This document summarizes the renewable energy systems installed at Fort Huachuca over 35 years, including solar water heating and photovoltaic systems. It describes the design, installation, performance, and lessons learned from various projects such as a 2000 sq ft unglazed solar collector system installed in 1980 to heat an indoor pool, saving over 8000 therms annually. It also discusses a 900 sq ft glazed solar domestic hot water system installed in 1981, and ongoing efforts to repair and upgrade aging renewable systems at the base.
This document provides information on solar greenhouses, including basic design principles, common designs, heat absorption, and glazing material options. It discusses the key factors in solar greenhouse design such as orientation, slope of glazing, and types of glazing materials. The document also provides a table comparing characteristics of different glazing materials and their advantages and disadvantages. Resources for further information on solar greenhouse design are listed, including books, articles, websites and software.
The document summarizes renovations made to the Janesville Ice Arena in Wisconsin, including installing a pond loop geothermal refrigeration system. The system uses an adjacent pond as a heat source and sink for the ice rink's refrigeration system. Other upgrades included a new ice sheet, hot water heating system, and fire protection system. The renovations reduced the arena's energy use intensity by 24.1% and annual natural gas use by 33.5% compared to before the renovations. The pond loop geothermal system provides cost and environmental benefits over a conventional refrigeration system.
The Effects of Heating and Cooling Energy Piles Under Working load at Lambeth...Tonyamis
The document summarizes a study on the effects of heating and cooling energy piles under working loads. Instrumented load tests were conducted on test piles at Lambeth College in the UK. Temperature cycles were applied to the piles using a ground source heat pump system. Results from strain gauges and fiber optic sensors confirmed that pile load-settlement response was not adversely affected by temperature cycles. Monitoring also showed temperature variations within the pile from the heating and cooling, with the pile reaching equilibrium after two weeks of cooling. Installation method of fiber optic sensors did not significantly impact results.
Solarsa Inc. is a company located in Tampa, FL that designs, manufactures, and integrates solar energy solutions including absorption chillers, electric chillers, solar panels, and control systems. They also provide renewable energy integration with building management systems using the Tridium Niagara framework. Some of their project examples include residential and commercial solar cooling and hot water systems in Florida, California, and Oklahoma. Solarsa also offers system design, equipment, installation, and long-term maintenance contracts.
AN EXPERIMENTAL INVESTIGATION ON STATIONARY V TROUGH & PARABOLIC SOLAR WATER ...Journal For Research
Now a day, plenty of hot water is used for domestic, commercial and industrial purposes. Various resources i.e. coal, diesel, gas etc, are used to heat water and sometimes for steam production. Solar energy is the main alternative to replace the conventional energy sources. There are various types of solar water heater system available in the commercial market to fulfill different customers demand, such as flat plate collector, concentrating collector, evacuated tube collector and integrated collector storage. A cost effective cum easy fabricated V-trough solar water heater system using forced circulation system is proposed. Integrating the solar absorber with the easily fabricated V-trough reflector can improve the performance of solar water heater system. In this paper, experiments on the efficiency were conducted for a week during which the atmospheric conditions were almost uniform and data was collected from the collector. The experimental result has shown very promising results in both thermal efficiency of V-trough reflector & parabolic solar water heater.
It is possible to consider that adsorption systems can be alternative to reduce the CO2 emissions and electricity demand when they driven by waste heat or solar energy. Although, for a broader utilization the researches should continue aiming for improvements in heat transfer,reductions of new adsorbent compounds with enhanced adsorption capacity and improved heat and mass transfer properties.
Bill Gould, CTO at SolarReserve, presented at the GW Solar Institute Symposium on April 19, 2010. For more information visit: solar.gwu.edu/Symposium.html
This document provides information on solar greenhouses, including basic design principles, common designs, heat absorption, and glazing material options. It discusses the key factors in solar greenhouse design such as orientation, slope of glazing, and types of glazing materials. The document also provides a table comparing characteristics of different glazing materials and their advantages and disadvantages. Resources for further information on solar greenhouse design are listed, including books, articles, websites and software.
The document summarizes renovations made to the Janesville Ice Arena in Wisconsin, including installing a pond loop geothermal refrigeration system. The system uses an adjacent pond as a heat source and sink for the ice rink's refrigeration system. Other upgrades included a new ice sheet, hot water heating system, and fire protection system. The renovations reduced the arena's energy use intensity by 24.1% and annual natural gas use by 33.5% compared to before the renovations. The pond loop geothermal system provides cost and environmental benefits over a conventional refrigeration system.
The Effects of Heating and Cooling Energy Piles Under Working load at Lambeth...Tonyamis
The document summarizes a study on the effects of heating and cooling energy piles under working loads. Instrumented load tests were conducted on test piles at Lambeth College in the UK. Temperature cycles were applied to the piles using a ground source heat pump system. Results from strain gauges and fiber optic sensors confirmed that pile load-settlement response was not adversely affected by temperature cycles. Monitoring also showed temperature variations within the pile from the heating and cooling, with the pile reaching equilibrium after two weeks of cooling. Installation method of fiber optic sensors did not significantly impact results.
Solarsa Inc. is a company located in Tampa, FL that designs, manufactures, and integrates solar energy solutions including absorption chillers, electric chillers, solar panels, and control systems. They also provide renewable energy integration with building management systems using the Tridium Niagara framework. Some of their project examples include residential and commercial solar cooling and hot water systems in Florida, California, and Oklahoma. Solarsa also offers system design, equipment, installation, and long-term maintenance contracts.
AN EXPERIMENTAL INVESTIGATION ON STATIONARY V TROUGH & PARABOLIC SOLAR WATER ...Journal For Research
Now a day, plenty of hot water is used for domestic, commercial and industrial purposes. Various resources i.e. coal, diesel, gas etc, are used to heat water and sometimes for steam production. Solar energy is the main alternative to replace the conventional energy sources. There are various types of solar water heater system available in the commercial market to fulfill different customers demand, such as flat plate collector, concentrating collector, evacuated tube collector and integrated collector storage. A cost effective cum easy fabricated V-trough solar water heater system using forced circulation system is proposed. Integrating the solar absorber with the easily fabricated V-trough reflector can improve the performance of solar water heater system. In this paper, experiments on the efficiency were conducted for a week during which the atmospheric conditions were almost uniform and data was collected from the collector. The experimental result has shown very promising results in both thermal efficiency of V-trough reflector & parabolic solar water heater.
It is possible to consider that adsorption systems can be alternative to reduce the CO2 emissions and electricity demand when they driven by waste heat or solar energy. Although, for a broader utilization the researches should continue aiming for improvements in heat transfer,reductions of new adsorbent compounds with enhanced adsorption capacity and improved heat and mass transfer properties.
Bill Gould, CTO at SolarReserve, presented at the GW Solar Institute Symposium on April 19, 2010. For more information visit: solar.gwu.edu/Symposium.html
Solar energy is the primary source of energy on Earth and is produced by nuclear fusion reactions in the Sun's core. It provides nearly all the heat and light received by Earth and sustains life. There are two main types of solar collectors - flat plate collectors and concentrating collectors. Flat plate collectors use sunlight to heat a fluid like water or air for uses like water and space heating. Concentrating collectors reflect and focus sunlight to achieve higher temperatures suitable for applications like electricity generation and industrial processes. While solar energy technologies are advancing, generating electricity from solar power remains more expensive than from fossil fuels currently. However, as technologies improve and fossil fuels become more scarce, solar power generation may become more widespread and competitive.
This document discusses solar energy storage and applications. It describes different methods of solar energy storage including sensible heat storage using materials like water, rocks, and concrete. Latent heat storage using phase change is also discussed. Thermal energy storage techniques like solar ponds are explained. Applications of solar energy covered include solar heating/cooling, distillation, drying, and photovoltaic energy conversion. Basic elements of a solar water heating system and different types including natural circulation and forced circulation models are outlined.
Solar Power: Solar Heating, Photovoltaics, and Solar Thermal PowerToni Menninger
The document compares two methods for generating large-scale electricity from solar energy: photovoltaic (PV) power plants and solar thermal power plants. PV plants directly convert sunlight to electricity using solar panels, while solar thermal plants use concentrated solar power to heat a fluid and generate electricity through a steam turbine. Solar thermal plants have advantages of energy storage and ability to supplement with fossil fuels, but are limited geographically to desert areas with strong sunlight. The largest solar thermal plant is in California, while PV installations have grown rapidly worldwide in recent years.
This document summarizes a senior design project report submitted by three students at North South University for their capstone design course. The project involved developing a solar-based refrigerator system to provide refrigeration for rural areas without reliable electricity access. Key components of the system included a 100W solar panel, charge controller, 12V battery, 500W inverter, refrigerator, and data logging equipment to monitor voltage, current and temperature over time. The goal of the project was to optimize the power usage of the refrigerator and provide an affordable solution for off-grid refrigeration needs in developing areas.
This document provides an introduction to geothermal comfort systems. It defines geothermal energy as relating to the internal heat of the earth, noting that the earth acts as a giant solar collector. It distinguishes between high-temperature geothermal from deep underground and low-temperature geothermal, which utilizes shallow earth temperatures via a heat pump. The basic system involves circulating water through underground pipes to transfer heat to and from the ground. During heating the earth serves as a heat source, and during cooling it serves as a heat sink.
This document provides an introduction to geothermal comfort systems. It defines geothermal energy as relating to the internal heat of the earth, noting that the earth acts as a giant solar collector. It distinguishes between high-temperature geothermal from deep underground and low-temperature geothermal, which utilizes shallow earth temperatures via a heat pump. The basic system involves circulating water through underground pipes to transfer heat to and from the ground. During heating the earth serves as a heat source, and during cooling it serves as a heat sink.
The document discusses solar refrigeration systems, including their theory, types (photovoltaic, solar mechanical, absorption), and applications. It describes how solar refrigeration works by using solar energy to power a vapor compression refrigeration cycle. Three main types are described: photovoltaic systems use solar panels to power a compressor, solar mechanical uses solar heat to power a Rankine cycle and generate mechanical energy, and absorption replaces compression with heat-powered absorption into a liquid. Solar refrigeration can provide off-grid refrigeration for food storage, vaccines, and more to address energy access issues.
This document provides information on various renewable energy systems, including how photovoltaic (PV) cells, PV systems, solar thermal systems, solar air panels, and a solar tour work. It then lists the sites and times that will be included on the solar tour, along with brief descriptions of the renewable energy installations at each location.
This document discusses passive and active design strategies for energy efficient buildings and infrastructure. It begins by defining passive design as using natural energy sources like sunlight and wind without electricity or fuel, while active design uses electricity or produces it. It then provides examples of passive design strategies like adaptive reuse, heritage conservation, site optimization, passive solar, thermal mass, deep overhangs, natural cross-ventilation, recycled materials, green roofs, and interior materials. Active design strategies discussed include geothermal heat exchange, wind power, grid-connected systems, solar electrical power, solar thermal energy, high efficiency HVAC systems, HRV/ERV, building automation, high-efficiency appliances, and greywater reuse.
The document discusses the Skytherm roof pond system invented by Harold Hay in 1973. The system uses water and solar energy to heat and cool a building without electricity. It consists of water stored in plastic bags or tanks on the roof, covered with insulation panels. In hot climates, the system maintains indoor temperatures below 30°C with outdoor temperatures over 40°C. It works by collecting solar heat in the water during the day which is then radiated inside at night for heating in winter. In summer, the water cools at night by radiating heat and stays cool under insulation during the day. Studies show it can effectively heat and cool with no auxiliary systems.
The document discusses different types of energy sources including renewable and non-renewable sources. It provides details on how each source captures and stores energy. Wind energy captures kinetic energy from wind and can store excess in batteries. Solar energy captures radiation from the sun using panels and can be stored in batteries. Fossil fuels like coal and oil capture ancient stored solar energy and are stored in containers. Hydroelectric captures kinetic energy from moving water behind dams and in reservoirs. Biomass captures stored chemical energy from plants. Geothermal captures underground heat energy which is always present. Nuclear captures binding energy from atoms through fission or fusion and excess heat must be immediately used to generate electricity.
The document discusses various alternative energy sources including nuclear power (fission and fusion), solar energy, and geothermal energy. It provides details on the technologies and processes involved in each type of energy production. For nuclear power, it describes fission, fusion, and the use of uranium. For solar energy, it outlines photovoltaic systems, solar heating, and passive solar design. For geothermal, it discusses using the Earth's heat for electricity generation, direct use, and heat pumps. It also provides an example of geothermal energy use on the island of Leyte in the Philippines.
This document discusses principles of passive solar design for cooling buildings. It defines passive design as design that takes advantage of climate to maintain comfortable temperatures without mechanical heating or cooling. Key passive cooling strategies mentioned include building orientation, ventilation, shading, insulation, and thermal mass. The document provides details on these strategies and how they can be applied differently depending on climate type, such as hot humid, hot dry, or temperate climates. It also discusses design elements like roof ventilation, glazing selection and shading, and passive cooling of both buildings and occupants.
Solar energy originates from the thermonuclear fusion reactions of the sun. It represents the entire electromagnetic spectrum that reaches Earth. Solar energy has the advantage of being pollution-free and sustainable, as the sun provides incredible amounts of energy to Earth each day equivalent to all fossil fuels. However, solar energy is diffuse and intermittent, requiring technologies to concentrate and store it. Various technologies exist to harness solar energy for heating water and living spaces or generating electricity through solar thermal or photovoltaic means, but they remain more expensive than fossil fuel alternatives.
Solar energy originates from the thermonuclear fusion reactions of the sun. It represents the entire electromagnetic spectrum that reaches Earth. Solar energy has the advantage of producing no pollutants, as 30 days of sunshine provides more energy than all fossil fuels on Earth. However, solar energy is diffuse and intermittent, requiring concentration and storage to be useful. Various technologies have been developed to collect, convert, and store solar energy for heating water and buildings, or generating electricity through solar thermal power towers, parabolic dishes, and photovoltaic cells.
Solar energy originates from the thermonuclear fusion reactions occurring in the sun. It represents the entire electromagnetic radiation that reaches Earth. The advantages of solar energy are that it produces no polluting byproducts, and the energy reaching Earth in 30 days equals all fossil fuels on the planet. Challenges include its diffuse nature and inconsistent availability. Solar energy can be used to heat water and living spaces through passive and active collection and storage systems. It can also be converted to electricity through solar thermal power towers, dishes, troughs, and photovoltaic cells, though the latter have lower efficiency and higher costs than traditional power sources.
Concentrated Solar Power Technologies (CSP)swapnil_energy
Analysis of Concentrated solar power (CSP) or Solar Thermal (STH) technologies with focus on its technology assessment, financials, challenge areas and solar market scenario
EXPERIMENTAL INVESTIGATION OF THERMAL PERFORMANCE OF CURTAIN-WALL-INTEGRATED ...ijiert bestjournal
This document presents the results of an experimental investigation into the thermal performance of a curtain wall-integrated solar heater using different working fluids, including water and copper oxide nanofluid. Experiments were conducted with mass flow rates varying from 36 to 108 liters per hour. Higher efficiencies were found when using the 3% nanofluid compared to water alone. Outlet water temperature also increased at lower mass flow rates for both fluids. For a given fluid, efficiency slightly increased with higher mass flow rates. The study concluded the nanofluid improved the thermal performance and increased the outlet temperature of hot water compared to just using water.
Solar energy is the primary source of energy on Earth and is produced by nuclear fusion reactions in the Sun's core. It provides nearly all the heat and light received by Earth and sustains life. There are two main types of solar collectors - flat plate collectors and concentrating collectors. Flat plate collectors use sunlight to heat a fluid like water or air for uses like water and space heating. Concentrating collectors reflect and focus sunlight to achieve higher temperatures suitable for applications like electricity generation and industrial processes. While solar energy technologies are advancing, generating electricity from solar power remains more expensive than from fossil fuels currently. However, as technologies improve and fossil fuels become more scarce, solar power generation may become more widespread and competitive.
This document discusses solar energy storage and applications. It describes different methods of solar energy storage including sensible heat storage using materials like water, rocks, and concrete. Latent heat storage using phase change is also discussed. Thermal energy storage techniques like solar ponds are explained. Applications of solar energy covered include solar heating/cooling, distillation, drying, and photovoltaic energy conversion. Basic elements of a solar water heating system and different types including natural circulation and forced circulation models are outlined.
Solar Power: Solar Heating, Photovoltaics, and Solar Thermal PowerToni Menninger
The document compares two methods for generating large-scale electricity from solar energy: photovoltaic (PV) power plants and solar thermal power plants. PV plants directly convert sunlight to electricity using solar panels, while solar thermal plants use concentrated solar power to heat a fluid and generate electricity through a steam turbine. Solar thermal plants have advantages of energy storage and ability to supplement with fossil fuels, but are limited geographically to desert areas with strong sunlight. The largest solar thermal plant is in California, while PV installations have grown rapidly worldwide in recent years.
This document summarizes a senior design project report submitted by three students at North South University for their capstone design course. The project involved developing a solar-based refrigerator system to provide refrigeration for rural areas without reliable electricity access. Key components of the system included a 100W solar panel, charge controller, 12V battery, 500W inverter, refrigerator, and data logging equipment to monitor voltage, current and temperature over time. The goal of the project was to optimize the power usage of the refrigerator and provide an affordable solution for off-grid refrigeration needs in developing areas.
This document provides an introduction to geothermal comfort systems. It defines geothermal energy as relating to the internal heat of the earth, noting that the earth acts as a giant solar collector. It distinguishes between high-temperature geothermal from deep underground and low-temperature geothermal, which utilizes shallow earth temperatures via a heat pump. The basic system involves circulating water through underground pipes to transfer heat to and from the ground. During heating the earth serves as a heat source, and during cooling it serves as a heat sink.
This document provides an introduction to geothermal comfort systems. It defines geothermal energy as relating to the internal heat of the earth, noting that the earth acts as a giant solar collector. It distinguishes between high-temperature geothermal from deep underground and low-temperature geothermal, which utilizes shallow earth temperatures via a heat pump. The basic system involves circulating water through underground pipes to transfer heat to and from the ground. During heating the earth serves as a heat source, and during cooling it serves as a heat sink.
The document discusses solar refrigeration systems, including their theory, types (photovoltaic, solar mechanical, absorption), and applications. It describes how solar refrigeration works by using solar energy to power a vapor compression refrigeration cycle. Three main types are described: photovoltaic systems use solar panels to power a compressor, solar mechanical uses solar heat to power a Rankine cycle and generate mechanical energy, and absorption replaces compression with heat-powered absorption into a liquid. Solar refrigeration can provide off-grid refrigeration for food storage, vaccines, and more to address energy access issues.
This document provides information on various renewable energy systems, including how photovoltaic (PV) cells, PV systems, solar thermal systems, solar air panels, and a solar tour work. It then lists the sites and times that will be included on the solar tour, along with brief descriptions of the renewable energy installations at each location.
This document discusses passive and active design strategies for energy efficient buildings and infrastructure. It begins by defining passive design as using natural energy sources like sunlight and wind without electricity or fuel, while active design uses electricity or produces it. It then provides examples of passive design strategies like adaptive reuse, heritage conservation, site optimization, passive solar, thermal mass, deep overhangs, natural cross-ventilation, recycled materials, green roofs, and interior materials. Active design strategies discussed include geothermal heat exchange, wind power, grid-connected systems, solar electrical power, solar thermal energy, high efficiency HVAC systems, HRV/ERV, building automation, high-efficiency appliances, and greywater reuse.
The document discusses the Skytherm roof pond system invented by Harold Hay in 1973. The system uses water and solar energy to heat and cool a building without electricity. It consists of water stored in plastic bags or tanks on the roof, covered with insulation panels. In hot climates, the system maintains indoor temperatures below 30°C with outdoor temperatures over 40°C. It works by collecting solar heat in the water during the day which is then radiated inside at night for heating in winter. In summer, the water cools at night by radiating heat and stays cool under insulation during the day. Studies show it can effectively heat and cool with no auxiliary systems.
The document discusses different types of energy sources including renewable and non-renewable sources. It provides details on how each source captures and stores energy. Wind energy captures kinetic energy from wind and can store excess in batteries. Solar energy captures radiation from the sun using panels and can be stored in batteries. Fossil fuels like coal and oil capture ancient stored solar energy and are stored in containers. Hydroelectric captures kinetic energy from moving water behind dams and in reservoirs. Biomass captures stored chemical energy from plants. Geothermal captures underground heat energy which is always present. Nuclear captures binding energy from atoms through fission or fusion and excess heat must be immediately used to generate electricity.
The document discusses various alternative energy sources including nuclear power (fission and fusion), solar energy, and geothermal energy. It provides details on the technologies and processes involved in each type of energy production. For nuclear power, it describes fission, fusion, and the use of uranium. For solar energy, it outlines photovoltaic systems, solar heating, and passive solar design. For geothermal, it discusses using the Earth's heat for electricity generation, direct use, and heat pumps. It also provides an example of geothermal energy use on the island of Leyte in the Philippines.
This document discusses principles of passive solar design for cooling buildings. It defines passive design as design that takes advantage of climate to maintain comfortable temperatures without mechanical heating or cooling. Key passive cooling strategies mentioned include building orientation, ventilation, shading, insulation, and thermal mass. The document provides details on these strategies and how they can be applied differently depending on climate type, such as hot humid, hot dry, or temperate climates. It also discusses design elements like roof ventilation, glazing selection and shading, and passive cooling of both buildings and occupants.
Solar energy originates from the thermonuclear fusion reactions of the sun. It represents the entire electromagnetic spectrum that reaches Earth. Solar energy has the advantage of being pollution-free and sustainable, as the sun provides incredible amounts of energy to Earth each day equivalent to all fossil fuels. However, solar energy is diffuse and intermittent, requiring technologies to concentrate and store it. Various technologies exist to harness solar energy for heating water and living spaces or generating electricity through solar thermal or photovoltaic means, but they remain more expensive than fossil fuel alternatives.
Solar energy originates from the thermonuclear fusion reactions of the sun. It represents the entire electromagnetic spectrum that reaches Earth. Solar energy has the advantage of producing no pollutants, as 30 days of sunshine provides more energy than all fossil fuels on Earth. However, solar energy is diffuse and intermittent, requiring concentration and storage to be useful. Various technologies have been developed to collect, convert, and store solar energy for heating water and buildings, or generating electricity through solar thermal power towers, parabolic dishes, and photovoltaic cells.
Solar energy originates from the thermonuclear fusion reactions occurring in the sun. It represents the entire electromagnetic radiation that reaches Earth. The advantages of solar energy are that it produces no polluting byproducts, and the energy reaching Earth in 30 days equals all fossil fuels on the planet. Challenges include its diffuse nature and inconsistent availability. Solar energy can be used to heat water and living spaces through passive and active collection and storage systems. It can also be converted to electricity through solar thermal power towers, dishes, troughs, and photovoltaic cells, though the latter have lower efficiency and higher costs than traditional power sources.
Concentrated Solar Power Technologies (CSP)swapnil_energy
Analysis of Concentrated solar power (CSP) or Solar Thermal (STH) technologies with focus on its technology assessment, financials, challenge areas and solar market scenario
EXPERIMENTAL INVESTIGATION OF THERMAL PERFORMANCE OF CURTAIN-WALL-INTEGRATED ...ijiert bestjournal
This document presents the results of an experimental investigation into the thermal performance of a curtain wall-integrated solar heater using different working fluids, including water and copper oxide nanofluid. Experiments were conducted with mass flow rates varying from 36 to 108 liters per hour. Higher efficiencies were found when using the 3% nanofluid compared to water alone. Outlet water temperature also increased at lower mass flow rates for both fluids. For a given fluid, efficiency slightly increased with higher mass flow rates. The study concluded the nanofluid improved the thermal performance and increased the outlet temperature of hot water compared to just using water.
This document provides an overview of solar energy, including its history, current applications, and future potential. It discusses how solar energy works and the two key components (collectors and storage). Applications mentioned include solar thermal technologies for water and space heating, electricity production, cooking, process heat, and desalination. The document also reviews various energy storage methods and the development, deployment, and economics of solar power over history.
This document discusses various solar technologies including daylighting, solar thermal, solar cooking, solar water treatment, solar electricity generation, solar chemical processes, solar vehicles, and solar energy storage. It provides examples of each technology and highlights their applications, efficiencies, and historical uses. Key solar technologies mentioned include evacuated tube collectors, glazed flat plate collectors, solar chimneys, solar ponds, parabolic dishes, and thermal energy storage systems.
This document provides an overview of solar power, including its history, technologies, and future potential. It discusses both active solar systems that use mechanical means to distribute solar energy, as well as passive solar techniques used in building design. Photovoltaic cells that directly convert sunlight to electricity are described as the basic building block of solar energy production. Larger scale technologies like trough systems and concentrating solar power that use mirrors to focus sunlight are also summarized. The document outlines key aspects of passive solar home design and concludes by discussing the Department of Energy's projections that solar costs will be competitive with fossil fuels by 2020.
The Fukushima Daiichi nuclear power plant accident was caused by a magnitude 9 earthquake and subsequent tsunami on March 11, 2011 that disabled the plant's power and cooling systems. The loss of cooling caused three nuclear reactors to experience meltdowns. Over 500 petabecquerels of radioactive material was released into the environment, contaminating an area of around 640 square kilometers and forcing the evacuation of over 76,000 residents. Communication failures and leadership issues during the emergency response exacerbated the situation.
This document discusses the two main types of energy that can be derived from solar panels - electricity from photovoltaic panels and heated water from solar thermal panels. Solar hot water is described as generally being a more accessible and affordable approach to solar energy compared to solar electricity. For those living off the electric grid in remote areas, a stand-alone solar power system is needed, and these systems require batteries to store the solar-generated electricity, unlike grid-tied solar electricity systems.
Solar thermal energy systems harness solar energy as heat. There are three main types of solar thermal collectors: low-temperature collectors heat swimming pools, medium-temperature collectors heat water for homes and businesses, and high-temperature collectors concentrate sunlight to produce electricity or process heat. Heat from collectors is transferred using fluids like water or glycol and can be stored for later use through thermal mass materials or molten salts. Common solar thermal applications include water heating, space heating, drying crops and materials, and generating electricity through technologies like parabolic troughs and power towers.
1981: A 90.4-kW PV system was dedicated at Lovington Square Shopping Center (New Mexico) using Solar Power Corp. modules. A 97.6-kW PV system was dedicated at Beverly High School in Beverly, Massachusetts, using Solar Power Corp. modules. An 8-kW PV-powered (Mobil Solar), reverse-osmosis desalination facility was dedicated in Jeddah, Saudi Arabia. 1984: The IEEE Morris N. Liebmann Award was presented to Drs. David Carlson and Christopher Wronski at the 17th Photovoltaic Specialists Conference, "for crucial contributions to the use of amorphous silicon in low-cost, high-performance photovoltaic solar cells." 1991: The Solar Energy Research Institute was redesignated as the U.S. Department of Energy's National Renewable Energy Laboratory by President George Bush. 1993: The National Renewable Energy Laboratory's Solar Energy Research Facility (SERF), opened in Golden, Colorado. 1996: The U.S. Department of Energy announces the National Center for Photovoltaics, headquartered in Golden, Colorado.
Solar water heaters use solar energy (sun light) to generate heat which used to heat water for home uses, industrial uses hotel or many places where hot water necessary. Solar water system is safe, efficient and eco- friendly system
The document discusses solar thermal energy technologies. It describes how solar thermal technologies use the sun's heat energy to heat substances like water or air for applications such as space heating and water heating. It provides details on different solar thermal collector technologies, including flat-plate collectors that are mounted on roofs and concentrate sunlight to heat a fluid. Concentrating solar power systems are also discussed, which use mirrors to focus sunlight and produce steam to generate electricity. Solar thermal power generation is highlighted as a promising renewable energy technology due to its low costs and ability to provide firm, reliable power production with thermal storage or fossil fuel backup.
Geothermal energy piles use closed loop heat exchangers embedded in reinforced concrete piles to extract heat from below ground for building heating and cooling needs. While case studies have examined heating and cooling performance, little work has been done to understand the thermo-mechanical effects on pile structural performance from thermal cycles. This project uses analytical tools to create a 3D model of an energy pile system and conduct a finite element analysis to better understand performance under real conditions.
Performance of solar water heater in akure, nigeriaAlexander Decker
The document summarizes a study that designed, constructed, and tested a solar water heater in Akure, Nigeria. Key findings include:
- A flat plate collector covered with double glazing and tilted at 20 degrees recorded a maximum hot water temperature of 73°C with ambient temperature of 36°C. Collector efficiency peaked at 92% at 4pm.
- The study established solar water heating is feasible in Southwest Nigeria and most parts of the country due to high solar insolation.
- Collector efficiency increased slightly until 2pm then had a steep increase, peaking at 4pm, showing efficiency dances to the tune of insolation intensity.
The document discusses different types of solar thermal power generation systems that use mirrors to collect sunlight and produce steam to drive turbines for power generation. It describes the main types as parabolic trough systems, solar power tower systems, solar dish/engine systems, and compact linear Fresnel reflectors. These systems work by using mirrors to concentrate sunlight and heat a working fluid like molten salt that is then used to generate electricity via steam turbines. The document also discusses advantages like no fuel costs, disadvantages like high installation costs, and challenges around energy storage and bringing costs down further.
Kaushik Kishore submitted a seminar report on solar power towers. The report provides details on how solar power towers work, including focusing sunlight with heliostats onto a tower-mounted receiver to heat a working fluid like oil or molten salt. The heated fluid is then used to generate steam and power a turbine generator. Key advantages are the ability to store thermal energy for nighttime or cloudy conditions and generate electricity without emissions. Large solar power towers could provide 200MW of power but require significant land area and precise engineering for the tall tower structure.
This document discusses different methods of collecting and utilizing solar energy. It begins by explaining that solar energy comes from nuclear fusion reactions in the sun and reaches Earth as photons. There are two main types of solar collectors: flat plate collectors and concentrating collectors. Flat plate collectors use absorber plates and carrier fluids like water to collect solar energy for thermal processes. Concentrating collectors use reflectors to focus sunlight onto small areas, achieving higher temperatures suitable for applications like solar cooling or furnaces. The document also discusses passive solar energy systems that design structures to naturally collect, store, and distribute solar heat.
1. The document discusses the design of a cold water pipe for an OTEC power plant off the coast of the Philippines. It analyzes parameters from a theoretical 10MW OTEC system to determine requirements for the cold water pipe design.
2. Key parameters used include a seawater temperature difference of 21.5°C and mass flow rate. The document estimates that a pipe depth of 895.84m would achieve the required temperature difference off the Philippines coast.
3. Additional considerations for the pipe design include withstanding static/dynamic loads from waves and typhoons that occur in the Philippines location. The pipe structure, flow rate, diameter and pump requirements will be analyzed based on the estimated depth.
Solar thermal power generation systems use mirrors to collect sunlight and produce steam by solar heat to drive turbines for generating power. This system generates power by rotating turbines like thermal and nuclear power plants, and therefore, is suitable for large-scale power generation.
This document provides an overview of solar water heating systems. It discusses the different types of solar thermal collectors categorized by operating temperature, including low-temperature unglazed mats, mid-temperature glazed and insulated collectors, and high-temperature evacuated tubes and focusing collectors. The document then presents examples of solar water heating systems installed at various facilities in the US, including residential, commercial, and institutional buildings. Calculation methods are also provided for sizing a solar water heating system and estimating energy savings and cost effectiveness.
This document describes a study of a thermoacoustic refrigeration system. Thermoacoustic refrigeration uses sound waves to pump heat in a resonator tube, without ozone-depleting refrigerants. The study varied parameters like frequency, mean pressure, and cooling load to analyze their effects on the hot end temperature and temperature difference across the stack. Results showed that higher frequency, pressure, and cooling load increased hot end temperature, with an optimal pressure for maximum temperature difference. Compared to vapor compression systems, thermoacoustic refrigeration has fewer moving parts and lower maintenance costs while avoiding environmental hazards.
Similar to 35 years of RE project Exp at FHU 14 Aug 15 (20)
1. 1
Thirty Five Years of Renewable Energy Project Experience at Fort
Huachuca, Arizona (est. 1877)
William J. Stein, CEM, CEP,
CSDP, CMVP, CEA, REP, CDSM
U. S. Army Corps of Engineers
Construction Engineering
Research Laboratory
Champaign, Illinois, USA
Bruce R. Johnson, PE
Network Enterprise Technology
Command
Fort Huachuca, AZ, USA
ABSTRACT
Fort Huachuca, AZ, located 60 mi Southeast of
Tucson, has had 35 years of experience with various
renewable energy systems. This session discusses
lessons learned from the successes and failures in that
experience over the past 35 years, including: an indoor
pool solar water heating system installed in 1980; a
solar domestic hot water system installed in 1981; a
grid connected PhotoVoltaic (PV) system installed in
1982; transpired air solar collectors (Solarwalls™)
installed in 2001; daylighting installed in 2001; a 10-
KW wind turbine installed in 2002; a 1 MW wind
turbine installed in September 2011; PV powered
outdoor lighting installed in 1994; a prototype
Dish/Stirling solar thermal electric generator installed
in 1996; two 30-KW Building Integrated Photovoltaic
systems installed on new membrane roofs in January
2009; a 42.84 KW Photovoltaic system that was
moved from the Pentagon in June 2009 and was
operational in early November 2009 on a truck shed
roof at Fort Huachuca; and a utility owned 13.6 MW
(AC) Photovoltaic system installed from April to
December 2014.. Also discussed is an experimental
solar attic system that collects the hot air in an attic
and uses a heat exchanger and tank to produce solar
domestic hot water. This 1000 SF system was first
installed in 2003 and is now being fully monitored.
This paper discusses the design, installation, metering,
operations, and maintenance of these systems, and
also work in progress on the installation of
commercial, off-the-shelf 3-KW Dish/Stirling solar
thermal electric generators and solar thermal/natural
gas-to-electric systems at a central plant. Discussions
also include biogas (methane from a wastewater
digester) and biomass (a wood chip boiler) recently
installed at a central heating/cooling plant.
INTRODUCTION
Fort Huachuca, AZ is a U.S. Army installation
established in 1877, originally established as a camp
to conduct the Indian Wars in the Southwest and also
the base camp for the founder of Tombstone, AZ,
located 20 mi (32 km)) to the East of Fort Huachuca.
It became a stationing and training ground for the
“Buffalo Soldiers” of that era, and for training in
World Wars I and II. Since 1954, it has been the
location of the Army Electronic Proving Ground, and
more recently, the home of the Network Enterprise
Technology Command and the Army Intelligence
Center and School. It also houses the Department of
Defense Joint Operability Test Command. Located 60
mi Southeast of Tucson and 6 mi (9.6 km) from the
border with Mexico, Fort Huachuca is one of the few
places in the United States with a Mediterranean type
climate. Available renewable energy resources include
solar at 80 percent availability, wind with some areas
at class three, biomass from forestry thinnings for fire
control and grass land restoration, biogas from a
wastewater treatment plant, and there is even some
evidence of Geothermal energy in the East Range area
and in the mountains. The Fort is a part of the city of
Sierra Vista and has a topography that runs from an
elevation of 3400 ft (1036.3 m) only 1 mi (1.6 km)
west of the San Pedro River to an elevation of 8400 ft
(2560.3 m) in the Huachuca Mountains. The main
building area is at an elevation of 4700 to 5100 ft
(1432.6 m to 1554.5 m). Experience with renewable
energy systems started in the late 70s with two solar
systems that had different ends. The first was a
parabolic trough solar system at the South Central
Plant that was used for heating and cooling for a single
building. This system used a single stage absorption
chiller for cooling. The system was a failure and was
eventually removed. Another system was a solar
domestic hot water system with two panels and a solar
tank. It was on a fire station and was eventually
abandoned when the fire station was moved to another
building. The system was still capable of operation,
and in 1996 that system was moved to another
2. 2
building on Fort Huachuca and is still operational.
This paper will cover each system type from start to
the present and include ongoing and future plans for
various renewable energy systems.
SOLAR HEATING FOR AN INDOOR POOL
Indoor pool solar heating project parameters are:
• Year Installed: 1980
• Collector Area: 2000 sq ft (185.806 m2
) unglazed
with copper waterways
• Cost: $53,000
• Cost/sq ft: $26.50 ($285/m2
)
• First Year Energy Savings: 8348 therms
(880,760.9 Mjoule [834.8 million BTU]
measured
• First Year Savings: $2337 measured
• First Year Solar Fraction: 49 percent
• Simple Payback: 23 years
• Present Status: End of life with a repair project
underway in 2015
Background
In the late 70s the Army published a plan that called
for 1 percent of its facilities’ energy to come from
solar energy. Bruce Johnson was a mechanical
engineer in the design branch of the Facilities
Engineering Directorate (now called the Directorate of
Public Works, or DPW) at Fort Huachuca, AZ. After
the second round of oil price increases in the United
States in 1979, Bruce Johnson became interested in
installing solar systems at Fort Huachuca. He did a
design (Figure 2) and economic analysis that
convinced the Director to approve the installation of a
solar heating system for the Indoor Pool at Barnes
Field House on Fort Huachuca (Figure 3).
Design Features
The 3500 sq ft (325.161 m2
) pool heating energy was
measured as part of the design process. It was noted
that the pool heating energy closely tracked the
outdoor air temperature during the winter. This was an
interesting development since the pool enclosure was
heated to a constant temperature. It was finally
determined that leaky sliding doors were causing cold
air to layer across the pool surface which greatly
increased the pool heat loss during winter storms. The
doors were replaced to correct the air leakage.
Innovative aspects of the design include: failsafe
collector drain back to the pool when solar energy is
not being collected (to prevent freezing of the solar
collectors); unglazed collectors (mild winter daytime
temperatures are common at Fort Huachuca) with high
flow to minimize collector heat loss (3-4°F [-16.1-
15.6 °C] delta T across the collectors); and a
stagnation sensor (located remote from the collector
field) tuned to the characteristics of the solar collectors
to sense when solar and outdoor air conditions were
adequate to collect solar energy. The stagnation sensor
consists of an enclosed box with a small black plate at
the same angle as the collector field with field
installed insulation behind the plate/sensor to tune it to
the same characteristics as the unglazed collectors.
Stagnation sensors sense the “no flow” condition of
the collector field, hence their name. Advantages of a
stagnation sensor include stable operation of the field
and optimization of the energy gathered. If a sensor
were placed on the collector plate it would result in
short cycling of the valve that directs pool water to the
collector field when the cold pool water entered the
collectors and cooled them. The system is activated if
the stagnation sensor (Figure 1) reaches set point and
if the pool thermostat is calling for heating (no
differential controller is used).
Figure 1. Stagnation Sensor.
The system was installed in the summer of 1980. The
system was ground mounted in two rows, facing true
South with a 45 degree tilt. The latitude of Fort
Huachuca is 31.6 degrees N, so the panels are 13.4
degrees plus latitude. The unglazed 3 x 10-ft (0.9 –
10 m) (10 panels were screwed to plywood which was
connected to steel racks.
Figure 2. Original System Drawing of Solar Pool
Heating.
3. 3
Figure 3. Solar Pool at Barnes Field House (1980)
Field Verification of Energy Savings
Sophisticated monitoring of the solar contribution was
not included in the project. Energy consumption of the
pool was monitored with a natural gas meter
connected to the pool heater. The solar system was
deactivated for about a week per month and the results
extrapolated to determine solar contribution and
overall pool energy usage.
Discussion of the economics as originally
projected
The design assumed a pool blanket would be installed
to minimize pool heat loss during unoccupied periods.
The annual pool heat loss was estimated to be 8500
therms (896,797.6 Mjoule) with a pool blanket. The
solar system was designed to save 75 percent of this
value, or 6407 therms (Figure 4). The pool blanket
was not installed and the solar system actually saved
8348 therms (880,760.9 Mjoule) measured, or
30 percent better than forecast.
Figure 4. Original Data for Solar Contribution,
Maintenance
A runaway pickup truck caused minor damage to the
collector field when it rolled down the embankment in
front of the collector field. There was wind damage to
the collector array that damaged one third of one of
the two rows of collectors in the early 90s. Until the
damage was repaired that section was shut down and
only 5/6ths of the system was operational. Bill Stein
started as the Energy Coordinator of Fort Huachuca in
October 1992. He did a failure analysis of the panels
and plywood and found that the panels had pulled out
because the plywood used was for interior use and the
glue dried out and the plywood had delaminated, so
the screws holding the panels in the plywood had
pulled out. The solution was a project that he initiated
that replaced all the plywood with a marine grade
plywood, installed edge flashing, and replaced the
damaged unglazed solar panels. That project was
accomplished in the mid 90s.
The indoor pool solar heating system is at end of life
(1980-2015) with extensive repairs required. The
Directorate of Public Works (DPW) presently has a
project underway to renovate the solar heating system.
The unglazed solar collectors are being replaced with
single glazed panels of about the same area and layout.
Refurbishment of the control system and some piping
components is also planned. The stagnation sensor is
being integrated into the new control system. It is
anticipated that winter performance will improve as a
result of the glazed panels. The designer (Kelly,
Wright & Associates, P.C., Tucson, Arizona)
anticipates the upgraded solar system will provide
about 7,597 Therms with the solar system providing
38% of the annual pool heating energy. As of 13
August the design we finalized and construction
should start soon on the replacement system.
SOLAR DOMESTIC HOT WATER
Parameters for the solar domestic hot water project
are:
• Location: Barnes Field House
• Year Installed: 1981
• Collector Area: 900 sq ft (83.613 m2
) glazed
collectors
• Cost: $82,000
• Cost/sq ft: $91/sq ft ($978.50/m2
)
• First Year Energy Savings: 5641 therms
(595157.1 Mjoule [564.1 million BTU]) based
on design
• First Year Monetary Savings: $1570 based on
design
• Solar Fraction: 40 percent
• Simple Payback: 52 years
• Present Status: End of life with a repair project
underway in 2015
4. 4
Background
Following on the success of the solar pool system, the
next project pursued by Bruce Johnson was a solar
domestic hot water system at the same building,
Barnes Field House (Figures 5 and 6).
Design Features
The load was measured for the domestic hot water
system and it was adjusted to account for energy
saving flow restricting shower heads to be installed as
part of the project. A drain back type system was
selected with captive water in the solar loop. A solar
preheat tank with an in-tank heat exchanger was used.
The heat exchanger was sized liberally to avoid
running the collectors warmer than necessary;
domestic hot water is on the outside of the heat
exchanger with the captive solar water loop on the
inside. The heat exchanger material is copper to
encourage a high rate of thermal expansion. The
constant expansion and contraction of the heat
exchanger tubes results in scale cracking off and
falling to the bottom of the solar preheat tank where it
does not impede heat transfer. The solar collectors are
protected against freezing by several important
features. The captive water is held in the solar
collectors by the normal pump head. When the pump
(controlled by a differential controller) is deactivated,
the water drains back to a drain back tank inside the
mechanical room. The use of isolation valves is
minimized to avoid accidental isolation of the
collector field to minimize freeze potential. Note that,
during normal operation, the captive solar loop forms
a siphon after the air is vented from the collectors to
minimize pump head during normal operation.
Figure 5. Original System Drawing of Solar
Domestic Hot Water System.
Figure 6. Solar Domestic Hot Water System at
Barnes Field House (1981)
Also, should the heat exchanger leak, the drain back
tank has an overflow line to a floor sink that will shunt
any pressurized water entering the captive solar
system to drain (to protect the collectors especially
during a freezing condition). Air vents on the solar
field are piped back to the drain back tank via a sight
glass so leaking air vents are detected. The collector
field is cantilevered off of a wall to keep the collectors
off of the roof to minimize roof penetrations. A pump
without seals minimizes introduction of raw water into
the captive solar loop.
Field Verification of Energy Savings and
Maintenance History
In October 2001, Bill Stein worked with the Solar
Thermal Design Assistance Center of Sandia National
Laboratories to get a permanent British Thermal Unit
(BTU) meter put on the solar domestic hot water
system at Barnes Field House. In the first year after
the BTU meter was installed, the recorded solar output
was 117.44 MBTU (123905.8 Mjoule). The meter
recorded a steady flow of 19.6 gallons (74.2 L) per
minute (GPM) to the collectors when in operation.
Repairs were made to some leaks in the system, and a
reading of 337681.2 Mjoule (320.06 MBTU) was
taken on 28 August 2003, for an 11-month output of
213775.5 Mjoule (202.62 MBTU). Data was collected
manually, as there was no system in place to export
the data from the meter in that building. A meter
reading of 682800.6 Mjoule (647.17 MBTU) was
taken on 30 September 2005. That gives an output of
345119.4 Mjoule (327.11 MBTU) for the 2 year,
1-month period. This indicates reduced output that
was caused by a failed pump and the period of time to
get it ordered and replaced, plus a few small leaks. A
read of 741567.2 Mjoule (702.87 MBTU) was taken
on 6 April 06, giving a 6-month output of
58766.6 Mjoule (55.7 MBTU). Before Bill Stein left
as the Fort Huachuca Energy Coordinator in April
2008, he detected a problem with the system that
appeared to be a bad temperature sensor in the
collectors. Sam Montanez, the Energy Engineer,
reported that the system had been non operational
since about June 2008, even though he had put in a
5. 5
work order to get the system repaired at that time. It
was also observed in the mechanical room that houses
the solar tank that there were new absorber plates for
the glazed solar collectors. This information was
passed on to the current Director of Public Works,
John Ruble. Mr. Ruble gave a commitment to getting
this system repaired. When Bill Stein took a reading of
the BTU meter on 21 December 2009, it was reading
1081348 Mjoule (1024.92 MBTU). It can be assumed
that the 339780.8 Mjoule (322.05 MBTU) was
produced from April 2006 to April 2008. In the entire
time this system has been in operation, the pump was
replaced three times and the differential controller
once. It is now the end of life time for the panels and
the absorber plates need to be replaced. A project was
done in the early 00s to replace the air vents. It is also
time to repair the insulation on the solar tank and
piping to and from the collectors.
The Barnes Field House solar domestic hot water
system is at end of life (1981-2015) with extensive
repairs required. The Directorate of Public Works
(DPW) presently has a project underway to renovate
the solar domestic hot water system. Many
components are being replaced to include: glazed
solar panels (same area); controls; drain back and solar
preheat tanks; conventional domestic hot water tank;
solar pump; BTU meter; thermal insulation; and
miscellaneous piping components. The basic design
philosophy will remain unchanged. The designer
(Kelly, Wright & Associates, P.C., Tucson, Arizona)
anticipates the upgraded solar system will provide
about 2,832 Therms with the solar system providing
49% of the annual domestic hot water energy with
5000 gallons of hot water used per day average. The
project has been delayed due to the required removal
and remediation of asbestos insulation on the existing
piping and tanks.
In 1996, Bill Stein worked with Larry Lister from the
U. S. Army Construction Engineering Research
Laboratory (USACERL) to get a solar domestic hot
water system installed on a barracks to test the use of a
solar design specification that USACERL had
developed for the Department of Defense. A
design/build contract was done with AAA Solar from
Albuquerque, NM. Due to limitations of space in the
mechanical room, a unique system was developed,
designed and installed by AAA Solar. This system
was installed in April 1996 and consisted of a ground
mounted system with 12, 4 x 8-ft (1.2–2.4 m) glazed
panels for a 384 sq ft (35.675 m2
) system at a cost of
$35,000. That comes to an average of $91.15/sq ft
($980/m2
)) of panel. The system also consisted of nine
80-gal solar water storage tanks and nine quad rod
heat exchangers. The total storage was 720 gal, for a
ratio of 1.875 gal of storage per sq ft (20.2 gal/m2
)) of
collector area. This was higher than the typical 1.5 gal
of storage per sq ft (16.1 gal/m2
) of collector area due
to the high solar resource at Fort Huachuca. The
storage tanks and heat exchangers were installed
behind the panels in an insulated sheet metal siding
enclosure. The 80-gal (302.8 L) tanks were installed
horizontally. The system had a Data Industrial BTU
meter installed on original construction. This system
was read manually, and at the time the meter was
replaced on 11 Sept (year unknown) the system had
produced 1297104.9 Mjoule (1229.418 MBTU). The
water lines to the building mechanical room were
installed underground, and there was a problem
discovered with the original construction. The system
had three subsystems, one in the front row with four
panels and two in the back row with eight panels. It
was discovered by the Fort Huachuca maintenance
personnel that the front row was hooked up backwards
with reverse flow to the panels. The system has a
water and propylene glycol mix in the panels and all
the tanks and heat exchangers are in the back row.
This was not detected originally because of the
underground connection. (One lesson learned is to do
a thorough check of the piping before burying the
pipe.) That 12 panel system is show in Figure 7.
Figure 7. Solar Domestic Hot Water System at
Koch Barracks (1996)
SOLAR ATTIC (EXPERIMENTAL)
(Experimental) solar attic project parameters are:
• Year Installed: 2002
• Collector Area: 1000 sq ft (92.903 m2) unglazed
roof
• Cost: $82,000
• Energy Savings to Date: 136.245 million BTU
(143,746.108 million Joules)
Background
The solar attic was an experimental solar domestic hot
water project that was first conceived by Dr. Dave
Menicucci of Sandia National Laboratories and Bill
Stein in the late 90s when discussing the standard dark
roof color for the barracks at Fort Huachuca and many
other military installations. It was discovered that
there was an air space of about 4-in. (10.16 cm)
between the roof insulation and the structural B deck
holding the standing seam metal roof. The concept
was proposed that if the temperatures were high
6. 6
enough, air could be circulated under the hot metal
deck and run through a heat exchanger to make
domestic hot water. Data was taken in the late 90s
with some instrumentation from Sandia National
Laboratories to verify stagnation temperatures of
185 °F (85 °C) in the summer and 140 °F (60 °C) in
the winter. Eventually Army Headquarters (Army
Chief of Staff for Installation Management) was
convinced this concept would work, and in September
2001 funding in the amount of $82,000 was sent from
Army Headquarters to Fort Huachuca to design and
build this system.
Design Features
The system was designed by Bruce Johnson and
installed in late 2002. No definitive design guidance
was available for an unglazed air cooled solar
collector. As a result extensive measurements of the
roof temperature and entering and leaving air
temperature across the “collector” with varying air
flow rates were made. Analysis of the results led to the
conclusion that the optimum airflow for this scenario
was around 2 cu ft/minute (CFM, or 0.057 m3
/minute)
per square foot (0.093 m2
) of roof collector. Since the
“collector” parameters were unknown it was
impossible to model the performance of the system.
As more data are gathered it is hoped that perhaps
ways to model this type of system will be developed
and its viability for future installations determined.
The system has 1000 sq ft (92.903 m2) of “collector,”
an air-to-water heat exchanger and fan, and an 1100-
gal (4164 L) solar preheat tank. Ten gal/minute
(37.8L) was selected as the water flow rate for the
coil. The peak heat production was estimated as
79129.2 joule/hr (75,000 BTU/hr. Peak collector
efficiency was estimated at 25 to 30 percent based on
data obtained from the original monitoring. The
building domestic hot water load varied from
29541.6 Mjoule/month (28 MBTU/month to 54
million BTU/month based on varying occupancy. An
average of 10 gal/person (37.8L/person) was measured
as the actual domestic hot water use. A complete
weather station including solar insolation data
gathering was provided in the design to facilitate
modeling of this rather unusual solar application. The
roof used for the solar heat collection is shown in
Figure 8.
Figure 8: Roof used for the Solar Attic system
Energy Monitoring and Savings
The solar attic system was installed with a BTU meter
and was to be monitored for performance. Due to the
difficulty of connecting the data gathering system to
the Fort Huachuca information systems network, no
data was gathered real time. Bill Stein did a manual
read of the system on 21 December 2009, and since
the startup, the solar attic system produced 57.513
million BTU (60679.437 million Joules). Another
read on 27 July 2015 had a reading of 136.245 million
BTU (143,746.108 million Joules). The BTU meter
for this system is shown in Figure 9.
Figure 9: BTU meter for the Solar Attic System
Reads in BTU x 1,000 (1K)
A small, two-panel active solar domestic hot water
system was installed on a fire station in the old post
area in the late 70s. That system used a glycol/water
system and a heat exchanger. The system was not
being used by the early 90s because the fire station
was converted to a military police desk and
headquarters, so at the recommendation of a study
done by the Solar Thermal Design Assistance Center
of Sandia National Laboratories in February 1994, the
system was moved to the roof of the Joint
Interoperability Test Command in April 1996. The
system was metered, but there is no available record of
the output.
There were also passive solar hot water systems
installed in Family Housing units on Fort Huachuca.
In 1997 Russell Hewitt of the National Renewable
Energy Laboratory (NREL) funded a project to install
six passive solar domestic hot water units on housing
at Fort Huachuca and collect data for comparison. The
units installed were different manufacturers’ products
for insulated collection tanks (40 gal) and progressive
tube type systems. Freeze protection was inherent in
the mass of the water. While these systems worked
well, the data was never collected and analyzed.
Another passive solar hot water system was developed
in 2000 with funding from Sandia National
Laboratories and Salt River Project. This system was
called Roof Integrated Thermosiphon Heat (RITH).
7. 7
The system was a passive solar hot water system
designed with the collector on the roof surface and the
tank slung under the collector as one unit. The system
eventually gained Underwriters Laboratories (UL) and
Florida Solar Energy Center (FSEC) certification, but
was never put into production. The test system put on
a family housing unit at Fort Huachuca was installed
improperly and failed. The contractors did not
correctly install the integrated flashing on the panel
and the plumber put water in the system, then opened
the bypass valve and shut water flow off to the system.
The system then froze up in early winter.
In the past few years newer Solar Domestic Hot water
systems have been installed on newly constructed
buildings by both the Army and the Fort Huachuca
Accommodation Schools (not Army owned). The new
fire station on Fort Huachuca was built with a three
panel system and was operational on 17 May 2012.
When Bill Stein read the meter on 24 July 2015 it
showed the total production as 794.883 million BTU
(838,646.1 million Joules). That DHW system is
shown in Figure 10. The BTU meter for that system is
shown in Figure 11. There were also new buildings
built with solar domestic hot water systems at a new
complex near the Black Tower on the West Range.
These two buildings were maintenance and training
buildings. The systems were improperly designed and
had too many panels for the tank size. The
overheating ruined the glycol/water mix and panels
had to be removed from each system. The Fort
Huachuca Accommodation Schools built a new
Middle School and installed three solar domestic hot
water systems on the school.
Figure 10: Three panel Solar DHW system on the
new Fire Station (May 2012)
Figure 11: BTU meter on Solar DHW system at the
new Fire Station taken on 24 July 2015
TRANSPIRED AIR SOLAR SYSTEMS
Bill Stein encouraged the Energy Savings
Performance Contractor (ESPC) at Fort Huachuca to
put in renewable energy systems as part of each task
order along with standard energy conservation
measures. In 2001, as part of the third task order of the
ESPC contract, Southwest HEC (now AMERESCO)
installed two transpired air solar systems above the
South facing hangar doors of Hangars #1 and #3 on
Fort Huachuca. Each system (trade name Solarwall)
was 2300 sq ft (213.7 m2
) and used a 15000 CFM
(424.753 m3
/min) fan and sock duct to distribute the
solar heated air. One unique feature was that the
controller was also set to pull in outside cool air in the
summer to pre-cool the hangars. The system used an
Allerton Microview standalone microcomputer to
control the fan operation. NREL expressed a desire to
meter one of the systems, but never funded the project
to do so. There are currently operational problems
with the controller setpoints. The total cost for these
two Solarwalls was $191,381, for an average of
$41.60/sq ft ($447/m2
) of collector area. This system
was constructed by Weatherguard of Sierra Vista. The
estimated annual energy savings is
1797815.5 Mjoule (1704 MBTU) of natural gas for
both Solarwalls (combined) and the annual dollar
savings is $9006, for a simple payback period of 21.5
years. Current status is non-operational. A picture of
the two Solarwalls is shown in Figure 12.
Figure 12: Hangar #1 and Hangar #3 - 2300 SF
Transpired Air Solar Collectors (2001)
SOLAR AIR PANEL SYSTEMS
In Fiscal Year 2008 (FY08) the Army started a
program called the Installation Technology Transition
Program (ITTP). The goal of that program is to
demonstrate newer off-the-shelf technologies, prove
them at Army installations, and transfer them for use
in the entire Army through standard specifications.
One of the first projects done under ITTP installed a
solar air panel system at Fort Huachuca to preheat a
generator oil sump for the emergency generator at
Riley Barracks. This system was installed in July 2009
by American Solar and no data has been gathered yet
on this system. Preliminary estimates show that this
particular application may not be cost effective at Fort
Huachuca because of the mild climate there. There is
also a strong probability that it would be much more
cost effective to use these air panel type systems for
heating and solar domestic hot water production at
Fort Huachuca.
8. 8
DAYLIGHTING
Daylighting was first installed on family housing
projects at Fort Huachuca in 1997. The units used
were 10-in. diameter units produced by Solatube.
After remodeling or constructing over 1000 new
replacement housing units, there are about 3500 of
these daylighting units on Fort Huachuca. Each unit
cost about $300 to install.
In 1998 the first commercial daylighting units were
installed on Hangar #1 at Fort Huachuca as part of
ESPC task order #1. Thirty, 5 x 6-ft (1.5 x 1.8 m) units
were installed at a cost of about $50,000. A
daylighting controller was installed and data was taken
before installation and for the first 2 years of operation
to verify how long the lights stayed off. After 2 years
the average was 7.6 hours per day the lights were kept
off in the hangar due to the daylighting system. In
2001, as part of task order #3 of the ESPC contract,
450 daylighting units were installed in 22 buildings.
That project cost $671,071 and saved $86,685 in
annual electric costs (at an average rate of
$0.07/KWh). That project was constructed by Natural
Lighting Company, now called Daylight America.
Figure 13 shows one of the daylighting installations.
Figure 13: Daylighting on Hangar #1 (1998)
PARABOLIC TROUGH SOLAR HEATING
AND COOLING
As mentioned in the Introduction, this system was an
early attempt (late 70s) at using solar energy for
heating and cooling for a single classroom building. It
was located at the South Central Plant and was
designed by a reputable engineering firm in Tucson.
The system cost about $1.1M and was supposed to
save $2397 in electricity and $645 in natural gas the
first year. The simple payback for this system was
more than 360 years, however, it was considered a
demonstration project so economic payback was
secondary to its experimental findings. It should be
noted that the design firm forgot to take into account
the coefficient of performance of the absorption chiller
when calculating the energy savings. Calculations for
energy savings in those days were manual and
extensive so it is not surprising that errors crept into
the analysis. The primary reason for failure of the
system were problems with an overly complex design
(18 operating modes) and material failures of the
absorber (differential expansion and contraction
caused warping of the absorber tubes and breakage of
the glass tube over the absorber). Bruce Johnson
briefed the Vice Chief of Staff of the Army when he
visited the central plant solar system and its
shortcomings were presented and simpler solar
systems were emphasized.
GRID CONNECTED PHOTOVOLTAIC
SYSTEMS
The first grid connected Photovoltaic System installed
on Fort Huachuca was funded by the Federal
Photovoltaic Utilization Program (FPUP) and was
operational in September 1982. This system was also
the first grid connected system in the Army. The
system was designed by a professor from Arizona
State University and was installed under contract to
USACERL by Monegan, Ltd, of Gaithersburg,
Maryland. The system consisted of 196 Solarex
Corporation Model 5300EG photovoltaic (PV) panels
at a fixed tilt of 30 degrees from horizontal for a total
system peak of 6.2 KW. The array was installed on the
roof of the Holman Guest House with the grid tied
inverter in an enclosure on the west side of the
building. A meter was installed to measure the output
of the system. The inverter was a Windworks Gemini
three phase inverter. The system worked well for
2 years, and it was during this time that Roch Ducey
began working for USACERL. One of his first jobs in
1983 was to monitor the system and take data on
performance. After the first 2 years the system began
to trip off line. The repair of the system was not
prioritized, and during this time, the facilities
maintenance was contracted out with no specific
instructions for the contractor to maintain this system.
The system had been non-operational for 9 years when
the Photovoltaic Design Assistance Center (PVDAC)
from Sandia National Laboratories was funded to do a
study of the system and present options. Jerry Ginn
from the PVDAC identified a defective bridge circuit
in the inverter, that the array was in good condition,
and that a contactor in the ground fault circuitry was
not capable of interrupting the array’s short circuit
current. Options given were to repair the inverter,
replace the inverter with a new single phase inverter or
decommission the system and use the panels in
standalone systems elsewhere on Fort Huachuca.
Current voltage (I-V) curves were taken for the 14
strings of panels, and there was evidence of a few bad
panels. One panel was removed and taken to Sandia
National Laboratories Photovoltaic Evaluation
Laboratory for testing. The panel was tested at
standard test conditions (25 °C) and Typical Operating
Conditions (50 deg C) and was found to produce
24.9W at 50 °C. The original manufactures rating was
31.5W at 25 °C which equates to 29W at 50 °C. All
ratings are at one sun, or 1000W/m2
.
In December 1994, it was decided to repair the system
and a work order was put in by Bill Stein for repair of
failed components. Replacement parts for the inverter
were available from Omnion, so after isolating the bad
panels into an unused string and repairing the inverter
and the contactor, the system was again operational on
5 July 1995. By 19 July 1995 the PV meter was
9. 9
reading 757 KWh. On 21 December 2009 the meter
was reading 57,049 KWh. The meter went bad and
was replaced on 27 October, 2010. Since that time the
production to 30 June 2015 was 29,709 kWh. In 2001
funding was received to replace the inverter with an
off-the-shelf 10 KW 3 phase inverter from Omnion. In
September 2010, the PV meter was connected to the
automated meter reading system. Craig Hansen, the
former Energy Technician at Fort Huachuca, had been
working toward automating all of the metering there
since he started in November 1995. He has since
retired, but the meters are now automatically read.
Figure 14 shows the first grid connected PV system in
the Army (now 33 years old) and one that is still in
operation after all that time.
Figure 14: 5 KW 3 Phase Grid Connected
Photovoltaic system on Holman Guest House
(September 1982) First in the Army and still in
operation
The next grid connected PV system on Fort Huachuca
was funded by the Environmental Protection Agency
(EPA) Strategic Environmental Research and
Development Program (SERDP) and the local utility.
The original system cost was a total of $200K, with
the EPA funding $140K and Tucson Electric Power
(TEP) Company funding $60K. The system as
designed was an 18 KW single phase system. The
system was installed and operational in late January
1996. The installed system consisted of three arrays of
30 each 285W ASE Americas model GP-50-DG
panels and three Omnion Power Engineering Series
2400 6 KW inverters. The site chosen was the Thrift
Shop roof at the main gate of Fort Huachuca with the
inverters installed on the N wall exterior and the meter
on the East wall next to the building service. The
panels were mounted directly to a shingled roof, with
an orientation of 20 degrees East of South and a tilt of
16 degrees. The system was designed and installation
supervised by Miles Russell of Ascension
Technology. Bill Stein and Craig Hansen from Fort
Huachuca coordinated the support agreement with
Andy Myer of TEP. Since there is typically more than
one sun of insolation at Fort Huachuca and there was
almost 9 KW of panels for each 6 KW inverter, the
average time between failures for an inverter was
4 months. In the first year the system output was about
33,000 KWh. Bill Stein reached an agreement with
Andy Myer of TEP that if Fort Huachuca would get 10
more panels, TEP would buy and install two more
6 KW inverters and restring the array with 20 panels
per inverter. Bill Stein was able to get 10 more
identical panels for just shipping ($300) from Jack
Nixon at Yuma Proving Ground, AZ due to a stalled
project. He also got another 29 from that same stalled
project in the same shipment that was used for two
other projects.
In July 1997, TEP installed the new balanced system,
which now had 100 panels and five inverters for a 30
KW rating. Due to the fact that the system was at a
full summer tilt (latitude minus 15) and was only 4 in.
above a shingle roof (where it got very hot), the
system only averaged 50,000 KWh per year. The
panels were not installed according to the
manufacturer’s recommendation on wooden sleepers,
and over time, numerous leaks developed in the roof.
In October 2008, the system was removed from the
Thrift Shop. At that time, two of the five inverters had
failed and it was discovered that the PV panel
electrical connectors were defective. Funding was
secured from the Army ITTP program to replace the
defective connectors and relocate the system. At the
time of this writing, the contract had been awarded to
replace the defective electrical connectors on the PV
panels. All the panels were tested in 2009 and only the
good ones will get new connectors. Figure 15 shows
20 of the 100 panels on the Thrift Shop 30 KW PV
system. This system was removed and the roof was
repaired. The panels currently (as of August 2015) sit
in storage.
Figure 15: 20 panels of 100 on the Thrift Shop 30
KW Photovoltaic System (1996)
The next two grid connected systems were the result
of having the 29 panels from the prior project and
funding from Roch Ducey to install more PV systems
and repair existing solar thermal systems. Bill Stein
did the design of the new PV systems and chose west
facing systems for reasons of economics. While a
system using this orientation will produce less KWh,
the energy that is produced in the late afternoon is
worth much more than the average due to peak
demand charges. The two systems were installed by
Chuck Marken from AAA Solar in December 1998.
The larger system used 16 panels of the same model as
the Thrift Shop (4.8 KW nominal) and was run to a 5
KW Omnion inverter. The system was installed on the
West side of Barnes Field House with the panels
elevated on racks 10 ft (3 m) above the ground and at
a 45 degree tilt. This maximizes the output at 4 p.m.
on the 21st
of Jun, typically the hottest time of the year
at Fort Huachuca (thus the highest peak load). That
system was operational on the afternoon of 15
December 1998. By 9 February 2008 the system had
produced 50,661 KWh. The inverter had a small
10. 10
problem that was fixed in a few days in 2005 and one
of the panels had the glass break from compression.
There was no space between panels on the racks, and
the differential expansion of the steel racks and the
aluminum framed panels caused the failure. That
broken panel was replaced. The meter was replaced in
December 2009. Since that time to 30 June 2015 that
system has produced 34,740 kWh.
Figure 16: Grid–Connected Photovoltaic System
(4.8 KW System at Barnes Field House). 1998
The other small system was half the size at eight
panels (2.4 KW nominal) and was also run to a 5 KW
Omnion inverter. The system was installed on the
West side of the main supply warehouse on racks 10 ft
(3 m) above the loading dock. The panels faced
20 degrees South of West and were also at a 45 degree
tilt. This maximizes the output in mid afternoon. The
system was operational on the morning of 16
December 1998. By 21 December 2009, the system
had produced 30,856 KWh. The only maintenance
problem noted was that the meter base was pulling out
of the wall. That system was repaired with new
panels, a new inverter and a new meter in 2015. The
new system has produced 245 kWh (as of 27 July
2015) since it was installed. Figure 17 shows the
original system installed in 1998. Figure 18 shows the
new system installed in 2015.
Figure 17: Original 2.4 KW West facing
Photovoltaic system at the CIF warehouse (1998)
Figure 18: New 2.4 KW Photovoltaic system (2015)
at the CIF warehouse
The next two systems were conceived by Roch Ducey
of USACERL and funded by the Army ITTP program.
These were two Building Integrated Photovoltaic
(BIPV) systems. These systems were funded by the
first year of the ITTP program in FY08 and included
new membrane roofs and thermal welded flexible PV
systems. These two identical 30 KW systems were
designed and installed by Solar Integrated. The two
buildings chosen were the furniture warehouse and the
Military Intelligence Library. The total cost of the two
systems was $650K and the preliminary calculations
showed that the systems would produce from
91,830 KWh/year (BP website) to a high of 168,580
KWh/year. The high value appeared to be a
calculation error resulting from using the wrong angle
for the panels, and not accounting for dirt
accumulation. The initial calculated payback period
was about 25 years, with annual savings being $4.7K
for energy, $11.4K for demand, and $10K for roof
operation and maintenance savings. The systems were
installed and operational in mid January 2009. On 21
December 2009, Bill Stein took a reading from each
system, and the inverters (PV Powered Model PVP 30
KW) gave the following readings. The furniture
warehouse had a reading of 37,138 KWh and the
Military Intelligence (MI) Library had a reading of
39,951 KWh. It was also noted that a separate meter
installed on the furniture warehouse showed only 21,
078 KWh. A check with the automated metering
technician verified that the meter was installed on 21
May 2009. Also note that the inverter was tripped out
on a ground fault on the Military Intelligence Library.
The inverters were still under the 1-year warranty, so
it is anticipated that they will be fixed. The total for
the two systems for a 49 week period of 77,089 KWh
as compared with the projected 91,830 KWh is
reasonable, considering the time periods the one
system was down with ground faults on the inverter.
The meter on the MI library was installed in March
2012. By 30 June 2015 it was reading 61,434 kWh.
The monthly meter reads also showed there were
multiple times the system was offline for two to four
months. The meter on the furnishings warehouse read
176, 874 kWh on 30 June 2015. The monthly
readings showed this system was only offline for a
total of about three months. Figure 19 shows a picture
of the furnishings warehouse system.
11. 11
Figure 19: 30 KW Building Integrated Photovoltaic
(BIPV) system on the furnishings warehouse (2009)
The next grid connected PV system is one that was
originally at the Pentagon. The land space was needed,
and two systems had to be relocated from the
Pentagon. One was a 70 KW system and the other was
a 26 KW system. After the Air Force decided not to
take the systems, the Army was afforded the
opportunity. Fort Huachuca volunteered to take the
systems and using some of the ITTP funding and
funding from the Pentagon, retrieved both systems in
June 2009. The smaller system was first moved to Fort
Huachuca, then to Fort Sill, OK in October 2009 for
use in a micro-grid. The larger system was used for a
42.84 KW DC system installed on a truck shed roof.
That system was installed by Systems Integration of
Benson and Net Zero Solar of Tucson. The system
was operational on 3 November 2009. It used a new
SATCON PVS 50 KW inverter. That inverter has the
capability of exporting data directly to the internet.
Dale Benth of Fort Huachuca showed Bill Stein the
web site that monitored the system on 21 December
2009. The website showed a reading of 6884.3 KWh
at 1:20 p.m. Bill Stein went to the actual site and, at
1:46 p.m., the inverter showed 6895 KWh. There is
also a meter on this system, and it showed 7050 KWh
and a peak output of 35.45 KW. On 30 June 2015 the
meter showed the system had produced 265,055 kWh.
The panels are facing due south and are currently at a
15 degree tilt on adjustable racks. The original plan
was to change the tilt angle on a seasonal or annual
basis to verify the optimal configuration. Due to
safety concerns and the cost of changing the rack
angles, the system is in the original configuration. The
reinstallation of the system cost $30K for the new
inverter and $70K for the balance of the system
(panels, racks, conduit, and wiring). There was no
follow on funding from the ITTP program to publish
the energy output and lessons learned from this system
to the Army. This section of the paper is the only
venue. Figure 20 shows this 42.84 KW truck shed
mounted system. Figure 21 shows the 50 KW
SATCON inverter. SATCON went bankrupt in
October 2012.
Figure 20: 42.84 KW truck shed Photovoltaic
system moved from a ground mounted system at
the Pentagon (2009)
Figure 21: 50 KW SATCON inverter for 42.84 KW
(DC) truck shed Photovoltaic system
Starting in March 2013 there were 97 remote training
area buildings that were outfitted with small grid
connected Photovoltaic systems that included a battery
back-up which would island as a secure microgrid
when the electric grid failed. By 30 June 2015 each
system had produced an average of 2800 kWh, with
the larger systems producing over 6000 kWh. Figure
22 shows the batteries for these systems. Figure 23
shows one of the inverters.
12. 12
Figure 22: Batteries for small training building grid
connected Photovoltaic systems (2013)
Figure 23: Inverter for small training building grid
connected Photovoltaic systems
The Fort Huachuca Accommodation Schools (not
Army owned) installed various Photovoltaic systems
under different programs starting in 2009. Under a
program run by Sulphur Springs Valley Electric
Cooperative (SSVEC) there were three identical 24.1
KW (DC) RV shed Photovoltaic systems installed at
the three schools in August 2009. Each system had an
elevated structure with 104 each 60 cell SOLON
Photovoltaic panels. Each system had a 30 KW
SATCON inverter. The total cost of each system was
$240,607.00. Project was funded by Clean Renewable
Energy Bonds (CREBS). It was paid for by the REST
program funded by the REST surcharge on everyone
SSVEC member's bills. There was a 15 year warranty
paid for on the SATCON inverters with is now
worthless due to the bankruptcy of SATCON in
October 2012. No SSVEC operating funds were
involved. The output of each system feeds to the
schools at no charge for the energy (kWh). One of
these three systems is shown in Figure 24.
Figure 24: 24 KW RV Shed Photovoltaic system
located at the former Colonel Smith Middle School,
now Cochise College (2009)
By 30 June 2015 one of the systems had produced
209,644 kWh of energy at the Johnston elementary
school.
Much larger Photovoltaic systems were installed on
carport structures at the new Colonel Smith Middle
School (CSMS) plus a roof mounted system. There
were also three roof mounted systems installed at the
Colonel Johnston Elementary School. One of the
larger carport mounted Photovoltaic systems at CSMS
has produced 939, 180 kWh of electricity from
November 2013 to 30 June 2015. The two larger
systems are at a 9 degree tilt with one facing 15 degree
South of East and one facing 15 degrees West of
South. A picture of two of those carport type systems
is shown in Figure 25. Figure 26 shows the meter for
one of those systems.
Figure 25: Two of the larger carport type
Photovoltaic systems at Colonel Smith Middle
School (2012)
Figure 26: Meter for one of the larger Photovoltaic
systems at Colonel Smith Middle School
13. 13
And last but not least is a first of its’ kind utility
owned large scale Photovoltaic system on an Army
installation. A project that was facilitated by the then
Army Energy Initiatives Task Force (EITF), now the
Army Office of Energy Initiatives (OEI) and a GSA
area wide utility contract resulted in a nominal 20
Mega-Watt (MW) ground mounted Photovoltaic
System. The system is owned by Tucson Electric
Power (TEP) Company. The construction contractor
was EON. It was built in phases, with Phase one
consisting of 17.26 MW of DC and 13.6 MW of AC
inverters. The total site is 90 acres. The first phase
was started on 14 April 2014. Construction on Phase I
was completed on 17 December 2014. As of 30 June
2015 the system had produced 15,450.55 MWh.
There were 57,600 each 305 watt BYD panels and 16
each SMA 850 KW inverters. Phase II construction is
due to start in September 2015. It will consist of 5
MW of DC BYD (46,729 each 107W First Solar
modules) and 3.4 MW of AC (4 each SMA 850 KW
Inverters). Phase II is scheduled for completion by 1
April 2016. When Bill Stein asked at a meeting in
early 2014 with Fort Huachuca and TEP the cost of
the system, he was told that the Phase I system was
$40 million with an additional $6 million for the two
mile connection and substation upgrades. Figure 27
shows the Phase I system looking West. Figure 28
shows the Phase I system looking East.
Figure 27: Phase I of the 20 MW PV system on Fort
Huachuca owned by Tucson Electric Power (TEP)
looking West (2014)
Figure 28: Phase I of the 20 MW PV system looking
East
NON-GRID CONNECTED
PHOTOVOLTAIC SYSTEMS
The first non-grid connected PV systems were range
weather-monitoring stations used in the late 70s to
present by the Meteorological team of the U.S. Army
Electronic Proving Ground. The next document use
was for marquee signs used for information and
advertisements in October 1992. There were a total of
six signs, one at the main gate and one at the East gate
of Fort Huachuca. One of these signs was upgraded
and moved in 2003, and the others were removed or
grid connected. The next independent PV system was
an entrance to a parking lot at the Non-Commissioned
Officers Academy. It was a Scientific Engineering
system with a panel, square box pole, battery box,
controller, and of course a light at the top of the pole.
It was installed in July 1994. The next project used the
same manufacturer and eight units were installed by
Electrical Power and Control of Phoenix at a parking
lot at Alchesay barracks. These units were installed in
July 1995. The project cost was $32K, but this was
lower cost than excavating and existing paved parking
lot and installing grid connected parking lot lights.
These units were replaced with four single unit and
four double units from Solar Outdoor Lighting (SOL)
in August 2009. There were two more units from that
manufacturer installed in a secure are called Trojan
Switch in March 1996. The next round of grid
independent PV systems was installed in 2004 at the
Electronic Proving Ground main building parking lot,
and were from SOL. A substantial grid independent
PV system was installed in 2005 at the Golf Course
entrance. This system had four lights (two on each
side of the road) that were connected underground and
the panels and battery enclosure on the South side of
the road. This system was installed by 1MD of Sierra
Vista. Another non grid connected PV system was
installed in the main Directorate of Public Works
building in 2007. There were three PV powered attic
fans. There is no battery storage with this system, but
there is a thermostat to prevent the fans from running
in attic temperatures below 70 °F (21.1 °C) (to help
trap winter heat gain).
DISH/STIRLING SOLAR THERMAL
ELECTRIC GENERATOR
In 1995 Fort Huachuca was chosen as the one
Department of Defense (DoD) site to receive a
SERDP funded 7.5 KW Dish/Stirling Solar Thermal
Electric Generator. Dave Menicucci, Rich Diver, Tim
Moss, and Chuck Andraka from Sandia National
Laboratories (SNL) ran this program for the DOD.
The original project cost was $900K. In January 1996,
the system was operational and the Southwest
Technical Development Institute (SWTDI) of New
Mexico State University (Las Cruces) collected a
year’s worth of data. The unit was built and installed
by Cummins Power Group (CPG). The unit was
located in the compound of the Joint Interoperability
Test Command (JITC) with the enthusiastic support of
14. 14
their operations officer, Bill DePew. As part of the
project, an operator from JITC (Andrea Beaudet) was
trained to operate and maintain the system. The
original system had a free piston Stirling engine
coupled to a linear generator with a sodium heat
receiver. When CPG sold the technology to the
Turkish government, U.S. Support for the system was
lost. There was still funding left from the original
amount, so SNL bought a new 10 KW two cylinder
kinematic Stirling engine with a direct illumination
receiver from SB&P in Germany. The unit at Fort
Huachuca was adapted to receive this engine and the
unit was back in operation by June 1999. Andre
Beaudet went to Germany for factory training on the
engine. The data and development of the system in the
early 00s was instrumental in the development of
Dish/Stirling technology both at SNL and tangentially
by a U.S. firm, Stirling Energy Systems. There was no
funding in the DOD SERDP program for ongoing
maintenance, so from June 2003 until October 2009
the unit was not operational. JITC finally decided it
needed the land, so it paid Systems Integration $1 to
remove the unit in November 2009. The Dish/Stirling
is shown in Figure 29 after the new mirrors and engine
and direct illumination receiver.
Figure 29: 10 KW Dish/Stirling when it was located
on the JITC compound (1996)
WIND TURBINE
Wind power development started with data gathering
in 1996. Roch Ducey funded a study to identify wind
resources for three specific areas on Fort Huachuca.
Due to limited funding, only one, 40-m tower was
used and two existing towers were used for the data
gathering. The three sites were not good wind sites
and one lesson learned was that the mesoscale model
was very inaccurate in sky island topography. Later
wind data was taken with a 40-m tower at a South
Range, then moved to a West Range site funded by
Tom Hansen of TEP. The data showed that both sites
had a low class three wind, with the West Range being
slightly better than the South Range site. Data showed
a wind pattern that only varied 9 percent month to
month (even year to year). In September 2001 Army
Headquarters funded $72K to Fort Huachuca for the
installation of a 10 KW Bergey Windpower
Corporation (BWC) horizontal axis wind turbine. The
turbine was installed by 1 MD with a subcontract to
BWC. It was installed on a 120 ft (36.4 m) tower. It
was operational on 12 February 2002. The site finally
chosen turned out to be a poor wind site. The unit was
installed at an elevation of 5000 ft (1524 m) so the
power is derated by 20 percent due to air density. The
highest power recorded at the electric meter was 8.882
KW. From the time the unit was installed until 21
December 2009 it produced 31,925 KWh. On 19
February 2003, the meter read 5256 KWh. On 8
February 2005, the reading was 12,323 KWh,
averaging 3534 KWh in years two and three. In
October 2003, the fiberglass spinner (nosecone)
cracked and was replaced with an aluminum one. In
June 2006, the Xantrex inverter failed and was
returned for repair under the 5-year warranty period.
On 11 January 2007, the meter read 18075 KWh. On
29 January 2008, the reading was 23695 KWh, for a
production of 5620 KWh in year six. On 21 December
2009, the meter read 31,925 KWh for a production of
8230 KWh for a 1 year, 11-month period. The meter
was replaced on the wind turbine in January 2012 with
no read on the old meter. On 30 September 2014 it had
produced 6195 KWh. After that date the reading
stayed the same due to an inverter failure.
Figure 30: 10 KW Bergey wind turbine on the West
Range (2002)
Bill Stein pushed for a newer type wind system for
inclusion in the fourth task order of the ESPC contract
in January 2008. That task order with AMERESCO
included a multiple vertical axis wind machine from
Massmegawatts. The unit was designed at 90 KW and
had canvas augmenters. The unit was constructed on
the West Range, but there were safety issues with the
actual construction, and the unit was removed in
November 2009. While that unit never was functional,
other vertical axis wind machines are commercially
available.
In FY07, the Army funded an 850 KW commercial
scale wind turbine under the Energy Conservation
Investment Program, run by Ron Diehl of the Office
of the Army Chief of Staff for Installation
15. 15
Management (OACSIM). That project was originally
estimated at $1.15M, which would no longer purchase
that size turbine. In FY08, the Army increased the
funding to $3.1M and increased the turbine size to 1
megawatt (MW). A contract was awarded by the U. S.
Army Corps of Engineers to install a 1 MW Nordic
Windpower turbine on a 70 meter (231 ft) tower.
Final contract cost was $3.3 M and the West range
location was changed due to a conflict with a new
Unmanned Aerial System. The new location on the
South Range was not an optimum location for the
turbine. The turbine was installed and first operated in
September 2011. Operation was intermittent due to
issues with the remote monitoring of the system by
Nordic and parts failures. Nordic went bankrupt in
October 2012. The final month of operation for the 1
MW wind turbine was February 2013. The last meter
read was 4663 with an 80 multiplier for a total
production of 373,040 KWh. The wind turbine was
used in a $1.05 million funded Army electronics and
wind interaction study. Bill Stein called ETHOS
Services, the company doing the operations and
maintenance of all the other Nordic wind turbines in
the USA, to get an estimate to fix the turbine. The
cost was a low of $20K to $160K worst cast. Due to
the bankruptcy of Nordic, the Supervisory Control and
Data Acquisition (SCADA) system lost permission to
operate over the Army network. Finish history and
production and put in picture.
Figure 31: 1 MW Nordic wind turbine on the South
Range (2011)
The accommodation schools also put in three small
wind turbines with the construction of the new
Colonel Smith Middle School (CSMS) in 2012. These
three turbines are mounted on 30 foot American
Resource & Energy (ARE) monopole towers. Two
are Skystream 3.7s that had meter reads of 3507 KWh
and 3136 KWh and an Urban Green Energy (UGE)
Eddy that read 96 KWh on 3 August 2015. These
systems were installed by Westwind Solar, whom also
installed some of the original Photovoltaic systems.
These systems are in the front (South) side of the
school and are more for demonstration than for
optimal production. The three wind turbines are show
in Figure 32.
Figure 32: Three wind turbines at the Colonel
Smith Middle School (2012)
BIOMASS
In 2008, the Resource Efficiency Manager of Fort
Huachuca, Wilson Prichett, started exploring biomass
options as an alternative to the open burning of tree
thinnings for fire control. In preparation, a 5-acre site
was set up to start stockpiling the fuel. A project was
funded in FY09 from funds received from the
American Recovery and Reinvestment Act (ARRA),
commonly known as the “stimulus bill,” to install a
wood chip boiler at the West Central Heating and
Cooling Plant. One lesson learned from this process
was that the boiler needed to be sized from the lesser
of the required load and the available fuel. The system
that will be installed will be a 50 Boiler Horsepower
(BHP) ACT Bioenergy Model CP#1700 with fuel
auger 1793.6 Mjoule (1.7 MBTU) wood chip boiler.
Installation is due to was completed in February 2010.
The system was tested and ran well, but there was an
issue with the fuel chip size being too large coming
from the wood chipper. The system also had issues
with the storage hopper as it was not well designed to
keep the rain off the fuel. Figure 33 is a picture of the
biomass boiler at the South Central Plant.
Figure 33: Biomass boiler at the South Central
Plant 2010
16. 16
BIOGAS
In the early 90s an attempt was made to capture
methane from the wastewater digester and use in a
boiler. This attempt failed due to the lack of a
dewatering system on the gas and a dip in the line.
Currently the digester lacks a dewatering system and
is in need of repair to be able to generate and store
large amounts of methane.
ORGANIC RANKIN CYCLE SOLAR
THERMAL ELECTRIC
In late FY09 the Army decided to fund an ITTP
project at Fort Huachuca to use an organic Rankin
cycle generator designed to run off hot water to
generate electricity. The unit was to run using a dual-
fuel natural gas boiler and solar input. The project was
to be done at Fort Huachuca due to the excellent
available solar resource and available space in one of
the central plants. Craig Hansen worked as project
manager and the project budget was $745K. A
contract was awarded to 1MD of Sierra Vista for
$700K to install an ElectraTherm Green Machine of
50 KW rating. The unit was installed at the South
Central Plant in February 2010 and will use the space
from the removed absorption chiller that was part of
the failed solar heating and cooling system mentioned
earlier. The system will use both an existing natural
gas boiler and install new evacuated tubes solar
thermal systems on the roof of the building for solar
thermal input. The evacuated tube technology was
chosen over the parabolic trough because of a lack of
available land around the central plant and the desire
to have no moving parts on the roof. Some of the
existing piping and the original solar tank was to be
used in this project. There were two issues that
prevented operation of this system. The first was
leaks in the piping or tank of the existing solar thermal
storage system. The second was a hardware and
safety issue in that the switch gear on the South
Central Plant was not set up to safely flow power in
both directions (to/from the plant). Bill Stein and
Craig Hansen went back to the ITTP board for funds
to correct these issues but were told no. The system
only ran for four hours of commissioning but has not
run since. Figure 34 is the Organic Rankin Cycle
Solar Thermal and Gas boiler input electric generator.
Figure 35 is the data plate from the ElectraTherm.
Figure 36 is a picture of the Evacuated Tube solar on
the roof of the South Central Plant.
LONG TERM FUTURE
Fort Huachuca is looking at expanding the use of
renewable energy through expanded use of the
aforementioned technologies. Alternative financing
methods are being considered and the Fort typically
will volunteer to be a test site for new technology.
The current focus is on a waste to energy plant and
additional Photovoltaic parking shade structures.
Figure 34: Organic Rankin Cycle (ORC) Solar
Thermal and Natural Gas boiler electric generator
(2010)
Figure 35: The data plate from the ElectraTherm 50
KW ORC electric generator
Figure 36: Evacuated Tube solar system used to
provide heat to the 50 KW Green Machine
17. 17
CONCLUSION
Renewable energy systems that are low maintenance
have the highest probability of still operating after 20
years. Any organization must conduct due diligence
before installing a renewable energy system. A good
easy to operate and maintain system is critical to
success. Full organization support, including funding
for maintenance and any data acquisition, is required
for a successful renewable energy project. Funding is
critical for both a good design and a successful
installation. Training may be necessary and must be
accomplished for the more complex renewable energy
systems. If there are no on-site personnel qualified to
maintain the more complex systems, you must get a
warranty and long term maintenance contract.
Automated data gathering is extremely difficult in the
Army. Fort Huachuca is currently working on getting
connectivity to the Army Meter Data Management
System (MDMS) and permission to operate the
existing Utility Monitoring and Control Systems
(UMCS). With the high number of Army owned
renewable systems that are broken without repair
funds, the best course of action may be to privatize
these systems then buy the energy back using the
dollars costs avoided on the conventional utility bills.
RECOMMENDATIONS
When pursuing a renewable energy project, secure
both organizational cooperation and funding sources
to increase the chances of success. Find local success
projects and imitate them. Adapt proven design to
your local climate and situation. As a general rule
focus on renewable energy systems that are simple and
the most cost effective. For the Army, use third party
financed contracts for renewable energy systems and
privatize the existing systems.
REFERENCES
http://photovoltaics.sandia.gov/TecassforSolAmer
Solarci- ties/Docs/new%20docs/A%20Technical%20
and%20Economic%20Analysis%20of%20So
lar%20Energy%20Projects%20At%20Fort%
20Huachuca%20AZ.pdf
http://www.azsolarcenter.org/solar-in-
arizona/virtual-tours-galleries/solar-and-wind-
systems-in-sv-az.html
http://www.imcom.army.mil/hq/kd/cache/files/0D0
8EABE1E124899A387328347F05977.pdf pp. 24-
25
http://www.p2pays.org/ref/19/18995.pdf, pg. 14
http://prod.sandia.gov/techlib/access-
control.cgi/2000/001124.pdf slides 36-37
http://www.nrel.gov/data/pix/searchpix.php?getre
c=05183&display_type=verbose
http://www.imcom.army.mil/hq/kd/cache/files/AD
BAF0A0-423D-452D- 48F5438F7876F5C0.pdf
14