Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official


GEOTECHNICAL GUIDELINES FOR THE USE OF LIME DURING CONSTRUCTION

Section                                                                                                Page

4-0X0l Applicability and Restrictions                                                                    2

4-0X02 Expansive Soil Determination                                                                      5

4-0X03 Mixture Design for Lime Stabilization of Soil                                                     5

4-0X04 Lime Treatment Requirements for Lime Stabilization of Soil                                        6

4-0X05 Health and Safety Precautions for Soil Treatment with Lime                                        7

4-0X06 Lime Stabilization Specifications                                                                 8

4-0X07 Field Quality Control for Lime Modification and Stabilization of Soil                             8

4-0X08 Quality Assurance                                                                                 11




(Note: This policy was jointly developed by Fairfax, Loudoun and Prince William Counties. The
formatting from Fairfax County’s original Lime Policy has been maintained for uniformity.)




                                                  Page 1 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official


PART X 4-0X00 USE OF LIME FOR DRYING, MODIFICATION AND STABILIZATION

4-0X0l Applicability and Restrictions

1. Part X presents geotechnical guidelines and minimum requirements for the design and
construction of projects using lime for drying, modification and stabilization of soil. The
following definitions apply to this geotechnical guideline:

A. Active Zone or Zone of Seasonal Fluctuation is the zone under and around a structure where
the soil’s moisture content is appreciably affected by climatic conditions and environmental
factors. For building footings the Active Zone extends up to a minimum of 4 feet below the
exterior finish grade, or 2 feet below the bottom of the footing, whichever is deeper. For
pavements, the Active Zone extends to 4 feet below the finished pavement surface.

B. Authority Having Jurisdiction (AHJ) is the local jurisdiction issuing this policy.

C. Expansive Soil within the Active Zone is defined by the International Building Code as:

“Soils meeting all four of the following provisions shall be considered expansive, except that
tests to show compliance with Items 1, 2 and 3 shall not be required if the test prescribed in Item
4 is conducted:

 1. Plasticity Index (PI) of 15 or greater, determined in accordance with ASTM D 4318.

 2. More than 10 percent of the soil particles pass a No. 200 sieve (75 µm), determined
    in accordance with ASTM D 422.

 3. More than 10 percent of the soil particles are less than 5 micrometers in size,
    determined in accordance with ASTM D 422.

 4. Expansion Index greater than 20, determined in accordance with ASTM D 4829.”

D. Mellowing is the textural change of soil due to the phenomenon of cation exchange followed
by flocculation and agglomeration due to the chemical reaction between lime and clay soil
particles.




                                                  Page 2 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

E. Soil Drying is a rapid decrease in soil moisture content due to the chemical reaction between
water in the soil and lime and is limited to non-expansive soil.

F. Soil Modification is a reduction in soil plasticity, increase in optimum moisture content,
decrease in maximum dry density, and improved compactability due to the chemical reaction
between soil and lime. Soil Modification shall not be considered permanent.

G. Soil Stabilization is a permanent reduction in soil plasticity or expansion index so the soil is
not expansive, and permanent strength gain occurs through pozzolanic reaction due to the
chemical reaction between soil and lime.

H. Lime is quicklime or hydrated lime meeting the requirements of ASTM C 977, “Standard
Specification for Quicklime and Hydrated Lime for Soil Stabilization.”

2. Soil Drying is limited to the soil that meets the standards of suitable structural fill material as
established by the VDOT Road and Bridge Specifications, Virginia Uniform Statewide Building
Code, the AHJ’s site construction standards, and project documents approved by the AHJ. For
Soil Drying a separate geotechnical study or report is not required to be submitted to the AHJ;
however, notice in writing shall be given to the AHJ prior to the use of lime for Soil Drying.

3. Soil Modification is limited to soils that are below the Active Zone. For Soil Modification, a
geotechnical study or report shall be submitted to and approved by the AHJ. The lime modified
soils below the Active Zone shall have a Plasticity Index (PI) of 20 or less.

4. Stabilization of expansive soils by mixing or blending with dry or slurry lime may be
considered for various engineering applications requiring the placement of structural or
engineered fill within the Active Zone. For Soil Stabilization, a geotechnical study or report shall
be submitted to and approved by the AHJ.

5. Lime storage, handling and mixing shall not allow airborne dust particles to leave the
property. Additionally, lime storage, handling and mixing shall not occur where occupied
structures or areas of public use are within 300 feet, unless the contractor can demonstrate, to the
satisfaction of the AHJ that the construction techniques will not allow visible airborne dust
particles to drift over the occupied structures or areas of public use.

6. The AHJ may require that regardless of location, adjoining property owner notices must be
served on all properties adjoining the lime project site. A minimum of five adjoining properties



                                                  Page 3 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

must be served with notices at the time of geotechnical report submission. The format of such
notices shall be approved by the AHJ.

7. Each proposal to use lime shall be reviewed and approved on a case by case basis by the AHJ,
except when lime is used for Soil Drying, in which case a written notice shall be given to the
AHJ prior to the use of lime for Soil Drying.

8. Lime stabilization shall not be used if the soluble sulfate content by weight in the expansive
soils exceeds 5,000 parts per million. The soluble sulfate content in soils to be stabilized shall be
determined in accordance with AASHTO T290.

9. Strength gain due to the pozzolanic reaction of lime treated soils shall not be included in the
design of slopes.

10. Strength gain due to the pozzolanic reaction of lime treated soils, Soil Stabilization, will only
be recognized in pavement design in the following manner: The Thickness Index shall be
determined based on the CBR values in accordance with VTM-8 of the natural subgrade soils
prior to stabilization. Only the top 8 inches of the stabilized soil may be considered as part of the
pavement structure necessary to achieve the required Thickness Index.

11. Soil modified or stabilized by lime shall not be used as backfill for basement walls and
retaining walls unless approved otherwise by the AHJ.

12. Lime modification and lime stabilization will not be permitted when the soil, aggregate or the
surface on which the lime treated soil is to be placed is frozen, and manipulation (i.e. mixing)
shall not be started until the surface is free of frost. Lime modification shall not start until the
temperature of the soil to be treated with lime is at least 35 degrees F. Lime stabilization shall
not start until the air temperature at the project site is at least 40 degrees F.

13. All lime stabilization within the VDOT Right-of-Way shall be completed in accordance with
the current VDOT Road and Bridge Specifications and this policy. If there is a conflict between
the current VDOT Road and Bridge Specifications and this policy, the most restrictive
requirement applies.

14. Lime shall not be used in Storm Water Management facilities.




                                                  Page 4 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

4-0X02 Expansive Soil Determination

1. The geotechnical engineer shall use the properties identified in Section 4.0X01.C to evaluate
the volume change of potentially expansive soils. These tests shall be performed on
representative samples from each soil mapping unit deemed potentially expansive soils
impacting the proposed construction.

2. All laboratory test data, interpretations and supporting graphs shall be included in the
geotechnical report.

4-0X03 Mixture Design for Lime Stabilization of Soil

1. The appropriate lime content for field application shall be determined in accordance with the
National Lime Association (NLA) Technical Brief, Mixture Design and Testing Procedures for
Lime Stabilized Soil, October 2006 (attached) with the following amendments:

A. Organic Content – The soil proposed to be stabilized shall be natural inorganic soil as defined
by ASTM D 2487 and shall contain no more than two percent (2%) organic material by dry
weight as determined by ASTM D 2974. The intentional mixing of organic material with natural
inorganic soil is not permitted.

B. Expansion Index (EI) Testing Procedures – In accordance with the Virginia Uniform
Statewide Building Code ASTM D 4829 shall be used for EI Testing.

C. Lime used to perform the laboratory tests shall be of the same type, grade, and consistency as
the lime to be used for field application.

D. Validation testing for the prescribed minimum amount of lime determined for stabilization of
soil:

    1) Determine the Expansive Index (EI) of the cured specimens using a minimum of two
       duplicate tests conducted in accordance with ASTM D 4829. The EI shall be equal to or
       less than 20 in order for lime stabilization to be considered as effective in controlling soil
       expansion; or

    2) Determine the Plasticity Index (PI) of material from the cured specimens in accordance
       with ASTM 4318. The PI shall be less than 15 in order for lime stabilization to be



                                                  Page 5 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

        considered as effective in controlling soil expansion.

E. To allow for variations in the soil properties in the field, increase the required minimum lime
content as determined by the above procedures by at least 0.5 percent by dry weight and use this
value as the design lime content.

F. Maps, boring logs and laboratory test data and their interpretations (including analysis; plots;
the location of each of the proposed lime mix designs including the depth and lateral extent of
the proposed lime stabilization; and conclusions) must be included in the geotechnical report.

4-0X04 Treatment Requirements for Lime Stabilization of Soil

1. The minimum depth and lateral extent of treatment specified below shall be used in the
absence of engineering analyses and/or controlled experiments or pilot studies substantiating the
adequacy of alternative treatment depths and areas. If vegetation is to be established, it shall be
planted in non-stabilized soil in accordance with standard landscaping practices.

A. Fills: The depth and extent of treatment shall conform to the minimum requirements specified
below for the specific engineered structure to be supported by the fill.

B. Building Pads: When lime stabilization is used, the depth of stabilization shall extend through
the active zone. The lime stabilization shall extend at least five (5) feet beyond the projected
perimeter of the building’s or structure’s footing/foundation.

C. Backfill behind Basement Walls and Retaining Walls: Lime modified and lime stabilized soils
shall not be placed as backfill behind basement walls and retaining walls, unless approved
otherwise by the AHJ.

D. Backfill for Utility Trenches: Lime modified and lime stabilized soils may be used to backfill
utility trenches.

E. Roadway and Parking Lot Subgrades: In fill areas, the depth of stabilization shall be at least 4
feet below the finished pavement surface. In cut areas, the depth of stabilization shall extend to at
least 2 feet below the subgrade elevation. The lime stabilization shall extend at least 2 feet
beyond the proposed edges of the pavement, shoulders and sidewalks.




                                                  Page 6 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

If lime stabilized soils are to be used in the determination of the Thickness Index for the
pavement design, the stabilized soil shall have a minimum unconfined compressive strength of
150 psi when prepared and tested in accordance with VTM-11. The required pavement
Thickness Index shall be determined based on the CBR values in accordance VTM-8 of the
natural subgrade soils prior to stabilization. Only the top 8 inches of the stabilized soil may be
considered as part of the pavement structure necessary to achieve the required Thickness Index.

2. Alternative treatment depths and areas may be used provided their adequacy is satisfactorily
demonstrated and pursuant to obtaining approval from the AHJ. All supporting data, logic,
rationale, assumptions, field control procedures and conclusions shall be thoroughly documented
in the geotechnical report.

A. The geotechnical engineer shall evaluate the variation of the swell potential and swell
pressure with depth for the expansive soils encountered at a particular site.

B. Swell tests shall be conducted on disturbed or undisturbed soil samples or both depending on
the requirements of the particular application. These tests shall be conducted in accordance with
ASTM Test Method D 4546 (Method B), ASTM D 4829 and/or other testing methods approved
by the AHJ. The tests shall take into account field conditions, including but not limited to:
moisture variation, compacted densities, and surcharge loads.

C. Based on pilot studies, the geotechnical engineer may recommend alternative treatment for
the depth and lateral extent to which treatment should extend in order to achieve the desired
performance or required design parameters, such as allowable differential movement and
swelling pressures.

4-0X05 Health and Safety Precautions for Soil Treatment with Lime

1. Various types of lime can be used in a dry or slurry form for soil treatment. Care must be
taken during construction to avoid skin and eye burns, especially if quicklime is used. Water
shall be applied and mixing operations shall be started immediately after spreading lime in order
to avoid or minimize unnecessary exposure

2. The contractor shall be responsible for controlling fugitive dust due to lime application, on and
off the project limits. Dry lime shall not be delivered, spread or mixed when wind or other
conditions allow lime dust to leave the construction site. In the event that lime leaves or appears
likely to leave the construction site - as determined from visual observation - the contractor shall



                                                  Page 7 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

immediately cease operations. Operations shall not be resumed until working conditions are
suitable or alternate construction techniques are employed to ensure that lime dust does not leave
the construction site.

3. Water runoff from any project site must be controlled by the contractor. Lime must not be
allowed to flow with water runoff to any surface water body on or off a project site or onto an
adjacent site.

4. The AHJ may require that a Health and Safety Plan be called for in the project specifications.
The health and safety plan shall include, but not be limited to, the identification of precautions
for exposure to lime, associated operations and products, protocols for ensuring adherence to the
plan requirements, and emergency medical treatment available on and near the job site. The
Health and Safety Plan shall be prepared by a competent professional for the contractor. If
required by the AHJ, a copy of the Health and Safety Plan shall be provided to the AHJ.

4-0X06 Lime Stabilization Specifications

1. Lime stabilization shall be accomplished according to a set of specifications prepared by the
Registered Design Professional of Record (RDPR) registered in the Commonwealth of Virginia,
which shall include a Field Quality Control Plan meeting the minimum requirements of Sections
4-0X01, 4-0X04 and 4-0X07. These specifications shall be submitted to the AHJ for review and
approval. If the RDPR is not the Geotechnical Engineer of Record (GER) for project, the GER
shall provide a certification to the AHJ indicating that they have reviewed the specifications
prepared by the RDPR and concur with the specifications, findings and recommendations.

2. The specifications shall describe the work, identify suitable material (lime, water, etc.)
requirements, identify the type of equipment for mixing, describe the contractor’s experience and
address at a minimum, the following construction methods: soil preparation; lime spreading;
mixing and watering; mellowing; and compaction and finishing.

4-0X07 Field Quality Control for Lime Modification and Stabilization of Soil

1. Field quality control must be provided on every project where lime modification and lime
stabilization is used and shall be monitored under the direction of the RDPR, qualified and
experienced in soil and foundation engineering. Daily written documentation of all monitoring
activities, including, but not limited to, field observations, construction equipment, source, type,
grade and consistency of lime, sampling and test locations, test results and supporting



                                                  Page 8 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

measurements, etc., shall be maintained and readily available at the project field office and be
made available to the AHJ upon request.

2. At a minimum, the following elements shall be included in the Field Quality Control Plan
which shall be submitted to the AHJ for review prior to approval of the Site Plan. (Where
required, random sampling, measurement and testing locations, and random locations shall be
determined in accordance with ASTM Standard D 3665.)

A. Depth of Lime Treatment. The depth of treatment shall be investigated for every application
by digging test holes and spraying a non-hazardous color sensitive indicator solution on the
treated soil exposed on the sides of the test holes. If lime is present in the soil, it should react
with the indicator solution and cause a change in color to develop. For subgrade stabilization
applications, one (1) test hole is required per 3,000 square foot area of treated soil. A minimum
of three (3) test holes are required for any subgrade stabilization application. The test holes shall
be randomly located. The minimum number of test holes required is on a per layer (lift) basis
when mixing is accomplished in-place by a traveling mixer. When lime-soil mixing is
accomplished using a stationary mixer, the minimum number of test holes required may be based
on the surface area of the total thickness of lime stabilized soil.

B. Lateral Extent of Lime Treatment. Prior to stabilizing an area, the limits of lime treatment
shall be established in the field by a survey. The extent of the treated areas will be identified by
the geotechnical engineer and the field surveys shall be conducted by a professional land
surveyor or registered design professional registered in the Commonwealth of Virginia. In
addition, test holes used to check the depth of treatment shall also be used to verify the lateral
extent of treatment.

C. Dry Lime Spread Rate. The spread rate of dry lime shall be determined or measured for every
lift in terms of pounds of lime per unit area of surface. If lime is applied in bags, the spread rate
can be determined from: the number of bags used, the weight of lime per bag, and the area being
treated. If lime is applied in bulk via mechanical means, a one-square-yard piece of canvas or
other suitable material shall be placed on the ground at random locations at least once per day
during continuous operation, and the weight of lime spread on it measured after lime application
is completed. A minimum of three (3) measurements shall be conducted for bulk applications,
with one (1) test being conducted at the start of spreading lime.

D. Spread Rate of Lime-Slurry Composition. The spread rate of lime-slurry over a known
(measured) area can be based on the lime solids content. The amount of lime solids in a lime-
slurry mixture can be determined by measuring the specific gravity of the slurry. The specific



                                                  Page 9 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

gravity shall be determined via hydrometer test in accordance with ASTM D 422. Alternative
methods to measure the specific gravity of lime slurry may be proposed to the AHJ for review
and approval. A minimum of one (1) test shall be conducted for every 2,500 gallons of slurry
mix or portion thereof. Samples must be taken at random locations after slurry spreading begins.

E. Mellowing and Pulverization. A minimum duration of 24 hours is required for mellowing,
unless laboratory studies show that the PI is reduced to less than 15 in a shorter period of time.
Tests shall be conducted in the field to assure proper pulverization after mellowing and prior to
final placement or compaction. The lime treated material must be mixed until 100 percent of it,
exclusive of the coarse aggregate, passes the 1-inch sieve and a minimum of 60 percent of it,
exclusive of the coarse aggregate, passes the U.S. Number 4 sieve. If the lime stabilization is
completed in two (2) days or less, three (3) tests shall be conducted, with one (1) test being
conducted at the start of operations. If the lime stabilization is completed in more than 2 days, at
least one (1) test per lift shall be conducted each day during continuous operation.

F. Testing Prior to Final Compaction. The maximum allowable loose lift thickness is 8 inches.
After pulverization and prior to final compaction, samples from random locations within each lift
shall be taken for pH (ASTM D 6276) and PI (ASTM D 4318) or EI (ASTM D 4829)
determinations. One (1) soil sample shall be taken and tested for every 1,000 cubic yards of
stabilized soil with a minimum of one (1) soil sample per day from each lift of stabilized soil.
However, if the test results indicate the work is not in compliance with the approved
specifications, the AHJ may require a greater testing frequency. The pH determination shall not
be less than a pH of 12.2 and no more than 10% of pH determinations shall be less than a pH of
12.3. Field pH testing is not required for lime modified soil.

G. Compaction Characteristics. For every type of expansive soil to be modified or stabilized at
the job site, laboratory moisture density curves must be determined for a mixture of that soil with
the design lime content. The laboratory compaction tests shall be conducted in accordance with
ASTM Test Method D 698. The compaction in the field shall be monitored based on the
laboratory moisture-density test results. One (1) field density test shall be conducted per 10,000
square foot area of each compacted lift, with a minimum of three (3) tests per lift. Tests shall be
made at random locations within each lift. Field density tests shall be conducted in accordance
with ASTM Standard D 2922 or ASTM D 1556 or a combination of the two standards. Since the
moisture-density relationships change with time during curing, testing for field moisture-density
characteristics must be conducted as soon as the compaction of the mixture has been completed.

H. Other Engineering Characteristics. Other field tests may be appropriate to demonstrate the
quality control or verify the anticipated performance of the lime-treated material for the



                                                 Page 10 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
Effective Date:
                          BUILDING DEVELOPMENT                                    September 4, 2007
                         POLICIES AND PROCEDURES
                             ADMINISTRATIVE/GENERAL                               Supersedes Policy Dated:
                                                                                  March 21, 2006
                                                                                  Issued by:
                    1.13 Soils – Use of Lime during Construction                  Eric M. Mays, P.E.
                                                                                  Building Official

particular application. The type, purpose, frequency, and location of all other field tests shall be
documented in the quality control plan.

I. The RDPR shall compile a summary report of all site observations and testing performed on a
daily basis and submit signed and sealed reports to the AHJ within 5 business days. All
technicians performing work within the VDOT Right-of-Way shall obtain certification through
VDOT, and certification by any other agency is not acceptable.

4-0X08 Quality Assurance

1. Quality assurance shall be provided by the Geotechnical Engineer of Record (GER) on every
project where lime treatment is used, and shall include at a minimum, a weekly audit of field
quality control activities and a final written summary report.

A. The final report shall be signed and sealed by the GER and shall include, but not be limited
to: a summary of all monitoring data; audit results; steps taken to correct any deficiencies or
items not in compliance with the specifications and Field Quality Control Plan; a statement
indicating whether or not lime modification or stabilization for all applications of the subject
project has been performed in accordance with the specifications and Field Quality Control Plan;
a recommendation for any work to be completed prior to the release of performance bonds
and/or the issuance of residential or non-residential use permits; and all supporting data.

B. The audits and final summary report shall be conducted and prepared under the direction of a
Virginia registered design professional, specializing in soil and foundation engineering.

C. The final summary report shall be submitted to the AHJ for review prior to the release of
performance bonds and/or the issuance of the Certificate of Occupancy related to the subject
project.


Attachment/Hyperlink:
        •   National Lime Association (NLA) Technical Brief,
            Mixture Design and Testing Procedures for Lime Stabilized Soil, October 2006




                                                 Page 11 of 11                                    Version 2009-07-08
Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD

More Related Content

What's hot

IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...IRJET Journal
 
Soil stabilization methods_and_materials
Soil stabilization methods_and_materialsSoil stabilization methods_and_materials
Soil stabilization methods_and_materialspriyank 59
 
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...IRJET Journal
 
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALPALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALWilliam J. Pehaim
 
Grouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of StructuresGrouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of StructuresRamanuj Jaldhari
 
Soil stabilization techniques
Soil stabilization techniquesSoil stabilization techniques
Soil stabilization techniquesShubham Shah
 
Effect of RBI Grade81 on Engineering Properties of Black Cotton Soil
Effect of RBI Grade81 on Engineering Properties of Black Cotton SoilEffect of RBI Grade81 on Engineering Properties of Black Cotton Soil
Effect of RBI Grade81 on Engineering Properties of Black Cotton SoilIRJET Journal
 

What's hot (7)

IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
 
Soil stabilization methods_and_materials
Soil stabilization methods_and_materialsSoil stabilization methods_and_materials
Soil stabilization methods_and_materials
 
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...
IRJET - Experimental Study on Replacement of Fine Aggregate as Black Cotton S...
 
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINALPALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
 
Grouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of StructuresGrouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of Structures
 
Soil stabilization techniques
Soil stabilization techniquesSoil stabilization techniques
Soil stabilization techniques
 
Effect of RBI Grade81 on Engineering Properties of Black Cotton Soil
Effect of RBI Grade81 on Engineering Properties of Black Cotton SoilEffect of RBI Grade81 on Engineering Properties of Black Cotton Soil
Effect of RBI Grade81 on Engineering Properties of Black Cotton Soil
 

Viewers also liked

Identifying sources fall 2011
Identifying sources fall 2011Identifying sources fall 2011
Identifying sources fall 2011aharvey60
 
Identifying sources fall 2011
Identifying sources fall 2011Identifying sources fall 2011
Identifying sources fall 2011aharvey60
 
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...lagunero3000
 
Paul Kaplan Samples
Paul Kaplan SamplesPaul Kaplan Samples
Paul Kaplan Samplespkeditor
 
Paul Kaplan Samples
Paul Kaplan SamplesPaul Kaplan Samples
Paul Kaplan Samplespkeditor
 
GPIA Curriculum
GPIA CurriculumGPIA Curriculum
GPIA Curriculumgpiamilano
 
The business case for safety and health at work
The business case for safety and health at workThe business case for safety and health at work
The business case for safety and health at workLuna Oliveira
 
Renacer Lagunero: Informe de Actividades 2015
Renacer Lagunero: Informe de Actividades 2015Renacer Lagunero: Informe de Actividades 2015
Renacer Lagunero: Informe de Actividades 2015lagunero3000
 
Os objetos de aprendizagem para pessoas com deficiência
Os objetos de aprendizagem para pessoas com deficiênciaOs objetos de aprendizagem para pessoas com deficiência
Os objetos de aprendizagem para pessoas com deficiênciaHalyson Gomes
 
Computer hardware servicing ncii
Computer hardware servicing nciiComputer hardware servicing ncii
Computer hardware servicing nciiMarsha Superio
 
งานนำเสนอ31ส.ค
งานนำเสนอ31ส.คงานนำเสนอ31ส.ค
งานนำเสนอ31ส.คPornpan Larbsib
 
ครูเกษียณ
ครูเกษียณครูเกษียณ
ครูเกษียณPornpan Larbsib
 
งานธุรกิจการท่องเที่ยว
งานธุรกิจการท่องเที่ยวงานธุรกิจการท่องเที่ยว
งานธุรกิจการท่องเที่ยวPornpan Larbsib
 
Renacer Lagunero: Informe Económico y Social al 2014
Renacer Lagunero: Informe Económico y Social al 2014 Renacer Lagunero: Informe Económico y Social al 2014
Renacer Lagunero: Informe Económico y Social al 2014 lagunero3000
 

Viewers also liked (18)

Identifying sources fall 2011
Identifying sources fall 2011Identifying sources fall 2011
Identifying sources fall 2011
 
Identifying sources fall 2011
Identifying sources fall 2011Identifying sources fall 2011
Identifying sources fall 2011
 
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...
Agenda Ciudadana para el Fortalecimiento de la Cohesión Comunitaria, el Desar...
 
Paul Kaplan Samples
Paul Kaplan SamplesPaul Kaplan Samples
Paul Kaplan Samples
 
Paul Kaplan Samples
Paul Kaplan SamplesPaul Kaplan Samples
Paul Kaplan Samples
 
GPIA Curriculum
GPIA CurriculumGPIA Curriculum
GPIA Curriculum
 
The business case for safety and health at work
The business case for safety and health at workThe business case for safety and health at work
The business case for safety and health at work
 
Renacer Lagunero: Informe de Actividades 2015
Renacer Lagunero: Informe de Actividades 2015Renacer Lagunero: Informe de Actividades 2015
Renacer Lagunero: Informe de Actividades 2015
 
Os objetos de aprendizagem para pessoas com deficiência
Os objetos de aprendizagem para pessoas com deficiênciaOs objetos de aprendizagem para pessoas com deficiência
Os objetos de aprendizagem para pessoas com deficiência
 
Computer hardware servicing ncii
Computer hardware servicing nciiComputer hardware servicing ncii
Computer hardware servicing ncii
 
MS excel functions
MS excel functionsMS excel functions
MS excel functions
 
OD Gamut encircling HR
OD Gamut encircling HROD Gamut encircling HR
OD Gamut encircling HR
 
งานนำเสนอ31ส.ค
งานนำเสนอ31ส.คงานนำเสนอ31ส.ค
งานนำเสนอ31ส.ค
 
El alumno ideal bien
El alumno ideal bienEl alumno ideal bien
El alumno ideal bien
 
ครูเกษียณ
ครูเกษียณครูเกษียณ
ครูเกษียณ
 
งานธุรกิจการท่องเที่ยว
งานธุรกิจการท่องเที่ยวงานธุรกิจการท่องเที่ยว
งานธุรกิจการท่องเที่ยว
 
Plan marketingowy
Plan marketingowyPlan marketingowy
Plan marketingowy
 
Renacer Lagunero: Informe Económico y Social al 2014
Renacer Lagunero: Informe Económico y Social al 2014 Renacer Lagunero: Informe Económico y Social al 2014
Renacer Lagunero: Informe Económico y Social al 2014
 

Similar to 005774

IRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET Journal
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...Nzar Braim
 
Structural Analysis of Stabilization and Consolidation Settlement of Selected...
Structural Analysis of Stabilization and Consolidation Settlement of Selected...Structural Analysis of Stabilization and Consolidation Settlement of Selected...
Structural Analysis of Stabilization and Consolidation Settlement of Selected...ijtsrd
 
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...IRJET Journal
 
Soils stabilization jaffna center
Soils stabilization jaffna centerSoils stabilization jaffna center
Soils stabilization jaffna centerVeluppillai Mohan
 
A Schematic Review on Environment Friendly Soil Stabilization Materials
A Schematic Review on Environment Friendly Soil Stabilization MaterialsA Schematic Review on Environment Friendly Soil Stabilization Materials
A Schematic Review on Environment Friendly Soil Stabilization MaterialsIRJET Journal
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesaditya choudhary
 
A New Look at Pervious Concrete
A New Look at Pervious Concrete A New Look at Pervious Concrete
A New Look at Pervious Concrete Dale Fisher
 
Soil Stabilisation
Soil StabilisationSoil Stabilisation
Soil StabilisationArbaz Kazi
 
IRJET- To Study Behavior of Pile in Liquefaction of Soil using Ansys
IRJET- 	  To Study Behavior of Pile in Liquefaction of Soil using AnsysIRJET- 	  To Study Behavior of Pile in Liquefaction of Soil using Ansys
IRJET- To Study Behavior of Pile in Liquefaction of Soil using AnsysIRJET Journal
 
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive Soil
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive SoilIRJET- Effect of Lime (Content & Duration) on Strength of Cohesive Soil
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive SoilIRJET Journal
 
Stabilization of Expansive Soils Employing Activated Fly Ash: A Review
Stabilization of Expansive Soils Employing Activated Fly Ash: A ReviewStabilization of Expansive Soils Employing Activated Fly Ash: A Review
Stabilization of Expansive Soils Employing Activated Fly Ash: A ReviewIRJET Journal
 
IRJET- Microstructure Study and Plasticity Characteristics of Clay
IRJET- Microstructure Study and Plasticity Characteristics of ClayIRJET- Microstructure Study and Plasticity Characteristics of Clay
IRJET- Microstructure Study and Plasticity Characteristics of ClayIRJET Journal
 
118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.pptFlittiAbdelhamid
 
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...IRJET Journal
 

Similar to 005774 (20)

IRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick Dust
 
The Soil Problems in Constructions of Airport
The Soil Problems in Constructions of AirportThe Soil Problems in Constructions of Airport
The Soil Problems in Constructions of Airport
 
Soil Improvement Techniques
Soil Improvement TechniquesSoil Improvement Techniques
Soil Improvement Techniques
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
 
Structural Analysis of Stabilization and Consolidation Settlement of Selected...
Structural Analysis of Stabilization and Consolidation Settlement of Selected...Structural Analysis of Stabilization and Consolidation Settlement of Selected...
Structural Analysis of Stabilization and Consolidation Settlement of Selected...
 
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...
IRJET- Experimental Study of Waste Foundry Sand and Marble Dust as a Soil Sta...
 
Soils stabilization jaffna center
Soils stabilization jaffna centerSoils stabilization jaffna center
Soils stabilization jaffna center
 
A Schematic Review on Environment Friendly Soil Stabilization Materials
A Schematic Review on Environment Friendly Soil Stabilization MaterialsA Schematic Review on Environment Friendly Soil Stabilization Materials
A Schematic Review on Environment Friendly Soil Stabilization Materials
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Ref#36.pdf
Ref#36.pdfRef#36.pdf
Ref#36.pdf
 
A New Look at Pervious Concrete
A New Look at Pervious Concrete A New Look at Pervious Concrete
A New Look at Pervious Concrete
 
Soil Stabilisation
Soil StabilisationSoil Stabilisation
Soil Stabilisation
 
IRJET- To Study Behavior of Pile in Liquefaction of Soil using Ansys
IRJET- 	  To Study Behavior of Pile in Liquefaction of Soil using AnsysIRJET- 	  To Study Behavior of Pile in Liquefaction of Soil using Ansys
IRJET- To Study Behavior of Pile in Liquefaction of Soil using Ansys
 
Ref#7.pdf
Ref#7.pdfRef#7.pdf
Ref#7.pdf
 
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive Soil
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive SoilIRJET- Effect of Lime (Content & Duration) on Strength of Cohesive Soil
IRJET- Effect of Lime (Content & Duration) on Strength of Cohesive Soil
 
Stabilization of Expansive Soils Employing Activated Fly Ash: A Review
Stabilization of Expansive Soils Employing Activated Fly Ash: A ReviewStabilization of Expansive Soils Employing Activated Fly Ash: A Review
Stabilization of Expansive Soils Employing Activated Fly Ash: A Review
 
IRJET- Microstructure Study and Plasticity Characteristics of Clay
IRJET- Microstructure Study and Plasticity Characteristics of ClayIRJET- Microstructure Study and Plasticity Characteristics of Clay
IRJET- Microstructure Study and Plasticity Characteristics of Clay
 
118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt118039141-Soil-Improvement-Techniques.ppt
118039141-Soil-Improvement-Techniques.ppt
 
Ref#2.pdf
Ref#2.pdfRef#2.pdf
Ref#2.pdf
 
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...
Experimental Study on Variation of Unconfined Compressive Strength of a Lime ...
 

Recently uploaded

Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 

Recently uploaded (20)

Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 

005774

  • 1. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official GEOTECHNICAL GUIDELINES FOR THE USE OF LIME DURING CONSTRUCTION Section Page 4-0X0l Applicability and Restrictions 2 4-0X02 Expansive Soil Determination 5 4-0X03 Mixture Design for Lime Stabilization of Soil 5 4-0X04 Lime Treatment Requirements for Lime Stabilization of Soil 6 4-0X05 Health and Safety Precautions for Soil Treatment with Lime 7 4-0X06 Lime Stabilization Specifications 8 4-0X07 Field Quality Control for Lime Modification and Stabilization of Soil 8 4-0X08 Quality Assurance 11 (Note: This policy was jointly developed by Fairfax, Loudoun and Prince William Counties. The formatting from Fairfax County’s original Lime Policy has been maintained for uniformity.) Page 1 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 2. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official PART X 4-0X00 USE OF LIME FOR DRYING, MODIFICATION AND STABILIZATION 4-0X0l Applicability and Restrictions 1. Part X presents geotechnical guidelines and minimum requirements for the design and construction of projects using lime for drying, modification and stabilization of soil. The following definitions apply to this geotechnical guideline: A. Active Zone or Zone of Seasonal Fluctuation is the zone under and around a structure where the soil’s moisture content is appreciably affected by climatic conditions and environmental factors. For building footings the Active Zone extends up to a minimum of 4 feet below the exterior finish grade, or 2 feet below the bottom of the footing, whichever is deeper. For pavements, the Active Zone extends to 4 feet below the finished pavement surface. B. Authority Having Jurisdiction (AHJ) is the local jurisdiction issuing this policy. C. Expansive Soil within the Active Zone is defined by the International Building Code as: “Soils meeting all four of the following provisions shall be considered expansive, except that tests to show compliance with Items 1, 2 and 3 shall not be required if the test prescribed in Item 4 is conducted: 1. Plasticity Index (PI) of 15 or greater, determined in accordance with ASTM D 4318. 2. More than 10 percent of the soil particles pass a No. 200 sieve (75 µm), determined in accordance with ASTM D 422. 3. More than 10 percent of the soil particles are less than 5 micrometers in size, determined in accordance with ASTM D 422. 4. Expansion Index greater than 20, determined in accordance with ASTM D 4829.” D. Mellowing is the textural change of soil due to the phenomenon of cation exchange followed by flocculation and agglomeration due to the chemical reaction between lime and clay soil particles. Page 2 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 3. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official E. Soil Drying is a rapid decrease in soil moisture content due to the chemical reaction between water in the soil and lime and is limited to non-expansive soil. F. Soil Modification is a reduction in soil plasticity, increase in optimum moisture content, decrease in maximum dry density, and improved compactability due to the chemical reaction between soil and lime. Soil Modification shall not be considered permanent. G. Soil Stabilization is a permanent reduction in soil plasticity or expansion index so the soil is not expansive, and permanent strength gain occurs through pozzolanic reaction due to the chemical reaction between soil and lime. H. Lime is quicklime or hydrated lime meeting the requirements of ASTM C 977, “Standard Specification for Quicklime and Hydrated Lime for Soil Stabilization.” 2. Soil Drying is limited to the soil that meets the standards of suitable structural fill material as established by the VDOT Road and Bridge Specifications, Virginia Uniform Statewide Building Code, the AHJ’s site construction standards, and project documents approved by the AHJ. For Soil Drying a separate geotechnical study or report is not required to be submitted to the AHJ; however, notice in writing shall be given to the AHJ prior to the use of lime for Soil Drying. 3. Soil Modification is limited to soils that are below the Active Zone. For Soil Modification, a geotechnical study or report shall be submitted to and approved by the AHJ. The lime modified soils below the Active Zone shall have a Plasticity Index (PI) of 20 or less. 4. Stabilization of expansive soils by mixing or blending with dry or slurry lime may be considered for various engineering applications requiring the placement of structural or engineered fill within the Active Zone. For Soil Stabilization, a geotechnical study or report shall be submitted to and approved by the AHJ. 5. Lime storage, handling and mixing shall not allow airborne dust particles to leave the property. Additionally, lime storage, handling and mixing shall not occur where occupied structures or areas of public use are within 300 feet, unless the contractor can demonstrate, to the satisfaction of the AHJ that the construction techniques will not allow visible airborne dust particles to drift over the occupied structures or areas of public use. 6. The AHJ may require that regardless of location, adjoining property owner notices must be served on all properties adjoining the lime project site. A minimum of five adjoining properties Page 3 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 4. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official must be served with notices at the time of geotechnical report submission. The format of such notices shall be approved by the AHJ. 7. Each proposal to use lime shall be reviewed and approved on a case by case basis by the AHJ, except when lime is used for Soil Drying, in which case a written notice shall be given to the AHJ prior to the use of lime for Soil Drying. 8. Lime stabilization shall not be used if the soluble sulfate content by weight in the expansive soils exceeds 5,000 parts per million. The soluble sulfate content in soils to be stabilized shall be determined in accordance with AASHTO T290. 9. Strength gain due to the pozzolanic reaction of lime treated soils shall not be included in the design of slopes. 10. Strength gain due to the pozzolanic reaction of lime treated soils, Soil Stabilization, will only be recognized in pavement design in the following manner: The Thickness Index shall be determined based on the CBR values in accordance with VTM-8 of the natural subgrade soils prior to stabilization. Only the top 8 inches of the stabilized soil may be considered as part of the pavement structure necessary to achieve the required Thickness Index. 11. Soil modified or stabilized by lime shall not be used as backfill for basement walls and retaining walls unless approved otherwise by the AHJ. 12. Lime modification and lime stabilization will not be permitted when the soil, aggregate or the surface on which the lime treated soil is to be placed is frozen, and manipulation (i.e. mixing) shall not be started until the surface is free of frost. Lime modification shall not start until the temperature of the soil to be treated with lime is at least 35 degrees F. Lime stabilization shall not start until the air temperature at the project site is at least 40 degrees F. 13. All lime stabilization within the VDOT Right-of-Way shall be completed in accordance with the current VDOT Road and Bridge Specifications and this policy. If there is a conflict between the current VDOT Road and Bridge Specifications and this policy, the most restrictive requirement applies. 14. Lime shall not be used in Storm Water Management facilities. Page 4 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 5. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official 4-0X02 Expansive Soil Determination 1. The geotechnical engineer shall use the properties identified in Section 4.0X01.C to evaluate the volume change of potentially expansive soils. These tests shall be performed on representative samples from each soil mapping unit deemed potentially expansive soils impacting the proposed construction. 2. All laboratory test data, interpretations and supporting graphs shall be included in the geotechnical report. 4-0X03 Mixture Design for Lime Stabilization of Soil 1. The appropriate lime content for field application shall be determined in accordance with the National Lime Association (NLA) Technical Brief, Mixture Design and Testing Procedures for Lime Stabilized Soil, October 2006 (attached) with the following amendments: A. Organic Content – The soil proposed to be stabilized shall be natural inorganic soil as defined by ASTM D 2487 and shall contain no more than two percent (2%) organic material by dry weight as determined by ASTM D 2974. The intentional mixing of organic material with natural inorganic soil is not permitted. B. Expansion Index (EI) Testing Procedures – In accordance with the Virginia Uniform Statewide Building Code ASTM D 4829 shall be used for EI Testing. C. Lime used to perform the laboratory tests shall be of the same type, grade, and consistency as the lime to be used for field application. D. Validation testing for the prescribed minimum amount of lime determined for stabilization of soil: 1) Determine the Expansive Index (EI) of the cured specimens using a minimum of two duplicate tests conducted in accordance with ASTM D 4829. The EI shall be equal to or less than 20 in order for lime stabilization to be considered as effective in controlling soil expansion; or 2) Determine the Plasticity Index (PI) of material from the cured specimens in accordance with ASTM 4318. The PI shall be less than 15 in order for lime stabilization to be Page 5 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 6. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official considered as effective in controlling soil expansion. E. To allow for variations in the soil properties in the field, increase the required minimum lime content as determined by the above procedures by at least 0.5 percent by dry weight and use this value as the design lime content. F. Maps, boring logs and laboratory test data and their interpretations (including analysis; plots; the location of each of the proposed lime mix designs including the depth and lateral extent of the proposed lime stabilization; and conclusions) must be included in the geotechnical report. 4-0X04 Treatment Requirements for Lime Stabilization of Soil 1. The minimum depth and lateral extent of treatment specified below shall be used in the absence of engineering analyses and/or controlled experiments or pilot studies substantiating the adequacy of alternative treatment depths and areas. If vegetation is to be established, it shall be planted in non-stabilized soil in accordance with standard landscaping practices. A. Fills: The depth and extent of treatment shall conform to the minimum requirements specified below for the specific engineered structure to be supported by the fill. B. Building Pads: When lime stabilization is used, the depth of stabilization shall extend through the active zone. The lime stabilization shall extend at least five (5) feet beyond the projected perimeter of the building’s or structure’s footing/foundation. C. Backfill behind Basement Walls and Retaining Walls: Lime modified and lime stabilized soils shall not be placed as backfill behind basement walls and retaining walls, unless approved otherwise by the AHJ. D. Backfill for Utility Trenches: Lime modified and lime stabilized soils may be used to backfill utility trenches. E. Roadway and Parking Lot Subgrades: In fill areas, the depth of stabilization shall be at least 4 feet below the finished pavement surface. In cut areas, the depth of stabilization shall extend to at least 2 feet below the subgrade elevation. The lime stabilization shall extend at least 2 feet beyond the proposed edges of the pavement, shoulders and sidewalks. Page 6 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 7. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official If lime stabilized soils are to be used in the determination of the Thickness Index for the pavement design, the stabilized soil shall have a minimum unconfined compressive strength of 150 psi when prepared and tested in accordance with VTM-11. The required pavement Thickness Index shall be determined based on the CBR values in accordance VTM-8 of the natural subgrade soils prior to stabilization. Only the top 8 inches of the stabilized soil may be considered as part of the pavement structure necessary to achieve the required Thickness Index. 2. Alternative treatment depths and areas may be used provided their adequacy is satisfactorily demonstrated and pursuant to obtaining approval from the AHJ. All supporting data, logic, rationale, assumptions, field control procedures and conclusions shall be thoroughly documented in the geotechnical report. A. The geotechnical engineer shall evaluate the variation of the swell potential and swell pressure with depth for the expansive soils encountered at a particular site. B. Swell tests shall be conducted on disturbed or undisturbed soil samples or both depending on the requirements of the particular application. These tests shall be conducted in accordance with ASTM Test Method D 4546 (Method B), ASTM D 4829 and/or other testing methods approved by the AHJ. The tests shall take into account field conditions, including but not limited to: moisture variation, compacted densities, and surcharge loads. C. Based on pilot studies, the geotechnical engineer may recommend alternative treatment for the depth and lateral extent to which treatment should extend in order to achieve the desired performance or required design parameters, such as allowable differential movement and swelling pressures. 4-0X05 Health and Safety Precautions for Soil Treatment with Lime 1. Various types of lime can be used in a dry or slurry form for soil treatment. Care must be taken during construction to avoid skin and eye burns, especially if quicklime is used. Water shall be applied and mixing operations shall be started immediately after spreading lime in order to avoid or minimize unnecessary exposure 2. The contractor shall be responsible for controlling fugitive dust due to lime application, on and off the project limits. Dry lime shall not be delivered, spread or mixed when wind or other conditions allow lime dust to leave the construction site. In the event that lime leaves or appears likely to leave the construction site - as determined from visual observation - the contractor shall Page 7 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 8. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official immediately cease operations. Operations shall not be resumed until working conditions are suitable or alternate construction techniques are employed to ensure that lime dust does not leave the construction site. 3. Water runoff from any project site must be controlled by the contractor. Lime must not be allowed to flow with water runoff to any surface water body on or off a project site or onto an adjacent site. 4. The AHJ may require that a Health and Safety Plan be called for in the project specifications. The health and safety plan shall include, but not be limited to, the identification of precautions for exposure to lime, associated operations and products, protocols for ensuring adherence to the plan requirements, and emergency medical treatment available on and near the job site. The Health and Safety Plan shall be prepared by a competent professional for the contractor. If required by the AHJ, a copy of the Health and Safety Plan shall be provided to the AHJ. 4-0X06 Lime Stabilization Specifications 1. Lime stabilization shall be accomplished according to a set of specifications prepared by the Registered Design Professional of Record (RDPR) registered in the Commonwealth of Virginia, which shall include a Field Quality Control Plan meeting the minimum requirements of Sections 4-0X01, 4-0X04 and 4-0X07. These specifications shall be submitted to the AHJ for review and approval. If the RDPR is not the Geotechnical Engineer of Record (GER) for project, the GER shall provide a certification to the AHJ indicating that they have reviewed the specifications prepared by the RDPR and concur with the specifications, findings and recommendations. 2. The specifications shall describe the work, identify suitable material (lime, water, etc.) requirements, identify the type of equipment for mixing, describe the contractor’s experience and address at a minimum, the following construction methods: soil preparation; lime spreading; mixing and watering; mellowing; and compaction and finishing. 4-0X07 Field Quality Control for Lime Modification and Stabilization of Soil 1. Field quality control must be provided on every project where lime modification and lime stabilization is used and shall be monitored under the direction of the RDPR, qualified and experienced in soil and foundation engineering. Daily written documentation of all monitoring activities, including, but not limited to, field observations, construction equipment, source, type, grade and consistency of lime, sampling and test locations, test results and supporting Page 8 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 9. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official measurements, etc., shall be maintained and readily available at the project field office and be made available to the AHJ upon request. 2. At a minimum, the following elements shall be included in the Field Quality Control Plan which shall be submitted to the AHJ for review prior to approval of the Site Plan. (Where required, random sampling, measurement and testing locations, and random locations shall be determined in accordance with ASTM Standard D 3665.) A. Depth of Lime Treatment. The depth of treatment shall be investigated for every application by digging test holes and spraying a non-hazardous color sensitive indicator solution on the treated soil exposed on the sides of the test holes. If lime is present in the soil, it should react with the indicator solution and cause a change in color to develop. For subgrade stabilization applications, one (1) test hole is required per 3,000 square foot area of treated soil. A minimum of three (3) test holes are required for any subgrade stabilization application. The test holes shall be randomly located. The minimum number of test holes required is on a per layer (lift) basis when mixing is accomplished in-place by a traveling mixer. When lime-soil mixing is accomplished using a stationary mixer, the minimum number of test holes required may be based on the surface area of the total thickness of lime stabilized soil. B. Lateral Extent of Lime Treatment. Prior to stabilizing an area, the limits of lime treatment shall be established in the field by a survey. The extent of the treated areas will be identified by the geotechnical engineer and the field surveys shall be conducted by a professional land surveyor or registered design professional registered in the Commonwealth of Virginia. In addition, test holes used to check the depth of treatment shall also be used to verify the lateral extent of treatment. C. Dry Lime Spread Rate. The spread rate of dry lime shall be determined or measured for every lift in terms of pounds of lime per unit area of surface. If lime is applied in bags, the spread rate can be determined from: the number of bags used, the weight of lime per bag, and the area being treated. If lime is applied in bulk via mechanical means, a one-square-yard piece of canvas or other suitable material shall be placed on the ground at random locations at least once per day during continuous operation, and the weight of lime spread on it measured after lime application is completed. A minimum of three (3) measurements shall be conducted for bulk applications, with one (1) test being conducted at the start of spreading lime. D. Spread Rate of Lime-Slurry Composition. The spread rate of lime-slurry over a known (measured) area can be based on the lime solids content. The amount of lime solids in a lime- slurry mixture can be determined by measuring the specific gravity of the slurry. The specific Page 9 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 10. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official gravity shall be determined via hydrometer test in accordance with ASTM D 422. Alternative methods to measure the specific gravity of lime slurry may be proposed to the AHJ for review and approval. A minimum of one (1) test shall be conducted for every 2,500 gallons of slurry mix or portion thereof. Samples must be taken at random locations after slurry spreading begins. E. Mellowing and Pulverization. A minimum duration of 24 hours is required for mellowing, unless laboratory studies show that the PI is reduced to less than 15 in a shorter period of time. Tests shall be conducted in the field to assure proper pulverization after mellowing and prior to final placement or compaction. The lime treated material must be mixed until 100 percent of it, exclusive of the coarse aggregate, passes the 1-inch sieve and a minimum of 60 percent of it, exclusive of the coarse aggregate, passes the U.S. Number 4 sieve. If the lime stabilization is completed in two (2) days or less, three (3) tests shall be conducted, with one (1) test being conducted at the start of operations. If the lime stabilization is completed in more than 2 days, at least one (1) test per lift shall be conducted each day during continuous operation. F. Testing Prior to Final Compaction. The maximum allowable loose lift thickness is 8 inches. After pulverization and prior to final compaction, samples from random locations within each lift shall be taken for pH (ASTM D 6276) and PI (ASTM D 4318) or EI (ASTM D 4829) determinations. One (1) soil sample shall be taken and tested for every 1,000 cubic yards of stabilized soil with a minimum of one (1) soil sample per day from each lift of stabilized soil. However, if the test results indicate the work is not in compliance with the approved specifications, the AHJ may require a greater testing frequency. The pH determination shall not be less than a pH of 12.2 and no more than 10% of pH determinations shall be less than a pH of 12.3. Field pH testing is not required for lime modified soil. G. Compaction Characteristics. For every type of expansive soil to be modified or stabilized at the job site, laboratory moisture density curves must be determined for a mixture of that soil with the design lime content. The laboratory compaction tests shall be conducted in accordance with ASTM Test Method D 698. The compaction in the field shall be monitored based on the laboratory moisture-density test results. One (1) field density test shall be conducted per 10,000 square foot area of each compacted lift, with a minimum of three (3) tests per lift. Tests shall be made at random locations within each lift. Field density tests shall be conducted in accordance with ASTM Standard D 2922 or ASTM D 1556 or a combination of the two standards. Since the moisture-density relationships change with time during curing, testing for field moisture-density characteristics must be conducted as soon as the compaction of the mixture has been completed. H. Other Engineering Characteristics. Other field tests may be appropriate to demonstrate the quality control or verify the anticipated performance of the lime-treated material for the Page 10 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD
  • 11. Effective Date: BUILDING DEVELOPMENT September 4, 2007 POLICIES AND PROCEDURES ADMINISTRATIVE/GENERAL Supersedes Policy Dated: March 21, 2006 Issued by: 1.13 Soils – Use of Lime during Construction Eric M. Mays, P.E. Building Official particular application. The type, purpose, frequency, and location of all other field tests shall be documented in the quality control plan. I. The RDPR shall compile a summary report of all site observations and testing performed on a daily basis and submit signed and sealed reports to the AHJ within 5 business days. All technicians performing work within the VDOT Right-of-Way shall obtain certification through VDOT, and certification by any other agency is not acceptable. 4-0X08 Quality Assurance 1. Quality assurance shall be provided by the Geotechnical Engineer of Record (GER) on every project where lime treatment is used, and shall include at a minimum, a weekly audit of field quality control activities and a final written summary report. A. The final report shall be signed and sealed by the GER and shall include, but not be limited to: a summary of all monitoring data; audit results; steps taken to correct any deficiencies or items not in compliance with the specifications and Field Quality Control Plan; a statement indicating whether or not lime modification or stabilization for all applications of the subject project has been performed in accordance with the specifications and Field Quality Control Plan; a recommendation for any work to be completed prior to the release of performance bonds and/or the issuance of residential or non-residential use permits; and all supporting data. B. The audits and final summary report shall be conducted and prepared under the direction of a Virginia registered design professional, specializing in soil and foundation engineering. C. The final summary report shall be submitted to the AHJ for review prior to the release of performance bonds and/or the issuance of the Certificate of Occupancy related to the subject project. Attachment/Hyperlink: • National Lime Association (NLA) Technical Brief, Mixture Design and Testing Procedures for Lime Stabilized Soil, October 2006 Page 11 of 11 Version 2009-07-08 Building Development Division. 5 County Complex Court, Prince William, VA, 22192. 703-792-6930. www.pwcgov.org/BDD