SlideShare a Scribd company logo
1 of 23
0
Running Head: MODULE 04 COURSE PROJECT
1
MODULE 04 COURSE PROJECT
Power Struggle
Rasmussen College
Select and support whether Michelle should take an integrative
or distributive approach to the negotiation. Be sure to fully
define both and argue the pros and cons of each prior to making
a selection.
Negotiation is almost inevitable to our daily lives. We all
engage in a form of negotiation once in a while. There are two
major methods of negotiation – the interactive and the
distributive approaches to negotiation. When it comes to the
latter, there is always a limit to what is being divided, shared,
or distributed among people. On the other hand, interactive
negotiation entails a twofold process. This is where after the
negotiations both parties walk away feeling that they have made
an accomplishment. The two methods are broadly taught in
schools as they are vital to ensuring a successful negotiation,
especially in business.
The term distributive can be defined as the giving out of
things. As such, the amount being distributed is fixed. Some
people call it the ‘fixed pie ‘method. Both parties negotiating
want to get as much as possible. This type of negotiation
involves people who have not had an interactive relationship
before and are less likely to have it in future. A good example is
when purchasing a product in the market and you bargain about
the price. In this type of negotiation, we hardly care about how
our opposing parties perceive of us. The interests are usually
self-serving to both parties ("Types of Negotiations |
Negotiation Experts", 2016).
There are always tips that one should follow in the
distributive negotiation process. Firstly, you ought to play your
cards close to your chest by not giving too much information to
your opposite party. This works as an advantage to you and a
disadvantage to them. Secondly, it is always advisable for you
to extract as much as possible information from the other party.
Moreover, it is always an advantage to you when you make
them make the first offer. Nonetheless, when it is up to you to
make the offer being realistic is vital.
Interactive negotiations involve joining of effort between two
parties with the aim of achieving something that has value.
Unlike in the distributive approach, this one entails a lot of
trusts. There are many benefits gained from this approach in
ensuring good relations between the parties. The process creates
a win - win scenario for both that goes along in creating long
term relationship for mutual gain. In my opinion, this is the
approach that Michelle should take in negotiating with Nikki for
a better shift.
The method has some several ideal basics. It has multiple
issues of discussions unlike in a distributive approach. Also, the
spirit sharing and selflessness are strongly expressed. Often the
parties engage in sharing of as much information as possible
with the aim of understanding each other's interests. Ultimately,
there is problem-solving. This is simply finding the solutions to
each other problems. After that there is the maintenance of a
strong relationship between the parties that offer security –
bridge building ("Types of Negotiations | Negotiation Experts",
2016).
Once an approach is selected, the next step is to formulate a
plan. A solid foundation to a good negotiation involves creating
an effective plan. For this section, create a plan for Michelle in
which you address the following points:
I would advise Michelle to take an interactive approach in
negotiating for a better shift with Nikki. The issues here are that
Michelle is disappointed. The reason being that her shift doesn’t
favor her. What she needs to be done is allocating her another
shift that would be favorable to her. Nikki here is assumed to be
Michelle's employer. With that in mind, she needs to get the
best out if her employees – her interest. With the shift allocated
to Michelle, Nikki seems to be getting just that. However,
Michelle is disgruntled and unhappy with it. Her interest is
getting a suitable shift for her.
Keeping all that in mind, Michelle should approach Nikki
by telling her reasonable reasons why the shift doesn’t auger
well with her. The reasons should picture an image where
Michelle doesn’t work maximize her abilities to work for her
employer solely due to her shift. The resistance point in such a
point would be that changing the shift for Michelle would
disorganize the whole organization employee structure in terms
of allocation of duties. Another point is that no employee might
be willing to swap shifts with Michelle.
There are not too many alternatives for Michelle. For
instance, if it really kills her to work during that shift and no
one is ready to swap for her she can just quit working.
However, that would lead to a lose – lose situation for both
parties. A better alternative would to try and convince a fellow
colleague to exchange shifts for her. I believe this would be the
best alternative. If this doesn’t materialize then she ought to
just put up with her shift until the next reorganization of
employee’s shifts is done.
In conclusion, the negotiation ought to be done formally.
Probably in Nikki’s office, the agenda being Michelle’s shift.
Michelle need be positive at all times and maintain a good
negotiating tone. Nikki on the other hand, should listen keenly
to her employee’s issue and respond to them in the best way
possible. If this is followed then not only is an amicable
solution is guaranteed for both parties but also the relationship
between them strengthened.
References
Types of Negotiations | Negotiation Experts. (2016).
Negotiations.com. Retrieved 12 September 2016, from
http://www.negotiations.com/articles/negotiation-types/
Project Management Case
You are working for a large, apparel design and manufacturing
company, Trillo Apparel Company (TAC), headquartered in
Albuquerque, New Mexico. TAC employs around 3000 people
and has remained profitable through tough economic times. The
operations are divided into 4 districts; District 1 – North,
District 2 – South, District 3 – West and District 4 – East. The
company sets strategic goals at the beginning of each year and
operates with priorities to reach those goals.Trillo Apparel
Company Current Year Priorities
· Increase Sales and Distribution in the East
· Improve Product Quality
· Improve Production in District 4
· Increase Brand Recognition
· Increase RevenuesCompany Details
Company Name: Trillo Apparel Company (TAC)
Company Type: Apparel design and production
Company Size: 3000 employees
Position
# Employees
Owner/CEO
1
Vice President
4
Chief Operating Officer
1
Chief Financial Officer
1
Chief Information Officer
1
IT Department
38
District Manager
4
Sales Team
30
Accountant
12
Administrative Assistant
7
Order Fullfilment
45
Customer Service
57
Designer
24
Project Manager
10
Maintenance
25
Operations
2500
Shipping Department
240
Total Employees
3000
Products: Various Apparel
Corporate Location: Albuquerque, New MexicoTAC
Organization Chart
District 4 Production Warehouse Move Project Details
The business has expanded considerably over the past few years
and District 4 in the East has outgrown its current production
facility. Because of this growth the executives want to expand
the current facility, moving the whole facility 10 miles away.
The location selected has enough room for the production and
the shipping department. However, the current warehouse needs
some renovation to accommodate the district’s operational
needs.
The VP of Operations estimates the production and shipping
warehouse move for District 4 will provide room required to
generate the additional $1 million/year product revenues to
meet the current demand due to the expanded production
capacity. Daily production generates $50,000 revenue so a week
of downtime will cost $250,000 in lost revenues.
The move must be completed in 4 months.
Mileage between the old and new facilities is 10 miles.
Bids have been received from contractors to build out the new
office space and production floor and have signed contracts for
work as follows:
Activity
Company Providing Services
Total Contract
Supplies
Time Needed
Pack, move and unpack production equipment
City Equipment Movers
$150,000
n/a
5 Days
Move non-production equipment and materials
Express Moving Company
$125,000
n/a
5 Days
Framing
East Side Framing & Drywall
$121,000
$125,000
15 Days
Electrical
Sparks Electrical
$18,000
$12,000
10 Days
Plumbing
Waterworks Plumbing
$15,000
$13,000
10 Days
Drywall
East Side Framing & Drywall
$121,000
$18,000
15 Days
Finish Work
Woodcraft Carpentry
$115,000
$15,000
15 Days
Build work benches for production floor
Student Workers Carpentry
$112,000
$110,000
15 Days
Production workdays are Monday through Saturday. The actual
move must be completed in 5 days for as little disruption to
production activities as possible. All contractors are on other
projects but have been booked in advance. The contractors will
gain the necessary permits and schedule city and county
inspections but these tasks need to be identified separately due
to the length of time it can take. Permitting and inspections can
take from one to three weeks, depending upon schedule and the
flexibility of the inspector. The new warehouse is empty and
can be accessed immediately. Framing cannot start until the
permits are received. Electrical and plumbing can begin as soon
as the framing is finished. Drywall cannot start until the
electrical and plumbing inspections are complete. After the
drywall is completed, final inspections will be completed by the
county and city. After both the county and city have passed the
new construction, finish work can begin. Building the product
floor work benches can occur at any time before the move
occurs.
Chief Executive
Officer
Chief Operating
Officer
Chief Financial
Officer
VP Sales &
Marketing
Chief Information
Officer
Executive
Assistant
VP
Operations
VP Customer
Service
Inbound Call
Manager
Outbound Call
Manager
Outbound Call
Team (20)
Inbound Call
Team (35)
IT
Manager
IT Staff
(37)
Sales Team
(30)
Accountants
(12)
District2
Manager
District 3
Manager
District1
Manager
District 4
Manager
D1 Operations
(500)
D1 Operations
(650)
D3 Operations
(450)
D4 Operations
(900)
Administrative
Assistant
Administrative
Assistant
Administrative
Assistant
Administrative
Assistant
Administrative
Assistant
Administrative
Assistant
Order Fulfillment
(45)
Shipping
(50)
Shipping
(50)
Shipping
(50)
Shipping
(90)
Maintenance
(5)
Maintenance
(5)
Maintenance
(5)
Maintenance
(10)
Project Managers
(10)
VP
Design
Design Team
(24)
Trillo Apparel Company
Chief Executive
Officer
Chief Operating
Officer �
Chief Financial
Officer�
VP Sales &
Marketing �
Executive
Assistant�
Chief Information
Officer�
VP
Operations�
VP Customer
Service �
Inbound Call
Manager�
Outbound Call
Team (20)�
Outbound Call
Manager�
Inbound Call
Team (35)�
IT
Manager�
IT Staff
(37)�
Sales Team
(30)
Accountants
(12)�
District2
Manager�
District 3
Manager�
District1
Manager�
District 4
Manager�
D1 Operations
(500)�
D1 Operations
(650)�
D3 Operations
(450)�
D4 Operations
(900)�
Administrative
Assistant �
Administrative
Assistant �
Administrative
Assistant �
Administrative
Assistant �
Administrative
Assistant �
Administrative
Assistant�
Shipping
(50)�
Order Fulfillment
(45)�
Shipping
(50)�
Shipping
(50)�
Shipping
(90)�
Maintenance
(5)�
Maintenance
(5)�
Maintenance
(5)�
Maintenance
(10)�
Project Managers
(10)�
VP
Design�
Design Team
(24)�
Trillo Apparel Company
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11
2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager and A
6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11
7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project
Manager and W
9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11
12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11
Mon 1/3/11 Project Manager
15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11
Mon 1/3/11
16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and E
17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and S
18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and S
21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
Sparks Electrical PM
23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11
26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11
East Side Framing & D
27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11
28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side
Framing & D
30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11
33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Sparks Electrical PM
34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks
Electrical
35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11
38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed
1/5/11 Waterworks Plumbing
39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
Project Manager
Project Manager
Project Manager
Project Manager and Attend
Project Manager
Project Manager and
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager and East S
Project Manager and Spark
Project Manager and Water
Project Manager and Wood
Project Manager and Stude
Sparks Electrical P
Waterworks Plumbi
East Side Framing
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Sparks Electrical PM
Sparks Electrical
City & County
Project Manager
Waterworks Plumbing PM
Waterworks Plumbi
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: District4Move.mpp
Date: Sat 1/8/11
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City
& County
41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11
43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East
Side Framing & D
45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11
48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Woodcraft Carpentry P
49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11
Woodcraft Carpentry
50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11
53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue
1/4/11 Student Workers Mana
54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11
Student Workers
55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11
58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
61 15 Move 3 days Mon 1/3/11 Wed 1/5/11
62 15.1 Move production equipment 3 days Mon 1/3/11 Wed
1/5/11 Express Moving Comp
63 15.2 Move non-production equipment 3 days Mon 1/3/11
Wed 1/5/11 Express Moving Comp
64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11
66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11
70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project
Manager
71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
City & County
Project Manager
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Woodcraft Carpentry PM
Woodcraft Car
City & County
Project Manager
Student Workers Manager
Student Worke
Project Manager
Project Manager
City Equipment Movers PM
City Equipment Movers
Project Manager
Express Moving Company
Express Moving Company
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: District4Move.mpp
Date: Sat 1/8/11
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
0Running Head MODULE 04 COURSE PROJECT1MODULE 04 COURSE P.docx

More Related Content

Similar to 0Running Head MODULE 04 COURSE PROJECT1MODULE 04 COURSE P.docx

How to sharpen your presentation skills (from the Easter edition of The Barri...
How to sharpen your presentation skills (from the Easter edition of The Barri...How to sharpen your presentation skills (from the Easter edition of The Barri...
How to sharpen your presentation skills (from the Easter edition of The Barri...Douglas McPherson
 
Mastering the art of collaboration
Mastering the art of collaborationMastering the art of collaboration
Mastering the art of collaborationAndro Janiashvili
 
Managing Conflict in the Workplace
Managing Conflict in the WorkplaceManaging Conflict in the Workplace
Managing Conflict in the WorkplaceTammy Torrez
 
Design Thinking and Small Business Insurance (SMB)
Design Thinking and Small Business Insurance (SMB)Design Thinking and Small Business Insurance (SMB)
Design Thinking and Small Business Insurance (SMB)Josh Levine
 
Martin Letter.Consultants Jm[7]
Martin Letter.Consultants Jm[7]Martin Letter.Consultants Jm[7]
Martin Letter.Consultants Jm[7]mgifundraising
 
Turning Design into Strategy
Turning Design into StrategyTurning Design into Strategy
Turning Design into Strategymajomiselem
 
Workplace conflict - how organisations do (or don't) deal with it
Workplace conflict - how organisations do (or don't) deal with it Workplace conflict - how organisations do (or don't) deal with it
Workplace conflict - how organisations do (or don't) deal with it David Liddle
 
Assignment 1 - Certification in Dispute Management
Assignment 1 - Certification in Dispute ManagementAssignment 1 - Certification in Dispute Management
Assignment 1 - Certification in Dispute ManagementJyotpreet Kaur
 
project management.pptx
project management.pptxproject management.pptx
project management.pptxshanzaashraf5
 
Becoming a Champion for Change
Becoming a Champion for ChangeBecoming a Champion for Change
Becoming a Champion for ChangeTalMix
 
Presentation.pdf
Presentation.pdfPresentation.pdf
Presentation.pdfHaniMarina1
 
requierments 1- total 12 pages 2- Last page (page 12) res.docx
requierments  1- total 12 pages 2- Last page (page 12)  res.docxrequierments  1- total 12 pages 2- Last page (page 12)  res.docx
requierments 1- total 12 pages 2- Last page (page 12) res.docxkellet1
 
New Hire Training Manual
New Hire Training ManualNew Hire Training Manual
New Hire Training ManualBrett Chase
 

Similar to 0Running Head MODULE 04 COURSE PROJECT1MODULE 04 COURSE P.docx (18)

How to sharpen your presentation skills (from the Easter edition of The Barri...
How to sharpen your presentation skills (from the Easter edition of The Barri...How to sharpen your presentation skills (from the Easter edition of The Barri...
How to sharpen your presentation skills (from the Easter edition of The Barri...
 
Mastering the art of collaboration
Mastering the art of collaborationMastering the art of collaboration
Mastering the art of collaboration
 
Managing Conflict in the Workplace
Managing Conflict in the WorkplaceManaging Conflict in the Workplace
Managing Conflict in the Workplace
 
Design Thinking and Small Business Insurance (SMB)
Design Thinking and Small Business Insurance (SMB)Design Thinking and Small Business Insurance (SMB)
Design Thinking and Small Business Insurance (SMB)
 
Workplace Conflict Resolution
Workplace Conflict ResolutionWorkplace Conflict Resolution
Workplace Conflict Resolution
 
Martin Letter.Consultants Jm[7]
Martin Letter.Consultants Jm[7]Martin Letter.Consultants Jm[7]
Martin Letter.Consultants Jm[7]
 
Negotiation Skills.
Negotiation Skills.Negotiation Skills.
Negotiation Skills.
 
The 5 Myths of Working with Advertising Agencies
The 5 Myths of Working with Advertising AgenciesThe 5 Myths of Working with Advertising Agencies
The 5 Myths of Working with Advertising Agencies
 
Turning Design into Strategy
Turning Design into StrategyTurning Design into Strategy
Turning Design into Strategy
 
Workplace conflict - how organisations do (or don't) deal with it
Workplace conflict - how organisations do (or don't) deal with it Workplace conflict - how organisations do (or don't) deal with it
Workplace conflict - how organisations do (or don't) deal with it
 
Assignment 1 - Certification in Dispute Management
Assignment 1 - Certification in Dispute ManagementAssignment 1 - Certification in Dispute Management
Assignment 1 - Certification in Dispute Management
 
project management.pptx
project management.pptxproject management.pptx
project management.pptx
 
Becoming a Champion for Change
Becoming a Champion for ChangeBecoming a Champion for Change
Becoming a Champion for Change
 
Presentation.pdf
Presentation.pdfPresentation.pdf
Presentation.pdf
 
requierments 1- total 12 pages 2- Last page (page 12) res.docx
requierments  1- total 12 pages 2- Last page (page 12)  res.docxrequierments  1- total 12 pages 2- Last page (page 12)  res.docx
requierments 1- total 12 pages 2- Last page (page 12) res.docx
 
Change management
Change managementChange management
Change management
 
Branding Creative Agencies
Branding Creative AgenciesBranding Creative Agencies
Branding Creative Agencies
 
New Hire Training Manual
New Hire Training ManualNew Hire Training Manual
New Hire Training Manual
 

More from honey725342

NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docx
NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docxNRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docx
NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docxhoney725342
 
Now the Earth has had wide variations in atmospheric CO2-level throu.docx
Now the Earth has had wide variations in atmospheric CO2-level throu.docxNow the Earth has had wide variations in atmospheric CO2-level throu.docx
Now the Earth has had wide variations in atmospheric CO2-level throu.docxhoney725342
 
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docx
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docxNR224 Fundamentals SkillsTopic Safety Goals BOOK P.docx
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docxhoney725342
 
Nurse Education Today 87 (2020) 104348Contents lists avail.docx
Nurse Education Today 87 (2020) 104348Contents lists avail.docxNurse Education Today 87 (2020) 104348Contents lists avail.docx
Nurse Education Today 87 (2020) 104348Contents lists avail.docxhoney725342
 
Now that you’ve seen all of the elements contributing to the Devil’s.docx
Now that you’ve seen all of the elements contributing to the Devil’s.docxNow that you’ve seen all of the elements contributing to the Devil’s.docx
Now that you’ve seen all of the elements contributing to the Devil’s.docxhoney725342
 
NR360 We Can But Dare We.docx Revised 5 ‐ 9 .docx
NR360   We   Can   But   Dare   We.docx   Revised   5 ‐ 9 .docxNR360   We   Can   But   Dare   We.docx   Revised   5 ‐ 9 .docx
NR360 We Can But Dare We.docx Revised 5 ‐ 9 .docxhoney725342
 
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docx
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docxNurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docx
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docxhoney725342
 
NURS 6002 Foundations of Graduate StudyAcademic and P.docx
NURS 6002 Foundations of Graduate StudyAcademic and P.docxNURS 6002 Foundations of Graduate StudyAcademic and P.docx
NURS 6002 Foundations of Graduate StudyAcademic and P.docxhoney725342
 
Nurse workforce shortage are predicted to get worse as baby boomers .docx
Nurse workforce shortage are predicted to get worse as baby boomers .docxNurse workforce shortage are predicted to get worse as baby boomers .docx
Nurse workforce shortage are predicted to get worse as baby boomers .docxhoney725342
 
Now, for the exam itself. Below are 4 questions. You need to answer .docx
Now, for the exam itself. Below are 4 questions. You need to answer .docxNow, for the exam itself. Below are 4 questions. You need to answer .docx
Now, for the exam itself. Below are 4 questions. You need to answer .docxhoney725342
 
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docx
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docxNur-501-AP4- Philosophical and Theoretical Evidence-Based research.docx
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docxhoney725342
 
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docx
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docxNU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docx
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docxhoney725342
 
Nurse Working in the CommunityDescribe the community nurses.docx
Nurse Working in the CommunityDescribe the community nurses.docxNurse Working in the CommunityDescribe the community nurses.docx
Nurse Working in the CommunityDescribe the community nurses.docxhoney725342
 
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docx
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docxnursing diagnosis1. Decreased Cardiac Output  related to Alter.docx
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docxhoney725342
 
Nursing Documentation Is it valuable Discuss the value of nursin.docx
Nursing Documentation Is it valuable Discuss the value of nursin.docxNursing Documentation Is it valuable Discuss the value of nursin.docx
Nursing Documentation Is it valuable Discuss the value of nursin.docxhoney725342
 
NR631 Concluding Graduate Experience - Scope Project Managemen.docx
NR631 Concluding Graduate Experience - Scope  Project Managemen.docxNR631 Concluding Graduate Experience - Scope  Project Managemen.docx
NR631 Concluding Graduate Experience - Scope Project Managemen.docxhoney725342
 
Number 11. Describe at least five populations who are vulner.docx
Number 11. Describe at least five populations who are vulner.docxNumber 11. Describe at least five populations who are vulner.docx
Number 11. Describe at least five populations who are vulner.docxhoney725342
 
ntertainment, the media, and sometimes public leaders can perpetuate.docx
ntertainment, the media, and sometimes public leaders can perpetuate.docxntertainment, the media, and sometimes public leaders can perpetuate.docx
ntertainment, the media, and sometimes public leaders can perpetuate.docxhoney725342
 
Now that you have  completed Lesson 23 & 24 and have thought a.docx
Now that you have  completed Lesson 23 & 24 and have thought a.docxNow that you have  completed Lesson 23 & 24 and have thought a.docx
Now that you have  completed Lesson 23 & 24 and have thought a.docxhoney725342
 
nothing wrong with the paper, my professor just wants it to be in an.docx
nothing wrong with the paper, my professor just wants it to be in an.docxnothing wrong with the paper, my professor just wants it to be in an.docx
nothing wrong with the paper, my professor just wants it to be in an.docxhoney725342
 

More from honey725342 (20)

NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docx
NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docxNRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docx
NRS-493 Individual Success PlanREQUIRED PRACTICE HOURS 100 Direct.docx
 
Now the Earth has had wide variations in atmospheric CO2-level throu.docx
Now the Earth has had wide variations in atmospheric CO2-level throu.docxNow the Earth has had wide variations in atmospheric CO2-level throu.docx
Now the Earth has had wide variations in atmospheric CO2-level throu.docx
 
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docx
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docxNR224 Fundamentals SkillsTopic Safety Goals BOOK P.docx
NR224 Fundamentals SkillsTopic Safety Goals BOOK P.docx
 
Nurse Education Today 87 (2020) 104348Contents lists avail.docx
Nurse Education Today 87 (2020) 104348Contents lists avail.docxNurse Education Today 87 (2020) 104348Contents lists avail.docx
Nurse Education Today 87 (2020) 104348Contents lists avail.docx
 
Now that you’ve seen all of the elements contributing to the Devil’s.docx
Now that you’ve seen all of the elements contributing to the Devil’s.docxNow that you’ve seen all of the elements contributing to the Devil’s.docx
Now that you’ve seen all of the elements contributing to the Devil’s.docx
 
NR360 We Can But Dare We.docx Revised 5 ‐ 9 .docx
NR360   We   Can   But   Dare   We.docx   Revised   5 ‐ 9 .docxNR360   We   Can   But   Dare   We.docx   Revised   5 ‐ 9 .docx
NR360 We Can But Dare We.docx Revised 5 ‐ 9 .docx
 
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docx
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docxNurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docx
Nurse Practitioner Diagnosis- Chest Pain.SOAPS-Subjective.docx
 
NURS 6002 Foundations of Graduate StudyAcademic and P.docx
NURS 6002 Foundations of Graduate StudyAcademic and P.docxNURS 6002 Foundations of Graduate StudyAcademic and P.docx
NURS 6002 Foundations of Graduate StudyAcademic and P.docx
 
Nurse workforce shortage are predicted to get worse as baby boomers .docx
Nurse workforce shortage are predicted to get worse as baby boomers .docxNurse workforce shortage are predicted to get worse as baby boomers .docx
Nurse workforce shortage are predicted to get worse as baby boomers .docx
 
Now, for the exam itself. Below are 4 questions. You need to answer .docx
Now, for the exam itself. Below are 4 questions. You need to answer .docxNow, for the exam itself. Below are 4 questions. You need to answer .docx
Now, for the exam itself. Below are 4 questions. You need to answer .docx
 
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docx
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docxNur-501-AP4- Philosophical and Theoretical Evidence-Based research.docx
Nur-501-AP4- Philosophical and Theoretical Evidence-Based research.docx
 
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docx
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docxNU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docx
NU32CH19-Foltz ARI 9 July 2012 1945Population-Level Inter.docx
 
Nurse Working in the CommunityDescribe the community nurses.docx
Nurse Working in the CommunityDescribe the community nurses.docxNurse Working in the CommunityDescribe the community nurses.docx
Nurse Working in the CommunityDescribe the community nurses.docx
 
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docx
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docxnursing diagnosis1. Decreased Cardiac Output  related to Alter.docx
nursing diagnosis1. Decreased Cardiac Output  related to Alter.docx
 
Nursing Documentation Is it valuable Discuss the value of nursin.docx
Nursing Documentation Is it valuable Discuss the value of nursin.docxNursing Documentation Is it valuable Discuss the value of nursin.docx
Nursing Documentation Is it valuable Discuss the value of nursin.docx
 
NR631 Concluding Graduate Experience - Scope Project Managemen.docx
NR631 Concluding Graduate Experience - Scope  Project Managemen.docxNR631 Concluding Graduate Experience - Scope  Project Managemen.docx
NR631 Concluding Graduate Experience - Scope Project Managemen.docx
 
Number 11. Describe at least five populations who are vulner.docx
Number 11. Describe at least five populations who are vulner.docxNumber 11. Describe at least five populations who are vulner.docx
Number 11. Describe at least five populations who are vulner.docx
 
ntertainment, the media, and sometimes public leaders can perpetuate.docx
ntertainment, the media, and sometimes public leaders can perpetuate.docxntertainment, the media, and sometimes public leaders can perpetuate.docx
ntertainment, the media, and sometimes public leaders can perpetuate.docx
 
Now that you have  completed Lesson 23 & 24 and have thought a.docx
Now that you have  completed Lesson 23 & 24 and have thought a.docxNow that you have  completed Lesson 23 & 24 and have thought a.docx
Now that you have  completed Lesson 23 & 24 and have thought a.docx
 
nothing wrong with the paper, my professor just wants it to be in an.docx
nothing wrong with the paper, my professor just wants it to be in an.docxnothing wrong with the paper, my professor just wants it to be in an.docx
nothing wrong with the paper, my professor just wants it to be in an.docx
 

Recently uploaded

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 

Recently uploaded (20)

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 

0Running Head MODULE 04 COURSE PROJECT1MODULE 04 COURSE P.docx

  • 1. 0 Running Head: MODULE 04 COURSE PROJECT 1 MODULE 04 COURSE PROJECT Power Struggle Rasmussen College Select and support whether Michelle should take an integrative or distributive approach to the negotiation. Be sure to fully define both and argue the pros and cons of each prior to making a selection. Negotiation is almost inevitable to our daily lives. We all engage in a form of negotiation once in a while. There are two major methods of negotiation – the interactive and the distributive approaches to negotiation. When it comes to the latter, there is always a limit to what is being divided, shared, or distributed among people. On the other hand, interactive negotiation entails a twofold process. This is where after the negotiations both parties walk away feeling that they have made an accomplishment. The two methods are broadly taught in schools as they are vital to ensuring a successful negotiation, especially in business. The term distributive can be defined as the giving out of things. As such, the amount being distributed is fixed. Some people call it the ‘fixed pie ‘method. Both parties negotiating want to get as much as possible. This type of negotiation involves people who have not had an interactive relationship before and are less likely to have it in future. A good example is when purchasing a product in the market and you bargain about
  • 2. the price. In this type of negotiation, we hardly care about how our opposing parties perceive of us. The interests are usually self-serving to both parties ("Types of Negotiations | Negotiation Experts", 2016). There are always tips that one should follow in the distributive negotiation process. Firstly, you ought to play your cards close to your chest by not giving too much information to your opposite party. This works as an advantage to you and a disadvantage to them. Secondly, it is always advisable for you to extract as much as possible information from the other party. Moreover, it is always an advantage to you when you make them make the first offer. Nonetheless, when it is up to you to make the offer being realistic is vital. Interactive negotiations involve joining of effort between two parties with the aim of achieving something that has value. Unlike in the distributive approach, this one entails a lot of trusts. There are many benefits gained from this approach in ensuring good relations between the parties. The process creates a win - win scenario for both that goes along in creating long term relationship for mutual gain. In my opinion, this is the approach that Michelle should take in negotiating with Nikki for a better shift. The method has some several ideal basics. It has multiple issues of discussions unlike in a distributive approach. Also, the spirit sharing and selflessness are strongly expressed. Often the parties engage in sharing of as much information as possible with the aim of understanding each other's interests. Ultimately, there is problem-solving. This is simply finding the solutions to each other problems. After that there is the maintenance of a strong relationship between the parties that offer security – bridge building ("Types of Negotiations | Negotiation Experts", 2016). Once an approach is selected, the next step is to formulate a plan. A solid foundation to a good negotiation involves creating an effective plan. For this section, create a plan for Michelle in which you address the following points:
  • 3. I would advise Michelle to take an interactive approach in negotiating for a better shift with Nikki. The issues here are that Michelle is disappointed. The reason being that her shift doesn’t favor her. What she needs to be done is allocating her another shift that would be favorable to her. Nikki here is assumed to be Michelle's employer. With that in mind, she needs to get the best out if her employees – her interest. With the shift allocated to Michelle, Nikki seems to be getting just that. However, Michelle is disgruntled and unhappy with it. Her interest is getting a suitable shift for her. Keeping all that in mind, Michelle should approach Nikki by telling her reasonable reasons why the shift doesn’t auger well with her. The reasons should picture an image where Michelle doesn’t work maximize her abilities to work for her employer solely due to her shift. The resistance point in such a point would be that changing the shift for Michelle would disorganize the whole organization employee structure in terms of allocation of duties. Another point is that no employee might be willing to swap shifts with Michelle. There are not too many alternatives for Michelle. For instance, if it really kills her to work during that shift and no one is ready to swap for her she can just quit working. However, that would lead to a lose – lose situation for both parties. A better alternative would to try and convince a fellow colleague to exchange shifts for her. I believe this would be the best alternative. If this doesn’t materialize then she ought to just put up with her shift until the next reorganization of employee’s shifts is done. In conclusion, the negotiation ought to be done formally. Probably in Nikki’s office, the agenda being Michelle’s shift. Michelle need be positive at all times and maintain a good negotiating tone. Nikki on the other hand, should listen keenly to her employee’s issue and respond to them in the best way possible. If this is followed then not only is an amicable solution is guaranteed for both parties but also the relationship between them strengthened.
  • 4. References Types of Negotiations | Negotiation Experts. (2016). Negotiations.com. Retrieved 12 September 2016, from http://www.negotiations.com/articles/negotiation-types/ Project Management Case You are working for a large, apparel design and manufacturing company, Trillo Apparel Company (TAC), headquartered in Albuquerque, New Mexico. TAC employs around 3000 people and has remained profitable through tough economic times. The operations are divided into 4 districts; District 1 – North, District 2 – South, District 3 – West and District 4 – East. The company sets strategic goals at the beginning of each year and operates with priorities to reach those goals.Trillo Apparel Company Current Year Priorities · Increase Sales and Distribution in the East · Improve Product Quality · Improve Production in District 4 · Increase Brand Recognition · Increase RevenuesCompany Details Company Name: Trillo Apparel Company (TAC) Company Type: Apparel design and production Company Size: 3000 employees Position # Employees Owner/CEO 1 Vice President
  • 5. 4 Chief Operating Officer 1 Chief Financial Officer 1 Chief Information Officer 1 IT Department 38 District Manager 4 Sales Team 30 Accountant 12 Administrative Assistant 7 Order Fullfilment 45 Customer Service 57 Designer 24 Project Manager 10 Maintenance 25 Operations 2500 Shipping Department 240 Total Employees 3000 Products: Various Apparel Corporate Location: Albuquerque, New MexicoTAC
  • 6. Organization Chart District 4 Production Warehouse Move Project Details The business has expanded considerably over the past few years and District 4 in the East has outgrown its current production facility. Because of this growth the executives want to expand the current facility, moving the whole facility 10 miles away. The location selected has enough room for the production and the shipping department. However, the current warehouse needs some renovation to accommodate the district’s operational needs. The VP of Operations estimates the production and shipping warehouse move for District 4 will provide room required to generate the additional $1 million/year product revenues to meet the current demand due to the expanded production capacity. Daily production generates $50,000 revenue so a week of downtime will cost $250,000 in lost revenues. The move must be completed in 4 months. Mileage between the old and new facilities is 10 miles. Bids have been received from contractors to build out the new office space and production floor and have signed contracts for work as follows: Activity Company Providing Services Total Contract Supplies Time Needed Pack, move and unpack production equipment City Equipment Movers $150,000 n/a 5 Days Move non-production equipment and materials
  • 7. Express Moving Company $125,000 n/a 5 Days Framing East Side Framing & Drywall $121,000 $125,000 15 Days Electrical Sparks Electrical $18,000 $12,000 10 Days Plumbing Waterworks Plumbing $15,000 $13,000 10 Days Drywall East Side Framing & Drywall $121,000 $18,000 15 Days Finish Work Woodcraft Carpentry $115,000 $15,000 15 Days Build work benches for production floor Student Workers Carpentry $112,000 $110,000 15 Days Production workdays are Monday through Saturday. The actual
  • 8. move must be completed in 5 days for as little disruption to production activities as possible. All contractors are on other projects but have been booked in advance. The contractors will gain the necessary permits and schedule city and county inspections but these tasks need to be identified separately due to the length of time it can take. Permitting and inspections can take from one to three weeks, depending upon schedule and the flexibility of the inspector. The new warehouse is empty and can be accessed immediately. Framing cannot start until the permits are received. Electrical and plumbing can begin as soon as the framing is finished. Drywall cannot start until the electrical and plumbing inspections are complete. After the drywall is completed, final inspections will be completed by the county and city. After both the county and city have passed the new construction, finish work can begin. Building the product floor work benches can occur at any time before the move occurs. Chief Executive Officer Chief Operating Officer Chief Financial Officer VP Sales & Marketing Chief Information Officer Executive Assistant VP Operations VP Customer Service Inbound Call Manager Outbound Call
  • 9. Manager Outbound Call Team (20) Inbound Call Team (35) IT Manager IT Staff (37) Sales Team (30) Accountants (12) District2 Manager District 3 Manager District1 Manager District 4 Manager D1 Operations (500) D1 Operations (650) D3 Operations (450) D4 Operations (900) Administrative Assistant Administrative Assistant Administrative Assistant Administrative
  • 11. Officer� VP Sales & Marketing � Executive Assistant� Chief Information Officer� VP Operations� VP Customer Service � Inbound Call Manager� Outbound Call Team (20)� Outbound Call Manager� Inbound Call Team (35)� IT Manager� IT Staff (37)� Sales Team (30) Accountants (12)� District2 Manager� District 3 Manager� District1 Manager� District 4 Manager�
  • 12. D1 Operations (500)� D1 Operations (650)� D3 Operations (450)� D4 Operations (900)� Administrative Assistant � Administrative Assistant � Administrative Assistant � Administrative Assistant � Administrative Assistant � Administrative Assistant� Shipping (50)� Order Fulfillment (45)� Shipping (50)� Shipping (50)� Shipping (90)� Maintenance (5)� Maintenance (5)� Maintenance (5)�
  • 13. Maintenance (10)� Project Managers (10)� VP Design� Design Team (24)� Trillo Apparel Company ID WBS Task Name Duration Start Finish Predecessors Resource Names 1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11 2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and A 6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11 7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project Manager and W 9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11
  • 14. 12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11 Mon 1/3/11 16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and E 17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical PM 23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing 25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11 26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11 East Side Framing & D 27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11 28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D 30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager
  • 15. 32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11 33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Sparks Electrical PM 34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical 35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11 38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Waterworks Plumbing 39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing Project Manager Project Manager Project Manager Project Manager and Attend Project Manager Project Manager and Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager and East S Project Manager and Spark Project Manager and Water Project Manager and Wood Project Manager and Stude
  • 16. Sparks Electrical P Waterworks Plumbi East Side Framing East Side Framing & Dryw East Side Fra City & County Project Manager Sparks Electrical PM Sparks Electrical City & County Project Manager Waterworks Plumbing PM Waterworks Plumbi 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone Summary Project Summary
  • 17. External Tasks External Milestone Deadline Page 1 Project: District4Move.mpp Date: Sat 1/8/11 ID WBS Task Name Duration Start Finish Predecessors Resource Names 40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11 43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D 45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11 48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Woodcraft Carpentry P 49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11 Woodcraft Carpentry 50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County
  • 18. 51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11 53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue 1/4/11 Student Workers Mana 54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11 Student Workers 55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11 58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 61 15 Move 3 days Mon 1/3/11 Wed 1/5/11 62 15.1 Move production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 63 15.2 Move non-production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11 66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11 70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11
  • 19. Project Manager 72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project Manager City & County Project Manager East Side Framing & Dryw East Side Fra City & County Project Manager Woodcraft Carpentry PM Woodcraft Car City & County Project Manager Student Workers Manager Student Worke Project Manager Project Manager City Equipment Movers PM City Equipment Movers Project Manager Express Moving Company Express Moving Company Project Manager Project Manager
  • 20. Project Manager Project Manager Project Manager Project Manager Project Manager 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Page 2 Project: District4Move.mpp Date: Sat 1/8/11 Sheet1Work Breakdown StructureProject Name:District 4
  • 21. Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers Manger15Electrical Permits105.1Obtain Electrical PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing &
  • 22. Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject Manager1 Sheet2 Sheet3