SlideShare a Scribd company logo
1 of 40
Download to read offline
Demolition Considerations/Method
Statements.
Considerations.
Sequence and
operations
Durations
Demolition methods
Choice of plant
Quantities Involved
Risks
Based on drawings and information/legislation
Site visit
Look for significant elements/stages of demolition
Break them down into manageable activities
Detail dependent on stage of preparation and
information available.
Relate to construction
form/constraints.
Materials handling
Hoisting and access
equipment
Scaffolding
Temporary works.
Resource availability
Sub contractors
Specialist Contractors
Plant/labour
Supervision
Think
Think
Think
CDM 2015 has a specific Regulation on the H&S issues for
demolition or dismantling of a structure.
• Regulation 20 Demolition or dismantling
• (1) The demolition or dismantling of a structure must be planned and
carried out in such a manner as to prevent danger or, where it is not
practicable to prevent it, to reduce danger to as low a level as is
reasonably practicable.
• (2) The arrangements for carrying out such demolition or dismantling
must be recorded in writing before the demolition or dismantling work
begins.
• Demolition works can create major site hazards and can be the cause of
death and severe injury amongst site workers and others e.g. members of
the public passing by or those working in adjacent premises.
• The person planning the demolition or dismantling project must consider
all aspects of the task so as to prevent or reduce danger to all persons who
may be affected by the works.
CDM 2015 Practical requirements for
managing demolition
• First, ensure that whoever is designing and implementing the demolition
or dismantling works is competent to do so.
• All but the most simple of demolition works will benefit from the
assessment of a structural engineer and/or surveyor.
• Consider what needs to be demolished, when, why and how. Consider the
environmental factors — weather conditions, wind speeds, etc. What
information has been collected regarding the structure to be demolished
— i.e. information from the Health and Safety File for the building, the
way the original building was constructed and the recommended
sequence for demolition.
• Consider the use of the building and if any persons will still be in the
vicinity when demolition takes place.
Legal Considerations.
• The BSI Code of Practice for Demolition BS 6187 exerts further
influence.
• If the demolition contractor does not observe the
recommendation of the Code, this may influence a court’s
decision in any legal proceedings. The Code itself does not,
however, have any statutory powers.
Listed buildings
• Demolition of listed buildings requires listed building consent,
and consent is normally required for all buildings in a
conservation area. Listed building consent may be given
subject to conditions, and these can be quite onerous.
• In practice, any proposal to alter a listed building may involve
at least a partial demolition, but the matter needs to be
judged on a sensible basis, since not every piece of work of
alteration and extension necessarily amounts to demolition (R
v North Hertfordshire District Council (1981) JPL 752).
Building Act 1984
• The local authority must be given 6 weeks written notice of an
intention to carry out a demolition.
• The local authority has powers to serve a notice regarding
demolition orders. In England (outside London) and Wales, notice
of any proposed demolition must be given to the local authority,
the occupiers of neighbouring buildings, and gas and electricity
companies.
• Exceptions are buildings smaller than 50 m3 in volume,
greenhouses, sheds etc, where the building is an agricultural
building.
• In the UK the local authority has six weeks in which to serve notice,
specifying detailed requirements about shoring, adjacent buildings,
weatherproofing, disposal of rubbish, removal of sewers and
disconnection of services, together with general safety and related
matters. A person served with a notice under the Act requiring him
to do work has a right of appeal to the magistrate’s court.
Demolition notice
• This notification must specify the building to
which it relates and the area of demolition.
• Notification can be provided by letter, fax or
email, however, for convenience some LA’s
will have a designed a form that you can
complete.
Demolition requirements
(1)
• These requirements could include:
• To shore up any building adjacent to the building to which this
notice relates.
• To weatherproof any surfaces of an adjacent building which
are exposed by the demolition.
• To repair and make good any damage to an adjacent building
caused by the demolition or by the negligent act or of any
person engaged in it.
• To remove material or rubbish resulting from the clearance
and demolition of the site.
• (*)To disconnect and seal, at such points as the Council may
reasonably require, any sewer or drain in or under the
building.
Demolition requirements
(2)
• To remove any such sewer or drain and seal any sewer or
drain with which the sewer or drain to be removed is
connected.
• To make good to the satisfaction of the Council the surface of
the ground disturbed by anything done under paragraph(*).
• To make arrangements with relevant statutory undertakers for
the disconnection of the supply of gas, electricity and water to
the building.
• To make such arrangements with regard to the burning of
structures or materials on site as may be reasonably required:
– if the building forms part of special premises, by the Health
& Safety Executive and the Fire Authority; and
– in any other case, by the Fire Authority.
Environmental Consents.
Environmental Consents
Structured approaches
Methods Of Demolition.
• More care and consideration is now given to the development of
demolition strategies as part of the process of construction and
redevelopment than was typical in previous times. This is a result of:
• Current emphasis on reducing construction periods to ensure economic
redevelopments;
• Increasing town centre regeneration, calling for careful demolition on
constrained and restricted sites;
• The importance of conservation, public awareness, and increasing
pressure to reuse materials.
• The aim of this part of the lecture is to:
• Set the demolition of structures in perspective as part of the construction
process;
• Consider the factors that may determine the demolition method selected:
• Outline the range of techniques available to the modem demolition
contractor.
Developing a demolition strategy
• Obviously each case considered for demolition
requires an appropriate strategy, depending on the
circumstances. The strategy must take into account:
• Method of construction used for the original building;
• Proximity to other buildings, structures and the
general public;
• Location;
• Cost and availability of tipping and disposal:
• Desirability and economics of reuse.
Building Information
• Information on buildings, in terms of ‘as built’ drawings and
structural details, is often unavailable or unreliable.
Investigative site and desk work may therefore be necessary.
• To plan the most efficient method of demolition, it is
important to have a full understanding of both the original
method of construction and the stress patterns imposed upon
it.
• Failure to do so may risk the safety of both demolition site
operatives and those in close proximity to the site.
• In extreme cases a lack of knowledge of the structure could
result in uncontrolled collapse. Buildings containing pre or
post-tensioned components require particularly careful
analysis and calculation to avoid such risks.
Recycling of materials and conservation
• Recycling
• An important development associated with demolition techniques is the
recycling of materials for reuse. There has always been an element of
salvage in demolition. but until recently this was confined to the reuse of
timber, tiles, bricks etc. Modern equipment makes it possible to recycle a
number of materials.
• Concrete can be crushed to provide valuable aggregates, hardcore or fill.
• The recycling of bituminous-based materials such as tarmacadam and
asphalt has also proved to be very successful and economical
• The recycling of brickwork by crushing and using the resultant material for
calcium silicate bricks is now considered economically viable.
• In the near future, buildings may be viewed as ‘reservoirs’ of materials
that will become available at some later date (see DTI demolition protocol
for further information).
Selecting the appropriate techniques
• Major factors to be considered include:
• Safety of personnel and public.
• Working methods.
• Legislation applicable.
• Insurance cover.
Preliminary aspects before site demolition work
• If demolition work is not planned at an early stage, site operatives
invariably have to devise their own means of access and methods of
working without full information as to the risks and dangers involved.
Before work starts on site, therefore, the following preparations should be
made:
• Conduct a site and building survey, with a structural bias.
• Examine drawings and details of existing construction where available.
• Prepare details and drawings from site survey activities where information
is not available.
• Find out the previous use of premises, especially with regard to flammable
substances or substances hazardous to health or safety, such as chemicals.
• Programme the sequence of demolition work.
• Deal with services.
• Prepare a Method Statement.
Method Statements.
• Essential element of the contractor’s
planning process is the construction
method statement. These underpin the
programme.
• Three distinct formats
– The tender method statement.
– The construction or work method statement.
– The safety method statement.
Method Statement Formats.
Construction method statements
• A construction method statement precedes
preparation of the project programme and contains
the detail necessary for construction of each element
of a building.
• They are prepared in order to explain the
contractor’s proposed working methods and
demonstrate how the durations and sequence of
work shown on the master programme will be
achieved.
• At the pre-contract stage in the project, method
statements will be prepared in detail in order to be
sure that durations are accurate and reliable.
Method statement presentation
• Can be written statements or in tabular form and functions as a brief for
site staff and operatives in sequencing activities and are used to indicate
resource requirements and to determine the duration of each element.
• It complements construction programming by providing detailed analysis
of each activity.
• The main uses for work method statements are:
• To calculate activity durations for the programme.
• To decide on gang compositions and thus the resourcing requirements for
individual activities.
• To plan activities in detail so that a logical construction sequence is
adopted.
• To provide an easily understood document, which can be communicated
to those who will carry out the work on site.
Preparation
• Preparing method statements requires discipline and
logic in that the steps needed to complete an activity
have to be thought out.
• Hand in hand with this is consideration of what plant
and labour will be used, as this is fundamental to
achieving a sensible working method and sequence.
• Temporary works and working space requirements
will also have to be considered, as will
subcontractors’ attendance requirements for
packages such as piling and structural steel erection.
Duration Calculation
• In order to calculate the duration of an activity, the output of
the gang has to be considered.
• Outputs used by estimators are not suitable for planning as
these relate to measured bill items where both main
quantities and smaller items are included.
• E.g. brickwork, for instance, the bills of quantities will include
an item for facing brickwork, say, and there will also be items
for laying the damp-proof course, for closing cavities and for
building in lintels.
• All these items would make calculations too complex for
planning purposes and thus ‘incidental’ items should be
reflected in an overall output for the facing brickwork quantity
alone.
Example
• The activity duration in days would then be
given by:
Quantity of brickwork in m2
Output of gang/hr x 8 hrs/day
• Where output is expressed in m² per hour.
Example 2
• Alternatively, the quantity of bricks in thousands can
be calculated and divided by the output of the gang
in bricks laid per day. This is fairly straightforward but
the difficult bit is to judge what the output should be.
This will depend on factors such as:
• The gang make up
• The type of work
• Location of the work
• The standard expected in the specification
Useful additions/Access/Egress
Site Set Up/Hoardings
TPO’s
Example 3
• The handout illustrates the plan and section of
a reinforced concrete basement to be
constructed as part of a multi storey office
development project on an open site.
• Prepare an operational method statement
from the information provided.
Example 3
2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf

More Related Content

Similar to 2017Method statements and demolition techniques..pdf

Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAnimesh1714013
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Michael Shellshear
 
LAW AND LEGISLATION RELATED TO HOUSING
LAW AND LEGISLATION RELATED TO HOUSINGLAW AND LEGISLATION RELATED TO HOUSING
LAW AND LEGISLATION RELATED TO HOUSINGDeeksha yadhuvanshi
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aRai University
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aRai University
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aRai University
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptxJacquesTwubahimana1
 
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...the Environment Centre (tEC)
 
1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdfahsansaeed78
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering PresentationTehmas Saeed
 
CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptxFARSANA26
 
Daup mupd-upl-2015-lecture 2
Daup mupd-upl-2015-lecture 2Daup mupd-upl-2015-lecture 2
Daup mupd-upl-2015-lecture 2Galala University
 
Innovation in construction industry
Innovation in construction industryInnovation in construction industry
Innovation in construction industryYamini K
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копияLAZOVOY
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorLAZOVOY
 

Similar to 2017Method statements and demolition techniques..pdf (20)

Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
building construction
building constructionbuilding construction
building construction
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9
 
LAW AND LEGISLATION RELATED TO HOUSING
LAW AND LEGISLATION RELATED TO HOUSINGLAW AND LEGISLATION RELATED TO HOUSING
LAW AND LEGISLATION RELATED TO HOUSING
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptx
 
Damian Trevor- Building Materials and Methods of Construction
Damian Trevor- Building Materials and Methods of ConstructionDamian Trevor- Building Materials and Methods of Construction
Damian Trevor- Building Materials and Methods of Construction
 
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
 
1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering Presentation
 
CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptx
 
Daup mupd-upl-2015-lecture 2
Daup mupd-upl-2015-lecture 2Daup mupd-upl-2015-lecture 2
Daup mupd-upl-2015-lecture 2
 
Innovation in construction industry
Innovation in construction industryInnovation in construction industry
Innovation in construction industry
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копия
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sector
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

2017Method statements and demolition techniques..pdf

  • 2. Considerations. Sequence and operations Durations Demolition methods Choice of plant Quantities Involved Risks Based on drawings and information/legislation Site visit Look for significant elements/stages of demolition Break them down into manageable activities Detail dependent on stage of preparation and information available. Relate to construction form/constraints. Materials handling Hoisting and access equipment Scaffolding Temporary works. Resource availability Sub contractors Specialist Contractors Plant/labour Supervision Think Think Think
  • 3.
  • 4. CDM 2015 has a specific Regulation on the H&S issues for demolition or dismantling of a structure. • Regulation 20 Demolition or dismantling • (1) The demolition or dismantling of a structure must be planned and carried out in such a manner as to prevent danger or, where it is not practicable to prevent it, to reduce danger to as low a level as is reasonably practicable. • (2) The arrangements for carrying out such demolition or dismantling must be recorded in writing before the demolition or dismantling work begins. • Demolition works can create major site hazards and can be the cause of death and severe injury amongst site workers and others e.g. members of the public passing by or those working in adjacent premises. • The person planning the demolition or dismantling project must consider all aspects of the task so as to prevent or reduce danger to all persons who may be affected by the works.
  • 5. CDM 2015 Practical requirements for managing demolition • First, ensure that whoever is designing and implementing the demolition or dismantling works is competent to do so. • All but the most simple of demolition works will benefit from the assessment of a structural engineer and/or surveyor. • Consider what needs to be demolished, when, why and how. Consider the environmental factors — weather conditions, wind speeds, etc. What information has been collected regarding the structure to be demolished — i.e. information from the Health and Safety File for the building, the way the original building was constructed and the recommended sequence for demolition. • Consider the use of the building and if any persons will still be in the vicinity when demolition takes place.
  • 6. Legal Considerations. • The BSI Code of Practice for Demolition BS 6187 exerts further influence. • If the demolition contractor does not observe the recommendation of the Code, this may influence a court’s decision in any legal proceedings. The Code itself does not, however, have any statutory powers.
  • 7. Listed buildings • Demolition of listed buildings requires listed building consent, and consent is normally required for all buildings in a conservation area. Listed building consent may be given subject to conditions, and these can be quite onerous. • In practice, any proposal to alter a listed building may involve at least a partial demolition, but the matter needs to be judged on a sensible basis, since not every piece of work of alteration and extension necessarily amounts to demolition (R v North Hertfordshire District Council (1981) JPL 752).
  • 8. Building Act 1984 • The local authority must be given 6 weeks written notice of an intention to carry out a demolition. • The local authority has powers to serve a notice regarding demolition orders. In England (outside London) and Wales, notice of any proposed demolition must be given to the local authority, the occupiers of neighbouring buildings, and gas and electricity companies. • Exceptions are buildings smaller than 50 m3 in volume, greenhouses, sheds etc, where the building is an agricultural building. • In the UK the local authority has six weeks in which to serve notice, specifying detailed requirements about shoring, adjacent buildings, weatherproofing, disposal of rubbish, removal of sewers and disconnection of services, together with general safety and related matters. A person served with a notice under the Act requiring him to do work has a right of appeal to the magistrate’s court.
  • 9. Demolition notice • This notification must specify the building to which it relates and the area of demolition. • Notification can be provided by letter, fax or email, however, for convenience some LA’s will have a designed a form that you can complete.
  • 10. Demolition requirements (1) • These requirements could include: • To shore up any building adjacent to the building to which this notice relates. • To weatherproof any surfaces of an adjacent building which are exposed by the demolition. • To repair and make good any damage to an adjacent building caused by the demolition or by the negligent act or of any person engaged in it. • To remove material or rubbish resulting from the clearance and demolition of the site. • (*)To disconnect and seal, at such points as the Council may reasonably require, any sewer or drain in or under the building.
  • 11. Demolition requirements (2) • To remove any such sewer or drain and seal any sewer or drain with which the sewer or drain to be removed is connected. • To make good to the satisfaction of the Council the surface of the ground disturbed by anything done under paragraph(*). • To make arrangements with relevant statutory undertakers for the disconnection of the supply of gas, electricity and water to the building. • To make such arrangements with regard to the burning of structures or materials on site as may be reasonably required: – if the building forms part of special premises, by the Health & Safety Executive and the Fire Authority; and – in any other case, by the Fire Authority.
  • 15.
  • 16.
  • 17.
  • 18. Methods Of Demolition. • More care and consideration is now given to the development of demolition strategies as part of the process of construction and redevelopment than was typical in previous times. This is a result of: • Current emphasis on reducing construction periods to ensure economic redevelopments; • Increasing town centre regeneration, calling for careful demolition on constrained and restricted sites; • The importance of conservation, public awareness, and increasing pressure to reuse materials. • The aim of this part of the lecture is to: • Set the demolition of structures in perspective as part of the construction process; • Consider the factors that may determine the demolition method selected: • Outline the range of techniques available to the modem demolition contractor.
  • 19. Developing a demolition strategy • Obviously each case considered for demolition requires an appropriate strategy, depending on the circumstances. The strategy must take into account: • Method of construction used for the original building; • Proximity to other buildings, structures and the general public; • Location; • Cost and availability of tipping and disposal: • Desirability and economics of reuse.
  • 20. Building Information • Information on buildings, in terms of ‘as built’ drawings and structural details, is often unavailable or unreliable. Investigative site and desk work may therefore be necessary. • To plan the most efficient method of demolition, it is important to have a full understanding of both the original method of construction and the stress patterns imposed upon it. • Failure to do so may risk the safety of both demolition site operatives and those in close proximity to the site. • In extreme cases a lack of knowledge of the structure could result in uncontrolled collapse. Buildings containing pre or post-tensioned components require particularly careful analysis and calculation to avoid such risks.
  • 21. Recycling of materials and conservation • Recycling • An important development associated with demolition techniques is the recycling of materials for reuse. There has always been an element of salvage in demolition. but until recently this was confined to the reuse of timber, tiles, bricks etc. Modern equipment makes it possible to recycle a number of materials. • Concrete can be crushed to provide valuable aggregates, hardcore or fill. • The recycling of bituminous-based materials such as tarmacadam and asphalt has also proved to be very successful and economical • The recycling of brickwork by crushing and using the resultant material for calcium silicate bricks is now considered economically viable. • In the near future, buildings may be viewed as ‘reservoirs’ of materials that will become available at some later date (see DTI demolition protocol for further information).
  • 22. Selecting the appropriate techniques • Major factors to be considered include: • Safety of personnel and public. • Working methods. • Legislation applicable. • Insurance cover.
  • 23. Preliminary aspects before site demolition work • If demolition work is not planned at an early stage, site operatives invariably have to devise their own means of access and methods of working without full information as to the risks and dangers involved. Before work starts on site, therefore, the following preparations should be made: • Conduct a site and building survey, with a structural bias. • Examine drawings and details of existing construction where available. • Prepare details and drawings from site survey activities where information is not available. • Find out the previous use of premises, especially with regard to flammable substances or substances hazardous to health or safety, such as chemicals. • Programme the sequence of demolition work. • Deal with services. • Prepare a Method Statement.
  • 24. Method Statements. • Essential element of the contractor’s planning process is the construction method statement. These underpin the programme. • Three distinct formats – The tender method statement. – The construction or work method statement. – The safety method statement.
  • 26. Construction method statements • A construction method statement precedes preparation of the project programme and contains the detail necessary for construction of each element of a building. • They are prepared in order to explain the contractor’s proposed working methods and demonstrate how the durations and sequence of work shown on the master programme will be achieved. • At the pre-contract stage in the project, method statements will be prepared in detail in order to be sure that durations are accurate and reliable.
  • 27. Method statement presentation • Can be written statements or in tabular form and functions as a brief for site staff and operatives in sequencing activities and are used to indicate resource requirements and to determine the duration of each element. • It complements construction programming by providing detailed analysis of each activity. • The main uses for work method statements are: • To calculate activity durations for the programme. • To decide on gang compositions and thus the resourcing requirements for individual activities. • To plan activities in detail so that a logical construction sequence is adopted. • To provide an easily understood document, which can be communicated to those who will carry out the work on site.
  • 28. Preparation • Preparing method statements requires discipline and logic in that the steps needed to complete an activity have to be thought out. • Hand in hand with this is consideration of what plant and labour will be used, as this is fundamental to achieving a sensible working method and sequence. • Temporary works and working space requirements will also have to be considered, as will subcontractors’ attendance requirements for packages such as piling and structural steel erection.
  • 29. Duration Calculation • In order to calculate the duration of an activity, the output of the gang has to be considered. • Outputs used by estimators are not suitable for planning as these relate to measured bill items where both main quantities and smaller items are included. • E.g. brickwork, for instance, the bills of quantities will include an item for facing brickwork, say, and there will also be items for laying the damp-proof course, for closing cavities and for building in lintels. • All these items would make calculations too complex for planning purposes and thus ‘incidental’ items should be reflected in an overall output for the facing brickwork quantity alone.
  • 30. Example • The activity duration in days would then be given by: Quantity of brickwork in m2 Output of gang/hr x 8 hrs/day • Where output is expressed in m² per hour.
  • 31. Example 2 • Alternatively, the quantity of bricks in thousands can be calculated and divided by the output of the gang in bricks laid per day. This is fairly straightforward but the difficult bit is to judge what the output should be. This will depend on factors such as: • The gang make up • The type of work • Location of the work • The standard expected in the specification
  • 35. Example 3 • The handout illustrates the plan and section of a reinforced concrete basement to be constructed as part of a multi storey office development project on an open site. • Prepare an operational method statement from the information provided.