TOPS Offshore
                       Production Systems
                            (TOPS)
                             4th April 2011




Thursday, 28 July 11
Contact
                       • Inventor: Pat Haynes
                       • Organisations: A.P.Haynes Consulting/
                         Eboroil Ltd
                       • Norwegian Org nr 986455744
                       • Address: Jon Smørsv 4A, 1397 Nesøya
                       • Tel: +47 66847068 Mob Tel: +47 45275598
                       • Skype name : eboroil
                       • E-mail eboroil@me.com
Thursday, 28 July 11
The TOPS Concept
                       • The average water depth in the world is
                         3795m and this is a solution for the future
                       • all offshore oil and gas will based on having
                         a continuous process including exploration,
                         production, and refining and for certain
                         fields, transport ship (TOPS)
                       • most of the patents have lapsed
Thursday, 28 July 11
TOPS Eliminates
                 • delay in appraisal and development
                 • conventional rigs and platforms
                 • refineries
                 • over balanced drilling as per the BP GOM
                       blow-out
                 • significantly lowers blow out and pollution risk
                       in arctic areas and in deep water

Thursday, 28 July 11
Schedule
        •      Site survey and studies -
               15 months

        •      Construct Mooring
               tower - six months

        •      Install riser tower - 1
               day weather window

        •      Pre-Install production
               template - 60 days

        •      Drill - 15 plus days

        •      Start Production
                                           5
Thursday, 28 July 11
Preliminaries
                       • establish bottom conditions, sea water
                         properties as well as wave and current
                         profile at the site (GEMS)
                       • establish if affecting marine mammals,
                         seabed corals and migratory bird paths
                         (NPL)
                       • shoot 3D seismic of the area
                       • establish that when the reservoir is de-
                         pressurised that there is no earthquake risk
                         (Geomec)

Thursday, 28 July 11
Components
                       • Mooring tower in steel in shallower waters
                         and Titanium in deep water (Mercon)
                       • Well template with co-mingled production,
                         water and gas injection services and heavy
                         oil splitting services together with subsea
                         processing (FMC/others ?)
                       • Aframax sized TOPS with dp 2 providing
                         direct well access for drilling and
                         intervening throughout the field life


Thursday, 28 July 11
Exploration Phase
                       • Design site specific TOPS mooring tower in
                         steel/Ti with 2000 ton barytes ballasted
                         base and hydrogen generators to suit
                         location (Mercon with SBM as
                         subcontractor)
                       • Install ocean energy generators, template
                         and flowlines (Technip/others?)
                       • Mobilise the TOPS ship and drill first well
                       • In event of dry well redeploy equipment
Thursday, 28 July 11
Financing
                       • in 1980 TOPS was based on paying the
                         shipowner 20% rate of return on the equity
                         in the original acquisition cost of the
                         reuseable components of the project
                       • The oilco requires to pay for the lower
                         buoy, the installation work and 90 days of
                         operations
                       • The leasing partners in TOPS are sought
Thursday, 28 July 11
TOPS Mooring Tower
                       • 2000 tons of barytes ballast in the base
                       • Upper buoy contains ballast tanks to allow
                         for installation and removal - reuseable
                       • Lower buoy at minus 160 ft have hose take
                         offs to the TOPS ship - site specific
                         ( Contitech)
                       • Ocean power to generate H2
                         (Magnomatics/ITM Power)


Thursday, 28 July 11
TOPS Template (FMC)
                       • 4 by 8 on 8’6” centres well slots
                       • each Christmas tree to incorporate shear
                         and blind rams and to be connected to a
                         co-mingling distribution manifold on the
                         central two rows for production at the
                         flowing wellhead pressure of the best well
                         and subsea separation.
                       • use duplex acoustic controls with hydraulic
                         accumulators on the template


Thursday, 28 July 11
Subcontractors to FMC
                       • Advance Energy Systems to crack heavy oil
                         to C13 and gases as appropriate
                       • Nemo Engineering - pipeline sledges
                       • Acoustic controls - used Cameron
                         successfully before and Kongsberg
                       • Water injection pumps, artificial lift, gas
                         injection and compression - Clavis are
                         developing a unique pump technology


Thursday, 28 July 11
TOPS
                       • station keeping by Dp2 with constant
                         tension mooring winch working at between
                         70 and 90 tons (Huismann/AXTech)
                       • Converted Aframax or OBO which can
                         have LNG tanks put in the holds for later
                         life operations (previous model in Eboroil jv
                         m.v.Arctic which was 25,000 dwt)
                       • Receive oil, gas, water and distribute oil,
                         gas, drill cuttings removal and pigging
                         services

Thursday, 28 July 11
Drilling
                       • 30” conductors installed on all wells in the
                         construction phase (Technip)
                       • use Casing Drilling technology to drill
                         underbalanced in a closed loop to contain
                         kicks (Schlumberger)
                       • use composite cable based push/pull
                         wireline (supplier yet to be chosen) to
                         retrieve bits etc


Thursday, 28 July 11
Drilling Operations
                       • Mount Helirig on the Port side of the ship
                         to work in the lee based on heading bow
                         quarter into the weather
                       • Have top drive and coil for intervention
                       • Recover and treat drill cuttings with
                         biodegradable oil solvent and dump cuttings
                       • have slip joint design by Aker accepted by
                         Schlumberger

Thursday, 28 July 11
Thoughts
                       • Stern into weather towards SALM
                       • Accommodation at stern
                       • Shottels bow and stern instead of Becker/
                         other rudders such as Schilling from main
                         engines
                       • New build
                       •

Thursday, 28 July 11
Process plant
                       • Have main processing subsea for separation
                         of oil, gas and water
                       • Mount equipment 3 m above cargo holds
                       • Have surface oil treatment as heating to 80
                         deg C to remove metals with activated
                         charcoal and then crack at 400 deg C to
                         diesel product specifications with a catalyst
                       • Have chemical injection and pigging services
Thursday, 28 July 11
Maximise Oil Recovery
                       •   Continuous monitoring of reservoir behaviour and
                           optimisation of offtake using multiple realisation of
                           static and dynamic reservoir models.

                       •   Continuously drill and intervene guided by 4D
                           seismic

                       •   To inject gas super critically until reservoir until
                           dry

                       •   Inject cation rich sea water to recover oil prior to
                           low surface tension water to break up macro oil in
                           water emulsions


Thursday, 28 July 11
Ship Operations
                       • Have Captain in charge of all operations
                       • Change crew every three weeks and
                         recharge activated charcoal using the dry
                         evacuation system (GEC)
                       • Have unidirectional currents and wave
                         energy generate hydrogen for dp system
                         (Magnomatics/Pulse Tidal/Green Fuel/ITM
                         Power)
                       • Be a zero emission ship
                       • Have shuttle tankers use a Remora unit
Thursday, 28 July 11
Ocean Energy
       •      Install wave energy
              generators to
              provide power in
              storms

       •      Install
              unidirectional
              current generators
              for mid-water
              installations for
              constant power
              load

       •      install in 90deg arc


Thursday, 28 July 11
Contingencies
               • Have two dp UT 705 offshore platform support
                       vessels with active stability tanks and acoustic
                       responders to shut down the template in case
                       of problems
               • Have oil skimming with a biodegradable oil
                       dispersant, bulk barytes, cement, fi-fi services,
                       anti collision radar, dry evacuation transfer
                       services
               • in the arctic amphibious life-boats and infra red
                       satellite based radar to navigate in minimum ice

Thursday, 28 July 11
The First Project
                       • The Irish Authorities have been approached
                         to develop Barryroe in conjunction with
                         the current Option holders
                       • All contracts will be at cost plus 20% and
                         there will be no bidding with technical
                         excellence deciding the contract award
                       • Intend to work with Lloyds Registry and
                         have IOM flag


Thursday, 28 July 11

110515 0445 Tops

  • 1.
    TOPS Offshore Production Systems (TOPS) 4th April 2011 Thursday, 28 July 11
  • 2.
    Contact • Inventor: Pat Haynes • Organisations: A.P.Haynes Consulting/ Eboroil Ltd • Norwegian Org nr 986455744 • Address: Jon Smørsv 4A, 1397 Nesøya • Tel: +47 66847068 Mob Tel: +47 45275598 • Skype name : eboroil • E-mail eboroil@me.com Thursday, 28 July 11
  • 3.
    The TOPS Concept • The average water depth in the world is 3795m and this is a solution for the future • all offshore oil and gas will based on having a continuous process including exploration, production, and refining and for certain fields, transport ship (TOPS) • most of the patents have lapsed Thursday, 28 July 11
  • 4.
    TOPS Eliminates • delay in appraisal and development • conventional rigs and platforms • refineries • over balanced drilling as per the BP GOM blow-out • significantly lowers blow out and pollution risk in arctic areas and in deep water Thursday, 28 July 11
  • 5.
    Schedule • Site survey and studies - 15 months • Construct Mooring tower - six months • Install riser tower - 1 day weather window • Pre-Install production template - 60 days • Drill - 15 plus days • Start Production 5 Thursday, 28 July 11
  • 6.
    Preliminaries • establish bottom conditions, sea water properties as well as wave and current profile at the site (GEMS) • establish if affecting marine mammals, seabed corals and migratory bird paths (NPL) • shoot 3D seismic of the area • establish that when the reservoir is de- pressurised that there is no earthquake risk (Geomec) Thursday, 28 July 11
  • 7.
    Components • Mooring tower in steel in shallower waters and Titanium in deep water (Mercon) • Well template with co-mingled production, water and gas injection services and heavy oil splitting services together with subsea processing (FMC/others ?) • Aframax sized TOPS with dp 2 providing direct well access for drilling and intervening throughout the field life Thursday, 28 July 11
  • 8.
    Exploration Phase • Design site specific TOPS mooring tower in steel/Ti with 2000 ton barytes ballasted base and hydrogen generators to suit location (Mercon with SBM as subcontractor) • Install ocean energy generators, template and flowlines (Technip/others?) • Mobilise the TOPS ship and drill first well • In event of dry well redeploy equipment Thursday, 28 July 11
  • 9.
    Financing • in 1980 TOPS was based on paying the shipowner 20% rate of return on the equity in the original acquisition cost of the reuseable components of the project • The oilco requires to pay for the lower buoy, the installation work and 90 days of operations • The leasing partners in TOPS are sought Thursday, 28 July 11
  • 10.
    TOPS Mooring Tower • 2000 tons of barytes ballast in the base • Upper buoy contains ballast tanks to allow for installation and removal - reuseable • Lower buoy at minus 160 ft have hose take offs to the TOPS ship - site specific ( Contitech) • Ocean power to generate H2 (Magnomatics/ITM Power) Thursday, 28 July 11
  • 11.
    TOPS Template (FMC) • 4 by 8 on 8’6” centres well slots • each Christmas tree to incorporate shear and blind rams and to be connected to a co-mingling distribution manifold on the central two rows for production at the flowing wellhead pressure of the best well and subsea separation. • use duplex acoustic controls with hydraulic accumulators on the template Thursday, 28 July 11
  • 12.
    Subcontractors to FMC • Advance Energy Systems to crack heavy oil to C13 and gases as appropriate • Nemo Engineering - pipeline sledges • Acoustic controls - used Cameron successfully before and Kongsberg • Water injection pumps, artificial lift, gas injection and compression - Clavis are developing a unique pump technology Thursday, 28 July 11
  • 13.
    TOPS • station keeping by Dp2 with constant tension mooring winch working at between 70 and 90 tons (Huismann/AXTech) • Converted Aframax or OBO which can have LNG tanks put in the holds for later life operations (previous model in Eboroil jv m.v.Arctic which was 25,000 dwt) • Receive oil, gas, water and distribute oil, gas, drill cuttings removal and pigging services Thursday, 28 July 11
  • 14.
    Drilling • 30” conductors installed on all wells in the construction phase (Technip) • use Casing Drilling technology to drill underbalanced in a closed loop to contain kicks (Schlumberger) • use composite cable based push/pull wireline (supplier yet to be chosen) to retrieve bits etc Thursday, 28 July 11
  • 15.
    Drilling Operations • Mount Helirig on the Port side of the ship to work in the lee based on heading bow quarter into the weather • Have top drive and coil for intervention • Recover and treat drill cuttings with biodegradable oil solvent and dump cuttings • have slip joint design by Aker accepted by Schlumberger Thursday, 28 July 11
  • 16.
    Thoughts • Stern into weather towards SALM • Accommodation at stern • Shottels bow and stern instead of Becker/ other rudders such as Schilling from main engines • New build • Thursday, 28 July 11
  • 17.
    Process plant • Have main processing subsea for separation of oil, gas and water • Mount equipment 3 m above cargo holds • Have surface oil treatment as heating to 80 deg C to remove metals with activated charcoal and then crack at 400 deg C to diesel product specifications with a catalyst • Have chemical injection and pigging services Thursday, 28 July 11
  • 18.
    Maximise Oil Recovery • Continuous monitoring of reservoir behaviour and optimisation of offtake using multiple realisation of static and dynamic reservoir models. • Continuously drill and intervene guided by 4D seismic • To inject gas super critically until reservoir until dry • Inject cation rich sea water to recover oil prior to low surface tension water to break up macro oil in water emulsions Thursday, 28 July 11
  • 19.
    Ship Operations • Have Captain in charge of all operations • Change crew every three weeks and recharge activated charcoal using the dry evacuation system (GEC) • Have unidirectional currents and wave energy generate hydrogen for dp system (Magnomatics/Pulse Tidal/Green Fuel/ITM Power) • Be a zero emission ship • Have shuttle tankers use a Remora unit Thursday, 28 July 11
  • 20.
    Ocean Energy • Install wave energy generators to provide power in storms • Install unidirectional current generators for mid-water installations for constant power load • install in 90deg arc Thursday, 28 July 11
  • 21.
    Contingencies • Have two dp UT 705 offshore platform support vessels with active stability tanks and acoustic responders to shut down the template in case of problems • Have oil skimming with a biodegradable oil dispersant, bulk barytes, cement, fi-fi services, anti collision radar, dry evacuation transfer services • in the arctic amphibious life-boats and infra red satellite based radar to navigate in minimum ice Thursday, 28 July 11
  • 22.
    The First Project • The Irish Authorities have been approached to develop Barryroe in conjunction with the current Option holders • All contracts will be at cost plus 20% and there will be no bidding with technical excellence deciding the contract award • Intend to work with Lloyds Registry and have IOM flag Thursday, 28 July 11