SlideShare a Scribd company logo
Engineering Standards
Standard
6020
Page
1 of 3
TRANSREDES GUIDELINEFOR GROUNDING Issue Date
AND LIGHTNINGPROTECTION OF 4/98
ANTENNA SUPPORT STRUCTURE Rev. No.
Date
4/98
* Indicates revised paragraph, this Rev. No.
1. SCOPE
This standard provides design guidelines for grounding and lightning surge protection of communications system
antenna support structures (towers) where installed at Company facilities.
2. CODES AND STANDARDS
Lightning Protection Institute Code, LPI-175
United Laboratories, Master Label for Lightning Protection, UL96A
National Fire Protection Association (NFPA)
3. GENERAL
Communication system antenna towers, because of their height, are likely to attract lightning strikes which elevate
voltages on all conductive elements connected to the structure. Properly designed and installed surge protection
and grounding systems can adequately protect even the most delicate electronic communication systems from
damage from such lightning strikes. If all equipment, buildings and utility grounds are electrically bonded to a
common grounding electrode with sufficient capacity to carry the surge current to earth, a lightning strike or other
surge will cause all systemcomponents to rise and fall with the surge potential at the same rate. If the surge potential
on all equipment rises and falls at the same rate and the surge current is safely drained away, equipment damage due
to arcing and excessive current should not occur.
3.1 All permanently installed, stationary antenna towers should be bonded to all conductive equipment and
structure in the vicinity and to a suitable ground electrode. If the antenna tower is located at a facility
having an electrical grounding system, the tower grounding electrode should be bonded to the facility
electrical grounding system.
3.2 The tower grounding electrode should function as a single electrode. The design should avoid connection
of extraneous grounding electrodes to the communications grounding system in a manner that creates
alternate paths to ground.
3.3 The design of the grounding electrode should be based on economics considering the probability of
lightning strikes on the tower, the criticality of service of the communications system and the cost of
replacement or repair of potential damage to the equipment. In addition to the following guidelines, the
appropriate technical supervisors and specialists responsible for corrosion control and communications at
the field operating level should be consulted for recommendations relative to grounding electrode design or
surge related problems at existing communications facilities.
3.3.1 The steel reinforced concrete foundation of the antenna tower should be used as the tower
grounding electrode for communication systeminstallations meeting all of the following criteria.
a. Tower height is 75 feet or less.
b. Facility is not located in a high risk area for lightning strikes such as south-central Florida
or as demonstrated by experience on an existing or other similar installations in the local
area.
Engineering Standards
Standard
6020
Page
2 of 3
TRANSREDES GUIDELINEFOR GROUNDING Issue Date
AND LIGHTNINGPROTECTION OF 4/98
ANTENNA SUPPORT STRUCTURE Rev. No.
Date
4/98
* Indicates revised paragraph, this Rev. No.
c. The communications system does not handle information that, if temporarily lost, would
have potential serious financial or safety impact. Data from multiple operating facilities,
pipeline control signals and voice communications are examples of information that may
be considered to have such potential.
d. Soil resistivity at the site is not suspected or measured to exceed 2000 ohm-cm.
3.3.2 For communication systems not meeting the criteria in Section 3.3.1, a tower grounding
counterpoise should be installed.
4. DESIGN
4.1 For steel reinforced concrete foundation used as grounding electrodes, each tower anchor bolt should be
bonded to the steel reinforcement and all equipment and structural elements should be bonded to the tower.
If necessary to lower the resistance to earth of this design, as determined by the post-installation test, one
or more ground rods may be driven around the foundation and bonded to the leg(s) of the tower in a manner
similar to the grounding counterpoise described in Section 4.2.
4.2 A tower grounding counterpoise should consist of a minimum of four ground rods spaced a minimumof 12
feet apart in a symmetrical pattern around the base of the tower and connected with bonding conductors to
forma loop. The loop should be connected and bonded to each leg of the tower.
4.2.1 Ground rods should be installed with the top of the rod a minimum of one foot below finished
grade.
4.2.2 All buried bonding conductors should be insulated and installed in trenches a minimumof one
foot deep.
4.2.3 If the antenna tower is supported by guys, every guy and guy anchor should be connected to
the tower grounding electrode or counterpoise. A separate bonding conductor should be
routed to each guy anchor but may be tapped for bonding to each guy cable terminated at the
guy anchor.
4.3 Antennas with a non-conductive exterior surface such as fiberglass that are side-mounted on the tower
should be protected from a direct lightning strike by an air terminal installed on foot above the top or the
antenna and extending horizontally one foot beyond the top of the antenna.
4.4 All buried metallic components shall be cathodically protected by bonding to existing facilities or a separate
rectifier systemor anodes.
Engineering Standards
Standard
6020
Page
3 of 3
TRANSREDES GUIDELINEFOR GROUNDING Issue Date
AND LIGHTNINGPROTECTION OF 4/98
ANTENNA SUPPORT STRUCTURE Rev. No.
Date
4/98
* Indicates revised paragraph, this Rev. No.
5. MATERIALS
5.1 Bonding conductors should be heavy gauge, stranded, lead-coated, braided copper specifically
manufactured for conducting surge currents created by lightning. For example, Thompson Lightning
Protection Company, catalog #48 is acceptable for this application. Conductors bonding communications
equipment cabinets and chassis to the grounding electrode may be #6 AWG, bare, solid copper provided
such conductors are bonded to a lead-coated, braided, copper conductor prior to leaving the cabinet or
building containing the equipment.
5.2 Ground rods should be stainless steel, zinc or zinc clad rods, 5/8" diameter, non-sectionalized and a minimum
of 10 feet long.
5.3 Fittings and attachments should be copper-bronze bodied and specifically manufactured for application in
lightning protection systems. Exposed connections should be bolted compression type. Buried
connections should be made using a fusible metal process such as Cadweld.
5.4 Air terminals should be stainless steel and 1/2" diameter minimum.
6. TESTING
Using the Direct or Two-terminal measurement method, resistance to earth should be measured between all
equipment bonded to the antenna tower ground electrode and a derived earth reference electrode placed not less
than 50 feet away from the tower ground electrode. The measured resistance should be less than 5 ohms and shall
not exceed 25 ohms.

More Related Content

What's hot

One nation pride defence presentation jmv lps
One nation pride defence presentation jmv lpsOne nation pride defence presentation jmv lps
One nation pride defence presentation jmv lps
Mahesh Chandra Manav
 
Manual 868 mhz antenna with magnetic base and sma connector enocean - vitec
Manual 868 mhz antenna with magnetic base and sma connector   enocean - vitecManual 868 mhz antenna with magnetic base and sma connector   enocean - vitec
Manual 868 mhz antenna with magnetic base and sma connector enocean - vitec
Domotica daVinci
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEM
AISWARYA TV
 
Presentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmvPresentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmv
Mahesh Chandra Manav
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...
Mahesh Chandra Manav
 
Power quality presentation by jmv lps
Power quality presentation by jmv lpsPower quality presentation by jmv lps
Power quality presentation by jmv lps
Mahesh Chandra Manav
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiring
Vima Mali
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
switchboards
switchboardsswitchboards
switchboards
Maria Romina Angustia
 
Diploma i boee u 5 electrical wiring & safety and protection
Diploma i boee u 5 electrical wiring & safety and protectionDiploma i boee u 5 electrical wiring & safety and protection
Diploma i boee u 5 electrical wiring & safety and protectionRai University
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
Vincent Wedelich, PE MBA
 
Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY Jemish
Goti Jemish
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)
Ibrahim Ali
 
mechanical design of power system
mechanical design of power systemmechanical design of power system
mechanical design of power system
Bisnu Parida
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
vishalgohel12195
 
Wiring doc
Wiring docWiring doc

What's hot (16)

One nation pride defence presentation jmv lps
One nation pride defence presentation jmv lpsOne nation pride defence presentation jmv lps
One nation pride defence presentation jmv lps
 
Manual 868 mhz antenna with magnetic base and sma connector enocean - vitec
Manual 868 mhz antenna with magnetic base and sma connector   enocean - vitecManual 868 mhz antenna with magnetic base and sma connector   enocean - vitec
Manual 868 mhz antenna with magnetic base and sma connector enocean - vitec
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEM
 
Presentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmvPresentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmv
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...
 
Power quality presentation by jmv lps
Power quality presentation by jmv lpsPower quality presentation by jmv lps
Power quality presentation by jmv lps
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiring
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Eat105 chapter 2
 
switchboards
switchboardsswitchboards
switchboards
 
Diploma i boee u 5 electrical wiring & safety and protection
Diploma i boee u 5 electrical wiring & safety and protectionDiploma i boee u 5 electrical wiring & safety and protection
Diploma i boee u 5 electrical wiring & safety and protection
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
 
Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY Jemish
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)
 
mechanical design of power system
mechanical design of power systemmechanical design of power system
mechanical design of power system
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
 
Wiring doc
Wiring docWiring doc
Wiring doc
 

Similar to 6020 w2 tr

Instalaciones avionicas
Instalaciones avionicasInstalaciones avionicas
Instalaciones avionicas
Oscar Hermosa Garces
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout ofBhakti Stm
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)
Mahesh Chandra Manav
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
Mahesh Chandra Manav
 
Structured Ground BICSI Approved
Structured Ground   BICSI ApprovedStructured Ground   BICSI Approved
Structured Ground BICSI Approved
Tim Hurley
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02
Sajeewa Lakmal
 
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Mahesh Chandra Manav
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)
Mahesh Chandra Manav
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
Mahesh Chandra Manav
 
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTDESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
Mahesh Chandra Manav
 
Jmv presentation smart process plant (fertilizer)
Jmv  presentation  smart process  plant (fertilizer)Jmv  presentation  smart process  plant (fertilizer)
Jmv presentation smart process plant (fertilizer)
Mahesh Chandra Manav
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
Thorne & Derrick International
 
Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...
Mahesh Chandra Manav
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Mahesh Chandra Manav
 
Tes p-122.04-r0
Tes p-122.04-r0Tes p-122.04-r0
Tes p-122.04-r0
Ibrahim Ali
 
Corporate presentation for l&t solar div by jmv lps
Corporate presentation  for l&t solar div by jmv lpsCorporate presentation  for l&t solar div by jmv lps
Corporate presentation for l&t solar div by jmv lps
Mahesh Chandra Manav
 
Project sagarmala presentation jmv lps
Project sagarmala presentation jmv lpsProject sagarmala presentation jmv lps
Project sagarmala presentation jmv lps
Mahesh Chandra Manav
 
Ansi tia eia_607
Ansi tia eia_607Ansi tia eia_607
Ansi tia eia_607
Carlos Cordoba Cordoba
 
Nec and oesc-7
Nec and oesc-7Nec and oesc-7
Nec and oesc-7
grantlerc
 

Similar to 6020 w2 tr (20)

Instalaciones avionicas
Instalaciones avionicasInstalaciones avionicas
Instalaciones avionicas
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout of
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
 
Structured Ground BICSI Approved
Structured Ground   BICSI ApprovedStructured Ground   BICSI Approved
Structured Ground BICSI Approved
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02
 
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
 
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTDESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
 
Jmv presentation smart process plant (fertilizer)
Jmv  presentation  smart process  plant (fertilizer)Jmv  presentation  smart process  plant (fertilizer)
Jmv presentation smart process plant (fertilizer)
 
Safety for wiring methods
Safety for wiring methodsSafety for wiring methods
Safety for wiring methods
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
 
Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
 
Tes p-122.04-r0
Tes p-122.04-r0Tes p-122.04-r0
Tes p-122.04-r0
 
Corporate presentation for l&t solar div by jmv lps
Corporate presentation  for l&t solar div by jmv lpsCorporate presentation  for l&t solar div by jmv lps
Corporate presentation for l&t solar div by jmv lps
 
Project sagarmala presentation jmv lps
Project sagarmala presentation jmv lpsProject sagarmala presentation jmv lps
Project sagarmala presentation jmv lps
 
Ansi tia eia_607
Ansi tia eia_607Ansi tia eia_607
Ansi tia eia_607
 
Nec and oesc-7
Nec and oesc-7Nec and oesc-7
Nec and oesc-7
 

Recently uploaded

PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

6020 w2 tr

  • 1. Engineering Standards Standard 6020 Page 1 of 3 TRANSREDES GUIDELINEFOR GROUNDING Issue Date AND LIGHTNINGPROTECTION OF 4/98 ANTENNA SUPPORT STRUCTURE Rev. No. Date 4/98 * Indicates revised paragraph, this Rev. No. 1. SCOPE This standard provides design guidelines for grounding and lightning surge protection of communications system antenna support structures (towers) where installed at Company facilities. 2. CODES AND STANDARDS Lightning Protection Institute Code, LPI-175 United Laboratories, Master Label for Lightning Protection, UL96A National Fire Protection Association (NFPA) 3. GENERAL Communication system antenna towers, because of their height, are likely to attract lightning strikes which elevate voltages on all conductive elements connected to the structure. Properly designed and installed surge protection and grounding systems can adequately protect even the most delicate electronic communication systems from damage from such lightning strikes. If all equipment, buildings and utility grounds are electrically bonded to a common grounding electrode with sufficient capacity to carry the surge current to earth, a lightning strike or other surge will cause all systemcomponents to rise and fall with the surge potential at the same rate. If the surge potential on all equipment rises and falls at the same rate and the surge current is safely drained away, equipment damage due to arcing and excessive current should not occur. 3.1 All permanently installed, stationary antenna towers should be bonded to all conductive equipment and structure in the vicinity and to a suitable ground electrode. If the antenna tower is located at a facility having an electrical grounding system, the tower grounding electrode should be bonded to the facility electrical grounding system. 3.2 The tower grounding electrode should function as a single electrode. The design should avoid connection of extraneous grounding electrodes to the communications grounding system in a manner that creates alternate paths to ground. 3.3 The design of the grounding electrode should be based on economics considering the probability of lightning strikes on the tower, the criticality of service of the communications system and the cost of replacement or repair of potential damage to the equipment. In addition to the following guidelines, the appropriate technical supervisors and specialists responsible for corrosion control and communications at the field operating level should be consulted for recommendations relative to grounding electrode design or surge related problems at existing communications facilities. 3.3.1 The steel reinforced concrete foundation of the antenna tower should be used as the tower grounding electrode for communication systeminstallations meeting all of the following criteria. a. Tower height is 75 feet or less. b. Facility is not located in a high risk area for lightning strikes such as south-central Florida or as demonstrated by experience on an existing or other similar installations in the local area.
  • 2. Engineering Standards Standard 6020 Page 2 of 3 TRANSREDES GUIDELINEFOR GROUNDING Issue Date AND LIGHTNINGPROTECTION OF 4/98 ANTENNA SUPPORT STRUCTURE Rev. No. Date 4/98 * Indicates revised paragraph, this Rev. No. c. The communications system does not handle information that, if temporarily lost, would have potential serious financial or safety impact. Data from multiple operating facilities, pipeline control signals and voice communications are examples of information that may be considered to have such potential. d. Soil resistivity at the site is not suspected or measured to exceed 2000 ohm-cm. 3.3.2 For communication systems not meeting the criteria in Section 3.3.1, a tower grounding counterpoise should be installed. 4. DESIGN 4.1 For steel reinforced concrete foundation used as grounding electrodes, each tower anchor bolt should be bonded to the steel reinforcement and all equipment and structural elements should be bonded to the tower. If necessary to lower the resistance to earth of this design, as determined by the post-installation test, one or more ground rods may be driven around the foundation and bonded to the leg(s) of the tower in a manner similar to the grounding counterpoise described in Section 4.2. 4.2 A tower grounding counterpoise should consist of a minimum of four ground rods spaced a minimumof 12 feet apart in a symmetrical pattern around the base of the tower and connected with bonding conductors to forma loop. The loop should be connected and bonded to each leg of the tower. 4.2.1 Ground rods should be installed with the top of the rod a minimum of one foot below finished grade. 4.2.2 All buried bonding conductors should be insulated and installed in trenches a minimumof one foot deep. 4.2.3 If the antenna tower is supported by guys, every guy and guy anchor should be connected to the tower grounding electrode or counterpoise. A separate bonding conductor should be routed to each guy anchor but may be tapped for bonding to each guy cable terminated at the guy anchor. 4.3 Antennas with a non-conductive exterior surface such as fiberglass that are side-mounted on the tower should be protected from a direct lightning strike by an air terminal installed on foot above the top or the antenna and extending horizontally one foot beyond the top of the antenna. 4.4 All buried metallic components shall be cathodically protected by bonding to existing facilities or a separate rectifier systemor anodes.
  • 3. Engineering Standards Standard 6020 Page 3 of 3 TRANSREDES GUIDELINEFOR GROUNDING Issue Date AND LIGHTNINGPROTECTION OF 4/98 ANTENNA SUPPORT STRUCTURE Rev. No. Date 4/98 * Indicates revised paragraph, this Rev. No. 5. MATERIALS 5.1 Bonding conductors should be heavy gauge, stranded, lead-coated, braided copper specifically manufactured for conducting surge currents created by lightning. For example, Thompson Lightning Protection Company, catalog #48 is acceptable for this application. Conductors bonding communications equipment cabinets and chassis to the grounding electrode may be #6 AWG, bare, solid copper provided such conductors are bonded to a lead-coated, braided, copper conductor prior to leaving the cabinet or building containing the equipment. 5.2 Ground rods should be stainless steel, zinc or zinc clad rods, 5/8" diameter, non-sectionalized and a minimum of 10 feet long. 5.3 Fittings and attachments should be copper-bronze bodied and specifically manufactured for application in lightning protection systems. Exposed connections should be bolted compression type. Buried connections should be made using a fusible metal process such as Cadweld. 5.4 Air terminals should be stainless steel and 1/2" diameter minimum. 6. TESTING Using the Direct or Two-terminal measurement method, resistance to earth should be measured between all equipment bonded to the antenna tower ground electrode and a derived earth reference electrode placed not less than 50 feet away from the tower ground electrode. The measured resistance should be less than 5 ohms and shall not exceed 25 ohms.