PROJECT MANAGEMENT
NETWORK ANALYSIS (CPM & PERT)
Project Management
Tools and Techniques
Project management tools and techniques
assist project managers and their teams in
various aspects of project management.
1. Bar chats and milestone charts
2. Network Diagram
1. Bar Charts and
Milestone Charts
 Gantt charts are "time" oriented.
 Activities are graphically shown on a
calendar time scale, used primarily for
small projects.
 Bars show an activities duration in its
entirety, regardless of its dependency on
other activities.
 Effortless to construct, and are brief in
format.
Bar Charts
Advantages
1. It is very easy and simple to construct.
2. It is easy to understand.
3. Simplicity of updating.
4. It is very easy to show the progress of work and programme of
work.
5. Easy to incorporate resource plan in terms of the plant schedule,
material schedule and labour schedule required for the project.
Bar Charts
Disadvantages
1. Does not show relationship between the activities.
2. Does not give you the ability to visualize the exact progress of
the project. (Eg:If one activity is behind or ahead of time what effect
it will have on the overall project.)
3. Anticipate delays or problems soon enough to correct them.
4. Does not show detailed sequence of activities.
5. Does not show "critical activities".
6. Does not show precise effect of a delay or failure to complete an
activity on time.
Bar Charts
Example : The activity breakdown for certain project
Activity 2 and activity 3 can be done concurrently, and both
must follow activity 1. Activity 2 must precede activity 4. Activity
5 cannot begin until both activities 2 and 3 are completed.
Activity 6 can be started only after activities 4 and 5 are
complete. Activity 7 is the last activity which can be started only
after completion of activity 5. Prepare the bar chart for the
project.
Activity No. Duration (weeks)
1 1
2 2
3 4
4 3
5 1
6 2
7 4
Milestone Charts
Milestone chart is a modification over the original Gantt
chart. Milestones are key events of a math activity
represented by a bar: these are specific point in time which
marks the completion of certain portion of the main activity.
These points are those which can be easily identified over
the main bar. We have already been that when a particular
activity, represented by a bar on a bar-chart.
SEQUENCING OF ACTIVITIES
Activities
“Topo” project site
Lay gravel
Order gravel
Clear roadway
Prefabricate
forms
Layout pad batterboards
Pour concrete
Check pad elevations
Remove forms
Establish road grades
Set road alignments
Place concrete forms
Clear pad site
Create project drawings
Excavate pad footings
Cure concrete
Check Road grades
Perform “As-
built”
Rough activities listing
Sequencing Activities
After you have developed your rough activity list in no specific order,
you must now put the activities into a "logical" sequence to be
performed. The finished activity list is broken down as follows:

Activity Number Column

Activity Column

"Immediately Proceeded By" (IPB) Column
There are five types of activities associated with the development of a
finished activities list. Keeping these activities in mind will help you
in your logical thinking to develop the activity list on paper.

Starting activities. (beginning activity)

Preceding activities. (previous activity)

Concurring activities. (occurring at the same time)

Succeeding activities. (following activity)

Lagging activities. (slow or lingering activities)
Types of Activities
Question 1 - - Represent on GANTT Chart the Following Project,
The Activities and their Durations being as indicated.
(A) CONDUCTING AN EXAMINATION
No. ACTIVITY DURATION
1 Answer Questionaire 1 DAY
2 Print Question Paper 2 DAYS
3 Design Questionnaire 7 DAYS
4 Declare the result 1 DAY
5 Distribute to various centers 4 DAYS
6 Collect Answer Books at main
office
2 DAYS
7 Allot the marks and grades 1 DAY
8 Check the answer sheets 7 DAYS
Question 2 - The Following Project is to be represented by a bar
chart. The duration for each activity is in days. These are actual
work days. The project commences on Wednesday, November 15,
with five work day a week. Draw the bar chart with the horizontal
scale denoting calendar dates.
No. ACTIVITY DURATION
1 Activity 1 8 days
2 Activity 2 4 days
3 Activity 3 7 days
4 Activity 4 9 days
5 Activity 5 3 days
6 Activity 6 3 days
7 Activity 7 14 days
8 Activity 8 17 days
Question 2 – Continues ……….
 Activities 1 & 2 can occur concurrently.
 Activity 3 can take place after activity 2 is completed.
 Activities 4, 6 and 3 can occur concurrently.
 Activity 8 can start 4 days after the commencement of
activity 6.
 Activity 7 should follow activity 5.
 Activity 5 can begin concurrently with activity 8
25/7/2
016
1
9
Question 3- Roof
Structure
The following seven tasks are required for the erection of
a building roof structure. Some of the tasks can be
completed simultaneously; the overhang with sofit can
be constructed while the deck is being installed.
1 Place & secure trusses, 2 days
2 Install roof deck, 7 days
3 Apply vapor barrier, 2 days
4 Apply roof cladding, 2 days
5 Construct roof overhang, 4 days
6 Install soffits, 4 days
7 Apply flashing, 6 days
2. Network Methods
The network technique is a major advance in management science, The technique
is based on the basic characteristics of all projects, that all work must be done in
well-defined steps.
For example, for completing a foundation, the various steps are:) layout, digging,
placing side board and concreting.
The network technique exploits this characteristics by representing the steps of the
project objective graphically in the form of a network or arrow diagram. It would be
difficult to find in the history of management methods any technique which has
received such widespread attention as that accorded to network methods for
planning, scheduling and controlling
Following two major network system
PERT
CPM
NETWORK TECHNIQUES
PERT CPM
-Program Evaluation
and
Review Technique
- developed by the US
Navy with Booz
Hamilton Lockheed
- on the Polaris
Missile/Submarine
program 1958
Critical Path
Method
Developed by El
Dupont for
Chemical Plant
Shutdown
Project- about
same time as
PERT
Both use same calculations, almost similar
Main difference is probabilistic and deterministic
in time estimation
Gantt Chart also used in scheduling
Milestone chart vs
PERT network
• Milestone chart visually shows the duration
of Tasks whereas a PERT chart visually shows
the sequence dependencies between tasks.
• Milestone visually shows the Time overlap of
Tasks whereas a Network does not show
time overlap but does show which tasks
could be done in parallel.
• Most Project Managers find PERT very
helpful for scheduling, monitoring and
controlling Projects.
• PERT is recommended for Large Projects
with high inter-task dependencies and the
milestone chart for simpler Projects.
Most Project Management Case Tools nowadays
(eg. MS-Project ) allow the best feature of PERT to
be incorporated into milestone Charts.
Elements of Network
• Events
• Activity
• Dummy
Event
An event is either start or completion stage of an
activity.
It doesn’t require time and resources.
Examples of Events:-
• Design completed
• Excavation completed
• Lathe installed
• Parts assembled
• Excavated Foundation (Not an event )
Representation of Event
It is represented by nodes in a network which may be-
Circular Square
Rectangular
Oval
NETWORK SYMBOLS
SYMBOL MEANING
Activity
Event
Activity A must be completed
before Activity B completed
Activities A & B can occur
concurrently, but both must be
completed before activity C can
begin
Activities A & B must be completed
before activities C & D can begin,
but C can begin independently of D
& vice versa
Types of Event
A particular event out of various events on the
network diagram may be specified as:
1. Tail Event
2. Head Event
3. Dual role event
• A tail event is the one which marks the beginning of an
activity.
• It has only outgoing arrows.
(A)Tail Event (B) Initial Event
(C) Tail Event
Activity Activity
Activity B
Activity A
Activity C
Tail Event
10 1
17
n
Final or
End Event
Activity B
Activity A
Activity C
Head Event
All activities have an ending i.e. again a specific
point of time and is marked by an event. Such
an event is known as head event.
10
Activity B
Head Event
Most of the events serve dual function, they are head
event to some activity and tail event other activity
All events except initial and final events are dual events
Activity B
Activity E
Dual Role Event
10
Activity C
Activity A
Activity D
Activity B
Successor Event
The events that follow another event are called successor event
Predecessor events
The events that occur before another event are called predecessor
event.
• Events 2,3,4 and 5 are successor events to
event 1
• Event 2,3 and 4 are intermediate successor
event to event 1
• Event 1,2,3 and 4 are predecessor event to 5
• Event 2,3 and 4 are intermediate
predecessor event to 5
An activity is the actual performance of a task.
It requires time and resources for its completion.
Examples:-
Excavate Trench
Mix Concrete
Prepare Specifications
Assemble parts
Preparing Budget
Design Completed (not an activity)
Activity
In a network diagram, activities are represented by simple
arrows, usually drawn from left to right. The length of arrow
does not neither represent the magnitude of work involved
nor the time required for its completion. It is not a vector
quantity.
Representation of Activity
2
11
12
3
Concrete
foundation
13
Fix Electric Fitting
Excavate
foundation
Fix Sanitary Fitting
Activity Predecessor Successor
A - C*,E
B - D*,E
C A* E*
D B* E*
E A,C*,B,D* --
Note * indicate predecessor or successor
• A dummy is a type of operation in the network which neither
requires any time nor any resources.
• It’s a device to identify a dependence among operations.
• It is represented by dashed arrow.
Dummy
A. A wait delivery of new
machine.
B. Install new machine.
C. Remove existing machine.
D. Dispose of existing machine
Dummies serve two purposes in a network
(a) Grammatical purpose :A dummy is used to prevent two
arrows having common beginning and end points. For
example, consider the arrows of activities A and B both
start from node 1 and end at node 2. Due to this an
inconvenience results when the network is used for
computations, i.e., uniqueness in the identification is lost.
This inconvenience frequently leads to mistakes.
Use of dummies
Ambiguous
Representation
Grammatically Clear
Representation
Illogical
Representation
Logical
Representation
(b) Logical purpose Dummies are also used to give logical clear
representation in a network having an activity common to two sets
of operations running parallel to each other. For example, consider
two activities and R having common end node. Activity Q has O and
P as successor activities, while activity R has P and N as successor
activities Shows the illogical representation of the activities, because
activity P cannot have dual identity. It should have unique identity.
Redundant Dummy

1 Element Of a Netwok Construction .pptx

  • 1.
  • 2.
    Project Management Tools andTechniques Project management tools and techniques assist project managers and their teams in various aspects of project management. 1. Bar chats and milestone charts 2. Network Diagram
  • 3.
    1. Bar Chartsand Milestone Charts  Gantt charts are "time" oriented.  Activities are graphically shown on a calendar time scale, used primarily for small projects.  Bars show an activities duration in its entirety, regardless of its dependency on other activities.  Effortless to construct, and are brief in format.
  • 4.
    Bar Charts Advantages 1. Itis very easy and simple to construct. 2. It is easy to understand. 3. Simplicity of updating. 4. It is very easy to show the progress of work and programme of work. 5. Easy to incorporate resource plan in terms of the plant schedule, material schedule and labour schedule required for the project.
  • 5.
    Bar Charts Disadvantages 1. Doesnot show relationship between the activities. 2. Does not give you the ability to visualize the exact progress of the project. (Eg:If one activity is behind or ahead of time what effect it will have on the overall project.) 3. Anticipate delays or problems soon enough to correct them. 4. Does not show detailed sequence of activities. 5. Does not show "critical activities". 6. Does not show precise effect of a delay or failure to complete an activity on time.
  • 6.
  • 7.
    Example : Theactivity breakdown for certain project Activity 2 and activity 3 can be done concurrently, and both must follow activity 1. Activity 2 must precede activity 4. Activity 5 cannot begin until both activities 2 and 3 are completed. Activity 6 can be started only after activities 4 and 5 are complete. Activity 7 is the last activity which can be started only after completion of activity 5. Prepare the bar chart for the project. Activity No. Duration (weeks) 1 1 2 2 3 4 4 3 5 1 6 2 7 4
  • 10.
    Milestone Charts Milestone chartis a modification over the original Gantt chart. Milestones are key events of a math activity represented by a bar: these are specific point in time which marks the completion of certain portion of the main activity. These points are those which can be easily identified over the main bar. We have already been that when a particular activity, represented by a bar on a bar-chart.
  • 12.
  • 13.
    Activities “Topo” project site Laygravel Order gravel Clear roadway Prefabricate forms Layout pad batterboards Pour concrete Check pad elevations Remove forms Establish road grades Set road alignments Place concrete forms Clear pad site Create project drawings Excavate pad footings Cure concrete Check Road grades Perform “As- built” Rough activities listing
  • 14.
    Sequencing Activities After youhave developed your rough activity list in no specific order, you must now put the activities into a "logical" sequence to be performed. The finished activity list is broken down as follows:  Activity Number Column  Activity Column  "Immediately Proceeded By" (IPB) Column
  • 15.
    There are fivetypes of activities associated with the development of a finished activities list. Keeping these activities in mind will help you in your logical thinking to develop the activity list on paper.  Starting activities. (beginning activity)  Preceding activities. (previous activity)  Concurring activities. (occurring at the same time)  Succeeding activities. (following activity)  Lagging activities. (slow or lingering activities) Types of Activities
  • 17.
    Question 1 -- Represent on GANTT Chart the Following Project, The Activities and their Durations being as indicated. (A) CONDUCTING AN EXAMINATION No. ACTIVITY DURATION 1 Answer Questionaire 1 DAY 2 Print Question Paper 2 DAYS 3 Design Questionnaire 7 DAYS 4 Declare the result 1 DAY 5 Distribute to various centers 4 DAYS 6 Collect Answer Books at main office 2 DAYS 7 Allot the marks and grades 1 DAY 8 Check the answer sheets 7 DAYS
  • 18.
    Question 2 -The Following Project is to be represented by a bar chart. The duration for each activity is in days. These are actual work days. The project commences on Wednesday, November 15, with five work day a week. Draw the bar chart with the horizontal scale denoting calendar dates. No. ACTIVITY DURATION 1 Activity 1 8 days 2 Activity 2 4 days 3 Activity 3 7 days 4 Activity 4 9 days 5 Activity 5 3 days 6 Activity 6 3 days 7 Activity 7 14 days 8 Activity 8 17 days
  • 19.
    Question 2 –Continues ……….  Activities 1 & 2 can occur concurrently.  Activity 3 can take place after activity 2 is completed.  Activities 4, 6 and 3 can occur concurrently.  Activity 8 can start 4 days after the commencement of activity 6.  Activity 7 should follow activity 5.  Activity 5 can begin concurrently with activity 8 25/7/2 016 1 9
  • 20.
    Question 3- Roof Structure Thefollowing seven tasks are required for the erection of a building roof structure. Some of the tasks can be completed simultaneously; the overhang with sofit can be constructed while the deck is being installed. 1 Place & secure trusses, 2 days 2 Install roof deck, 7 days 3 Apply vapor barrier, 2 days 4 Apply roof cladding, 2 days 5 Construct roof overhang, 4 days 6 Install soffits, 4 days 7 Apply flashing, 6 days
  • 21.
    2. Network Methods Thenetwork technique is a major advance in management science, The technique is based on the basic characteristics of all projects, that all work must be done in well-defined steps. For example, for completing a foundation, the various steps are:) layout, digging, placing side board and concreting. The network technique exploits this characteristics by representing the steps of the project objective graphically in the form of a network or arrow diagram. It would be difficult to find in the history of management methods any technique which has received such widespread attention as that accorded to network methods for planning, scheduling and controlling Following two major network system PERT CPM
  • 22.
    NETWORK TECHNIQUES PERT CPM -ProgramEvaluation and Review Technique - developed by the US Navy with Booz Hamilton Lockheed - on the Polaris Missile/Submarine program 1958 Critical Path Method Developed by El Dupont for Chemical Plant Shutdown Project- about same time as PERT Both use same calculations, almost similar Main difference is probabilistic and deterministic in time estimation Gantt Chart also used in scheduling
  • 23.
    Milestone chart vs PERTnetwork • Milestone chart visually shows the duration of Tasks whereas a PERT chart visually shows the sequence dependencies between tasks. • Milestone visually shows the Time overlap of Tasks whereas a Network does not show time overlap but does show which tasks could be done in parallel. • Most Project Managers find PERT very helpful for scheduling, monitoring and controlling Projects. • PERT is recommended for Large Projects with high inter-task dependencies and the milestone chart for simpler Projects. Most Project Management Case Tools nowadays (eg. MS-Project ) allow the best feature of PERT to be incorporated into milestone Charts.
  • 24.
    Elements of Network •Events • Activity • Dummy
  • 25.
    Event An event iseither start or completion stage of an activity. It doesn’t require time and resources. Examples of Events:- • Design completed • Excavation completed • Lathe installed • Parts assembled • Excavated Foundation (Not an event )
  • 26.
    Representation of Event Itis represented by nodes in a network which may be- Circular Square Rectangular Oval
  • 27.
    NETWORK SYMBOLS SYMBOL MEANING Activity Event ActivityA must be completed before Activity B completed Activities A & B can occur concurrently, but both must be completed before activity C can begin Activities A & B must be completed before activities C & D can begin, but C can begin independently of D & vice versa
  • 28.
    Types of Event Aparticular event out of various events on the network diagram may be specified as: 1. Tail Event 2. Head Event 3. Dual role event
  • 29.
    • A tailevent is the one which marks the beginning of an activity. • It has only outgoing arrows. (A)Tail Event (B) Initial Event (C) Tail Event Activity Activity Activity B Activity A Activity C Tail Event 10 1 17
  • 30.
    n Final or End Event ActivityB Activity A Activity C Head Event All activities have an ending i.e. again a specific point of time and is marked by an event. Such an event is known as head event. 10 Activity B Head Event
  • 31.
    Most of theevents serve dual function, they are head event to some activity and tail event other activity All events except initial and final events are dual events Activity B Activity E Dual Role Event 10 Activity C Activity A Activity D Activity B
  • 32.
    Successor Event The eventsthat follow another event are called successor event Predecessor events The events that occur before another event are called predecessor event. • Events 2,3,4 and 5 are successor events to event 1 • Event 2,3 and 4 are intermediate successor event to event 1 • Event 1,2,3 and 4 are predecessor event to 5 • Event 2,3 and 4 are intermediate predecessor event to 5
  • 33.
    An activity isthe actual performance of a task. It requires time and resources for its completion. Examples:- Excavate Trench Mix Concrete Prepare Specifications Assemble parts Preparing Budget Design Completed (not an activity) Activity
  • 34.
    In a networkdiagram, activities are represented by simple arrows, usually drawn from left to right. The length of arrow does not neither represent the magnitude of work involved nor the time required for its completion. It is not a vector quantity. Representation of Activity 2 11 12 3 Concrete foundation 13 Fix Electric Fitting Excavate foundation Fix Sanitary Fitting
  • 35.
    Activity Predecessor Successor A- C*,E B - D*,E C A* E* D B* E* E A,C*,B,D* -- Note * indicate predecessor or successor
  • 36.
    • A dummyis a type of operation in the network which neither requires any time nor any resources. • It’s a device to identify a dependence among operations. • It is represented by dashed arrow. Dummy A. A wait delivery of new machine. B. Install new machine. C. Remove existing machine. D. Dispose of existing machine
  • 37.
    Dummies serve twopurposes in a network (a) Grammatical purpose :A dummy is used to prevent two arrows having common beginning and end points. For example, consider the arrows of activities A and B both start from node 1 and end at node 2. Due to this an inconvenience results when the network is used for computations, i.e., uniqueness in the identification is lost. This inconvenience frequently leads to mistakes. Use of dummies Ambiguous Representation Grammatically Clear Representation
  • 38.
    Illogical Representation Logical Representation (b) Logical purposeDummies are also used to give logical clear representation in a network having an activity common to two sets of operations running parallel to each other. For example, consider two activities and R having common end node. Activity Q has O and P as successor activities, while activity R has P and N as successor activities Shows the illogical representation of the activities, because activity P cannot have dual identity. It should have unique identity.
  • 39.