1. СЭА QUALITY MANAGEMENT SYSTEM
The document
name Procedure management of inappropriate production
Effective date:
Code: SEA P802 15.03.2006
THE MAINTENANCE:
1. THE PURPOSE
2. SCOPE OF APPLICATION
3. REFERENCES TO DOCUMENTS
4. THE INSTRUCTION DESCRIPTION
5. RESPONSIBILITY AND POWERS
6. DESIGNATIONS AND REDUCTIONS
7. APPENDICES
THE HAS PREPARED: HAS CHECKED UP: HAS CONFIRMED:
DOCUMENT
Post: Нач. Technological
department The chief engineer The general director
FIRST NAME,
MIDDLE
INITIAL, LAST
Varakin O. Lerner B. Lobach A.
NAME:
The signature:
№ 1. 2. 3. 4. 5.
Changes Date:
The signature:
SEA P802 Sheet 1 1from 5
2. СЭА QUALITY MANAGEMENT SYSTEM
The document
name Procedure management of inappropriate production
Effective date:
Code: SEA P802 15.03.2006
Sheet of mailing of the document
№ The name Date The
Post
пп Divisions Receptions signature
1 The top management The general director 16.03.06
2 The chief engineer 16.03.06 г
3 Head СМК 16.03.06 г
4 The chief accountant 16.03.06 г
5 The agent on supply 16.03.06 г
6 The manager on the personnel 16.03.06 г
7 Technological The chief of department 16.03.06 г
department
8 The mechanic 16.03.06 г
9 Industrial site №1 The chief of a site 17.03.06г.
10 Industrial site №2 The chief of a site 17.03.06г.
SEA P802 Sheet 1 2from 5
3. СЭА QUALITY MANAGEMENT SYSTEM
The document
name Procedure management of inappropriate production
Effective date:
Code: SEA P802 15.03.2006
1. The procedure purpose:
The given procedure describes managerial process by production which does not correspond to
requirements of specifications, standards, THAT of the project, etc.
2. Scope of application
Process is carried out: 1) – heads of divisions, departments;
2) – separate workers of departments and divisions on
To the decision of heads of divisions;
3) – manufacturers of works on building sites.
3. The reference to documents
ISO 9001: 2000, the river 8;
Quality manual of SEA QM-01
4. The process description
Н – the process Beginning.
1. Reception of the information on discrepancy of production or establishment of the fact of
discrepancy.
The Controller on a platform of building or the manufacturer of works fix discrepancy of production
(a separate element of process, a part of the design documentation, marriage in the put equipment,
etc.). The information is transferred in the form of records, certificates, reports, results of gaugings.
The fact of discrepancy of production to requirements of standard documents, the design or
technological documentation is established at entrance control, at performance of control operations
and acceptance tests in the course of building.
2. Documentation registration.
The certificate about discrepancy of production is made out. It is carried out by the controller on
a platform or under the direction of the chief of a site.
3. Isolation of inappropriate production.
4. The discrepancy analysis.
The commission appointed the Chief engineer which structure includes the qualified experts,
makes the analysis of marriage and defines the further actions with inappropriate production.
5. Probably to use?
Depending on defect degree decisions on possibility of further use are made.
6. Probably to use without alteration?
7. Transfer to repair or on alteration.
8. Registration, the coordination and the statement of permissions to use of inappropriate
production.
The permission is made out by division, the originator of the established discrepancies
The permission is co-ordinated with the Chief engineer, affirms the General director.
9. Completion or correction of inappropriate production.
Completion or alteration of inappropriate production is carried out by division, the originator of
the admitted discrepancy
10. Tests or control after completion or alteration of inappropriate production.
SEA P802 Sheet 1 3from 5
4. СЭА QUALITY MANAGEMENT SYSTEM
The document
name Procedure management of inappropriate production
Effective date:
Code: SEA P802 15.03.2006
Control and test is carried out by the manufacturer of works with the assistance of
representatives ПТО, according to the procedures developed for these purposes.
11. Production has passed control or tests?
Whether there has passed production control or tests are defined by the controller or the
commission.
12. Transfer to the further manufacture.
13. Informing of the client.
The client is informed in the event that it is stipulated in the contract or the contract.
To – the process end
5. Responsibility and powers
Responsibility for an establishment of the facts of discrepancies, them актирования, decision-
making on such production, and its further use, is assigned to controllers on a platform and chief
ПТО
6. Designations and reductions
СМК – quality management System
ПТО – Technological department
8. Appendices
SEA О802.01 «Magazine of registration of discrepancies»
The block the scheme of managerial process by inappropriate production
SEA P802 Sheet 1 4from 5
5. СЭА QUALITY MANAGEMENT SYSTEM
The document
name Procedure management of inappropriate production
Effective date:
Code: SEA P802 15.03.2006
The block – the process scheme.
The appendix
Н
Н – the process beginning
1
1 – Reception of the information on discrepancy
2
of production or an establishment of the fact of
discrepancy
3
2 – documentation Registration
It is carried out by the controller on a platform or
the chief of a site
4
3 – Isolation of inappropriate production
It is carried out by the chief of a site or the
5 manufacturer of works
NO
4 – the discrepancy Analysis
It is carried out by the commission
7 YES
5 – Probably to use?
YES 6 – Probably to use after repair?
6 7 – It is impossible to use
8 – Registration and the permission coordination
NO It is carried out by division – the originator of
8 marriage
9 9 – Completion or correction of inappropriate
production
10 It is carried out by industrial division - the
originator of marriage
10 – Tests or control after completion or alteration
11 NO of inappropriate production
It is carried out by the manufacturer of works
13
YES together with representatives ПТО
11 – Production has passed control or tests?
12 – Transfer to the further manufacture
13 – Informing of the client
14 – the process End
12
TO
SEA P802 Sheet 1 5from 5