FRP Bridge Drain Pipe
      Systems

    Basic Design
  Characteristics for
Successful Installations
Points of Concern
• Expansion and Contraction
Free Floating Connection




    Bridges are dynamic structures where slight shifts and vibrations are
 expected. The dynamic forces of both the bridge and drainage system don’t
 always agree. Leaving a free floating connection between deck outlets and
the subsequent pipe is one way to account for these anticipated movements.
Expansion Joints
For Approximately 200’ of Horizontal
Pipe 1 Expansion Joint is Required

The Thermal Expansion Coefficient
Value for FRP is 0.000014 in/in/F
So the Typical Expansion Formula is
ΔL (in) = L (in) x ΔT (F) x 0.000014

Anticipated Expansion of Pipe @
ΔT=100° & L=2400” ==> ΔL=3.36”
The Total Length of Movement for the
 Expansion Joint Fitting in Most Pipe
   Diameters is Approximately 7”
Points of Concern
• Expansion and Contraction
• System Slope
Slope Requirement of >2%
It is essential for conveyance systems being installed to meet these
minimum slope requirements. While fiberglass pipe does have an
excellent Hazen-Williams coefficient of 150, without the proper
slope, systems will become more likely to collect debris and clog.
Slope in Respect to Angle
   Slope (%) = (Rise/Run) * 100
     Angle = Arctan(Rise/Run)

      Example: Slope = 2%
     (Rise/Run) = .02 unit/unit
    Angle = Arctan(.02) = 1.15°

     Example: Slope = 3.5%
    (Rise/Run) = .035 unit/unit
     Angle = Arctan(.035) = 2°
Custom Fittings to Match
Any Slope You May Need
Points of Concern
• Expansion and Contraction
• System Slope
• Clean Outs
Clean Out Considerations
By placing clean out plugs at
 the end of long runs of pipe
maintenance crews will have
    the ability to service any
 potential system clogs. With
 clean outs its not always the
     quantity that matters.
  Strategic placement of the
      clean outs is just as
important. By placing a clean
  out in a hard to reach area
    crews may not have the
  required access to preform
       the needed work.
Points of Concern
•   Expansion and Contraction
•   System Slope
•   Clean Outs
•   Horizontal Curves
Horizontal Curve Performance
Our Product Exceeds a Stiffness Factor
value of 200 in^3·lbf/in^2 @ 5% Deflection
This Means that Approximately 1’ of
Deflection is Allowed Per 21’ Run of Pipe
If 1’ Deflection is Insufficient, Small Angled
Elbows in the Range of 1°- 5°can be
Added to Match the Horizontal Curves
Points of Concern
•   Expansion and Contraction
•   System Slope
•   Clean Outs
•   Horizontal Curves
•   System Outlets
System Outlets




A bent system outlet and a high class riprap will help
   minimize erosion at the base of the structure
Points of Concern
•   Expansion and Contraction
•   System Slope
•   Clean Outs
•   Horizontal Curves
•   System Outlets
•   Hanger System
System Supports
   Design Engineers Should Locate Pipe Supports Near
Directional Changes and Socket Connections to Ensure All
Joints Will Stay Secure Throughout the Systems Lifecycle
 For Most Pipe Diameters Be Sure to Include a Hanger at
 Least Once Every 20 Feet of Horizontal Pipe That Runs
              Parallel With the Bridge Deck
Recommended Maximum
   Support Spacing
Pipe    Support   Minimum        Hanger        Hanger
Size    Spacing    Support      Load Pipe     Load Pipe
(in.)     (ft.)   Width (in.)   Only (lbs.)    & Water
                                                (lbs.)
 4       16.5        1¼            21.5         145
 6       18.3        1½            36.6         288
 8       20.2        1¾            52.6         518
 10      21.3        1¾            70.3         829
 12      22.4         2            87.4         1221
 14      23.2         2           104.1         1708
 16      24.0        2½           124.8         2268
 18      24.8         3           143.9         2932
 20      25.7        3¾           218.5         3634
 24      26.7        4½           272.4         5586
Do you have specific questions
about the system you are currently
designing that we did not already
answer?
Please give us a call and we would
be more than happy to further
discuss your unique situation and
help find a solution!
Call Nathan Peters at (636)
938-6313

More Related Content

Similar to FRP Bridge Drain Pipe

FRP Bridge Drain Pipe
FRP Bridge Drain PipeFRP Bridge Drain Pipe
FRP Bridge Drain Pipe
seafoammedia
 
PNCWA Presentation Final_Alderwood
PNCWA Presentation Final_AlderwoodPNCWA Presentation Final_Alderwood
PNCWA Presentation Final_Alderwood
Abbie Lorensen, EIT
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
Ash Abel
 
drillingfluids-171223201136.pptx
drillingfluids-171223201136.pptxdrillingfluids-171223201136.pptx
drillingfluids-171223201136.pptx
MuammerAlakary
 
Niagara Middle East Water Catalog MEWC41013 - Copy
Niagara Middle East Water Catalog MEWC41013 - CopyNiagara Middle East Water Catalog MEWC41013 - Copy
Niagara Middle East Water Catalog MEWC41013 - Copy
djamil sakhri
 

Similar to FRP Bridge Drain Pipe (20)

FRP Bridge Drain Pipe
FRP Bridge Drain PipeFRP Bridge Drain Pipe
FRP Bridge Drain Pipe
 
Design Ideas
Design IdeasDesign Ideas
Design Ideas
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Fire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptxFire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptx
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
 
PNCWA Presentation Final_Alderwood
PNCWA Presentation Final_AlderwoodPNCWA Presentation Final_Alderwood
PNCWA Presentation Final_Alderwood
 
Getech Depanelling Process Technology
Getech Depanelling Process TechnologyGetech Depanelling Process Technology
Getech Depanelling Process Technology
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
drillingfluids-171223201136.pptx
drillingfluids-171223201136.pptxdrillingfluids-171223201136.pptx
drillingfluids-171223201136.pptx
 
drillingfluids-22.pptx
drillingfluids-22.pptxdrillingfluids-22.pptx
drillingfluids-22.pptx
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Alignment.pptx
Alignment.pptxAlignment.pptx
Alignment.pptx
 
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.pptExxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
 
Introduction to NX Nastran SOL 200 - Design Optimization
Introduction to NX Nastran SOL 200 - Design OptimizationIntroduction to NX Nastran SOL 200 - Design Optimization
Introduction to NX Nastran SOL 200 - Design Optimization
 
Niagara Middle East Water Catalog MEWC41013 - Copy
Niagara Middle East Water Catalog MEWC41013 - CopyNiagara Middle East Water Catalog MEWC41013 - Copy
Niagara Middle East Water Catalog MEWC41013 - Copy
 
Introduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh RajputIntroduction To Piping Engineering | Gaurav Singh Rajput
Introduction To Piping Engineering | Gaurav Singh Rajput
 
Walk-Through Pipe Stress.pdf
Walk-Through Pipe Stress.pdfWalk-Through Pipe Stress.pdf
Walk-Through Pipe Stress.pdf
 
pipes fittings &valves
 pipes fittings &valves pipes fittings &valves
pipes fittings &valves
 
Qualification of separation performance in gas\liquid separation
Qualification of separation performance in gas\liquid separationQualification of separation performance in gas\liquid separation
Qualification of separation performance in gas\liquid separation
 
Dlab2 presentation
Dlab2 presentationDlab2 presentation
Dlab2 presentation
 

Recently uploaded

Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
bleessingsbender
 
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Klinik kandungan
 

Recently uploaded (20)

Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
JHANSI CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JHANSI ESCORTS SERVICE PROVIDE
JHANSI CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JHANSI ESCORTS SERVICE PROVIDEJHANSI CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JHANSI ESCORTS SERVICE PROVIDE
JHANSI CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JHANSI ESCORTS SERVICE PROVIDE
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
A DAY IN THE LIFE OF A SALESPERSON .pptx
A DAY IN THE LIFE OF A SALESPERSON .pptxA DAY IN THE LIFE OF A SALESPERSON .pptx
A DAY IN THE LIFE OF A SALESPERSON .pptx
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDEGURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
 
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
 
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
 
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDEJIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
JIND CALL GIRL ❤ 8272964427❤ CALL GIRLS IN JIND ESCORTS SERVICE PROVIDE
 
Moradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in PenacovaMoradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in Penacova
 
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdfThe Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
 

FRP Bridge Drain Pipe

  • 1. FRP Bridge Drain Pipe Systems Basic Design Characteristics for Successful Installations
  • 2. Points of Concern • Expansion and Contraction
  • 3. Free Floating Connection Bridges are dynamic structures where slight shifts and vibrations are expected. The dynamic forces of both the bridge and drainage system don’t always agree. Leaving a free floating connection between deck outlets and the subsequent pipe is one way to account for these anticipated movements.
  • 4. Expansion Joints For Approximately 200’ of Horizontal Pipe 1 Expansion Joint is Required The Thermal Expansion Coefficient Value for FRP is 0.000014 in/in/F So the Typical Expansion Formula is ΔL (in) = L (in) x ΔT (F) x 0.000014 Anticipated Expansion of Pipe @ ΔT=100° & L=2400” ==> ΔL=3.36”
  • 5. The Total Length of Movement for the Expansion Joint Fitting in Most Pipe Diameters is Approximately 7”
  • 6. Points of Concern • Expansion and Contraction • System Slope
  • 8. It is essential for conveyance systems being installed to meet these minimum slope requirements. While fiberglass pipe does have an excellent Hazen-Williams coefficient of 150, without the proper slope, systems will become more likely to collect debris and clog.
  • 9. Slope in Respect to Angle Slope (%) = (Rise/Run) * 100 Angle = Arctan(Rise/Run) Example: Slope = 2% (Rise/Run) = .02 unit/unit Angle = Arctan(.02) = 1.15° Example: Slope = 3.5% (Rise/Run) = .035 unit/unit Angle = Arctan(.035) = 2°
  • 10. Custom Fittings to Match Any Slope You May Need
  • 11. Points of Concern • Expansion and Contraction • System Slope • Clean Outs
  • 13. By placing clean out plugs at the end of long runs of pipe maintenance crews will have the ability to service any potential system clogs. With clean outs its not always the quantity that matters. Strategic placement of the clean outs is just as important. By placing a clean out in a hard to reach area crews may not have the required access to preform the needed work.
  • 14. Points of Concern • Expansion and Contraction • System Slope • Clean Outs • Horizontal Curves
  • 15. Horizontal Curve Performance Our Product Exceeds a Stiffness Factor value of 200 in^3·lbf/in^2 @ 5% Deflection This Means that Approximately 1’ of Deflection is Allowed Per 21’ Run of Pipe If 1’ Deflection is Insufficient, Small Angled Elbows in the Range of 1°- 5°can be Added to Match the Horizontal Curves
  • 16. Points of Concern • Expansion and Contraction • System Slope • Clean Outs • Horizontal Curves • System Outlets
  • 17. System Outlets A bent system outlet and a high class riprap will help minimize erosion at the base of the structure
  • 18. Points of Concern • Expansion and Contraction • System Slope • Clean Outs • Horizontal Curves • System Outlets • Hanger System
  • 19. System Supports Design Engineers Should Locate Pipe Supports Near Directional Changes and Socket Connections to Ensure All Joints Will Stay Secure Throughout the Systems Lifecycle For Most Pipe Diameters Be Sure to Include a Hanger at Least Once Every 20 Feet of Horizontal Pipe That Runs Parallel With the Bridge Deck
  • 20. Recommended Maximum Support Spacing Pipe Support Minimum Hanger Hanger Size Spacing Support Load Pipe Load Pipe (in.) (ft.) Width (in.) Only (lbs.) & Water (lbs.) 4 16.5 1¼ 21.5 145 6 18.3 1½ 36.6 288 8 20.2 1¾ 52.6 518 10 21.3 1¾ 70.3 829 12 22.4 2 87.4 1221 14 23.2 2 104.1 1708 16 24.0 2½ 124.8 2268 18 24.8 3 143.9 2932 20 25.7 3¾ 218.5 3634 24 26.7 4½ 272.4 5586
  • 21. Do you have specific questions about the system you are currently designing that we did not already answer? Please give us a call and we would be more than happy to further discuss your unique situation and help find a solution! Call Nathan Peters at (636) 938-6313