INTRODUCTION OF MECHANICAL 
WORKSHOP GORAKHPUR 
 Gorakhpur mechanical workshop is established in 1903 
for repair and overhauling purpose of steam 
locomotives. 
 At present it is used to periodic over hauling and 
maintenance purpose of AC and NON AC coaches. 
 The workshop having capacity to overhauled 180 
coaches per month.
STATICS AND SPECIFICATION OF PLANT 
 TOTAL AREA COVERED - 29.8 HECTARE. 
 COVERED AREA –12.6 HECTARE. 
 NUMBER OF OFFICERS-19 
 NUMBER OF SUPERVISORS- 378 
 TOWNSHIP AREA- GORAKHPUR 
 POWER CONSUMPTION- 208662 KWH
LIST OF SHOPS IN THIS WORKSHOPS 
 INSPECTION SHOP. 
 MACHINE SHOP. 
 PAINTING SHOP. 
 WHEEL AND SHAFT SHOP. 
 SPRING SECTION 
 HEAT TREATMENT SHOP 
 JIG AND FIXTURE.
CONT…. 
 BRAKING SHOP. 
 SHELL SHOP. 
 FINAL ASSEMBLY.
INSPECTION SHOP 
 THIS SHOP IS USED FOR INSPECTION PURPOSES. 
 A LIST OF EXPERTS CAME IN THE SHOP AND LISTED THE 
ERRORS AND PROBLEM OCCURRED IN THE COACHES. 
 THEN THEY MAKE A MAJOR OR MINOR LSIT FOR THE 
CAOACH. 
 IF THE PROBLEM IS SMALL IT IS SOLVE IMMEDIATELY IN 
THAT SHOP AND IN NOT IT IS SEND FOR THE FURTHER 
SHOPS.
MACHINE SHOP 
 MACHINE SHOP IS DIVIDED INTO TWO CATEGORY- 
 Automatic machine---( N.C.BORING,CNC LATHE,HEAVY 
DRILLING MACHINE ETC.) 
 MANUAL MACHINE---DRILLING MACHINE, SHAPER, 
SLOTTER, PLANNER , LATHE,ETC. 
 The different type of machining is done on this shop. 
 For automatic machines skilled worker is required and in 
manual section average worker can work.
PAINT SHOP 
 In this shop painting has been done of different parts of 
coaches and bogie. 
 Painting is done by either manually or by spray 
machines as per requirement and depending upon 
work load . 
 The spray machines consume more paint and wastage 
of paint is more. 
 Manual painting is slow but no wastage of paint .
WHEEL AND SHAFT SHOP 
 In this shop repair of wheel and shaft(axel) is 
undertaken. 
 The wheel is first tested on wheel testing machine. 
 And after that further treatment is done on the basis of 
result of testing. 
 The shop consist of machine like-Axel journal testing 
machine, Hydraulic wheel press machine , Axel turning 
lathe, vertical turning lathe.
SPRING SECTION 
 In this section coil and leaf spring are made. 
 The testing of leaf spring is also done in this shop by 
(1)Visual and magnetic crack detection. (2)Spring 
scraping machine. (3) D’ buckling machine. 
 Various other machines in this shop-Quenching 
tank, Tempering furnace, Rolling machine, 
Cambering machine, Hardness testing 
machine.(BHN)
Coiled spring
HEAT TREATMENT SHOP 
 Heat treatment is the process of heating and cooling of 
material to change its physical and mechanical 
properties without changing the original shape and size. 
 In this shop machine parts are heated for long time 
below its melting point and after that some parts are 
cooled in water and some parts are cooled in air or oil 
as per physical and mechanical properties is required.
HEAT TREATMENT IN FURNANCE
JIGS AND FIXTURE SHOP 
 If a component to be produced in small numbers then 
procedure adopted is marketing out , setting on 
machine, clamping to machine table. 
 Nevertheless it would be for producing same 
component in large quantities because of economic 
reason. A faster and more profitable method calls for a 
device jig & fixture.
BRAKING SHOP 
 In this shop braking system of coaches is maintained. 
 In present time mainly air braking system in use in the 
coaches . 
 The main parts of air braking system are following- 
 BRAKE CYLINDER, BRAKE PIPE, FEED PIPE,DISTRIBUTOR 
PIPE, ANGLE COCK, HOUSE PIPE, AUXILIARY RESERVOIR, 
ISOLATING COCK, DIRT COLLECTOR, PASSENGER 
EMERGENCY ALARM SYSTEM.
SHELL SHOP 
 Shell shop is divided into two parts- 
 FITTING SHOP- In this shop roof, floor, body, seats etc 
maintained by using of tools . 
 WELDING SHOP-Co2 arc welding, Bharat cutting gas, 
Oxy-acetylene gas welding, electric arc welding is 
used. 
 Mainly oxy-acetylene gas welding is used due to 
orientation and space problem.
REFERENCES 
 GOOGLE IMAGES. 
 WIKIPEDIA.ORG.IN 
 INDIANRAILWAY.GOV.IN 
 GHOSH & MALIK.
THANKING YOU!

A presentation on mechanical workshop norh east railway

  • 1.
    A PRESENTATION ONMECHANICAL WORKSHOP NORH EAST RAILWAY GORAKHPUR PRESENTED BY INSTRUCTOR PIYUSH KUMAR TIWARI MR. ANIRUDHH SINGH 1101201022
  • 2.
    INTRODUCTION OF MECHANICAL WORKSHOP GORAKHPUR  Gorakhpur mechanical workshop is established in 1903 for repair and overhauling purpose of steam locomotives.  At present it is used to periodic over hauling and maintenance purpose of AC and NON AC coaches.  The workshop having capacity to overhauled 180 coaches per month.
  • 3.
    STATICS AND SPECIFICATIONOF PLANT  TOTAL AREA COVERED - 29.8 HECTARE.  COVERED AREA –12.6 HECTARE.  NUMBER OF OFFICERS-19  NUMBER OF SUPERVISORS- 378  TOWNSHIP AREA- GORAKHPUR  POWER CONSUMPTION- 208662 KWH
  • 4.
    LIST OF SHOPSIN THIS WORKSHOPS  INSPECTION SHOP.  MACHINE SHOP.  PAINTING SHOP.  WHEEL AND SHAFT SHOP.  SPRING SECTION  HEAT TREATMENT SHOP  JIG AND FIXTURE.
  • 5.
    CONT….  BRAKINGSHOP.  SHELL SHOP.  FINAL ASSEMBLY.
  • 6.
    INSPECTION SHOP THIS SHOP IS USED FOR INSPECTION PURPOSES.  A LIST OF EXPERTS CAME IN THE SHOP AND LISTED THE ERRORS AND PROBLEM OCCURRED IN THE COACHES.  THEN THEY MAKE A MAJOR OR MINOR LSIT FOR THE CAOACH.  IF THE PROBLEM IS SMALL IT IS SOLVE IMMEDIATELY IN THAT SHOP AND IN NOT IT IS SEND FOR THE FURTHER SHOPS.
  • 7.
    MACHINE SHOP MACHINE SHOP IS DIVIDED INTO TWO CATEGORY-  Automatic machine---( N.C.BORING,CNC LATHE,HEAVY DRILLING MACHINE ETC.)  MANUAL MACHINE---DRILLING MACHINE, SHAPER, SLOTTER, PLANNER , LATHE,ETC.  The different type of machining is done on this shop.  For automatic machines skilled worker is required and in manual section average worker can work.
  • 8.
    PAINT SHOP In this shop painting has been done of different parts of coaches and bogie.  Painting is done by either manually or by spray machines as per requirement and depending upon work load .  The spray machines consume more paint and wastage of paint is more.  Manual painting is slow but no wastage of paint .
  • 9.
    WHEEL AND SHAFTSHOP  In this shop repair of wheel and shaft(axel) is undertaken.  The wheel is first tested on wheel testing machine.  And after that further treatment is done on the basis of result of testing.  The shop consist of machine like-Axel journal testing machine, Hydraulic wheel press machine , Axel turning lathe, vertical turning lathe.
  • 10.
    SPRING SECTION In this section coil and leaf spring are made.  The testing of leaf spring is also done in this shop by (1)Visual and magnetic crack detection. (2)Spring scraping machine. (3) D’ buckling machine.  Various other machines in this shop-Quenching tank, Tempering furnace, Rolling machine, Cambering machine, Hardness testing machine.(BHN)
  • 11.
  • 12.
    HEAT TREATMENT SHOP  Heat treatment is the process of heating and cooling of material to change its physical and mechanical properties without changing the original shape and size.  In this shop machine parts are heated for long time below its melting point and after that some parts are cooled in water and some parts are cooled in air or oil as per physical and mechanical properties is required.
  • 13.
  • 14.
    JIGS AND FIXTURESHOP  If a component to be produced in small numbers then procedure adopted is marketing out , setting on machine, clamping to machine table.  Nevertheless it would be for producing same component in large quantities because of economic reason. A faster and more profitable method calls for a device jig & fixture.
  • 16.
    BRAKING SHOP In this shop braking system of coaches is maintained.  In present time mainly air braking system in use in the coaches .  The main parts of air braking system are following-  BRAKE CYLINDER, BRAKE PIPE, FEED PIPE,DISTRIBUTOR PIPE, ANGLE COCK, HOUSE PIPE, AUXILIARY RESERVOIR, ISOLATING COCK, DIRT COLLECTOR, PASSENGER EMERGENCY ALARM SYSTEM.
  • 18.
    SHELL SHOP Shell shop is divided into two parts-  FITTING SHOP- In this shop roof, floor, body, seats etc maintained by using of tools .  WELDING SHOP-Co2 arc welding, Bharat cutting gas, Oxy-acetylene gas welding, electric arc welding is used.  Mainly oxy-acetylene gas welding is used due to orientation and space problem.
  • 20.