Work Breakdown Structure (WBS)
1. Work breakdown Structure (WBS)
Prof. R. V. Kolhe
Department of Civil Engineering
Sanjivani College of Engineering, Kopargaon
2. What is Work Breakdown Structure
(WBS)…?
•Organized hierarchical grouping.
•It Involves breaking down of the project work into
manageable, deliverable, elements
A
B
BA BB BC
C
CA CB
3. WORK BREAKDOWN LEVELS
:
1.Sub–project level :
Dividing the project work into independent
task groups.
Town ship
Project
Residential
Buildings.
Public
Buildings.
Educational
Buildings.
External
Services.
4. 2.Task Level :
Split up into various tasks.
Residential
Buildings
150 Nos. of
Buildings
Foundation of
buildings.
Superstructure
of Buildings.
Finishes of
Buildings.
7. 3.Work-package Level :
◦ A task can be further sub–divided.
◦ Contains an identifiable, measurable,
sizeable, assignable and controllable
package of work.
9. 5.Operations Level :
A lowest level day-to-day operation,
or process, which is part of an activity.
10. S. No Features Sub-project Task Work
Package
Activity
1. Level designation Level 1 Level 2 Level 3 Level 4
2. Nature of plan Corporate strategic
plan
Project strategic
(milestones ) plan
Project tactical
plan
Project operational
plan
3. Time schedule - Summary schedule Master schedule Detailed schedule
4. Duration unit Months Months / Weeks Weeks Weeks / Days
5. Organization set-
up
- Task force Work centre Tradesmen team
6. Management
responsibility
Project team Manager-incharge Work supervisor Foreman incharge
7. Estimated project
cost percentage
- - 0.05% to 5.0% 1% to 2.5%
8. Project control
parameters
- Contribution (
profit ) control
Cost control Time control,
Resources control
9. Codifying data - - Cost codes Activity ID,
Resources ID
PROJECT WORK BREAKDOWN LEVELS
SALIENT FEATURES