SlideShare a Scribd company logo
ANALYTICAL MODELS OF
LEARNING CURVES WITH
VARIABLE
PROCESSING TIME
M.S.P,MUTHUKUMARANAGE
E/11/267 1
New
labour
INTRODUCTION
2
INTRODUCTION
New or unskilled operators cannot achieved
acceptable speed at first time.
The operator will require less and less time to
complete the similar task as time goes on.
This is the basic concept of learning curves.
3
INTRODUCTION
The concept of learning curve was
reported by wright in 1936.
Wright developed a mathematically
representation of learning curve
4
LEARNING RATE (¢)
 The operator’s performance will improve at a constant rate each time
the output doubles.
5
MATHEMATICALLY REPRESENTATION
Learning curve has mathematically representation.
The basic model is log linear model.
The equation of the log linear model
Y=KX ^n
Y- direct labour hours required to produce xth unit.
K- direct labour hours to produce first unit.
X- cumilative unit numbers
N- learning index
N= log ¢ / log 2
6
OTHER MODELS
1. The plateau model
2. The stanford-b model
3. The dejong model
4. The S model
Above all models are the different form of log linear model.
1
2
3
4
Cumulative unit number
Directlabourhoursper
unit
7
OBJECTIVES
Calculate the time to complete a given batch of items exactly for
1. One machine system
Start Buffer Activity End
8
• 2. Two machine system (2M1B)
Develop equations to find variability of processing time
and average processing time.
Start Activity Buffer Activity End
9
CALCULATION
 Single machine processing time to complete 1000 parts by using log
linear model when
Processing time is deterministic.
Cumulative Unit Number
Directlaborhours
10
11
Processing time has exponential distribution.
1 2 3 4 5
Cumulative Unit Number
Directlaborhours
K
K3n
K4
n K5n
K2
n
Mean = K*Xn
12
Exponential distribution
Mean=1/λ
Probability density function = λ 𝑒−λ 𝑥
Hypo-exponential distribution
𝑀𝑒𝑎𝑛 = 𝑖=1
𝑛
1/ λ(i)
𝑉𝑎𝑟𝑖𝑎𝑛𝑐𝑒 = 𝑖=1
𝑛
1/ λ(i)2
13
CALCULATION
Considering hypo exponential distribution
Mean time for produce 1000 parts =1587 hr
Variance =3062 hr
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0.000
X
Density
1479
0.025
1695
0.025
1587
Distribution Plot
Normal, Mean=1587, StDev=55.33
14
Results Using Other Models
Model Name Equation Mean Variance
Stanford-B
model
Y(x)=Y1(X+B)-b
1559.857 2813.13
Dejong’s
model
Y(x)=Y1[M+(1-M)X-b]
2428.25 6336.51
15
Work To Be Done
 Develop above calculations for two machine one buffer system
(2M1B)
1.With Infinite buffer size
Start Activity Buffer Activity End
Infinite 16
2. With finite buffer size(by increasing one by one)
Start Activity
Buffer
Size= 1
Activity End
Start Activity
Buffer
size=2
Activity End
17
THANK YOU
18

More Related Content

What's hot

Machine vision technique to avoid alignment failure in space launch vehicle
Machine vision technique to avoid alignment failure in space launch vehicleMachine vision technique to avoid alignment failure in space launch vehicle
Machine vision technique to avoid alignment failure in space launch vehicle
Suseetharan Vijayakumaran
 
Concept and application of cd and ces production function in resource managem...
Concept and application of cd and ces production function in resource managem...Concept and application of cd and ces production function in resource managem...
Concept and application of cd and ces production function in resource managem...
Nar B Chhetri
 
Graph partition 2
Graph partition 2Graph partition 2
Graph partition 2
Rohit Talwar
 
Graph Partition 3
Graph Partition 3Graph Partition 3
Graph Partition 3
Rohit Talwar
 
Pre-Cal 40S Slides February 26, 2008
Pre-Cal 40S Slides February 26, 2008Pre-Cal 40S Slides February 26, 2008
Pre-Cal 40S Slides February 26, 2008
Darren Kuropatwa
 
Control chart example
Control chart exampleControl chart example
Control chart example
Mujahed Alwagia
 
Passing stuctures to function
Passing stuctures to functionPassing stuctures to function
Passing stuctures to function
ALI RAZA
 
5.9 notes
5.9 notes5.9 notes
1
11
Co2 levels assignment
Co2 levels assignmentCo2 levels assignment
Co2 levels assignment
Harrison Lee
 
Cobb douglas
Cobb douglasCobb douglas
Cobb douglas
cr_mau
 
LINK
LINKLINK
Chapter 7: Production Economics
Chapter 7: Production EconomicsChapter 7: Production Economics
Chapter 7: Production Economics
sarkerzaman
 
Nidhi ppt (production function)
Nidhi ppt (production function)Nidhi ppt (production function)
Nidhi ppt (production function)
Nidhi Panday
 
BACK TRAJECTORY CLUSTER
BACK TRAJECTORY CLUSTERBACK TRAJECTORY CLUSTER
BACK TRAJECTORY CLUSTER
Sovan Sau
 
A169571 tugasan pisah ragaman
A169571 tugasan pisah ragamanA169571 tugasan pisah ragaman
A169571 tugasan pisah ragaman
AZEEMSHAHAMIRUDDIN
 
CHiMaD Hackathon 2
CHiMaD Hackathon 2CHiMaD Hackathon 2
CHiMaD Hackathon 2
Daniel Wheeler
 
College Algebra 5.3
College Algebra 5.3College Algebra 5.3
College Algebra 5.3
Jeneva Clark
 
Production function analysis
Production function analysisProduction function analysis
Production function analysis
Vaibhav verma
 
Production function
Production function Production function
Production function
Daksh Bapna
 

What's hot (20)

Machine vision technique to avoid alignment failure in space launch vehicle
Machine vision technique to avoid alignment failure in space launch vehicleMachine vision technique to avoid alignment failure in space launch vehicle
Machine vision technique to avoid alignment failure in space launch vehicle
 
Concept and application of cd and ces production function in resource managem...
Concept and application of cd and ces production function in resource managem...Concept and application of cd and ces production function in resource managem...
Concept and application of cd and ces production function in resource managem...
 
Graph partition 2
Graph partition 2Graph partition 2
Graph partition 2
 
Graph Partition 3
Graph Partition 3Graph Partition 3
Graph Partition 3
 
Pre-Cal 40S Slides February 26, 2008
Pre-Cal 40S Slides February 26, 2008Pre-Cal 40S Slides February 26, 2008
Pre-Cal 40S Slides February 26, 2008
 
Control chart example
Control chart exampleControl chart example
Control chart example
 
Passing stuctures to function
Passing stuctures to functionPassing stuctures to function
Passing stuctures to function
 
5.9 notes
5.9 notes5.9 notes
5.9 notes
 
1
11
1
 
Co2 levels assignment
Co2 levels assignmentCo2 levels assignment
Co2 levels assignment
 
Cobb douglas
Cobb douglasCobb douglas
Cobb douglas
 
LINK
LINKLINK
LINK
 
Chapter 7: Production Economics
Chapter 7: Production EconomicsChapter 7: Production Economics
Chapter 7: Production Economics
 
Nidhi ppt (production function)
Nidhi ppt (production function)Nidhi ppt (production function)
Nidhi ppt (production function)
 
BACK TRAJECTORY CLUSTER
BACK TRAJECTORY CLUSTERBACK TRAJECTORY CLUSTER
BACK TRAJECTORY CLUSTER
 
A169571 tugasan pisah ragaman
A169571 tugasan pisah ragamanA169571 tugasan pisah ragaman
A169571 tugasan pisah ragaman
 
CHiMaD Hackathon 2
CHiMaD Hackathon 2CHiMaD Hackathon 2
CHiMaD Hackathon 2
 
College Algebra 5.3
College Algebra 5.3College Algebra 5.3
College Algebra 5.3
 
Production function analysis
Production function analysisProduction function analysis
Production function analysis
 
Production function
Production function Production function
Production function
 

Viewers also liked

Hello
HelloHello
Copyright&Copylefght
Copyright&CopylefghtCopyright&Copylefght
Copyright&Copylefght
clarilla_14
 
Parece mentiraaaa
Parece mentiraaaaParece mentiraaaa
Parece mentiraaaa
Josue Suarez
 
MY MOM
MY MOMMY MOM
Paris-Antonio-CV
Paris-Antonio-CVParis-Antonio-CV
Paris-Antonio-CV
Paris Antonio
 
Women in Business: Reentering the Workforce
Women in Business: Reentering the WorkforceWomen in Business: Reentering the Workforce
Women in Business: Reentering the Workforce
Lucas Group
 
Summer 2012 handicaps
Summer 2012 handicapsSummer 2012 handicaps
Summer 2012 handicaps
CJH47
 
Bit
BitBit
Convocazione consiglio 27 settembre
Convocazione consiglio 27 settembreConvocazione consiglio 27 settembre
Convocazione consiglio 27 settembreredazione gioianet
 
Mi primer slideshare
Mi primer slideshareMi primer slideshare
Mi primer slideshare
Gisselasalas
 
Forecasting injuries in sport
Forecasting injuries in sportForecasting injuries in sport
Forecasting injuries in sport
Data Beers Tuscany
 

Viewers also liked (11)

Hello
HelloHello
Hello
 
Copyright&Copylefght
Copyright&CopylefghtCopyright&Copylefght
Copyright&Copylefght
 
Parece mentiraaaa
Parece mentiraaaaParece mentiraaaa
Parece mentiraaaa
 
MY MOM
MY MOMMY MOM
MY MOM
 
Paris-Antonio-CV
Paris-Antonio-CVParis-Antonio-CV
Paris-Antonio-CV
 
Women in Business: Reentering the Workforce
Women in Business: Reentering the WorkforceWomen in Business: Reentering the Workforce
Women in Business: Reentering the Workforce
 
Summer 2012 handicaps
Summer 2012 handicapsSummer 2012 handicaps
Summer 2012 handicaps
 
Bit
BitBit
Bit
 
Convocazione consiglio 27 settembre
Convocazione consiglio 27 settembreConvocazione consiglio 27 settembre
Convocazione consiglio 27 settembre
 
Mi primer slideshare
Mi primer slideshareMi primer slideshare
Mi primer slideshare
 
Forecasting injuries in sport
Forecasting injuries in sportForecasting injuries in sport
Forecasting injuries in sport
 

Similar to Analytical models of learning curves with variable processing time

final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
xicohos114
 
Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...
Alexander Decker
 
11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...
Alexander Decker
 
Fx570 ms 991ms_e
Fx570 ms 991ms_eFx570 ms 991ms_e
Fx570 ms 991ms_e
Yosep Widian
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
sadiqfarhan2
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
Tyler812505
 
III. work studyprinciples of Ergonomics,
III. work studyprinciples of Ergonomics,III. work studyprinciples of Ergonomics,
III. work studyprinciples of Ergonomics,
Krushna Ktk
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
RonnelAmparado1
 
Unit 3
Unit 3Unit 3
Monte Carlo Simulation for project estimates v1.0
Monte Carlo Simulation for project estimates v1.0Monte Carlo Simulation for project estimates v1.0
Monte Carlo Simulation for project estimates v1.0
PMILebanonChapter
 
Job shop scheduling
Job shop schedulingJob shop scheduling
Job shop scheduling
Sujeet TAMBE
 
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORYGE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
ANJALAI AMMAL MAHALINGAM ENGINEERING COLLEGE
 
Learning curve
Learning curveLearning curve
Learning curve
ShafiulArefinPial
 
202003261537530756sanjeev_eco_Linear_Programming.pdf
202003261537530756sanjeev_eco_Linear_Programming.pdf202003261537530756sanjeev_eco_Linear_Programming.pdf
202003261537530756sanjeev_eco_Linear_Programming.pdf
AnshitTanwar
 
186 ashish
186 ashish186 ashish
DJA3032 CHAPTER 2
DJA3032   CHAPTER 2DJA3032   CHAPTER 2
DJA3032 CHAPTER 2
mechanical86
 
Lotstreaming
LotstreamingLotstreaming
Lotstreaming
Amirtha Ganesh
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
SyedAmirIqbal3
 
Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,
Dronak Sahu
 
22424roduction Slides 33623-1.ppt
22424roduction Slides 33623-1.ppt22424roduction Slides 33623-1.ppt
22424roduction Slides 33623-1.ppt
MuskanKhan320706
 

Similar to Analytical models of learning curves with variable processing time (20)

final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
 
Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...
 
11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...
 
Fx570 ms 991ms_e
Fx570 ms 991ms_eFx570 ms 991ms_e
Fx570 ms 991ms_e
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
 
III. work studyprinciples of Ergonomics,
III. work studyprinciples of Ergonomics,III. work studyprinciples of Ergonomics,
III. work studyprinciples of Ergonomics,
 
Production Slides (F).ppt
Production Slides (F).pptProduction Slides (F).ppt
Production Slides (F).ppt
 
Unit 3
Unit 3Unit 3
Unit 3
 
Monte Carlo Simulation for project estimates v1.0
Monte Carlo Simulation for project estimates v1.0Monte Carlo Simulation for project estimates v1.0
Monte Carlo Simulation for project estimates v1.0
 
Job shop scheduling
Job shop schedulingJob shop scheduling
Job shop scheduling
 
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORYGE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
GE3171-PROBLEM SOLVING AND PYTHON PROGRAMMING LABORATORY
 
Learning curve
Learning curveLearning curve
Learning curve
 
202003261537530756sanjeev_eco_Linear_Programming.pdf
202003261537530756sanjeev_eco_Linear_Programming.pdf202003261537530756sanjeev_eco_Linear_Programming.pdf
202003261537530756sanjeev_eco_Linear_Programming.pdf
 
186 ashish
186 ashish186 ashish
186 ashish
 
DJA3032 CHAPTER 2
DJA3032   CHAPTER 2DJA3032   CHAPTER 2
DJA3032 CHAPTER 2
 
Lotstreaming
LotstreamingLotstreaming
Lotstreaming
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
 
Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,
 
22424roduction Slides 33623-1.ppt
22424roduction Slides 33623-1.ppt22424roduction Slides 33623-1.ppt
22424roduction Slides 33623-1.ppt
 

Analytical models of learning curves with variable processing time

  • 1. ANALYTICAL MODELS OF LEARNING CURVES WITH VARIABLE PROCESSING TIME M.S.P,MUTHUKUMARANAGE E/11/267 1
  • 3. INTRODUCTION New or unskilled operators cannot achieved acceptable speed at first time. The operator will require less and less time to complete the similar task as time goes on. This is the basic concept of learning curves. 3
  • 4. INTRODUCTION The concept of learning curve was reported by wright in 1936. Wright developed a mathematically representation of learning curve 4
  • 5. LEARNING RATE (¢)  The operator’s performance will improve at a constant rate each time the output doubles. 5
  • 6. MATHEMATICALLY REPRESENTATION Learning curve has mathematically representation. The basic model is log linear model. The equation of the log linear model Y=KX ^n Y- direct labour hours required to produce xth unit. K- direct labour hours to produce first unit. X- cumilative unit numbers N- learning index N= log ¢ / log 2 6
  • 7. OTHER MODELS 1. The plateau model 2. The stanford-b model 3. The dejong model 4. The S model Above all models are the different form of log linear model. 1 2 3 4 Cumulative unit number Directlabourhoursper unit 7
  • 8. OBJECTIVES Calculate the time to complete a given batch of items exactly for 1. One machine system Start Buffer Activity End 8
  • 9. • 2. Two machine system (2M1B) Develop equations to find variability of processing time and average processing time. Start Activity Buffer Activity End 9
  • 10. CALCULATION  Single machine processing time to complete 1000 parts by using log linear model when Processing time is deterministic. Cumulative Unit Number Directlaborhours 10
  • 11. 11
  • 12. Processing time has exponential distribution. 1 2 3 4 5 Cumulative Unit Number Directlaborhours K K3n K4 n K5n K2 n Mean = K*Xn 12
  • 13. Exponential distribution Mean=1/λ Probability density function = λ 𝑒−λ 𝑥 Hypo-exponential distribution 𝑀𝑒𝑎𝑛 = 𝑖=1 𝑛 1/ λ(i) 𝑉𝑎𝑟𝑖𝑎𝑛𝑐𝑒 = 𝑖=1 𝑛 1/ λ(i)2 13
  • 14. CALCULATION Considering hypo exponential distribution Mean time for produce 1000 parts =1587 hr Variance =3062 hr 0.008 0.007 0.006 0.005 0.004 0.003 0.002 0.001 0.000 X Density 1479 0.025 1695 0.025 1587 Distribution Plot Normal, Mean=1587, StDev=55.33 14
  • 15. Results Using Other Models Model Name Equation Mean Variance Stanford-B model Y(x)=Y1(X+B)-b 1559.857 2813.13 Dejong’s model Y(x)=Y1[M+(1-M)X-b] 2428.25 6336.51 15
  • 16. Work To Be Done  Develop above calculations for two machine one buffer system (2M1B) 1.With Infinite buffer size Start Activity Buffer Activity End Infinite 16
  • 17. 2. With finite buffer size(by increasing one by one) Start Activity Buffer Size= 1 Activity End Start Activity Buffer size=2 Activity End 17