Latest_resume_10.9.14
Latest_resume_10.9.14Latest_resume_10.9.14
Latest_resume_10.9.14
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
 
Drew Whitney Final Presentation
Drew Whitney Final PresentationDrew Whitney Final Presentation
Drew Whitney Final Presentation
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Resume 2016 - Product Scheduler
Resume 2016 - Product SchedulerResume 2016 - Product Scheduler
Resume 2016 - Product Scheduler
 
Sathishkumar mechanical engineer - 2016
Sathishkumar   mechanical engineer - 2016Sathishkumar   mechanical engineer - 2016
Sathishkumar mechanical engineer - 2016
 
Part one of project brown field for operational excellencies in scm integert...
Part one of project brown field for operational excellencies in scm  integert...Part one of project brown field for operational excellencies in scm  integert...
Part one of project brown field for operational excellencies in scm integert...
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
DOUGLAS D 2
DOUGLAS D 2DOUGLAS D 2
DOUGLAS D 2
 
Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010
 
SAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-ExternalSAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-External
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 

As on 12 Jan 12 JOTHI Yellow Belt Presentation Template GFF-HXM-Y0001 [Repaired]

  • 1. High Bay Lighting Energisation
  • 2. Background Work in the Pot Line area – Mc Connell Dowell & Brasco Ferretti is critical to FHM. These contractors will need to work in night shift in order to meet schedule. Currently the high bay lighting will not be ready to support this night shift work. We need to help Kentz get permanent high bay lighting operational in time to support this work in order to save the cost of temporary lighting and gain the benefit of better illuminated work environment. Hence this PIP was selected to utilize the six sigma tools to improve the process.
  • 3. High bay Lighting Plan for North Pot Line – 1
  • 4. Problem Statement Currently there will be a six months waiting period between need date and availability date of High bay Lighting Energisation in Pot Rooms. Lighting Energisation Y Panel Board Transformer Cables X’s
  • 5. Problem Objective Reduce the waiting time from June 2012 (180 days) to April 2012 (100 days) to achieve our target/desire time schedule to energize the High Bay lightings in Pot Rooms phase by phase. COPQ for this process will be the cost avoidance of Temporary Lighting arrangement cost approximately US$ 408 K
  • 7. Primary Metric Energisation duration 70 60 60 120 190 35 40 45 65 100 0 20 40 60 80 100 120 140 160 180 200 Cables Distribution Boards Lighting Transformers Construction Work Energisation (Materials + construction ) MaterialsConstruction No of Days High Bay Lighting Energisation Actual # of days Target # of days Acitivities Actual # of days Target # of days Cables 70 35 Distribution Boards 60 40 Lighting Transformers 60 45 Construction Work 120 65 Energisation (Materials + construction ) 190 100
  • 8. Secondary Metric - Job hours / month 0 2000 4000 6000 8000 10000 12000 14000 16000 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 JOBHOURS MONTHS High bay Lighting Energisation *SAMPLE DATA*
  • 10. Customer Identification Internal External Direct Bechtel Reduction Area Manager Brasco Ferretti - Pot lining Mc Connell Dowell - Mechanical Reduction Area contractors Secondary Bechtel Reduction Area Superintendent /FE Ma'aden Area Manager Indirect N/A KENTZ E&I contractor
  • 11. RUMBA RUMBA - Customer Valid Requirements Matrix Customer Perceived Valid Requirements R U M B A Y/N Reduction Area Manager Sequential and completion in time Y Y Y Y Y Y Bechtel Area Superintendent & Area Field Engineer Meets standards and specification Y Y Y Y Y Y
  • 13. XY Matrix Material availability Delay Permanent power receiving delay Construction Implementatio n CT delay Approved documents & Mobilization CT delay Equipments Mobilization delay Schedule delay Rating 170 162 134 108 102 92 Cum % 22.14% 43.23% 60.68% 74.74% 88.02% 100.00% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 20 40 60 80 100 120 140 160 180 Rating PARETO Chart - HB Lighting Energisation
  • 14. Supply – Input – Process Output - Customer C – Controllable ( Inputs can be adjusted or controlled while process is in running) SOP – Site Operating procedures N – Noise ( Things that cannot be controlled or too expensive or too difficult) Materials available in time at site Permanent power Available in sub station Review for Permanent power receiving Document Approval & Mobilization Review CT for approval of Documents & Date for mobilization Materials take off quantity Material Approval documents Intending for procurement Expedite on time delivery Preparation of required documents Submission for approval Manpower planning as scheduled Equipment planning as scheduled GIS Energisation Main 34.5 KV SS Energisation Cable work to Pot Room SS MV/LV Testing and commissioning C C C C C C C C C SOP C C Bechtel Planner Bechtel Area Supd. Construction Completion to handover Expedite Material availability Analysis for Construction Implementation Plan work schedule Site clearance and access permit Materials, Tools & Equipments Skilled manpower SOP C C C Bechtel Field Engineer Bechtel Area Supd.
  • 15. Specifications of Outputs & Inputs Y's - Outputs Specification High bay Lighting Energisation 180 Days by Temporary Power 90 days by Permanent Power 30 days X's - Inputs Specification C Materials take off quantity 25457-4200-SR2-E00Z-0001ee C Material Approval documents MM/DD/YYYY C Intending for procurement No of Materials C Expedite on time delivery MM/DD/YYYY C GIS Energisation MM/DD/YYYY C Main 34.5 KV SS Energisation MM/DD/YYYY C Cable work to Pot Room SS No of days C MV/LV Testing and commissioning No of days SOP Preparation of required documents No of documents & days C Submission for approval MM/DD/YYYY C Manpower planning as scheduled MM/DD/YYYY C Equipment planning as scheduled MM/DD/YYYY C Plan work schedule Number of Days SOP Site clearance and access permit SWPP 4MP-T81-03303 TO 03305 C Materials, Tools & Equipments Quantity in Numbers C Skilled manpower No of Man hours
  • 16. Upstream & Outcome Indicators Customer Valid Requirements Customer Specification(s) Outcome (Y) Indicators Upstream (X) Indicator Completion in Time 90 days Number of days to High bay Lighting Energisation X1 - Approved documents & Mobilization CT delay X2 - Material availability CT Delay X3- Construction Implémentation CT Delay Meets standards & Specification Zero Deviation Number of Deviations X4 – Number of Items in poor quality X5- Number of items fails in Inspection checklist
  • 18. Conclusions & Recommendations Improvements Mobilize Manpower & Equipment on time – In Progress Discuss the High Bay Lighting Materials availability issues in contractor weekly meetings Develop a level 5 schedule of High bay Lighting activities from main schedule Display High bay Lighting Energisation as a concern during Reduction Area Readiness Review meetings. Recommendations Develop data collection methods for weekly job hours data (Secondary Metric) Set up data collection methods for Xs and Ys and analyze Project controls –Prioritize scope for this process from base line schedule Contracts – Administrator to expedite FSR related issues. Field Engineering – Expedite material approval, RFIs, ITPs, Method Statements. Construction – Coordinate with contractor for site clearance. Discuss access issues during regular POD meetings. Contractor – Rigorously respect 3 week look ahead schedule preparation + adherence A new PIP for Wait time reduction for permanent power availability.
  • 19. Team involved – Thanks Yellow Belt Anandhajothi Murugan Reduction E&I supervisor. Black Belt Mentor Narayanan Doraswamy Lead six sigma Engineer Champion Charles (Mark) Read Reduction Area Manager Process owner Jeffrey Reibel Reduction Area Superintendent Others Bassem Semaan Reduction Area Planner Others Danilo Molina Reduction E&I QC Inspector Others Bernard Fogarty KENTZ Reduction E&I Site Manager Others Michael Fiorill Reduction Area E&I supervisor