SlideShare a Scribd company logo
1 of 39
Download to read offline
Technology Updates
Outline & Objectives
Longevity Updates
ArmorFill System
Project Case Studies
Frequently Asked Question:
How long will the ClosureTurf
system last?
Page
Longevity & Design Life
• Structural geomembrane installs
on subgrade
– Site-dependent
• Engineered synthetic turf is placed
directly onto the geomembrane
• Sand infill is placed directly into
the turf layer
• Synthetic (HDPE) turf fibers are
effectively the only exposed
component of the system
Synthetic Turf (PE) - Functional
Longevity UV Resistance
• Significant advancements in UV resistance
• Need 3.5 lbs of tensile strength in the turf fiber
• Turf Fiber has 20 lbs at time of manufacture
• Projected to retain 65% (13 lbs) at 100 years
• More than three (3) times the tensile strength needed at 100 years
Outline & Objectives
Longevity Updates
ArmorFill System
Project Case Studies
Historic Problems: Vegetative Soil Caps
• ‘Borrow’ Areas- where the
issues begin
• Cover soil can be low
quality
• Will need to weather
excessive saturation as well
as severe drought- in
perpetuity
• Uncertainty of vegetative
growth
Soil Cap: Drainage Requirements
• Water accumulates &
moves downhill
– Picks up volume and
transports cover soil
• Result- runoff loaded with
sediment
• Settle out & store the
sediment prior to ultimate
discharge
Traditional ClosureTurf®
• Fundamentally similar to
prescriptive design except
took the unpredictability of
vegetation and weather out
– No soil borrow
– Eliminate erosion
– Clean water quality (filters
through sand)- 11 NTU’s
– Decreased storage
requirements due to no
sediment runoff
– Less maintenance
ClosureTurf® System with ArmorFill™
• 40 Mil MicroSpike®
(Geomembrane Layer)
• Engineered Synthetic Turf
• Polymer bound sand
(ArmorFill) – for slopes
greater then 5%
• Appropriate for slopes and
top decks
• Were velocities may be 5-10
FPS then a emulsion based
binder can be applied to
prevent sand movement
Page
BALDWIN COUNTY LANDFILL
Owner: Baldwin County
Location: Milledgeville, GA
Completed: 2017 (Jan.)
Size: 23 acres
Outline & Objectives
Longevity Updates
ArmorFill System
Project Case Studies
Page
Over 40 Million Square Feet of
COVANTA- CARVER-MARION-
WAREHAM LANDFILL
Owner: Covanta Energy
Location: Carver, MA
Completed: 2015
Size: 4 acres
ClosureTurf relief
valves were installed
every acre.
WARD HILL NECK LANDFILL
Owner: Covanta Energy
Location: Haverhill, MA
Completed: 2016
Size: 12 acres
HydroTurf lined
channels handle high
velocities and result in
clean runoff.
CITY OF PORT ANGELES
LANDFILL
Owner: City of Port Angeles
Location: Port Angeles, WA
Completed: 2016
Size: 16 acres
ClosureTurf® increases stability on steeper grades.
ClosureTurf: Permitting, Design, and CQA
Challenges and Lessons Learned
Prepared By:
Paul Shamoian, P.E.
March 2017
Prepared For
2017 RECYCLING AND SOLID WASTE CONFERENCE
► Geomembrane Barrier
► Drainage Layer
► Topsoil/Vegetation
► Tack-on Stormwater Berms
▪ Long Term O&M Care & Costs
o Mowing
o Animal Burrows
o Erosion
o Vegetation Growth
Conventional Subtitle D Landfill Cap
ClosureTurf - Benefits
► Decrease Erosion Exposure
For Initial Vegetation Growth
► Decrease Long Term
Maintenance and Costs
► Decrease Potential Runoff
with Sediment
▪ Construction: install and
covered, no erosion
► Increase Airspace
PERMITTING
► Background
▪ Massachusetts, Rhode Island
► Lessons Learned
▪ Approach Regulators early
and provide background of
materials
▪ Permitting Conditions may
contain increased visual
inspections and tensile
strength testing of turf blades
DESIGN - Challenges
► Stormwater
▪ High Curve Number
o Need to meet maximum discharge conditions with higher
curve number
▪ Structures
o Berms/swales to control high velocities
▪ Stormwater Basins
o Provide retainage to meet discharge limits for site
► Landfill Gas Management
▪ LFG management will be necessary immediately after
installation
▪ May need additional landfill gas collectors to prevent
possible uplift
▪ Passive gas venting
DESIGN - Challenges (Continued)
► Grading
▪ Constructability
o Slope transitions and tie-ins require
foresight and planning
▪ Slope transitions can present
installation challenges
▪ Tie-in locations to existing
▪ Access roads
o Anchor ClosureTurf into sides; proper
fill above geomembrane
o Consideration for type of vehicles
DESIGN – Lessons Learned
► Specifications provided by
Watershed Geosynthetics
► Super Gripnet – HDPE appeared to
be more workable, less thermal
expansion/contraction
► Specs/Drawings indicate welding
all tie-ins and backfill top of slope
anchor trench at end of day to deal
with thermal expansion/contraction
► Specs/Drawings indicate removing
turf blades from sewn seams
DESIGN – Lessons Learned (Continued)
► Specs indicate seams to be snapped
after welding (or sandbags placed on
welds) to prevent “tenting” from
occurring
► Install passive vents close to existing
LFG wells
► Stormwater berms and swales built
into subgrade layer
► Consider stone toe drains or rip-rap
at toe of slope needs for sheet flow
CONSTRUCTION - Challenges
► Installation
▪ Slower installation (geosynthetics)
o Additional extrusion welding
o ClosureTurf sewing
o Additional Sandbags required
o Sand infill and hydrobinder installation
o Bonus: once it’s down  project complete, no soils
▪ Access
o Limited access during construction (sand infill &
hydrobinder installation) must utilize downchutes and
diversion berms
o Limited access after construction - LFG well maintenance
▪ Sand Infill
o Confirming sand thickness
CONSTRUCTION – Challenges (continued)
► Installation
▪ Weather
o Bridging at slope transitions (stormwater structures, tie-
ins) requires more sandbags than typical installation until
infill is installed
▪ Settlement on landfill surface
o Ponding is possible from settlement or equipment rutting
during construction  requires raking of tracks
o Survey – confirm slopes prior to installation of Super
Gripnet/Turf. Minimize work/patches if problems noticed
later
Hydrobinder Installation
Sand Infill Installation
CONSTRUCTION – Lessons Learned
► Rubber Tired Vehicles with Wide Turf Tires
▪ Preferred over rubber-tracked vehicles for sand infill
and hydrobinder installation = less subgrade
deformation
► Contactor indicate early plan for installation sand
infill
▪ Cannot drive on Turf with >5 psi machine (ground
pressure) without sand infill on slopes>15%
▪ Equipment w/<5 psi are allowed prior to sand infill on
slopes <15%
▪ After sand infill installation: Slopes >10% = ground
pressure allowed up to 35 psi. Top decks allow higher
ground pressures
► Access Points necessary for sand infill and
hydrobinder
▪ Design downchute channels for equipment to drive up
and down
▪ Design berms and swales as trapezoidal channels
Overall ClosureTurf Project Benefits
► Overall reduced construction timeframe
► No slope erosion during construction or while waiting for
grass to grow
► Construction soil stockpile areas not needed
► Public perception: instant green grass
► Airspace gains
► Reduced post-closure O&M costs
► Clean run-off  no sediment or TSS
QUESTIONS?

More Related Content

What's hot

Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1amrhaggag
 
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationReston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationFairfax County
 
Think outside the box (culvert): How creativity sells more precast
Think outside the box (culvert): How creativity sells more precastThink outside the box (culvert): How creativity sells more precast
Think outside the box (culvert): How creativity sells more precastHamilton_Kent
 
GTL Oil & Gas Supplement
GTL Oil & Gas SupplementGTL Oil & Gas Supplement
GTL Oil & Gas Supplementgavinrixon
 
IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)Theerepat Suppachoknirun
 
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)Theerepat Suppachoknirun
 
Aqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureAqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureDarren Miller
 
Foam Bitumen Presentation
Foam Bitumen PresentationFoam Bitumen Presentation
Foam Bitumen PresentationCraig Gordon
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 
Professional WORK EXPERIENCE
Professional WORK EXPERIENCEProfessional WORK EXPERIENCE
Professional WORK EXPERIENCEJesse Marley
 
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...Dan Brown and Associates, PC
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Pont Samuel-De Champlain Bridge
 
Soutenance de-stage-groupe-cayon-sebastien-valette
Soutenance de-stage-groupe-cayon-sebastien-valetteSoutenance de-stage-groupe-cayon-sebastien-valette
Soutenance de-stage-groupe-cayon-sebastien-valetteSbastienValette1
 

What's hot (19)

Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1
 
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationReston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
 
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
 
Think outside the box (culvert): How creativity sells more precast
Think outside the box (culvert): How creativity sells more precastThink outside the box (culvert): How creativity sells more precast
Think outside the box (culvert): How creativity sells more precast
 
Narrow Pavement Widening - Atlanta District
Narrow Pavement Widening - Atlanta DistrictNarrow Pavement Widening - Atlanta District
Narrow Pavement Widening - Atlanta District
 
GTL Oil & Gas Supplement
GTL Oil & Gas SupplementGTL Oil & Gas Supplement
GTL Oil & Gas Supplement
 
IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)
 
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)
SPE 192047 technical presentation - 2018 SPE Conference (Brisbane, AU)
 
Aqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureAqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams Literature
 
Foam Bitumen Presentation
Foam Bitumen PresentationFoam Bitumen Presentation
Foam Bitumen Presentation
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 
Professional WORK EXPERIENCE
Professional WORK EXPERIENCEProfessional WORK EXPERIENCE
Professional WORK EXPERIENCE
 
Canopy Case Study 2
Canopy Case Study 2Canopy Case Study 2
Canopy Case Study 2
 
Resume 1
Resume 1 Resume 1
Resume 1
 
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
 
Drainage Salvation-JRiopelle
Drainage Salvation-JRiopelleDrainage Salvation-JRiopelle
Drainage Salvation-JRiopelle
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
Soutenance de-stage-groupe-cayon-sebastien-valette
Soutenance de-stage-groupe-cayon-sebastien-valetteSoutenance de-stage-groupe-cayon-sebastien-valette
Soutenance de-stage-groupe-cayon-sebastien-valette
 
311576 DD Inserts
311576 DD Inserts311576 DD Inserts
311576 DD Inserts
 

Similar to Technology Updates for Landfill Closure Systems

"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...Instituto del cemento y Hormigón de Chile
 
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...New Jersey Future
 
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...California Asphalt Pavement Association
 
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementVDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementPatrick McPartland, E.I.T.
 
Groundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft SinkingGroundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft SinkingMartin Preene
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesSravan Muguda
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfKeat Wei, Gavin Chung
 
A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesSuper Arc Consultant
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDr. Malek Smadi
 
Stormwater Guidebook_Permeable Pavement Systems.pdf
Stormwater Guidebook_Permeable Pavement Systems.pdfStormwater Guidebook_Permeable Pavement Systems.pdf
Stormwater Guidebook_Permeable Pavement Systems.pdfShielaSorino1
 
pavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdfpavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdfsunilghosh11
 

Similar to Technology Updates for Landfill Closure Systems (20)

"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
 
Soil improvement techniques
Soil improvement techniquesSoil improvement techniques
Soil improvement techniques
 
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...
James Purcell "Porous Asphalt Pavement for Storm Water Management" March 14, ...
 
addition consideration in pile
addition consideration in pileaddition consideration in pile
addition consideration in pile
 
2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans
 
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...
2023 CalAPA Spring Conference presentation by John Harvey on compaction of as...
 
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementVDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
 
Groundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft SinkingGroundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft Sinking
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdf
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniques
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 
2016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-162016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-16
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
 
CC Intro
CC IntroCC Intro
CC Intro
 
Stormwater Guidebook_Permeable Pavement Systems.pdf
Stormwater Guidebook_Permeable Pavement Systems.pdfStormwater Guidebook_Permeable Pavement Systems.pdf
Stormwater Guidebook_Permeable Pavement Systems.pdf
 
pavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdfpavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdf
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 

More from MassRecycle .

2018 R3 Conference SWANA Afternoon Keynote
2018 R3 Conference SWANA Afternoon Keynote2018 R3 Conference SWANA Afternoon Keynote
2018 R3 Conference SWANA Afternoon KeynoteMassRecycle .
 
2018 R3 Conference Furniture Reuse IRN/Casella
2018 R3 Conference Furniture Reuse IRN/Casella2018 R3 Conference Furniture Reuse IRN/Casella
2018 R3 Conference Furniture Reuse IRN/CasellaMassRecycle .
 
2018 R3 Conference Yarmouth Energy Park
2018 R3 Conference Yarmouth Energy Park2018 R3 Conference Yarmouth Energy Park
2018 R3 Conference Yarmouth Energy ParkMassRecycle .
 
2018 R3 Conference Cambridge Curbside Composting
2018 R3 Conference Cambridge Curbside Composting2018 R3 Conference Cambridge Curbside Composting
2018 R3 Conference Cambridge Curbside CompostingMassRecycle .
 
2018 R3 Conference Decentralized Composting
2018 R3 Conference Decentralized Composting2018 R3 Conference Decentralized Composting
2018 R3 Conference Decentralized CompostingMassRecycle .
 
2018 R3 Conference Interstate MSW Flow Griffith
2018 R3 Conference Interstate MSW Flow Griffith2018 R3 Conference Interstate MSW Flow Griffith
2018 R3 Conference Interstate MSW Flow GriffithMassRecycle .
 
2018 R3 Conference SWMP Goddard
2018 R3 Conference SWMP Goddard2018 R3 Conference SWMP Goddard
2018 R3 Conference SWMP GoddardMassRecycle .
 
2018 R3 Conference MA Capacity Constraints Koehler
2018 R3 Conference MA Capacity Constraints Koehler2018 R3 Conference MA Capacity Constraints Koehler
2018 R3 Conference MA Capacity Constraints KoehlerMassRecycle .
 
2018 R3 Conference LeanPath Food Waste Reduction
2018 R3 Conference LeanPath Food Waste Reduction2018 R3 Conference LeanPath Food Waste Reduction
2018 R3 Conference LeanPath Food Waste ReductionMassRecycle .
 
2018 R3 Conference Boston College Food Waste Reduction
2018 R3 Conference Boston College Food Waste Reduction2018 R3 Conference Boston College Food Waste Reduction
2018 R3 Conference Boston College Food Waste ReductionMassRecycle .
 
2018 R3 Conference Green Team
2018 R3 Conference Green Team2018 R3 Conference Green Team
2018 R3 Conference Green TeamMassRecycle .
 
2018 R3 Conference Andover Public Schools Composting
2018 R3 Conference Andover Public Schools Composting2018 R3 Conference Andover Public Schools Composting
2018 R3 Conference Andover Public Schools CompostingMassRecycle .
 
2018 R3 Conference Cambridge Cafeteria Composting
2018 R3 Conference Cambridge Cafeteria Composting2018 R3 Conference Cambridge Cafeteria Composting
2018 R3 Conference Cambridge Cafeteria CompostingMassRecycle .
 
2018 R3 Conference ACA Paint Stewardship
2018 R3 Conference ACA Paint Stewardship2018 R3 Conference ACA Paint Stewardship
2018 R3 Conference ACA Paint StewardshipMassRecycle .
 
2018 R3 Conference ISPA Mattress Recycling
2018 R3 Conference ISPA Mattress Recycling2018 R3 Conference ISPA Mattress Recycling
2018 R3 Conference ISPA Mattress RecyclingMassRecycle .
 
2018 R3 Conference MASSPSC Update
2018 R3 Conference MASSPSC Update2018 R3 Conference MASSPSC Update
2018 R3 Conference MASSPSC UpdateMassRecycle .
 
2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning
2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning
2018 R3 Conference Morning Keynote - City of Boston Zero Waste PlanningMassRecycle .
 
2018 R3 Conference Intro and Annual Meeting
2018 R3 Conference Intro and Annual Meeting2018 R3 Conference Intro and Annual Meeting
2018 R3 Conference Intro and Annual MeetingMassRecycle .
 
Donovan mr 2017 k12 compost final
Donovan mr 2017 k12 compost finalDonovan mr 2017 k12 compost final
Donovan mr 2017 k12 compost finalMassRecycle .
 
Ipswich systemsofsustainabilitypres3 2017
Ipswich systemsofsustainabilitypres3 2017Ipswich systemsofsustainabilitypres3 2017
Ipswich systemsofsustainabilitypres3 2017MassRecycle .
 

More from MassRecycle . (20)

2018 R3 Conference SWANA Afternoon Keynote
2018 R3 Conference SWANA Afternoon Keynote2018 R3 Conference SWANA Afternoon Keynote
2018 R3 Conference SWANA Afternoon Keynote
 
2018 R3 Conference Furniture Reuse IRN/Casella
2018 R3 Conference Furniture Reuse IRN/Casella2018 R3 Conference Furniture Reuse IRN/Casella
2018 R3 Conference Furniture Reuse IRN/Casella
 
2018 R3 Conference Yarmouth Energy Park
2018 R3 Conference Yarmouth Energy Park2018 R3 Conference Yarmouth Energy Park
2018 R3 Conference Yarmouth Energy Park
 
2018 R3 Conference Cambridge Curbside Composting
2018 R3 Conference Cambridge Curbside Composting2018 R3 Conference Cambridge Curbside Composting
2018 R3 Conference Cambridge Curbside Composting
 
2018 R3 Conference Decentralized Composting
2018 R3 Conference Decentralized Composting2018 R3 Conference Decentralized Composting
2018 R3 Conference Decentralized Composting
 
2018 R3 Conference Interstate MSW Flow Griffith
2018 R3 Conference Interstate MSW Flow Griffith2018 R3 Conference Interstate MSW Flow Griffith
2018 R3 Conference Interstate MSW Flow Griffith
 
2018 R3 Conference SWMP Goddard
2018 R3 Conference SWMP Goddard2018 R3 Conference SWMP Goddard
2018 R3 Conference SWMP Goddard
 
2018 R3 Conference MA Capacity Constraints Koehler
2018 R3 Conference MA Capacity Constraints Koehler2018 R3 Conference MA Capacity Constraints Koehler
2018 R3 Conference MA Capacity Constraints Koehler
 
2018 R3 Conference LeanPath Food Waste Reduction
2018 R3 Conference LeanPath Food Waste Reduction2018 R3 Conference LeanPath Food Waste Reduction
2018 R3 Conference LeanPath Food Waste Reduction
 
2018 R3 Conference Boston College Food Waste Reduction
2018 R3 Conference Boston College Food Waste Reduction2018 R3 Conference Boston College Food Waste Reduction
2018 R3 Conference Boston College Food Waste Reduction
 
2018 R3 Conference Green Team
2018 R3 Conference Green Team2018 R3 Conference Green Team
2018 R3 Conference Green Team
 
2018 R3 Conference Andover Public Schools Composting
2018 R3 Conference Andover Public Schools Composting2018 R3 Conference Andover Public Schools Composting
2018 R3 Conference Andover Public Schools Composting
 
2018 R3 Conference Cambridge Cafeteria Composting
2018 R3 Conference Cambridge Cafeteria Composting2018 R3 Conference Cambridge Cafeteria Composting
2018 R3 Conference Cambridge Cafeteria Composting
 
2018 R3 Conference ACA Paint Stewardship
2018 R3 Conference ACA Paint Stewardship2018 R3 Conference ACA Paint Stewardship
2018 R3 Conference ACA Paint Stewardship
 
2018 R3 Conference ISPA Mattress Recycling
2018 R3 Conference ISPA Mattress Recycling2018 R3 Conference ISPA Mattress Recycling
2018 R3 Conference ISPA Mattress Recycling
 
2018 R3 Conference MASSPSC Update
2018 R3 Conference MASSPSC Update2018 R3 Conference MASSPSC Update
2018 R3 Conference MASSPSC Update
 
2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning
2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning
2018 R3 Conference Morning Keynote - City of Boston Zero Waste Planning
 
2018 R3 Conference Intro and Annual Meeting
2018 R3 Conference Intro and Annual Meeting2018 R3 Conference Intro and Annual Meeting
2018 R3 Conference Intro and Annual Meeting
 
Donovan mr 2017 k12 compost final
Donovan mr 2017 k12 compost finalDonovan mr 2017 k12 compost final
Donovan mr 2017 k12 compost final
 
Ipswich systemsofsustainabilitypres3 2017
Ipswich systemsofsustainabilitypres3 2017Ipswich systemsofsustainabilitypres3 2017
Ipswich systemsofsustainabilitypres3 2017
 

Recently uploaded

Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Tina Ji
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BHbill846304
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012sapnasaifi408
 
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurVIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurSuhani Kapoor
 
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service Mumbai
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service MumbaiCall Girls Mumbai Gayatri 8617697112 Independent Escort Service Mumbai
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service MumbaiCall girls in Ahmedabad High profile
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)RaviPrajapat11
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerSuhani Kapoor
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...Call Girls in Nagpur High Profile
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 

Recently uploaded (20)

Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
 
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort serviceyoung Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
 
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi NcrCall Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BH
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
 
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurVIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service Mumbai
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service MumbaiCall Girls Mumbai Gayatri 8617697112 Independent Escort Service Mumbai
Call Girls Mumbai Gayatri 8617697112 Independent Escort Service Mumbai
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 

Technology Updates for Landfill Closure Systems

  • 2. Outline & Objectives Longevity Updates ArmorFill System Project Case Studies
  • 3. Frequently Asked Question: How long will the ClosureTurf system last? Page
  • 4. Longevity & Design Life • Structural geomembrane installs on subgrade – Site-dependent • Engineered synthetic turf is placed directly onto the geomembrane • Sand infill is placed directly into the turf layer • Synthetic (HDPE) turf fibers are effectively the only exposed component of the system
  • 5. Synthetic Turf (PE) - Functional Longevity UV Resistance • Significant advancements in UV resistance • Need 3.5 lbs of tensile strength in the turf fiber • Turf Fiber has 20 lbs at time of manufacture • Projected to retain 65% (13 lbs) at 100 years • More than three (3) times the tensile strength needed at 100 years
  • 6. Outline & Objectives Longevity Updates ArmorFill System Project Case Studies
  • 7. Historic Problems: Vegetative Soil Caps • ‘Borrow’ Areas- where the issues begin • Cover soil can be low quality • Will need to weather excessive saturation as well as severe drought- in perpetuity • Uncertainty of vegetative growth
  • 8. Soil Cap: Drainage Requirements • Water accumulates & moves downhill – Picks up volume and transports cover soil • Result- runoff loaded with sediment • Settle out & store the sediment prior to ultimate discharge
  • 9. Traditional ClosureTurf® • Fundamentally similar to prescriptive design except took the unpredictability of vegetation and weather out – No soil borrow – Eliminate erosion – Clean water quality (filters through sand)- 11 NTU’s – Decreased storage requirements due to no sediment runoff – Less maintenance
  • 10. ClosureTurf® System with ArmorFill™ • 40 Mil MicroSpike® (Geomembrane Layer) • Engineered Synthetic Turf • Polymer bound sand (ArmorFill) – for slopes greater then 5% • Appropriate for slopes and top decks • Were velocities may be 5-10 FPS then a emulsion based binder can be applied to prevent sand movement
  • 11. Page BALDWIN COUNTY LANDFILL Owner: Baldwin County Location: Milledgeville, GA Completed: 2017 (Jan.) Size: 23 acres
  • 12.
  • 13.
  • 14. Outline & Objectives Longevity Updates ArmorFill System Project Case Studies
  • 15. Page Over 40 Million Square Feet of
  • 16. COVANTA- CARVER-MARION- WAREHAM LANDFILL Owner: Covanta Energy Location: Carver, MA Completed: 2015 Size: 4 acres
  • 17.
  • 18. ClosureTurf relief valves were installed every acre.
  • 19. WARD HILL NECK LANDFILL Owner: Covanta Energy Location: Haverhill, MA Completed: 2016 Size: 12 acres
  • 20.
  • 21. HydroTurf lined channels handle high velocities and result in clean runoff.
  • 22. CITY OF PORT ANGELES LANDFILL Owner: City of Port Angeles Location: Port Angeles, WA Completed: 2016 Size: 16 acres
  • 23. ClosureTurf® increases stability on steeper grades.
  • 24.
  • 25. ClosureTurf: Permitting, Design, and CQA Challenges and Lessons Learned Prepared By: Paul Shamoian, P.E. March 2017 Prepared For 2017 RECYCLING AND SOLID WASTE CONFERENCE
  • 26. ► Geomembrane Barrier ► Drainage Layer ► Topsoil/Vegetation ► Tack-on Stormwater Berms ▪ Long Term O&M Care & Costs o Mowing o Animal Burrows o Erosion o Vegetation Growth Conventional Subtitle D Landfill Cap
  • 27. ClosureTurf - Benefits ► Decrease Erosion Exposure For Initial Vegetation Growth ► Decrease Long Term Maintenance and Costs ► Decrease Potential Runoff with Sediment ▪ Construction: install and covered, no erosion ► Increase Airspace
  • 28. PERMITTING ► Background ▪ Massachusetts, Rhode Island ► Lessons Learned ▪ Approach Regulators early and provide background of materials ▪ Permitting Conditions may contain increased visual inspections and tensile strength testing of turf blades
  • 29. DESIGN - Challenges ► Stormwater ▪ High Curve Number o Need to meet maximum discharge conditions with higher curve number ▪ Structures o Berms/swales to control high velocities ▪ Stormwater Basins o Provide retainage to meet discharge limits for site ► Landfill Gas Management ▪ LFG management will be necessary immediately after installation ▪ May need additional landfill gas collectors to prevent possible uplift ▪ Passive gas venting
  • 30. DESIGN - Challenges (Continued) ► Grading ▪ Constructability o Slope transitions and tie-ins require foresight and planning ▪ Slope transitions can present installation challenges ▪ Tie-in locations to existing ▪ Access roads o Anchor ClosureTurf into sides; proper fill above geomembrane o Consideration for type of vehicles
  • 31. DESIGN – Lessons Learned ► Specifications provided by Watershed Geosynthetics ► Super Gripnet – HDPE appeared to be more workable, less thermal expansion/contraction ► Specs/Drawings indicate welding all tie-ins and backfill top of slope anchor trench at end of day to deal with thermal expansion/contraction ► Specs/Drawings indicate removing turf blades from sewn seams
  • 32. DESIGN – Lessons Learned (Continued) ► Specs indicate seams to be snapped after welding (or sandbags placed on welds) to prevent “tenting” from occurring ► Install passive vents close to existing LFG wells ► Stormwater berms and swales built into subgrade layer ► Consider stone toe drains or rip-rap at toe of slope needs for sheet flow
  • 33. CONSTRUCTION - Challenges ► Installation ▪ Slower installation (geosynthetics) o Additional extrusion welding o ClosureTurf sewing o Additional Sandbags required o Sand infill and hydrobinder installation o Bonus: once it’s down  project complete, no soils ▪ Access o Limited access during construction (sand infill & hydrobinder installation) must utilize downchutes and diversion berms o Limited access after construction - LFG well maintenance ▪ Sand Infill o Confirming sand thickness
  • 34. CONSTRUCTION – Challenges (continued) ► Installation ▪ Weather o Bridging at slope transitions (stormwater structures, tie- ins) requires more sandbags than typical installation until infill is installed ▪ Settlement on landfill surface o Ponding is possible from settlement or equipment rutting during construction  requires raking of tracks o Survey – confirm slopes prior to installation of Super Gripnet/Turf. Minimize work/patches if problems noticed later
  • 37. CONSTRUCTION – Lessons Learned ► Rubber Tired Vehicles with Wide Turf Tires ▪ Preferred over rubber-tracked vehicles for sand infill and hydrobinder installation = less subgrade deformation ► Contactor indicate early plan for installation sand infill ▪ Cannot drive on Turf with >5 psi machine (ground pressure) without sand infill on slopes>15% ▪ Equipment w/<5 psi are allowed prior to sand infill on slopes <15% ▪ After sand infill installation: Slopes >10% = ground pressure allowed up to 35 psi. Top decks allow higher ground pressures ► Access Points necessary for sand infill and hydrobinder ▪ Design downchute channels for equipment to drive up and down ▪ Design berms and swales as trapezoidal channels
  • 38. Overall ClosureTurf Project Benefits ► Overall reduced construction timeframe ► No slope erosion during construction or while waiting for grass to grow ► Construction soil stockpile areas not needed ► Public perception: instant green grass ► Airspace gains ► Reduced post-closure O&M costs ► Clean run-off  no sediment or TSS