3. Project Summary
Contract No :
NHIIP-WB-60A (2nd Call) under Phase-I of National Highways Inter Connectivity
Improvement Projects (NHIIP)
Description :
Rehabilitation and Upgrading to 2 Lane with Paved Shoulders of Bankura-Purulia Road
(Km: 0+000 to 84+000)
Employer : MINISTRY OF ROAD TRANSPORT & HIGHWAYS, GOVT. OF INDIA
EPC Contractor : M/s SHEL-ASSIGNIA (JV)
Authority Engineer : Lea Associates South Asia Private Limited
Nominated Sub-Contractor M/s Bharat Vanijya Eastren Private Limited
Total Length (KM) : 83.562 Kms
Contract Value : 322 (Rupees Three Hundred and Twenty Two Crores Only)
Commencement Date : 4th September-2015
Project Completion Date : 2nd March 2018 (910 days from Appointed Date)
4. Status of Schedule – F
(Required Applicable Permits)
S.No Activities Category Statutory Authority Status Remarks
a) Permission of the State Government for Extraction of the Boulders
Quarry for aggregates Geo & Mining Available Valid up to 21/02/2016
b)
Permission from Village Panchayats and pollution control Board for
Installation of Crushers
Available from
Panchayat
Consent for Establishment (CFE) for Crusher RED WBPCB Applied
Consent for Operation (CFO) for Crusher RED WBPCB Applied
c) Licence for use of Explosives Geo & Mining Available
d)
Permission of State Government for drawing water from River /
Reservoir
CGWB/DC Not Applicable
e)
Licence from Inspector of Factories or other competent Authority for
setting up Batching Plant
Consent for Establishment (CFE) for Batching Plant RED WBPCB Applied 02-11-2015
Consent for Operation (CFO) for Batching Plant RED WBPCB -- --
f) Clearance of Pollution Control Board for setting up Batching Plant WBPCB Applied
g)
Clearance from Village Panchayats and pollution control Board for
setting up Asphalt Plant (Hot Mix Plant)
Available from
Panchayat
Consent for Establishment (CFE) for Hot Mix Plant RED WBPCB Applied 02-11-2015
Consent for Operation (CFO) for Hot Mix Plant RED WBPCB --
h)
Permission of Village Panchayats and State Government for Barrow
Earth
Available
Borrow Area SEIAA In Progress
5. S.No Activities Category
Statutory
Authority
Status Remarks
i)
Any Other Permits or Clearances required under
Applicable Laws
Storage, Handling, and Transport of Hazardous Materials WBPCB In Process
Installation of Generators
Electricity
Board/WBPCB
Applied 28-10-2015
Explosive License for storing fuel oil, lubricants, diesel, etc.
at construction camp
Chief Controller of
Explosives
Applied 30-11-2015
Registration of vehicles & Road Equipments
Motor Vehicle
Department
Available
PUC of all Vehicles/ Machinery
Motor Vehicle
Department
Available
Labour License
Labour
Commissioner,
Purulia/Bankura
Available
Extraction of Sand from River ORANGE
Mining
Dept/WBPCB
Available
Camp Layout Plan Available
Status of Schedule – F
(Required Applicable Permits)
6. On Site Snap Shots
Base Camp Office
Bhoomi Pooja on 19.11.2015 at Base Camp
7. On Site Snap Shots
EHS Induction _ Addressing towards
Employees
EHS Induction _ Addressing towards
Employees
8. Adequate Fire Point & Waste Bin
Provided Camp site
We achieved 1 Lakh safe Man Hours
On Site Snap Shots
9. Smoking Zone Provided with the concept of
Cautionary Awareness
PPE zone Camp site Area
On Site Snap Shots
10. First Aid Room Functioning at Camp
site Area
HSE Induction Hall at Camp Site Area
On Site Snap Shots
11. Play ground provided for employees
Environmental monitoring job is going on
On Site Snap Shots
12. Signage and caution boards displayed at site
Signage and caution boards displayed at site
On Site Snap Shots
13. Standard Septic tank & Soak Pit provided for
Sanitary System
Employees Recreation Room at Camp
site Area
On Site Snap Shots
14. Drainage System Implemented around
the Camp Site
Lightening Arrester functioning at total
Camp Area
On Site Snap Shots
15. Emergency Preparedness at Camp Area
Top Soil Preservation, Implementation at Camp
Area
On Site Snap Shots