HBS Backfill
Grouting system

The Häny HBS backfill grouting system is developed especially for the grouting of segmental liners behind mechanised TBM
tunnelling. The system is designed for pressure controlled grouting for filling the entire annulus, or for quantity controlled grouting
of the invert segments only.
The Häny HBS backfill grouting system always uses one

This highly flexible system is based on standard pump

grout pump for each point of injection. It can be adapted

components and various control options to allow different

for either mixing pre-blended dry mortar, or for using

degrees of automation.

ready-mixed mortar.

Touch panel
(TBM Control room)

Main control
Mixer

Agitator

Pumps

P4

P4

P1

P1
P2
Agitator car

P2

P3

P3
Pressure
Transducers

Control functions
Control by pressure
The injection pressure is continuously measured by

accelerator is added to the grout mix, the dosing pumps

means of transducers mounted in or close to the tail

can be switched off earlier to avoid setting of the mortar in

shield injection pipe of the TBM. A PLC with touch screen

the grout lines.

panel monitors and controls the pre-set pressure range
for that specific line. If pressure reaches the pre-set max-

The entire backfill process is controlled from a touch screen

imum the pump automatically stops, to start again auto-

panel, placed either in the main TBM control room or at

matically when pressure hits the lower limit.

the main control cabinet. A window, showing the schematic
of the tail shield allows the TBM or grouting operator to

Once each pump is activated, plc control function is fully

start and stop the grout pumps.

automatic. If the pressure at the injection point fails to
increase to the required pressure within an adjustable

It also shows the pressure at the tail shield grout pipes; the

time limit after start of pumping, an alarm triggers imme-

pressure at the pumps; the pumping rate and total quantity

diate attention by the operator.

pumped by each pump; as well as the accumulated injection
values for all pumps.

Control by quantity
In cases where only the invert is to be grouted, the desired

Quantities are measured by either counting the pump

quantity of grout can be pre-set. Whenever this quantity

strokes or recorded by inductive flow meters and are dis-

is reached, the pump will automatically be stopped. If an

played in a control screen window that also indicates the
values for the last 20 shoves and the total quantity of
grout pumped since the start of the project.

Recording of quantity.

The volume per stroke, start and stop pressures, delays
for alarms, and other operating data are displayed and set
in a separate window. After each shove, the total quantity
per shove can be re-set.

Space saving, vertical
arrangement of the pump.

Pump and alarm settings.

Integral system
By complimenting the HBS with a Häny HCM series high-

The main control comprises a plc and all the high voltage

shear mixer, several other operations are possible. Ben-

components necessary for the operation of the grout

tonite, for example, can be mixed in place to clean out the

pumps. For maintenance and cleaning, a switch allows

grout lines for longer periods of downtime. The same equip-

direct control of the pump at the grout station while a

ment can also be used if pre-excavation grouting is required

safety switch prevents unauthorised or accidental opera-

to stabilise bad ground conditions. Cement or ultra fine

tion of the system from a remote control panel.

cement is mixed efficiently in the HCM mixer and injected
by the same pumps normally used for backfilling. Since

Maximum pressure and maximum output of each pump

backfilling and pre-grouting processes are never needed

can be manually pre-set at the pump. Through this func-

or executed at the same time, this dual-purpose applica-

tion, the maximum pressure in the system can be limited

tion is importantly cost efficient, saves considerable space

and the output of the pump can be adapted to the advance

on the TBM back-up gantries, and reduces the inventory of

rate of the TBM. The fine control is affected through the

equipment that needs to be managed and maintained by

pressure- and quantity-dependent plc control.

the tunnelling crews.
1

2
1) Grouting of invert with
continuous mixer for
pre-blended dry mortar.
Bözberg Highway Tunnel,
Switzerland.
2) TBM control room
with touch screen control
panel for segmental lining
backfilling. Guadarrama
High Speed Rail Tunnel.
North Portal, Spain.

3

4
3) Grouting of invert with
continuous mixer for
pre-blended dry mortar.
Guadarrama High Speed
Rail Tunnel. South Portal,
Spain.
4) Pumps for backfilling
of the tunnel lining arch
section with ready mixed
grout. Guadarrama High
Speed Rail Tunnel.
North Portal, Spain.

5

6
5) Grouting with
continuous mixer for
pre-blended dry mortar
Abdalajis High Speed Rail

6) Pumps for backfilling
of the entire segmental
lining annulus with ready
mixed grout.
Channel Tunnel Rail Link
(CTRL) Contract 240.
London UK.
Häny AG reserves the right to make improvements and modifications to their equipment without notice.

Häny AG • Buechstrasse 20 • CH-8645 Jona/Switzerland
Tel. +41 44 925 41 11 • Fax +41 44 923 62 45 • info@haeny.com • www.haeny.com

100 48 17–6/2009–e–fdf

Tunnel. Malaga, Spain.

HBS Backfill Grouting system from Häny AG

  • 1.
    HBS Backfill Grouting system TheHäny HBS backfill grouting system is developed especially for the grouting of segmental liners behind mechanised TBM tunnelling. The system is designed for pressure controlled grouting for filling the entire annulus, or for quantity controlled grouting of the invert segments only.
  • 2.
    The Häny HBSbackfill grouting system always uses one This highly flexible system is based on standard pump grout pump for each point of injection. It can be adapted components and various control options to allow different for either mixing pre-blended dry mortar, or for using degrees of automation. ready-mixed mortar. Touch panel (TBM Control room) Main control Mixer Agitator Pumps P4 P4 P1 P1 P2 Agitator car P2 P3 P3 Pressure Transducers Control functions Control by pressure The injection pressure is continuously measured by accelerator is added to the grout mix, the dosing pumps means of transducers mounted in or close to the tail can be switched off earlier to avoid setting of the mortar in shield injection pipe of the TBM. A PLC with touch screen the grout lines. panel monitors and controls the pre-set pressure range for that specific line. If pressure reaches the pre-set max- The entire backfill process is controlled from a touch screen imum the pump automatically stops, to start again auto- panel, placed either in the main TBM control room or at matically when pressure hits the lower limit. the main control cabinet. A window, showing the schematic of the tail shield allows the TBM or grouting operator to Once each pump is activated, plc control function is fully start and stop the grout pumps. automatic. If the pressure at the injection point fails to increase to the required pressure within an adjustable It also shows the pressure at the tail shield grout pipes; the time limit after start of pumping, an alarm triggers imme- pressure at the pumps; the pumping rate and total quantity diate attention by the operator. pumped by each pump; as well as the accumulated injection values for all pumps. Control by quantity In cases where only the invert is to be grouted, the desired Quantities are measured by either counting the pump quantity of grout can be pre-set. Whenever this quantity strokes or recorded by inductive flow meters and are dis- is reached, the pump will automatically be stopped. If an played in a control screen window that also indicates the
  • 3.
    values for thelast 20 shoves and the total quantity of grout pumped since the start of the project. Recording of quantity. The volume per stroke, start and stop pressures, delays for alarms, and other operating data are displayed and set in a separate window. After each shove, the total quantity per shove can be re-set. Space saving, vertical arrangement of the pump. Pump and alarm settings. Integral system By complimenting the HBS with a Häny HCM series high- The main control comprises a plc and all the high voltage shear mixer, several other operations are possible. Ben- components necessary for the operation of the grout tonite, for example, can be mixed in place to clean out the pumps. For maintenance and cleaning, a switch allows grout lines for longer periods of downtime. The same equip- direct control of the pump at the grout station while a ment can also be used if pre-excavation grouting is required safety switch prevents unauthorised or accidental opera- to stabilise bad ground conditions. Cement or ultra fine tion of the system from a remote control panel. cement is mixed efficiently in the HCM mixer and injected by the same pumps normally used for backfilling. Since Maximum pressure and maximum output of each pump backfilling and pre-grouting processes are never needed can be manually pre-set at the pump. Through this func- or executed at the same time, this dual-purpose applica- tion, the maximum pressure in the system can be limited tion is importantly cost efficient, saves considerable space and the output of the pump can be adapted to the advance on the TBM back-up gantries, and reduces the inventory of rate of the TBM. The fine control is affected through the equipment that needs to be managed and maintained by pressure- and quantity-dependent plc control. the tunnelling crews.
  • 4.
    1 2 1) Grouting ofinvert with continuous mixer for pre-blended dry mortar. Bözberg Highway Tunnel, Switzerland. 2) TBM control room with touch screen control panel for segmental lining backfilling. Guadarrama High Speed Rail Tunnel. North Portal, Spain. 3 4 3) Grouting of invert with continuous mixer for pre-blended dry mortar. Guadarrama High Speed Rail Tunnel. South Portal, Spain. 4) Pumps for backfilling of the tunnel lining arch section with ready mixed grout. Guadarrama High Speed Rail Tunnel. North Portal, Spain. 5 6 5) Grouting with continuous mixer for pre-blended dry mortar Abdalajis High Speed Rail 6) Pumps for backfilling of the entire segmental lining annulus with ready mixed grout. Channel Tunnel Rail Link (CTRL) Contract 240. London UK. Häny AG reserves the right to make improvements and modifications to their equipment without notice. Häny AG • Buechstrasse 20 • CH-8645 Jona/Switzerland Tel. +41 44 925 41 11 • Fax +41 44 923 62 45 • info@haeny.com • www.haeny.com 100 48 17–6/2009–e–fdf Tunnel. Malaga, Spain.