Eglinton West/Allen Road Station
              Preliminary Design
             Online Consultation
              Feb 2, 2012 – Feb 17, 2012



                                 2/3/2012
2/3/2012       2




Online Consultation Overview
Part 1
•Introduction
•Crosstown Update
•Station Design 101 - Design Principles
Part 2
•Eglinton West Station Preliminary Design

*Our partners in City Planning can answer any questions
about existing development applications at Eglinton West or
the future Land Use Study around Crosstown Stations



                 Eglinton West / Allen Rd Station Preliminary Design
                                                                                  2
2/3/2012   3




The Purpose of this Online Consultation
• Provide a brief Crosstown project update
• Present the Crosstown station design philosophy
• Explain the anatomy of a station and challenges
• Display the preliminary design of Eglinton West Station
Most importantly:
*Get your input on the Preliminary Design early in this
  process.
• Architectural Station design will be prepared for Open House #2 in
  late Spring 2012. Significant outreach will follow prior to
  construction.




                    Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   4




Eglinton West Station Design Process
Timelines
Open House #1 - Feb 2, 2012
Online Consultation – Feb 2 to Feb 17, 2012
Open House #2 – late Spring, 2012
• Response to Open House #1 input
• Architectural Treatments
• Final Station Design Open House
• Tunnel Extraction & Launch Shaft Construction Plans
Tunnel Extraction Shaft at Allen West - Summer 2012 (TBD)
Launch Shaft Construction at Allen East - Fall 2012 (TBD)
Open House #3 - Fall 2013
  • Station Construction staging
    Ongoing Outreach on Construction
Eglinton West Station-specific Construction - Spring 2014 (TBD)



                              Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   5




 Format for Feedback
• Please submit your feedback online at www.thecrosstown.ca by
  February 17, 2012
• A consultation report to inform the designers will be posted
  online at: www.thecrosstown.ca




                     Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   6




Presentation Part 1:
Crosstown Overview &
Construction Update




           Crosstown Station Preliminary Design
2/3/2012   7




The Crosstown
* Final number and location of stations subject to review




                                 Crosstown Station Preliminary Design
2/3/2012       8




Congestion Today




             Crosstown Station Preliminary Design
                                                               8
2/3/2012   9




The Eglinton-Scarborough Crosstown Plan
• $8.4 billion transit investment from the Province of Ontario through
  Metrolinx
• 25 km east-west transit corridor between Black Creek Drive and
  Scarborough Centre
• 60% faster than bus service today (e.g. only 15 minutes from Keele to
  Yonge)
• 19 km underground tunnel (Black Creek Drive to Kennedy Station)*
• 6km seamless service will replace the SRT from Kennedy Station to
  Scarborough Centre
• Up to 26 stations
• *Exact alignment west of Keele Street and east of Laird Drive TBD


                          Crosstown Station Preliminary Design
2/3/2012   10




Crosstown Construction Update
• Crosstown tunnel preparation
  work at Black Creek and Eglinton
  in Keelesdale Park
• Piling rigs are building concrete
  support walls for the future tunnel
  launch shaft
• The shaft will enable tunnelling
  eastward in summer 2012
• Soil testing for the tunnel and
  stations continues from Keele
  Street to Kennedy Station in
  Scarborough



                          Crosstown Station Preliminary Design
2/3/2012   11




Conceptual Design
Typical Crosstown Station




Urban Design and Architectural
Guidelines have been developed:
•    ensure positive change along the
     corridor
•    guide individual station designs
     and achieve consistency
•    guide configuration of surface
     elements
•    integrate surface elements with
     existing and future development



                                        Crosstown Station Preliminary Design
2/3/2012   12




Stations 101
What’s needed to make a Station Work?
•   Main Entrance
•   Secondary Entrance
•   Passenger Transportation (elevators, escalators)
•   Mechanical and Electrical Systems
•   Ventilation Shafts and Ventilation Fan Rooms
•   Traction Power Substations
    Guiding Principle:
    Consolidate Surface Elements to enhance design
    & minimize impacts
• Reduce construction impacts (traffic, staging area, noise, dust )
• Preserve public space and development potential
• Save $



                             Crosstown Station Preliminary Design
2/3/2012            13




Design Philosophy
•   Integrate with surrounding neighbourhood
•   Safe and enjoyable user experience
•   Full accessibility
•   Preserve space for future re-development
•   Enhance the local “sense of place”
                                                                      Accessibility for all users
•   Long-term sustainability
•   Reduce Construction Footprint & Impacts
•   Reduce Costs




                                                                            Compatible scale


                               Crosstown Station Preliminary Design
                                                                                             13
2/3/2012        14




Accessibility Principles & Features
 • Access for persons with all levels of mobility

 • Elevators

 • Escalators

 • Low-Floor Access




                            Crosstown Station Preliminary Design
                                                                              14
2/3/2012        15




Safety and Security Features
 • Monitored CCTV Security Cameras

 • Urban Braille

 • High Quality Lighting




                           Crosstown Station Preliminary Design
                                                                             15
2/3/2012   16




Public Realm Elements
     Elements to be determined
     and considered:
    • Streetscape & integration
      of Public Realm Elements
    • Wayfinding
    • Bicycle Facilities




                           Crosstown Station Preliminary Design
2/3/2012         17




Architectural Design Approach

•   Excellence in architectural/urban
    design treatments
•   Cost effective and maintainable
    structures
•   Standard station box
    configurations
•   Creative use of materials, color,
    textures, artwork, light
•   Brand identification with graphics
•   Use standard elements whenever
    possible                                                          Eglinton West Station




                               Crosstown Station Preliminary Design
2/3/2012   18




Integrated Artwork
  Any architectural finish can contain
  integrated artwork, including:
  • walls
  • floors
  • ceilings
  • glazing




                         Crosstown Station Preliminary Design
2/3/2012   19




Presentation Part 2:
Eglinton West Station
Preliminary Design
Preliminary Design by:




                         Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   20




Eglinton West Station
Existing Built Form and Land Use




            Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   21




Eglinton West Station
Local Site Context




            Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   22




Eglinton West Station
Local Context




            Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   23




Eglinton West Station
Local Context
Upper Village Business Improvement Area (BIA)

• www.uppervillagetoronto.ca
• Represents merchants, shops and services from Allen Road to
  Bathurst Street
• Wide selection of shops, restaurants and services




                       Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   24




Eglinton West Station
Existing Transportation Network




            Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   25




Eglinton West Station
Existing Conditions – Eglinton West Subway Station




                Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   26




Eglinton West Station
Existing Pedestrian and Passenger Traffic:




                Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   27




Eglinton West Station
Future Pedestrian and Bus Traffic:




                Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   28




Eglinton West Station
Existing Passenger Transfer Volumes




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   29




Eglinton West Station
Projected Passenger Transfer Volumes 2031




             Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   30




Eglinton West Station
Eglinton 32 and 34 Bus Service
After The Crosstown Opens
• A decision on the future of the Eglinton 32 and
  34 bus service will be made closer to the
  opening of the Crosstown, based on forecast
  ridership and budget availability compared to
  passenger needs across the system.

• The TTC recognizes the importance of providing
  local accessibility. Today, some sections of the
  subway do have parallel bus service and some
  do not.




                           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   31




Eglinton West Station
Environmental Assessment - 2010



   EMERGENCY
      EXIT
                                              EMERGENCY
                      ADDITION TO                EXIT
                        EXISTING
                       ENTRANCE




                                                                      VENT SHAFT
       SOUTH                                                          EMERGENCY EXIT
     ENTRANCE

                                                  STREET LEVEL PLAN



                Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   32




Eglinton West Station
Future Crosstown Station Entrances




            Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   33




Eglinton West Station
New Preliminary Design 2012




          Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   34




Eglinton West Station
Crosstown Concourse Levels




          Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   35




Eglinton West Station
Centre Platform – Crosstown Level




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   36




Eglinton West Station
Crosstown FAQs
1.   If I enter at the existing Subway entrance on Eglinton, how will I get to the Crosstown?
     Use the existing staircases and elevators (or two new escalators that are being installed) to get
     to the subway platform level, where you’ll proceed through a new corridor and down one level to
     the Crosstown platform.
2.   How many levels below the main subway entrance is the future Crosstown?
     The Crosstown is three levels below the existing subway entrance, and three levels below the
     future West and East entrances.
3.   If I get off of the subway at Eglinton West Station northbound or southbound, how will I connect
     to the future Eglinton Crosstown (escalators, elevators)?
     There will be escalators, an elevator and stairs to take you down to the Crosstown level.
4.    Which future Crosstown entrances will have an elevator?
     The west entrance will be accessible with an elevator.
5.   At which level will I pay my fare to get on the Crosstown?
     Fares will be paid at the Upper Concourse Level.
6.   Will I be able to pay my fare at a Crosstown entrance and access the subway instead of the
     Crosstown?
     Yes



                                Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   37




Eglinton West Station
Key Advantages of New Design
• Reduces construction footprint, cost & impacts

• Improves look and feel from street for community

• New pedestrian underground walkway from east and west
  entrances to safely cross underneath Allen Road

• Preserves potential for future station entrance in Police
  Station Parking Lot when/if land is developed



                   Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   38




Eglinton West Station
Longitudinal Section 2012

                                                      UPPER CONCOURSE

                                                                                       LOWER CONCOURSE

                                             CROSSTOWN 
                                             PLATFORM

Close‐up view showing main entrance and underground levels




                                                                                                  CROSS‐OVER TRACKS




                                          Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   39




Eglinton West Station
Preliminary Design – 2012




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   40




Eglinton West Station
Preliminary Design – 2012




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   41




Eglinton West Station
Preliminary Design – 2012




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   42




Eglinton West Station
Preliminary Design – 2012




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   43




Eglinton West Station
Proposed Surface Layout 2012




           Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   44




Eglinton West Station
Surface Area Improvements
   Key Improvements:
 • New Crosswalks
 • Wider Sidewalks
 • Reinforcing pedestrian clearway with continuous paving and wider
   sidewalks
 • Consolidation of litter bins, multi-publication boxes
 • New seating area for station plaza areas and entrance zones
 • Pedestrian lighting along walkways and secondary entrance zones
 • New sunken garden along tunnel connecting main station building
   and east entrance


                       Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   45




Eglinton West Station
West Station Entrance –Surface Design - 2012




               Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   46




Eglinton West Station
East Station Entrance –Surface Design - 2012




               Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   47




 Eglinton West Station
 New Walkway Under Allen Road
• Walkway connecting
  the two new station
  entrances will allow
  pedestrians to cross
  Allen Road
  underground

• Existing crossings at
  street level will
  remain

• Existing entrance to
  Eglinton West
  Subway Station
  remains
                          Walkway & Sunken Garden – between east & west entrances


                              Eglinton West / Allen Rd Station Preliminary Design
2/3/2012   48




The Crosstown Team
Please Get in Touch with Us!
Devin Horne, Franca Di Giovanni,
Denise Jayawardene
E-mail: eglintontransit@ttc.ca                 Community Office Hours — 2012
Online: www.thecrosstown.ca                    Monday, Wednesday, Friday:
Tel: 416-338-6310                              9:00 a.m. – 5:00 p.m.
Fax: 416-397-8193                              Tuesday: 8:00 a.m. – 4:00 p.m.
TTY: 416-481-2523                              Thursday: 12:00 p.m. – 8:00 p.m.
Visit our West Community Office at
1848 Eglinton Avenue West
(at Dufferin)




                        Eglinton West / Allen Rd Station Preliminary Design

More Related Content

What's hot

05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards PresentationAISC/NSBA
 
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1Toronto Public Consultation Unit
 
Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18CirculateSD
 
Balboa Avenue Station Presentation
Balboa Avenue Station PresentationBalboa Avenue Station Presentation
Balboa Avenue Station PresentationCirculateSD
 
Clairemont subcommittee presentation 07.19.17
Clairemont subcommittee presentation  07.19.17Clairemont subcommittee presentation  07.19.17
Clairemont subcommittee presentation 07.19.17CirculateSD
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16omedina91
 
Clairemont ad hoc subcommittee presentation 11/2/16
Clairemont ad hoc subcommittee presentation 11/2/16 Clairemont ad hoc subcommittee presentation 11/2/16
Clairemont ad hoc subcommittee presentation 11/2/16 omedina91
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Chaplin station open house
Chaplin station open houseChaplin station open house
Chaplin station open houseCrosstown TO
 
Pb Community Planning Group May 24
Pb Community Planning Group May 24Pb Community Planning Group May 24
Pb Community Planning Group May 24CirculateSD
 
Caledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design ConsultationCaledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design ConsultationCrosstown TO
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingCirculateSD
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house Crosstown TO
 
Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)knelischer
 

What's hot (20)

05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation
 
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
 
Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18
 
East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
 
Balboa Avenue Station Presentation
Balboa Avenue Station PresentationBalboa Avenue Station Presentation
Balboa Avenue Station Presentation
 
Clairemont subcommittee presentation 07.19.17
Clairemont subcommittee presentation  07.19.17Clairemont subcommittee presentation  07.19.17
Clairemont subcommittee presentation 07.19.17
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16
 
Clairemont ad hoc subcommittee presentation 11/2/16
Clairemont ad hoc subcommittee presentation 11/2/16 Clairemont ad hoc subcommittee presentation 11/2/16
Clairemont ad hoc subcommittee presentation 11/2/16
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Chaplin station open house
Chaplin station open houseChaplin station open house
Chaplin station open house
 
Pb Community Planning Group May 24
Pb Community Planning Group May 24Pb Community Planning Group May 24
Pb Community Planning Group May 24
 
Caledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design ConsultationCaledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design Consultation
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house
 
13736
1373613736
13736
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)
 

Similar to Allen Road - Eglinton West Station: Preliminary Design Consultation

Bathurst Station: Preliminary Design Consultation
Bathurst Station: Preliminary Design ConsultationBathurst Station: Preliminary Design Consultation
Bathurst Station: Preliminary Design ConsultationCrosstown TO
 
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.SHASHANK SHEKHAR
 
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdf
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdfdocuments.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdf
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdfShekharRai20
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationCrosstown TO
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016VDOT Northern Virginia
 
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPS S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPs s n prasad akshintala
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Urban Design Works_Mayur Naik.pdf
Urban Design Works_Mayur Naik.pdfUrban Design Works_Mayur Naik.pdf
Urban Design Works_Mayur Naik.pdfMayurNaik35
 
Thandapani Portfolio
Thandapani PortfolioThandapani Portfolio
Thandapani PortfolioRONIEE Sparks
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Crosstown TO
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Crosstown TO
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 

Similar to Allen Road - Eglinton West Station: Preliminary Design Consultation (20)

Bathurst Station: Preliminary Design Consultation
Bathurst Station: Preliminary Design ConsultationBathurst Station: Preliminary Design Consultation
Bathurst Station: Preliminary Design Consultation
 
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
 
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdf
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdfdocuments.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdf
documents.pub_diesel-locomotive-works-varanasi-for-civil-engg.pdf
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPS S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Urban Design Works_Mayur Naik.pdf
Urban Design Works_Mayur Naik.pdfUrban Design Works_Mayur Naik.pdf
Urban Design Works_Mayur Naik.pdf
 
Thandapani Portfolio
Thandapani PortfolioThandapani Portfolio
Thandapani Portfolio
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 
Byron CV 2016v5
Byron CV 2016v5Byron CV 2016v5
Byron CV 2016v5
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
TRB Managed Lane Design Build
TRB Managed Lane Design BuildTRB Managed Lane Design Build
TRB Managed Lane Design Build
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一Fi L
 
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full NightCall Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,bhuyansuprit
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一lvtagr7
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailDesigntroIntroducing
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxnewslab143
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsCharles Obaleagbon
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 

Recently uploaded (20)

Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
 
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full NightCall Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detail
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past Questions
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 

Allen Road - Eglinton West Station: Preliminary Design Consultation

  • 1. Eglinton West/Allen Road Station Preliminary Design Online Consultation Feb 2, 2012 – Feb 17, 2012 2/3/2012
  • 2. 2/3/2012 2 Online Consultation Overview Part 1 •Introduction •Crosstown Update •Station Design 101 - Design Principles Part 2 •Eglinton West Station Preliminary Design *Our partners in City Planning can answer any questions about existing development applications at Eglinton West or the future Land Use Study around Crosstown Stations Eglinton West / Allen Rd Station Preliminary Design 2
  • 3. 2/3/2012 3 The Purpose of this Online Consultation • Provide a brief Crosstown project update • Present the Crosstown station design philosophy • Explain the anatomy of a station and challenges • Display the preliminary design of Eglinton West Station Most importantly: *Get your input on the Preliminary Design early in this process. • Architectural Station design will be prepared for Open House #2 in late Spring 2012. Significant outreach will follow prior to construction. Eglinton West / Allen Rd Station Preliminary Design
  • 4. 2/3/2012 4 Eglinton West Station Design Process Timelines Open House #1 - Feb 2, 2012 Online Consultation – Feb 2 to Feb 17, 2012 Open House #2 – late Spring, 2012 • Response to Open House #1 input • Architectural Treatments • Final Station Design Open House • Tunnel Extraction & Launch Shaft Construction Plans Tunnel Extraction Shaft at Allen West - Summer 2012 (TBD) Launch Shaft Construction at Allen East - Fall 2012 (TBD) Open House #3 - Fall 2013 • Station Construction staging Ongoing Outreach on Construction Eglinton West Station-specific Construction - Spring 2014 (TBD) Eglinton West / Allen Rd Station Preliminary Design
  • 5. 2/3/2012 5 Format for Feedback • Please submit your feedback online at www.thecrosstown.ca by February 17, 2012 • A consultation report to inform the designers will be posted online at: www.thecrosstown.ca Eglinton West / Allen Rd Station Preliminary Design
  • 6. 2/3/2012 6 Presentation Part 1: Crosstown Overview & Construction Update Crosstown Station Preliminary Design
  • 7. 2/3/2012 7 The Crosstown * Final number and location of stations subject to review Crosstown Station Preliminary Design
  • 8. 2/3/2012 8 Congestion Today Crosstown Station Preliminary Design 8
  • 9. 2/3/2012 9 The Eglinton-Scarborough Crosstown Plan • $8.4 billion transit investment from the Province of Ontario through Metrolinx • 25 km east-west transit corridor between Black Creek Drive and Scarborough Centre • 60% faster than bus service today (e.g. only 15 minutes from Keele to Yonge) • 19 km underground tunnel (Black Creek Drive to Kennedy Station)* • 6km seamless service will replace the SRT from Kennedy Station to Scarborough Centre • Up to 26 stations • *Exact alignment west of Keele Street and east of Laird Drive TBD Crosstown Station Preliminary Design
  • 10. 2/3/2012 10 Crosstown Construction Update • Crosstown tunnel preparation work at Black Creek and Eglinton in Keelesdale Park • Piling rigs are building concrete support walls for the future tunnel launch shaft • The shaft will enable tunnelling eastward in summer 2012 • Soil testing for the tunnel and stations continues from Keele Street to Kennedy Station in Scarborough Crosstown Station Preliminary Design
  • 11. 2/3/2012 11 Conceptual Design Typical Crosstown Station Urban Design and Architectural Guidelines have been developed: • ensure positive change along the corridor • guide individual station designs and achieve consistency • guide configuration of surface elements • integrate surface elements with existing and future development Crosstown Station Preliminary Design
  • 12. 2/3/2012 12 Stations 101 What’s needed to make a Station Work? • Main Entrance • Secondary Entrance • Passenger Transportation (elevators, escalators) • Mechanical and Electrical Systems • Ventilation Shafts and Ventilation Fan Rooms • Traction Power Substations Guiding Principle: Consolidate Surface Elements to enhance design & minimize impacts • Reduce construction impacts (traffic, staging area, noise, dust ) • Preserve public space and development potential • Save $ Crosstown Station Preliminary Design
  • 13. 2/3/2012 13 Design Philosophy • Integrate with surrounding neighbourhood • Safe and enjoyable user experience • Full accessibility • Preserve space for future re-development • Enhance the local “sense of place” Accessibility for all users • Long-term sustainability • Reduce Construction Footprint & Impacts • Reduce Costs Compatible scale Crosstown Station Preliminary Design 13
  • 14. 2/3/2012 14 Accessibility Principles & Features • Access for persons with all levels of mobility • Elevators • Escalators • Low-Floor Access Crosstown Station Preliminary Design 14
  • 15. 2/3/2012 15 Safety and Security Features • Monitored CCTV Security Cameras • Urban Braille • High Quality Lighting Crosstown Station Preliminary Design 15
  • 16. 2/3/2012 16 Public Realm Elements Elements to be determined and considered: • Streetscape & integration of Public Realm Elements • Wayfinding • Bicycle Facilities Crosstown Station Preliminary Design
  • 17. 2/3/2012 17 Architectural Design Approach • Excellence in architectural/urban design treatments • Cost effective and maintainable structures • Standard station box configurations • Creative use of materials, color, textures, artwork, light • Brand identification with graphics • Use standard elements whenever possible Eglinton West Station Crosstown Station Preliminary Design
  • 18. 2/3/2012 18 Integrated Artwork Any architectural finish can contain integrated artwork, including: • walls • floors • ceilings • glazing Crosstown Station Preliminary Design
  • 19. 2/3/2012 19 Presentation Part 2: Eglinton West Station Preliminary Design Preliminary Design by: Eglinton West / Allen Rd Station Preliminary Design
  • 20. 2/3/2012 20 Eglinton West Station Existing Built Form and Land Use Eglinton West / Allen Rd Station Preliminary Design
  • 21. 2/3/2012 21 Eglinton West Station Local Site Context Eglinton West / Allen Rd Station Preliminary Design
  • 22. 2/3/2012 22 Eglinton West Station Local Context Eglinton West / Allen Rd Station Preliminary Design
  • 23. 2/3/2012 23 Eglinton West Station Local Context Upper Village Business Improvement Area (BIA) • www.uppervillagetoronto.ca • Represents merchants, shops and services from Allen Road to Bathurst Street • Wide selection of shops, restaurants and services Eglinton West / Allen Rd Station Preliminary Design
  • 24. 2/3/2012 24 Eglinton West Station Existing Transportation Network Eglinton West / Allen Rd Station Preliminary Design
  • 25. 2/3/2012 25 Eglinton West Station Existing Conditions – Eglinton West Subway Station Eglinton West / Allen Rd Station Preliminary Design
  • 26. 2/3/2012 26 Eglinton West Station Existing Pedestrian and Passenger Traffic: Eglinton West / Allen Rd Station Preliminary Design
  • 27. 2/3/2012 27 Eglinton West Station Future Pedestrian and Bus Traffic: Eglinton West / Allen Rd Station Preliminary Design
  • 28. 2/3/2012 28 Eglinton West Station Existing Passenger Transfer Volumes Eglinton West / Allen Rd Station Preliminary Design
  • 29. 2/3/2012 29 Eglinton West Station Projected Passenger Transfer Volumes 2031 Eglinton West / Allen Rd Station Preliminary Design
  • 30. 2/3/2012 30 Eglinton West Station Eglinton 32 and 34 Bus Service After The Crosstown Opens • A decision on the future of the Eglinton 32 and 34 bus service will be made closer to the opening of the Crosstown, based on forecast ridership and budget availability compared to passenger needs across the system. • The TTC recognizes the importance of providing local accessibility. Today, some sections of the subway do have parallel bus service and some do not. Eglinton West / Allen Rd Station Preliminary Design
  • 31. 2/3/2012 31 Eglinton West Station Environmental Assessment - 2010 EMERGENCY EXIT EMERGENCY ADDITION TO EXIT EXISTING ENTRANCE VENT SHAFT SOUTH EMERGENCY EXIT ENTRANCE STREET LEVEL PLAN Eglinton West / Allen Rd Station Preliminary Design
  • 32. 2/3/2012 32 Eglinton West Station Future Crosstown Station Entrances Eglinton West / Allen Rd Station Preliminary Design
  • 33. 2/3/2012 33 Eglinton West Station New Preliminary Design 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 34. 2/3/2012 34 Eglinton West Station Crosstown Concourse Levels Eglinton West / Allen Rd Station Preliminary Design
  • 35. 2/3/2012 35 Eglinton West Station Centre Platform – Crosstown Level Eglinton West / Allen Rd Station Preliminary Design
  • 36. 2/3/2012 36 Eglinton West Station Crosstown FAQs 1. If I enter at the existing Subway entrance on Eglinton, how will I get to the Crosstown? Use the existing staircases and elevators (or two new escalators that are being installed) to get to the subway platform level, where you’ll proceed through a new corridor and down one level to the Crosstown platform. 2. How many levels below the main subway entrance is the future Crosstown? The Crosstown is three levels below the existing subway entrance, and three levels below the future West and East entrances. 3. If I get off of the subway at Eglinton West Station northbound or southbound, how will I connect to the future Eglinton Crosstown (escalators, elevators)? There will be escalators, an elevator and stairs to take you down to the Crosstown level. 4. Which future Crosstown entrances will have an elevator? The west entrance will be accessible with an elevator. 5. At which level will I pay my fare to get on the Crosstown? Fares will be paid at the Upper Concourse Level. 6. Will I be able to pay my fare at a Crosstown entrance and access the subway instead of the Crosstown? Yes Eglinton West / Allen Rd Station Preliminary Design
  • 37. 2/3/2012 37 Eglinton West Station Key Advantages of New Design • Reduces construction footprint, cost & impacts • Improves look and feel from street for community • New pedestrian underground walkway from east and west entrances to safely cross underneath Allen Road • Preserves potential for future station entrance in Police Station Parking Lot when/if land is developed Eglinton West / Allen Rd Station Preliminary Design
  • 38. 2/3/2012 38 Eglinton West Station Longitudinal Section 2012 UPPER CONCOURSE LOWER CONCOURSE CROSSTOWN  PLATFORM Close‐up view showing main entrance and underground levels CROSS‐OVER TRACKS Eglinton West / Allen Rd Station Preliminary Design
  • 39. 2/3/2012 39 Eglinton West Station Preliminary Design – 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 40. 2/3/2012 40 Eglinton West Station Preliminary Design – 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 41. 2/3/2012 41 Eglinton West Station Preliminary Design – 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 42. 2/3/2012 42 Eglinton West Station Preliminary Design – 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 43. 2/3/2012 43 Eglinton West Station Proposed Surface Layout 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 44. 2/3/2012 44 Eglinton West Station Surface Area Improvements Key Improvements: • New Crosswalks • Wider Sidewalks • Reinforcing pedestrian clearway with continuous paving and wider sidewalks • Consolidation of litter bins, multi-publication boxes • New seating area for station plaza areas and entrance zones • Pedestrian lighting along walkways and secondary entrance zones • New sunken garden along tunnel connecting main station building and east entrance Eglinton West / Allen Rd Station Preliminary Design
  • 45. 2/3/2012 45 Eglinton West Station West Station Entrance –Surface Design - 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 46. 2/3/2012 46 Eglinton West Station East Station Entrance –Surface Design - 2012 Eglinton West / Allen Rd Station Preliminary Design
  • 47. 2/3/2012 47 Eglinton West Station New Walkway Under Allen Road • Walkway connecting the two new station entrances will allow pedestrians to cross Allen Road underground • Existing crossings at street level will remain • Existing entrance to Eglinton West Subway Station remains Walkway & Sunken Garden – between east & west entrances Eglinton West / Allen Rd Station Preliminary Design
  • 48. 2/3/2012 48 The Crosstown Team Please Get in Touch with Us! Devin Horne, Franca Di Giovanni, Denise Jayawardene E-mail: eglintontransit@ttc.ca Community Office Hours — 2012 Online: www.thecrosstown.ca Monday, Wednesday, Friday: Tel: 416-338-6310 9:00 a.m. – 5:00 p.m. Fax: 416-397-8193 Tuesday: 8:00 a.m. – 4:00 p.m. TTY: 416-481-2523 Thursday: 12:00 p.m. – 8:00 p.m. Visit our West Community Office at 1848 Eglinton Avenue West (at Dufferin) Eglinton West / Allen Rd Station Preliminary Design