Signalling Installation and Testing Review
For more information on our services and capabilities
contact us on 0207 1010800 or enquiries@nuaspect.co.uk
or visit our website www.nuaspect.co.uk
© NuAspect Limited 2015
OurProjects
Client: London Underground (LU)
Scope: As a result of organisational
changes LU commissioned a review
of current signalling installation and
testing activities to identify key issues
and risks, together with
recommendations on short and long
term improvement actions.
When: Completed April 2011
Approach: NuAspect were
commissioned to undertake a “top
down” review, focused on
Management Controls, Critical
External Influences and Attitudes and
Approaches. NuAspect formed a
small team of signalling technical,
domain and quality assurance
experts to undertake the review. The
research methodology used was a
situational assessment of the current
operation (baseline), in comparison
with expectations governed by LU
standards, operating principles and
management systems, as well as
good practice for the activities
being undertaken. The comparison
provided the identification of gaps /
deficiencies and associated risks,
from which options for improvements
were developed.
Result: A summary report was
produced detailing the review
activities, including a series of Interim
Control Measures that were
developed to address the identified
immediate risks, together with longer
term improvement actions to
support a sustained improvement in
signalling installation and testing
activities. The client accepted the
report and adopted the Interim
Control Measures for
implementation, which NuAspect
were also asked to support.
Research methodology

More Related Content

What's hot

Service Transition Lead
Service Transition LeadService Transition Lead
Service Transition LeadRadu Ionita
 
4 steps to improved productivity
4 steps to improved productivity4 steps to improved productivity
4 steps to improved productivitySandvik Coromant
 
Acceptance Testing
Acceptance TestingAcceptance Testing
Acceptance Testingrosman
 
Software testing acceptance testing
Software testing  acceptance testingSoftware testing  acceptance testing
Software testing acceptance testingGaneshKumarKanthiah
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersTechWell
 
Financial controls management protiviti governance portal
Financial controls management protiviti governance portalFinancial controls management protiviti governance portal
Financial controls management protiviti governance portalSARVJEET KAUSHAL
 
Nerc Standardization & Automation
Nerc Standardization & AutomationNerc Standardization & Automation
Nerc Standardization & Automationjamesholler
 
Internal quality audit operational procedure
Internal quality audit operational procedureInternal quality audit operational procedure
Internal quality audit operational procedureTuan Anh Nguyen
 
A Utility company in UK leverages Cigniti UAT expertise to reduce defects
A Utility company in UK leverages Cigniti UAT expertise to reduce defectsA Utility company in UK leverages Cigniti UAT expertise to reduce defects
A Utility company in UK leverages Cigniti UAT expertise to reduce defectsethandoyle
 
ECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesAndrew Whittaker
 
Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.huangg
 
Supplier Quality Engineer
Supplier Quality EngineerSupplier Quality Engineer
Supplier Quality EngineerRonald Ehrhardt
 
Process Safety Kpi
Process Safety KpiProcess Safety Kpi
Process Safety KpiArthurGroot
 
Sox Lite Presentation
Sox Lite PresentationSox Lite Presentation
Sox Lite Presentationmpotorti
 

What's hot (20)

Service Transition Lead
Service Transition LeadService Transition Lead
Service Transition Lead
 
4 steps to improved productivity
4 steps to improved productivity4 steps to improved productivity
4 steps to improved productivity
 
Acceptance Testing
Acceptance TestingAcceptance Testing
Acceptance Testing
 
Software testing acceptance testing
Software testing  acceptance testingSoftware testing  acceptance testing
Software testing acceptance testing
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
PCAPP Update 28 May 2014
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test Managers
 
Financial controls management protiviti governance portal
Financial controls management protiviti governance portalFinancial controls management protiviti governance portal
Financial controls management protiviti governance portal
 
[Mush Honda] Metrics & Reports from Test Teams (QA)
[Mush Honda] Metrics & Reports from Test Teams (QA)[Mush Honda] Metrics & Reports from Test Teams (QA)
[Mush Honda] Metrics & Reports from Test Teams (QA)
 
Nerc Standardization & Automation
Nerc Standardization & AutomationNerc Standardization & Automation
Nerc Standardization & Automation
 
Test Metrics and KPIs
Test Metrics and KPIsTest Metrics and KPIs
Test Metrics and KPIs
 
Internal quality audit operational procedure
Internal quality audit operational procedureInternal quality audit operational procedure
Internal quality audit operational procedure
 
Prdz_resume_march16
Prdz_resume_march16Prdz_resume_march16
Prdz_resume_march16
 
K+S Repair Process
K+S Repair ProcessK+S Repair Process
K+S Repair Process
 
A Utility company in UK leverages Cigniti UAT expertise to reduce defects
A Utility company in UK leverages Cigniti UAT expertise to reduce defectsA Utility company in UK leverages Cigniti UAT expertise to reduce defects
A Utility company in UK leverages Cigniti UAT expertise to reduce defects
 
CV- ESLAM
CV- ESLAMCV- ESLAM
CV- ESLAM
 
ECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier Responsibilities
 
Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.
 
Supplier Quality Engineer
Supplier Quality EngineerSupplier Quality Engineer
Supplier Quality Engineer
 
Process Safety Kpi
Process Safety KpiProcess Safety Kpi
Process Safety Kpi
 
Sox Lite Presentation
Sox Lite PresentationSox Lite Presentation
Sox Lite Presentation
 

Viewers also liked

A2 risk assessment_form
A2 risk assessment_formA2 risk assessment_form
A2 risk assessment_formrachaelrowe98
 
Signalling and risk assessment of emerging zoonoses in The Netherlands
Signalling and risk assessment of emerging zoonoses in The NetherlandsSignalling and risk assessment of emerging zoonoses in The Netherlands
Signalling and risk assessment of emerging zoonoses in The NetherlandsGlobal Risk Forum GRFDavos
 
Introduction to Functional Safety and SIL Certification
Introduction to Functional Safety and SIL CertificationIntroduction to Functional Safety and SIL Certification
Introduction to Functional Safety and SIL CertificationISA Boston Section
 
Introduction to Railway Signalling
Introduction to Railway SignallingIntroduction to Railway Signalling
Introduction to Railway SignallingSandeep Patalay
 
indian railway signal system ppt
indian railway signal system pptindian railway signal system ppt
indian railway signal system pptVimal Tripathi
 
Automatic Train Control System using Wireless Sensor Networks
Automatic Train Control System using Wireless Sensor NetworksAutomatic Train Control System using Wireless Sensor Networks
Automatic Train Control System using Wireless Sensor NetworksPrakhar Bansal
 

Viewers also liked (9)

A2 risk assessment_form
A2 risk assessment_formA2 risk assessment_form
A2 risk assessment_form
 
RPPS E5122 - Sistem Komunikasi
RPPS E5122  - Sistem KomunikasiRPPS E5122  - Sistem Komunikasi
RPPS E5122 - Sistem Komunikasi
 
Signalling and risk assessment of emerging zoonoses in The Netherlands
Signalling and risk assessment of emerging zoonoses in The NetherlandsSignalling and risk assessment of emerging zoonoses in The Netherlands
Signalling and risk assessment of emerging zoonoses in The Netherlands
 
Safety Integrity Levels
Safety Integrity LevelsSafety Integrity Levels
Safety Integrity Levels
 
Introduction to Functional Safety and SIL Certification
Introduction to Functional Safety and SIL CertificationIntroduction to Functional Safety and SIL Certification
Introduction to Functional Safety and SIL Certification
 
Introduction to Railway Signalling
Introduction to Railway SignallingIntroduction to Railway Signalling
Introduction to Railway Signalling
 
indian railway signal system ppt
indian railway signal system pptindian railway signal system ppt
indian railway signal system ppt
 
Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
 
Automatic Train Control System using Wireless Sensor Networks
Automatic Train Control System using Wireless Sensor NetworksAutomatic Train Control System using Wireless Sensor Networks
Automatic Train Control System using Wireless Sensor Networks
 

Similar to 2920 - Signalling Installation and Testing Review

Integrated Continuous Improvements Ecosystem
Integrated Continuous Improvements EcosystemIntegrated Continuous Improvements Ecosystem
Integrated Continuous Improvements EcosystemQuEST Forum
 
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...Semakula Allan Kinene
 
7_Necip-Polat-Turkey.pdf
7_Necip-Polat-Turkey.pdf7_Necip-Polat-Turkey.pdf
7_Necip-Polat-Turkey.pdfHarariMki1
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...Nesma
 
The 7 steps lean implementation
The 7 steps lean implementationThe 7 steps lean implementation
The 7 steps lean implementationTeh Chin Weng
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Corporate Presentation MRS
Corporate Presentation MRSCorporate Presentation MRS
Corporate Presentation MRSPaul Morffew
 
Creative Performance Audit
Creative Performance AuditCreative Performance Audit
Creative Performance AuditHumanology
 
Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Filo Tubo
 
Wealth Technology Strategy
Wealth Technology StrategyWealth Technology Strategy
Wealth Technology StrategyAlison Rooney
 
Scope of lean process in AOI (Automatic optical inspection ).pdf
Scope of lean process in AOI (Automatic optical inspection ).pdfScope of lean process in AOI (Automatic optical inspection ).pdf
Scope of lean process in AOI (Automatic optical inspection ).pdfJABIL circuit india pvt ltd pune
 
Leonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith
 

Similar to 2920 - Signalling Installation and Testing Review (20)

Integrated Continuous Improvements Ecosystem
Integrated Continuous Improvements EcosystemIntegrated Continuous Improvements Ecosystem
Integrated Continuous Improvements Ecosystem
 
PM
PMPM
PM
 
Project experience_ACN
Project experience_ACNProject experience_ACN
Project experience_ACN
 
CV_KannanK
CV_KannanKCV_KannanK
CV_KannanK
 
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
 
7_Necip-Polat-Turkey.pdf
7_Necip-Polat-Turkey.pdf7_Necip-Polat-Turkey.pdf
7_Necip-Polat-Turkey.pdf
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
 
Driving Performance
Driving PerformanceDriving Performance
Driving Performance
 
Project Monitoring and Evaluation (M and E Plan) Notes
Project Monitoring and Evaluation (M and E Plan) NotesProject Monitoring and Evaluation (M and E Plan) Notes
Project Monitoring and Evaluation (M and E Plan) Notes
 
Basics of ISO14001
Basics of ISO14001Basics of ISO14001
Basics of ISO14001
 
Rwp performance review john metzger
Rwp performance review john metzgerRwp performance review john metzger
Rwp performance review john metzger
 
Nigel Penny 3, Forming of audit opinions, SIGMA, Ankara, 26 October 2013
Nigel Penny 3, Forming of audit opinions, SIGMA, Ankara, 26 October 2013Nigel Penny 3, Forming of audit opinions, SIGMA, Ankara, 26 October 2013
Nigel Penny 3, Forming of audit opinions, SIGMA, Ankara, 26 October 2013
 
The 7 steps lean implementation
The 7 steps lean implementationThe 7 steps lean implementation
The 7 steps lean implementation
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Corporate Presentation MRS
Corporate Presentation MRSCorporate Presentation MRS
Corporate Presentation MRS
 
Creative Performance Audit
Creative Performance AuditCreative Performance Audit
Creative Performance Audit
 
Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...
 
Wealth Technology Strategy
Wealth Technology StrategyWealth Technology Strategy
Wealth Technology Strategy
 
Scope of lean process in AOI (Automatic optical inspection ).pdf
Scope of lean process in AOI (Automatic optical inspection ).pdfScope of lean process in AOI (Automatic optical inspection ).pdf
Scope of lean process in AOI (Automatic optical inspection ).pdf
 
Leonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE only
 

2920 - Signalling Installation and Testing Review

  • 1. Signalling Installation and Testing Review For more information on our services and capabilities contact us on 0207 1010800 or enquiries@nuaspect.co.uk or visit our website www.nuaspect.co.uk © NuAspect Limited 2015 OurProjects Client: London Underground (LU) Scope: As a result of organisational changes LU commissioned a review of current signalling installation and testing activities to identify key issues and risks, together with recommendations on short and long term improvement actions. When: Completed April 2011 Approach: NuAspect were commissioned to undertake a “top down” review, focused on Management Controls, Critical External Influences and Attitudes and Approaches. NuAspect formed a small team of signalling technical, domain and quality assurance experts to undertake the review. The research methodology used was a situational assessment of the current operation (baseline), in comparison with expectations governed by LU standards, operating principles and management systems, as well as good practice for the activities being undertaken. The comparison provided the identification of gaps / deficiencies and associated risks, from which options for improvements were developed. Result: A summary report was produced detailing the review activities, including a series of Interim Control Measures that were developed to address the identified immediate risks, together with longer term improvement actions to support a sustained improvement in signalling installation and testing activities. The client accepted the report and adopted the Interim Control Measures for implementation, which NuAspect were also asked to support. Research methodology