SlideShare a Scribd company logo
1 of 1
Volume V Issue No. 3
The Global Leader in Managing Construction Risk
NEC – FIDIC ADJUDICATION
Disclaimer: This article does not constitute advice, legal or
otherwise, and is provided only as general
commentary. Appropriate professional advice should always
be obtained before taking or refraining from taking any
action in relation to such information and/or the application
of applicable law. This article and the materials contained in
it are provided on the basis that all liability for any loss or
damage, whether direct or indirect, arising out of or in
connection with any use or reliance upon this article is
excluded to the fullest extent permitted by law.
David Brodie-Stedman
Senior Vice President & Managing Director
Asia, Middle East and Africa
Abu Dhabi Office
Butti Al Otaiba Bldg., Suite 1601 & 1602
Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E
Tel : +971 – 2 – 627 2855
Fax: +971 – 2 – 627 2042
E-mail: auh@hillintl.com
David Merritt
Senior Vice President & Managing Director
Middle East and Africa
Sultan Business Centre
5th
Floor, Suite 501
P.O. Box: 71467, Dubai - U.A.E.
Tel. : +971 - 4 - 337 2145
Fax : +971 - 4 - 335 6077
E-mail : dxb@hillintl.com
Introduction
Adjudication is a procedure for resolving
disputes without resorting to lengthy and
expensive court procedure. It has become
increasingly popular in international
construction contracts as a fast and efficient
means of resolving disputes. Adjudication is
now a statutory requirement in Malaysia, and
Qatar is considering making adjudication
mandatory for its World Cup developments.
Adjudication allows parties to resolve disputes
on an interim basis, thus allowing the works to
continue pending (possible) later litigation or
arbitration. The following article compares
the adjudication provisions in FIDIC’s 1999 Red
Book (“FIDIC”) and NEC 2005 (“NEC”), two
forms of contract used on international
construction projects. NEC’s Option W1
(outside the UK) has been considered in this
review.
By envisaging a three-member Dispute
Adjudication Board (“DAB”), compared to
NEC’s single adjudicator, FIDIC’s DAB can
potentially provide a more diverse set of skills
to consider issues on major projects. Parties
can however make amendments to NEC to
make it more suitable to their particular
project. For example, the London Olympic
Delivery Authority appointed eleven
adjudicators who provided varying areas of
expertise to deal with the anticipated variety
of disputes on this major NEC-based contract.
Both forms consider the adjudicator’s/DAB’s
decision to be binding. If neither party serves a
notice of dissatisfaction of the Adjudicator’s
decision, that decision becomes final.
Nevertheless, the adjudicator’s decision is to
be revised by litigation/arbitration if either
party issues a notice of dissatisfaction to the
other party within a certain time period. The
drafting of the relevant sub-clause of FIDIC has
created an unintended weakness; it has been
argued that by serving a notice of
dissatisfaction, parties may not be bound to
the decision. This error is rectified in the FIDIC
Gold Book.
Besides the adjudicatory role of FIDIC’s DAB,
the parties can jointly refer a matter to the
DAB for its non-binding opinion. This can
provide an opportunity for amicable
settlement, as the opinion gives the parties an
idea of the likely decision of the DAB. A
negative side is that this may result in a
lengthier process by creating an additional
stage in the resolution of a dispute. NEC does
not envisage this role for the adjudicator.
FIDIC also provides an opportunity for
amicable settlement by requiring the
dissatisfied party not to commence arbitration
before fifty six days have passed from serving
the notice of dissatisfaction. However,
anecdotal evidence would suggest that the
parties seldom reach a settlement during this
period and that such requirement may only
delay the dispute resolution process. Under
NEC, the dissatisfied party can commence
arbitration immediately after serving the
notice.
Furthermore, the DAB has eighty four days to
issue its decision, NEC’s adjudicator has four
weeks. FIDIC, therefore, seems to have taken
a slower route and relied on a more traditional
approach, despite one purpose of adjudication
being intended as a means to enable the quick
resolution of disputes.
NEC provides a number of rules which seem to
be beneficial in terms of efficiency and clarity
of the adjudication process. These rules
provide that either party should be aware of
any communication between the adjudicator
and the other party, that the adjudicator
should follow the contractual compensation
event mechanism in its assessment of time
and cost liabilities, and that the adjudicator
can correct any clerical mistakes or
ambiguities in his decision within a specified
period.
NEC also provides that the adjudicator cannot
be called as witness in subsequent
proceedings, a provision that can help create
trust and confidence for the parties in the
adjudication process. In addition, when
referring a dispute to the adjudicator, a
relevant subcontract dispute may also be
referred to the adjudicator at the same time,
which may sometimes be useful for clarifying
the parties’ liabilities. FIDIC is silent in respect
of all these matters.
Adjudication is a fundamental and inseparable
part of NEC. Under FIDIC, adjudication is a
preferred method from which the parties can
choose to depart and give the Engineer its
traditional role. NEC’s approach with its
decision-making process within four weeks
facilitates dealing with disputes as they arise,
ensuring that most, if not all, of the disputes
have been resolved by the completion date.
FIDIC’s approach is reasonably fast, but slower
and more time-consuming than that of NEC.
FIDIC seems however more inclined to give the
parties the opportunity to deal with their
differences on an amicable basis.
With the Government of Abu Dhabi having
adopted adjudication into its conditions of
construction contracts, it is likely that other
emirates, particularly Dubai, will follow suit,
moving towards a more adjudication-friendly
environment. It will however be interesting to
see whether this move will result in a growth
in the use of NEC form of contract in the
country.
Ali Akbar Fard
Associate Director
Hill International Claims Group
United Arab Emirates
Hill International, with 3,800
employees in 100 offices worldwide,
provides program management,
project management, construction
management and construction claims
and consulting services. Engineering
News - Record magazine recently
ranked Hill as the 8th largest
construction management firm in the
United States.
For more information on Hill, please
visit our website at www.hillintl.com.

More Related Content

What's hot

The Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial ArbitrationThe Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial ArbitrationOluwaseyi Bamigboye
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONOluwaseyi Bamigboye
 
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...Project Controls Expo
 
Us Courts Bankruptcy Basics
Us Courts   Bankruptcy BasicsUs Courts   Bankruptcy Basics
Us Courts Bankruptcy BasicsPeter Ho
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)John McMahon
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolutionrcnewcomer
 
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...Francis Ho
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?Sarah Fox
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
The Practical Side of Bankruptcy
The Practical Side of BankruptcyThe Practical Side of Bankruptcy
The Practical Side of BankruptcyAnthony Kelley
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionFrancis Ho
 
ABF Journal You say tomato article
ABF Journal You say tomato articleABF Journal You say tomato article
ABF Journal You say tomato articleGraham Wedlake
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
The singapore mediation convention
The singapore mediation conventionThe singapore mediation convention
The singapore mediation conventionZafar Kalanauri
 
Liquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiLiquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiAdam Ramlugon
 
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process Raghu Babu Gunturu
 

What's hot (20)

The Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial ArbitrationThe Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial Arbitration
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
 
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
 
Us Courts Bankruptcy Basics
Us Courts   Bankruptcy BasicsUs Courts   Bankruptcy Basics
Us Courts Bankruptcy Basics
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)
 
Arbitration agreement
Arbitration agreementArbitration agreement
Arbitration agreement
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
 
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
The Practical Side of Bankruptcy
The Practical Side of BankruptcyThe Practical Side of Bankruptcy
The Practical Side of Bankruptcy
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's Jurisdiction
 
Essential of arbitration agreement
Essential of arbitration agreementEssential of arbitration agreement
Essential of arbitration agreement
 
Presentation on arbitration
Presentation on arbitrationPresentation on arbitration
Presentation on arbitration
 
ABF Journal You say tomato article
ABF Journal You say tomato articleABF Journal You say tomato article
ABF Journal You say tomato article
 
Arbitration and Conciliation Act 1996
Arbitration and Conciliation Act 1996Arbitration and Conciliation Act 1996
Arbitration and Conciliation Act 1996
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
The singapore mediation convention
The singapore mediation conventionThe singapore mediation convention
The singapore mediation convention
 
Liquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiLiquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v Makdessi
 
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process
Insolvency and Bankruptcy Code - Corporate Insolvency Resolution Process
 

Similar to Article v issue 3 nec-fidic adjudication

ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxzulkiflimohdzain1
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana engAndrey Artyushenko
 
UK Adjudicators Newsletter December 2021
UK Adjudicators Newsletter December  2021UK Adjudicators Newsletter December  2021
UK Adjudicators Newsletter December 2021SeanGibbs12
 
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...Camille Silla Paldi
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021SeanGibbs12
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidicAhmetArslan47
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith mark woodward-smith
 
Welcoming the 2021 ICC Arbitration Rules What's Different.pdf
Welcoming the 2021 ICC Arbitration Rules What's Different.pdfWelcoming the 2021 ICC Arbitration Rules What's Different.pdf
Welcoming the 2021 ICC Arbitration Rules What's Different.pdfAHRP Law Firm
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of ResolutionRoland Schroeder
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationOluwaseyi Bamigboye
 
The interphase between the english national arbitation laws
The interphase between the english national arbitation lawsThe interphase between the english national arbitation laws
The interphase between the english national arbitation lawsValentine Ataka
 

Similar to Article v issue 3 nec-fidic adjudication (20)

ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptx
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng
 
UK Adjudicators Newsletter December 2021
UK Adjudicators Newsletter December  2021UK Adjudicators Newsletter December  2021
UK Adjudicators Newsletter December 2021
 
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...
Proposal for Dubai World Islamic Finance Arbitration Centre (DWIFAC) and Juri...
 
UKA March 2020 newsletter
UKA March 2020 newsletterUKA March 2020 newsletter
UKA March 2020 newsletter
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
Welcoming the 2021 ICC Arbitration Rules What's Different.pdf
Welcoming the 2021 ICC Arbitration Rules What's Different.pdfWelcoming the 2021 ICC Arbitration Rules What's Different.pdf
Welcoming the 2021 ICC Arbitration Rules What's Different.pdf
 
Against all odds
Against all odds Against all odds
Against all odds
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of Resolution
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
January 2018 newsletter
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial Arbitration
 
The interphase between the english national arbitation laws
The interphase between the english national arbitation lawsThe interphase between the english national arbitation laws
The interphase between the english national arbitation laws
 

More from Iffat Al Gharbi

Letters of intent vol. iv issue no. 6
Letters of intent   vol. iv issue no. 6Letters of intent   vol. iv issue no. 6
Letters of intent vol. iv issue no. 6Iffat Al Gharbi
 
The saga of concurrent delay vol. iv issue no. 4
The saga of concurrent delay   vol. iv issue no. 4The saga of concurrent delay   vol. iv issue no. 4
The saga of concurrent delay vol. iv issue no. 4Iffat Al Gharbi
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Iffat Al Gharbi
 
Star rates vol. iv issue no. 2
Star rates   vol. iv issue no. 2Star rates   vol. iv issue no. 2
Star rates vol. iv issue no. 2Iffat Al Gharbi
 
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1Iffat Al Gharbi
 

More from Iffat Al Gharbi (6)

Time management (sb)
Time management (sb)Time management (sb)
Time management (sb)
 
Letters of intent vol. iv issue no. 6
Letters of intent   vol. iv issue no. 6Letters of intent   vol. iv issue no. 6
Letters of intent vol. iv issue no. 6
 
The saga of concurrent delay vol. iv issue no. 4
The saga of concurrent delay   vol. iv issue no. 4The saga of concurrent delay   vol. iv issue no. 4
The saga of concurrent delay vol. iv issue no. 4
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Star rates vol. iv issue no. 2
Star rates   vol. iv issue no. 2Star rates   vol. iv issue no. 2
Star rates vol. iv issue no. 2
 
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1
On demand bonds; all is not necessarily lost part 2 - vol. iv issue no. 1
 

Article v issue 3 nec-fidic adjudication

  • 1. Volume V Issue No. 3 The Global Leader in Managing Construction Risk NEC – FIDIC ADJUDICATION Disclaimer: This article does not constitute advice, legal or otherwise, and is provided only as general commentary. Appropriate professional advice should always be obtained before taking or refraining from taking any action in relation to such information and/or the application of applicable law. This article and the materials contained in it are provided on the basis that all liability for any loss or damage, whether direct or indirect, arising out of or in connection with any use or reliance upon this article is excluded to the fullest extent permitted by law. David Brodie-Stedman Senior Vice President & Managing Director Asia, Middle East and Africa Abu Dhabi Office Butti Al Otaiba Bldg., Suite 1601 & 1602 Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E Tel : +971 – 2 – 627 2855 Fax: +971 – 2 – 627 2042 E-mail: auh@hillintl.com David Merritt Senior Vice President & Managing Director Middle East and Africa Sultan Business Centre 5th Floor, Suite 501 P.O. Box: 71467, Dubai - U.A.E. Tel. : +971 - 4 - 337 2145 Fax : +971 - 4 - 335 6077 E-mail : dxb@hillintl.com Introduction Adjudication is a procedure for resolving disputes without resorting to lengthy and expensive court procedure. It has become increasingly popular in international construction contracts as a fast and efficient means of resolving disputes. Adjudication is now a statutory requirement in Malaysia, and Qatar is considering making adjudication mandatory for its World Cup developments. Adjudication allows parties to resolve disputes on an interim basis, thus allowing the works to continue pending (possible) later litigation or arbitration. The following article compares the adjudication provisions in FIDIC’s 1999 Red Book (“FIDIC”) and NEC 2005 (“NEC”), two forms of contract used on international construction projects. NEC’s Option W1 (outside the UK) has been considered in this review. By envisaging a three-member Dispute Adjudication Board (“DAB”), compared to NEC’s single adjudicator, FIDIC’s DAB can potentially provide a more diverse set of skills to consider issues on major projects. Parties can however make amendments to NEC to make it more suitable to their particular project. For example, the London Olympic Delivery Authority appointed eleven adjudicators who provided varying areas of expertise to deal with the anticipated variety of disputes on this major NEC-based contract. Both forms consider the adjudicator’s/DAB’s decision to be binding. If neither party serves a notice of dissatisfaction of the Adjudicator’s decision, that decision becomes final. Nevertheless, the adjudicator’s decision is to be revised by litigation/arbitration if either party issues a notice of dissatisfaction to the other party within a certain time period. The drafting of the relevant sub-clause of FIDIC has created an unintended weakness; it has been argued that by serving a notice of dissatisfaction, parties may not be bound to the decision. This error is rectified in the FIDIC Gold Book. Besides the adjudicatory role of FIDIC’s DAB, the parties can jointly refer a matter to the DAB for its non-binding opinion. This can provide an opportunity for amicable settlement, as the opinion gives the parties an idea of the likely decision of the DAB. A negative side is that this may result in a lengthier process by creating an additional stage in the resolution of a dispute. NEC does not envisage this role for the adjudicator. FIDIC also provides an opportunity for amicable settlement by requiring the dissatisfied party not to commence arbitration before fifty six days have passed from serving the notice of dissatisfaction. However, anecdotal evidence would suggest that the parties seldom reach a settlement during this period and that such requirement may only delay the dispute resolution process. Under NEC, the dissatisfied party can commence arbitration immediately after serving the notice. Furthermore, the DAB has eighty four days to issue its decision, NEC’s adjudicator has four weeks. FIDIC, therefore, seems to have taken a slower route and relied on a more traditional approach, despite one purpose of adjudication being intended as a means to enable the quick resolution of disputes. NEC provides a number of rules which seem to be beneficial in terms of efficiency and clarity of the adjudication process. These rules provide that either party should be aware of any communication between the adjudicator and the other party, that the adjudicator should follow the contractual compensation event mechanism in its assessment of time and cost liabilities, and that the adjudicator can correct any clerical mistakes or ambiguities in his decision within a specified period. NEC also provides that the adjudicator cannot be called as witness in subsequent proceedings, a provision that can help create trust and confidence for the parties in the adjudication process. In addition, when referring a dispute to the adjudicator, a relevant subcontract dispute may also be referred to the adjudicator at the same time, which may sometimes be useful for clarifying the parties’ liabilities. FIDIC is silent in respect of all these matters. Adjudication is a fundamental and inseparable part of NEC. Under FIDIC, adjudication is a preferred method from which the parties can choose to depart and give the Engineer its traditional role. NEC’s approach with its decision-making process within four weeks facilitates dealing with disputes as they arise, ensuring that most, if not all, of the disputes have been resolved by the completion date. FIDIC’s approach is reasonably fast, but slower and more time-consuming than that of NEC. FIDIC seems however more inclined to give the parties the opportunity to deal with their differences on an amicable basis. With the Government of Abu Dhabi having adopted adjudication into its conditions of construction contracts, it is likely that other emirates, particularly Dubai, will follow suit, moving towards a more adjudication-friendly environment. It will however be interesting to see whether this move will result in a growth in the use of NEC form of contract in the country. Ali Akbar Fard Associate Director Hill International Claims Group United Arab Emirates Hill International, with 3,800 employees in 100 offices worldwide, provides program management, project management, construction management and construction claims and consulting services. Engineering News - Record magazine recently ranked Hill as the 8th largest construction management firm in the United States. For more information on Hill, please visit our website at www.hillintl.com.