SlideShare a Scribd company logo
1 of 8
Download to read offline
Construction Engineering Formula Sheet
Earthwork Construction and Layout
Basic Conversions
1 cubic yard = 27 cubic feet
Basic must know properties
Density of Water = 62.42 pounds per CF (pcf), 1,000 g/liter = 1,000kg/m3
Economic Haul Distance; Large Dozer up to 3000 ft; Scraper 3000 – 5000 ft; Trucks > 5000 ft
lbs of concrete/sack of cement = 94 lbs
One gallon of water = 8.34 lbs
Density = Weight (lbs) / Volume(cf)
Specific gravity = Density of material / Density of water
Density of Water = 62.4 lbs/cf or 1000 kg/cubic meter
1 liter = 1 kg
Excavation and embankment
General Trapezoidal Formula: Area = (h0/2 + h1 + h2 + …+ h(n-1) + hn/2) x w
Average end area Method = V = ((A1+A2)/2) * L
Prismoidal Method = Vp = L*(A1+4AM+A2) / 6
Pyramid Method = V = AL / 3
Borrow Pit Volumes
Conical Spoil Pile = Vol = (Ab x H) / 3; D = (7.64V / tan )1/3
; H = (D/2) tan  ;where Ab=base area;
H=pile height;D=diameter;  = angle of repose (deg)
Triangular Spoil Bank = Vol = Cross section Area x L ; B = (4V/(L x tan )1/3
; H = (B x tan ) / 2 ; V=
pile volume; B= base width ; H = pile ht; L = pile length ;  = angle of repose (deg)
Density of Water = γwater = Mw/Vw
Moisture Content (w) = Mw/Ms
Degree of Saturation (S) = Vw/Vv
Total or Wet Density of Soil (γwet) = M/V where M = Mw + Ms ; V = Vw + Vs + Va
Density of Solids = Ms/Vs
Specific Gravity = Gs = γsolids /γwater ; or = Ms/(Vs * γwater )
Porosity (n) = Vv/Vt ; Vv = Volume of Voids = Vw + Va ; Vt = Total Volume = Vs +Vw + Va
Void Ratio (e) = Vv/Vs
Dry Density of Soil (γdry) = Ms /V
Dry Density of Soil (γdry) = γwet / (1+w); (γdry) = (γwater*Gs) / (1+(w/S)*Gs)
(γdry)=(γwater * Gs)/(1+e)
Specific Gravity = S * e = Gs * w
Porosity (n) = e/(1+e)
Void Ratio (e) = n/(1-n)
VCompacted = VBanked (1 – SHRINKAGE)
VLoose = VBanked (1+SWELL)
Swell % = ((DB – DL) / DL) x 100 ; Swell = (DB – DL)/DL
Shrinkage % = ((DC – DB) / DL) x 100 ; Shrinkage = (DC – DB)/DL
DL = Dry Loose unit wt (pcf) ; DB = Dry Bank unit wt (pcf) ; DC = Dry compacted unit wt(pcf)
Vloose = Vc (1+Swll)/(1- Shrinkage) ; Vbank = Vc / (1-Shrinkage)
Site Layout and Control
Height of Instrument (HI) = Known elevation + Backsight (BS)
Turning Point (TP) = Height of Instrument (HI) – Foresight (FS)
Trigonometric Leveling  Elevation at unknown location = elevation at known + HI + (slope distance sin
(angle of slope)) – distance from known to unknown location
Traverse Area: Method of Coordinates; The area is A = ½ (Sum of full line products – Sum of broken line
products)
Earthwork Mass Diagrams
Rising section = cut; Falling section = fill; zero slope = moving from cut to fill or vice versa
Estimating Quantities and Cost
Quantity take-off methods
Trenching: Be careful to fully understand what the dimensions represent, Use horizontal In-In and Vertical
Out-Out
Estimating # bricks in wall : net wall (sf) = Gross surface Area of Wall (sf) – Area of open surface (sf)
 then find surface area of brick with mortar (sf)  (net wall / SA of one brick) x # rows = bricks in
wall
Volume of mortar per brick = (mortar thickness)(brick width)(length + height + mortar thickness)
Board feet = Thickness(in) x Width (in) x Length (in) / 144
Rebar = When finding the number of rebar bars in wall = # rebar = (the length of wall / spacing of bars) +
1
Engineering economics
Present/Future Value: F= P(1+i)
n
or P = F/ (1+i)
n
; i= (F/P)
1/n
– 1
Series Payment : P=A[(1+i)
n
- 1]/[I (1+i)
n
] ; F=A[(1+i)
n
- 1]/[i]
Future/Present Value and Arithmetic gradient: F=G/i[((1+i)
n
- 1)/i)-n] ; P=G(i(1+i)
n
- iN - 1)/(i2
(1+i)n
]
Depreciation:
Straight Line Method : Dn = (Initial Cost – Salvage Value)/ N
Sum of the years Digit Method: Dn = (n2 + n)/ 2
Declining balance Method: Dn = 2 x (1/n)
Construction Operations and Methods
Lifting and Rigging
Solve for Center of Gravity: Ax = (A1)(x1) + (A2)(x2) + … + (An)(xn) ; where A= Total Area
x = distance to the CoG in the x direction, A1 and A2 = Area/Volume or Mass; x1 and x2 = distance to the CoG
Crane selection erection and stability
Crane Stability: Factor of Safety against toppling = Resisting moment / Toppling moment
Toppling Moment = (Weight of Load(WL)) x (Distance from toppling pt to Load)(LL) + Weight of
boom(WB) x Distance to Center of Boom(LB)
Resisting Moment = = (Weight of Counter Weight (WC)) x (Distance from toppling pt to
Counterweight)(LC) + Weight of Crane Body(WG) x Distance to Center of Crane Body(LG)
Equipment Production
Dozer: Total Time = Q / (P x N) : Q = Quantity of material to be moved; P = hourly production rate per
dozer; N = Number of Dozers
Grader: Total Time = (P x D) / (S x E): P= number of passes required; D = distance traveled in each pass,
in miles or feet; S = speed of grader, in mph or fpm (multiply mph by 88 to convert to fpm; E = efficiency
factor
Scraper: Total time (hours) = Q / P x N  Q = total volume to move(BCY), P = hourly production rate
(BCY/hr), N = number of scrapers
Loader: Maximum production rate (LCY per hour) = heaped bucket capacity x bucket fill factor x 60
minutes/ loader cycle time (min)
Net production rate (LCY per hour) = maximum production rate (LCY per hour) x efficiency factor
Excavator: q = ((3600 sec/hour x B x E x P)/ C) x Volume Correction  q = Volume of soil excavated and
dumped in a truck by the excavator (CY/hr), B = Bucket struck capacity (CY), E = Bucket efficiency factor, P
= Productivity factor, C = Cycle time for 90 degree angle and optimum depth
Compactor: Production (CCY per hour) = (16.3 x W x S x L x E) / N  W = compacted width per pass (in
feet), S = compactor speed(mph), L= compacted lift thickness(in), E = efficiency, N = number of passes
required
Compactor: Compactors required = FD x SCF / CP  FD = amount of fill delivered (LCY per hour), SCF =
soil conversion factor (LCY:BCY), CP = compactor production (CCY per hour)
Dump Truck: Number of trucks required = 1 + truck cycle time (minutes) / loader cycle time (minutes)
Scheduling
CPM Network Analysis
Total Float(TF) = Late Finish(LF) – Early Finish(EF) ;
TF = LF – (Early Start(ES)) + Duration(D)) = LF – ES – D
Total Float (TF) = Late Start (LS) – Early Start (ES)
TF = LS – ES = LS – (EF – D) = LS – EF + D
Total Float (TF) = Free Float (FF) + Independent Float (IF)
Free Float = Early Start of successor – Early Finish of Activity
Independent Float = Early start of successor – Late finish of predecessor – duration of Activity
Forward pass  Early start + Duration = Early Finish :
Backward pass  Late Finish – Duration = Late Start
Early Finish = Early Start + Duration ; Early Start = Early Finish – Duration
Activity Time Analysis
Expected Duration of activity = (a + 4b + c) / 6  where a = optimistic estimate; b = most likely
Estimate; c = pessimistic estimate
Time Cost Trade off
Cost Slope = (crash cost – normal cost) / (normal time – crash time)
Material Quality Control and Production
Concrete Mix Design
Water / Cement Ratio = Weight of Water (lbs) / Weight of Cement (lbs)
Air Content (%) = Volume of Air (cf) / Total Volume of Concrete (cf)
Volume of material (cf) = Weight of material (lbs) / ( 62.4 x specific gravity of material)
Volume = Weight of material (lbs) / density of material (lbs/cf)
Temporary Structures
Construction Loads
As per ASCE 37-02,
Cp = Lo (.25 + 15/sqrt(AI))  Cp = reduced design uniformly distributed Personnel and Equipment load per
sf, Lo = is the unreduced uniformly distributed P&E per sf; AI = is the influence area, sf
P&E on slope roof; R = 1.2 –0.5F  where F = slope of the roof (in/ft); R = Reduction Factor (.6 < R < 1.0)
Formwork
Lateral pressure of concrete(p) = wh or ρgh  p = lateral pressure, lb/ft2
; w = unit weight of concrete,
lb/ft3
; ρ = density of concrete (kg/m3
); g = gravitational constant, 9.81 N/kg ; h = depth of fluid or plastic
concrete from top of placement to point of consideration in form, ft(m).
ACI Lateral pressure equations:
Columns: For slump 7in or less to depth of 4ft or less: pmax = CwCc[150 + 9000 R/T]
Walls: rate of placement (R) less than 7ft/h and height not exceeding 14 ft: pmax = CwCc[150 + 9000 R/T]
Walls: R is 7ft/hr to 15ft/hr and height not exceeding 14 ft: pmax = CwCc[150 + 43,400/T +2800R/T]
R = rate of placement(ft/hr), T = temperature of concrete during placing, o
F, Cw = unit weight coefficient, Cc
= chemistry coefficient
Shoring and Reshoring
Use ACI SP-4 Formwork for concrete
Concrete maturity and early strength evaluation
Bracing
P = (H x h1 x L1) / (h2 x L2)  P = strut load per foot of form (lb/ft)(kN/m) ;
H = lateral load at top of form ( lb/ft ) (kN/m) ; h1 = height of form (ft)(m) ;
H2 = height of top of strut (ft)(m) ; L1 = length of strut (ft) (m) ;
L2 = horizontal distance from form to bottom of strut (ft) (m)
Pressure applied to wall due to wind ; P = .00256 Vc2
 Vc = Wind Velocity
Anchorage
The force required to pull the concrete apart = Force (lbs) = material cohesion (lbs/in2
) x Surface Area of
failure
Surface Area of a Cone = pi x r x sqrt (r2
+ h2
)
Volume of the Cone = 1/3 (pi x r2
x h)
Cofferdam (systems for temporary excavation support)
F1 = wh1
2
/ 2 ; F2 = wh2
2
/ 2 ; w = unit weight of water ; h1 = outside water height ; h2 = inside water
height
F1 = outside hydrostatic force ; F2 = inside hydrostatic force ; F3 = water
buoyancy force
If h1 = 2 h2, then F1 = 4 F2 and F3 = ¾ F1
Worker Health, Safety, and Environment
Safety Statistics (e.g., incident rate, EMR)
OSHA Incident Rate = (# of Injuries & Illness * 200,000) / Total hrs all employees
Fatal Accident Rate = (# of Fatalities * 108
) / Total hrs all employees
Fatality Rate = (# of Fatalities / yr) / (Total # people exposed)

More Related Content

What's hot

Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...
 Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog... Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...
Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...Mario Yuven
 
Program dan Flowchart Perkalian Matriks
Program dan Flowchart Perkalian MatriksProgram dan Flowchart Perkalian Matriks
Program dan Flowchart Perkalian MatriksSimon Patabang
 
T2 mektan 1_iwansutriono_41112120104.ppt
T2 mektan 1_iwansutriono_41112120104.pptT2 mektan 1_iwansutriono_41112120104.ppt
T2 mektan 1_iwansutriono_41112120104.pptIwan Sutriono
 
Pemerikasaan Kadar lumpur dalam pasir
Pemerikasaan Kadar lumpur dalam pasirPemerikasaan Kadar lumpur dalam pasir
Pemerikasaan Kadar lumpur dalam pasirfirdiaudi
 
Makalah logika informatika
Makalah logika informatikaMakalah logika informatika
Makalah logika informatikaCidals Ferry
 
Diktat logika informatika unsoed
Diktat logika informatika unsoedDiktat logika informatika unsoed
Diktat logika informatika unsoedLarasWiranti2
 
Sifat Batuan dan Fluida Panas Bumi
Sifat Batuan dan Fluida Panas BumiSifat Batuan dan Fluida Panas Bumi
Sifat Batuan dan Fluida Panas BumiEstrela Bellia Muaja
 
Cara membuat pintu di autocad
Cara membuat pintu di autocadCara membuat pintu di autocad
Cara membuat pintu di autocadEdi Kusyanto
 
Laboratorium Uji Tanah - CBR Lapangan
Laboratorium Uji Tanah - CBR LapanganLaboratorium Uji Tanah - CBR Lapangan
Laboratorium Uji Tanah - CBR LapanganReski Aprilia
 
Laporan praktek batu beton ( ptb unimed )
Laporan praktek batu beton ( ptb unimed )Laporan praktek batu beton ( ptb unimed )
Laporan praktek batu beton ( ptb unimed )Fingki Amelia
 
Soal tambang terbuka
Soal tambang terbukaSoal tambang terbuka
Soal tambang terbukayudi05
 
Produktivitas Alat Berat Dozer
Produktivitas Alat Berat DozerProduktivitas Alat Berat Dozer
Produktivitas Alat Berat DozerElis Wahyuni
 
Pengantar teknologi mineral3
Pengantar teknologi mineral3Pengantar teknologi mineral3
Pengantar teknologi mineral3Sylvester Saragih
 
Prosedur Desain Perkerasan ppt (kelompok 6)
Prosedur Desain Perkerasan ppt (kelompok 6)Prosedur Desain Perkerasan ppt (kelompok 6)
Prosedur Desain Perkerasan ppt (kelompok 6)Fatayah Rannanda
 
Analisa biaya penggunaan alat berat
Analisa biaya penggunaan alat beratAnalisa biaya penggunaan alat berat
Analisa biaya penggunaan alat beratMetodeKonstruksi
 
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahra
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahrakapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahra
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahraAyu Fatimah Zahra
 
Pembuatan laporan pemetaan geologi
Pembuatan laporan pemetaan geologiPembuatan laporan pemetaan geologi
Pembuatan laporan pemetaan geologiDelta Milano
 
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbuka
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbukaTugas tambang terbuka hubungan rumus bser dan sr tambang terbuka
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbukaSylvester Saragih
 

What's hot (20)

Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...
 Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog... Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...
Materi Kuliah Teknik Pertambangan ; Geologi Struktur Semester III STTNAS Yog...
 
Program dan Flowchart Perkalian Matriks
Program dan Flowchart Perkalian MatriksProgram dan Flowchart Perkalian Matriks
Program dan Flowchart Perkalian Matriks
 
T2 mektan 1_iwansutriono_41112120104.ppt
T2 mektan 1_iwansutriono_41112120104.pptT2 mektan 1_iwansutriono_41112120104.ppt
T2 mektan 1_iwansutriono_41112120104.ppt
 
Pemerikasaan Kadar lumpur dalam pasir
Pemerikasaan Kadar lumpur dalam pasirPemerikasaan Kadar lumpur dalam pasir
Pemerikasaan Kadar lumpur dalam pasir
 
Penambangan Batubara
Penambangan BatubaraPenambangan Batubara
Penambangan Batubara
 
Makalah logika informatika
Makalah logika informatikaMakalah logika informatika
Makalah logika informatika
 
Iuw 6v beda tinggi
Iuw   6v beda tinggiIuw   6v beda tinggi
Iuw 6v beda tinggi
 
Diktat logika informatika unsoed
Diktat logika informatika unsoedDiktat logika informatika unsoed
Diktat logika informatika unsoed
 
Sifat Batuan dan Fluida Panas Bumi
Sifat Batuan dan Fluida Panas BumiSifat Batuan dan Fluida Panas Bumi
Sifat Batuan dan Fluida Panas Bumi
 
Cara membuat pintu di autocad
Cara membuat pintu di autocadCara membuat pintu di autocad
Cara membuat pintu di autocad
 
Laboratorium Uji Tanah - CBR Lapangan
Laboratorium Uji Tanah - CBR LapanganLaboratorium Uji Tanah - CBR Lapangan
Laboratorium Uji Tanah - CBR Lapangan
 
Laporan praktek batu beton ( ptb unimed )
Laporan praktek batu beton ( ptb unimed )Laporan praktek batu beton ( ptb unimed )
Laporan praktek batu beton ( ptb unimed )
 
Soal tambang terbuka
Soal tambang terbukaSoal tambang terbuka
Soal tambang terbuka
 
Produktivitas Alat Berat Dozer
Produktivitas Alat Berat DozerProduktivitas Alat Berat Dozer
Produktivitas Alat Berat Dozer
 
Pengantar teknologi mineral3
Pengantar teknologi mineral3Pengantar teknologi mineral3
Pengantar teknologi mineral3
 
Prosedur Desain Perkerasan ppt (kelompok 6)
Prosedur Desain Perkerasan ppt (kelompok 6)Prosedur Desain Perkerasan ppt (kelompok 6)
Prosedur Desain Perkerasan ppt (kelompok 6)
 
Analisa biaya penggunaan alat berat
Analisa biaya penggunaan alat beratAnalisa biaya penggunaan alat berat
Analisa biaya penggunaan alat berat
 
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahra
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahrakapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahra
kapasitas daya dukung friksi pondasi tiang pancang_ayufatimahzahra
 
Pembuatan laporan pemetaan geologi
Pembuatan laporan pemetaan geologiPembuatan laporan pemetaan geologi
Pembuatan laporan pemetaan geologi
 
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbuka
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbukaTugas tambang terbuka hubungan rumus bser dan sr tambang terbuka
Tugas tambang terbuka hubungan rumus bser dan sr tambang terbuka
 

Viewers also liked

Load reduction factor_ǿ
Load reduction factor_ǿLoad reduction factor_ǿ
Load reduction factor_ǿPrionath Roy
 
Marshal mix design
Marshal mix designMarshal mix design
Marshal mix designPrionath Roy
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)Prionath Roy
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavelPrionath Roy
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)Prionath Roy
 
Document given by hassan
Document given by hassanDocument given by hassan
Document given by hassanPrionath Roy
 
Suggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examSuggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examPrionath Roy
 
Suggestion done by me
Suggestion done by meSuggestion done by me
Suggestion done by mePrionath Roy
 
Borrow pit-volumes
Borrow pit-volumesBorrow pit-volumes
Borrow pit-volumesPrionath Roy
 
Construction engineering formula sheet
Construction engineering formula sheetConstruction engineering formula sheet
Construction engineering formula sheetPrionath Roy
 
Structur e very helpfull
Structur e very helpfullStructur e very helpfull
Structur e very helpfullPrionath Roy
 
Portal and cantilever method
Portal and cantilever methodPortal and cantilever method
Portal and cantilever methodPrionath Roy
 
Serially subject wise question
Serially subject wise questionSerially subject wise question
Serially subject wise questionPrionath Roy
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavelPrionath Roy
 

Viewers also liked (20)

Load reduction factor_ǿ
Load reduction factor_ǿLoad reduction factor_ǿ
Load reduction factor_ǿ
 
Active tab
Active tabActive tab
Active tab
 
Marshal mix design
Marshal mix designMarshal mix design
Marshal mix design
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavel
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)
 
Document given by hassan
Document given by hassanDocument given by hassan
Document given by hassan
 
Suggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examSuggestion for govt. job recruitment exam
Suggestion for govt. job recruitment exam
 
Civil ques
Civil quesCivil ques
Civil ques
 
Suggestion done by me
Suggestion done by meSuggestion done by me
Suggestion done by me
 
Settlement
SettlementSettlement
Settlement
 
Ad exam
Ad examAd exam
Ad exam
 
Borrow pit-volumes
Borrow pit-volumesBorrow pit-volumes
Borrow pit-volumes
 
Construction engineering formula sheet
Construction engineering formula sheetConstruction engineering formula sheet
Construction engineering formula sheet
 
Structur e very helpfull
Structur e very helpfullStructur e very helpfull
Structur e very helpfull
 
Portal and cantilever method
Portal and cantilever methodPortal and cantilever method
Portal and cantilever method
 
Serially subject wise question
Serially subject wise questionSerially subject wise question
Serially subject wise question
 
Document1
Document1Document1
Document1
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavel
 

Similar to Construction engineering formula sheet

Watertaxi3-1st Project Presentation-BUET
Watertaxi3-1st Project Presentation-BUET Watertaxi3-1st Project Presentation-BUET
Watertaxi3-1st Project Presentation-BUET shisalsunny
 
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUB
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUBPresentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUB
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUBWorld University of Bangladesh
 
137518876 bearing-capacity-from-spt
137518876 bearing-capacity-from-spt 137518876 bearing-capacity-from-spt
137518876 bearing-capacity-from-spt James Chan
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheetKasinathan PMP
 
Take Off And Landing Performance
Take Off And Landing PerformanceTake Off And Landing Performance
Take Off And Landing Performanceahmad bassiouny
 
Introduction to Ship Resistance and Propulsion.pdf
Introduction to Ship Resistance and Propulsion.pdfIntroduction to Ship Resistance and Propulsion.pdf
Introduction to Ship Resistance and Propulsion.pdfMUswahPawara
 
Dead load of structure
Dead load of structureDead load of structure
Dead load of structureKen Wong
 
Python code for the determination of equivalent horizontal and vertical hydra...
Python code for the determination of equivalent horizontal and vertical hydra...Python code for the determination of equivalent horizontal and vertical hydra...
Python code for the determination of equivalent horizontal and vertical hydra...Joyson Parmar
 
Building Structure calculation
Building Structure calculationBuilding Structure calculation
Building Structure calculationJy Chong
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheetsankalptiwari
 
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdf
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdfLecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdf
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdfMuhammadNura7
 
Oscar individual b structure report
Oscar individual b structure reportOscar individual b structure report
Oscar individual b structure reportlee yiang siang
 
CHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxCHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxMamushLeta
 

Similar to Construction engineering formula sheet (20)

23320 1632955207
23320  163295520723320  1632955207
23320 1632955207
 
Watertaxi3-1st Project Presentation-BUET
Watertaxi3-1st Project Presentation-BUET Watertaxi3-1st Project Presentation-BUET
Watertaxi3-1st Project Presentation-BUET
 
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUB
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUBPresentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUB
Presentation 3 ce801 by Rabindra Ranjan Saha, PEng, Assoc. Prof. WUB
 
137518876 bearing-capacity-from-spt
137518876 bearing-capacity-from-spt 137518876 bearing-capacity-from-spt
137518876 bearing-capacity-from-spt
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheet
 
Take Off And Landing Performance
Take Off And Landing PerformanceTake Off And Landing Performance
Take Off And Landing Performance
 
Introduction to Ship Resistance and Propulsion.pdf
Introduction to Ship Resistance and Propulsion.pdfIntroduction to Ship Resistance and Propulsion.pdf
Introduction to Ship Resistance and Propulsion.pdf
 
Dead load of structure
Dead load of structureDead load of structure
Dead load of structure
 
Roof truss design
Roof truss designRoof truss design
Roof truss design
 
Python code for the determination of equivalent horizontal and vertical hydra...
Python code for the determination of equivalent horizontal and vertical hydra...Python code for the determination of equivalent horizontal and vertical hydra...
Python code for the determination of equivalent horizontal and vertical hydra...
 
Basic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining projectBasic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining project
 
G.p presentation
G.p presentationG.p presentation
G.p presentation
 
Building Structure calculation
Building Structure calculationBuilding Structure calculation
Building Structure calculation
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheet
 
Chap 02
Chap 02Chap 02
Chap 02
 
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdf
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdfLecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdf
Lecture5-Chapter4_Soil_Bearing Capacity_fall21-nf(1) (2).pdf
 
Scantling of Ship
Scantling of ShipScantling of Ship
Scantling of Ship
 
[7] trim
[7] trim[7] trim
[7] trim
 
Oscar individual b structure report
Oscar individual b structure reportOscar individual b structure report
Oscar individual b structure report
 
CHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxCHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptx
 

More from Prionath Roy

Pile capacity equations
Pile capacity equationsPile capacity equations
Pile capacity equationsPrionath Roy
 
Civil engineering suggestions for wasa
Civil engineering suggestions for wasaCivil engineering suggestions for wasa
Civil engineering suggestions for wasaPrionath Roy
 
Civil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationCivil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationPrionath Roy
 
Bearing capaciy equations
Bearing capaciy equationsBearing capaciy equations
Bearing capaciy equationsPrionath Roy
 
সেনাবাহিনী
সেনাবাহিনীসেনাবাহিনী
সেনাবাহিনীPrionath Roy
 
~$Aring capaciy equations
~$Aring capaciy equations~$Aring capaciy equations
~$Aring capaciy equationsPrionath Roy
 
Why cod is greater than bod
Why cod is greater than bodWhy cod is greater than bod
Why cod is greater than bodPrionath Roy
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mistPrionath Roy
 
Rcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentRcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentPrionath Roy
 
Rcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentRcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentPrionath Roy
 
Water resource engineering question for gov
Water resource engineering question for govWater resource engineering question for gov
Water resource engineering question for govPrionath Roy
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mistPrionath Roy
 
Titas gas transmission and distribution company ltd
Titas gas transmission and distribution company ltdTitas gas transmission and distribution company ltd
Titas gas transmission and distribution company ltdPrionath Roy
 

More from Prionath Roy (15)

Pile capacity equations
Pile capacity equationsPile capacity equations
Pile capacity equations
 
Civil engineering suggestions for wasa
Civil engineering suggestions for wasaCivil engineering suggestions for wasa
Civil engineering suggestions for wasa
 
Civil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationCivil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examination
 
Bearing capaciy equations
Bearing capaciy equationsBearing capaciy equations
Bearing capaciy equations
 
Ad exam
Ad examAd exam
Ad exam
 
Active tab
Active tabActive tab
Active tab
 
সেনাবাহিনী
সেনাবাহিনীসেনাবাহিনী
সেনাবাহিনী
 
~$Aring capaciy equations
~$Aring capaciy equations~$Aring capaciy equations
~$Aring capaciy equations
 
Why cod is greater than bod
Why cod is greater than bodWhy cod is greater than bod
Why cod is greater than bod
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mist
 
Rcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentRcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitment
 
Rcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitmentRcc suggestion for up coming govt recruitment
Rcc suggestion for up coming govt recruitment
 
Water resource engineering question for gov
Water resource engineering question for govWater resource engineering question for gov
Water resource engineering question for gov
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mist
 
Titas gas transmission and distribution company ltd
Titas gas transmission and distribution company ltdTitas gas transmission and distribution company ltd
Titas gas transmission and distribution company ltd
 

Construction engineering formula sheet

  • 1. Construction Engineering Formula Sheet Earthwork Construction and Layout Basic Conversions 1 cubic yard = 27 cubic feet Basic must know properties Density of Water = 62.42 pounds per CF (pcf), 1,000 g/liter = 1,000kg/m3 Economic Haul Distance; Large Dozer up to 3000 ft; Scraper 3000 – 5000 ft; Trucks > 5000 ft lbs of concrete/sack of cement = 94 lbs One gallon of water = 8.34 lbs Density = Weight (lbs) / Volume(cf) Specific gravity = Density of material / Density of water Density of Water = 62.4 lbs/cf or 1000 kg/cubic meter 1 liter = 1 kg Excavation and embankment General Trapezoidal Formula: Area = (h0/2 + h1 + h2 + …+ h(n-1) + hn/2) x w Average end area Method = V = ((A1+A2)/2) * L Prismoidal Method = Vp = L*(A1+4AM+A2) / 6 Pyramid Method = V = AL / 3 Borrow Pit Volumes Conical Spoil Pile = Vol = (Ab x H) / 3; D = (7.64V / tan )1/3 ; H = (D/2) tan  ;where Ab=base area; H=pile height;D=diameter;  = angle of repose (deg) Triangular Spoil Bank = Vol = Cross section Area x L ; B = (4V/(L x tan )1/3 ; H = (B x tan ) / 2 ; V= pile volume; B= base width ; H = pile ht; L = pile length ;  = angle of repose (deg) Density of Water = γwater = Mw/Vw Moisture Content (w) = Mw/Ms Degree of Saturation (S) = Vw/Vv Total or Wet Density of Soil (γwet) = M/V where M = Mw + Ms ; V = Vw + Vs + Va
  • 2. Density of Solids = Ms/Vs Specific Gravity = Gs = γsolids /γwater ; or = Ms/(Vs * γwater ) Porosity (n) = Vv/Vt ; Vv = Volume of Voids = Vw + Va ; Vt = Total Volume = Vs +Vw + Va Void Ratio (e) = Vv/Vs Dry Density of Soil (γdry) = Ms /V Dry Density of Soil (γdry) = γwet / (1+w); (γdry) = (γwater*Gs) / (1+(w/S)*Gs) (γdry)=(γwater * Gs)/(1+e) Specific Gravity = S * e = Gs * w Porosity (n) = e/(1+e) Void Ratio (e) = n/(1-n) VCompacted = VBanked (1 – SHRINKAGE) VLoose = VBanked (1+SWELL) Swell % = ((DB – DL) / DL) x 100 ; Swell = (DB – DL)/DL Shrinkage % = ((DC – DB) / DL) x 100 ; Shrinkage = (DC – DB)/DL DL = Dry Loose unit wt (pcf) ; DB = Dry Bank unit wt (pcf) ; DC = Dry compacted unit wt(pcf) Vloose = Vc (1+Swll)/(1- Shrinkage) ; Vbank = Vc / (1-Shrinkage) Site Layout and Control Height of Instrument (HI) = Known elevation + Backsight (BS) Turning Point (TP) = Height of Instrument (HI) – Foresight (FS) Trigonometric Leveling  Elevation at unknown location = elevation at known + HI + (slope distance sin (angle of slope)) – distance from known to unknown location Traverse Area: Method of Coordinates; The area is A = ½ (Sum of full line products – Sum of broken line products) Earthwork Mass Diagrams Rising section = cut; Falling section = fill; zero slope = moving from cut to fill or vice versa
  • 3. Estimating Quantities and Cost Quantity take-off methods Trenching: Be careful to fully understand what the dimensions represent, Use horizontal In-In and Vertical Out-Out Estimating # bricks in wall : net wall (sf) = Gross surface Area of Wall (sf) – Area of open surface (sf)  then find surface area of brick with mortar (sf)  (net wall / SA of one brick) x # rows = bricks in wall Volume of mortar per brick = (mortar thickness)(brick width)(length + height + mortar thickness) Board feet = Thickness(in) x Width (in) x Length (in) / 144 Rebar = When finding the number of rebar bars in wall = # rebar = (the length of wall / spacing of bars) + 1 Engineering economics Present/Future Value: F= P(1+i) n or P = F/ (1+i) n ; i= (F/P) 1/n – 1 Series Payment : P=A[(1+i) n - 1]/[I (1+i) n ] ; F=A[(1+i) n - 1]/[i] Future/Present Value and Arithmetic gradient: F=G/i[((1+i) n - 1)/i)-n] ; P=G(i(1+i) n - iN - 1)/(i2 (1+i)n ] Depreciation: Straight Line Method : Dn = (Initial Cost – Salvage Value)/ N Sum of the years Digit Method: Dn = (n2 + n)/ 2 Declining balance Method: Dn = 2 x (1/n) Construction Operations and Methods Lifting and Rigging Solve for Center of Gravity: Ax = (A1)(x1) + (A2)(x2) + … + (An)(xn) ; where A= Total Area x = distance to the CoG in the x direction, A1 and A2 = Area/Volume or Mass; x1 and x2 = distance to the CoG
  • 4. Crane selection erection and stability Crane Stability: Factor of Safety against toppling = Resisting moment / Toppling moment Toppling Moment = (Weight of Load(WL)) x (Distance from toppling pt to Load)(LL) + Weight of boom(WB) x Distance to Center of Boom(LB) Resisting Moment = = (Weight of Counter Weight (WC)) x (Distance from toppling pt to Counterweight)(LC) + Weight of Crane Body(WG) x Distance to Center of Crane Body(LG)
  • 5. Equipment Production Dozer: Total Time = Q / (P x N) : Q = Quantity of material to be moved; P = hourly production rate per dozer; N = Number of Dozers Grader: Total Time = (P x D) / (S x E): P= number of passes required; D = distance traveled in each pass, in miles or feet; S = speed of grader, in mph or fpm (multiply mph by 88 to convert to fpm; E = efficiency factor Scraper: Total time (hours) = Q / P x N  Q = total volume to move(BCY), P = hourly production rate (BCY/hr), N = number of scrapers Loader: Maximum production rate (LCY per hour) = heaped bucket capacity x bucket fill factor x 60 minutes/ loader cycle time (min) Net production rate (LCY per hour) = maximum production rate (LCY per hour) x efficiency factor Excavator: q = ((3600 sec/hour x B x E x P)/ C) x Volume Correction  q = Volume of soil excavated and dumped in a truck by the excavator (CY/hr), B = Bucket struck capacity (CY), E = Bucket efficiency factor, P = Productivity factor, C = Cycle time for 90 degree angle and optimum depth Compactor: Production (CCY per hour) = (16.3 x W x S x L x E) / N  W = compacted width per pass (in feet), S = compactor speed(mph), L= compacted lift thickness(in), E = efficiency, N = number of passes required Compactor: Compactors required = FD x SCF / CP  FD = amount of fill delivered (LCY per hour), SCF = soil conversion factor (LCY:BCY), CP = compactor production (CCY per hour) Dump Truck: Number of trucks required = 1 + truck cycle time (minutes) / loader cycle time (minutes) Scheduling CPM Network Analysis Total Float(TF) = Late Finish(LF) – Early Finish(EF) ; TF = LF – (Early Start(ES)) + Duration(D)) = LF – ES – D Total Float (TF) = Late Start (LS) – Early Start (ES) TF = LS – ES = LS – (EF – D) = LS – EF + D Total Float (TF) = Free Float (FF) + Independent Float (IF) Free Float = Early Start of successor – Early Finish of Activity Independent Float = Early start of successor – Late finish of predecessor – duration of Activity Forward pass  Early start + Duration = Early Finish : Backward pass  Late Finish – Duration = Late Start Early Finish = Early Start + Duration ; Early Start = Early Finish – Duration
  • 6. Activity Time Analysis Expected Duration of activity = (a + 4b + c) / 6  where a = optimistic estimate; b = most likely Estimate; c = pessimistic estimate Time Cost Trade off Cost Slope = (crash cost – normal cost) / (normal time – crash time) Material Quality Control and Production Concrete Mix Design Water / Cement Ratio = Weight of Water (lbs) / Weight of Cement (lbs) Air Content (%) = Volume of Air (cf) / Total Volume of Concrete (cf) Volume of material (cf) = Weight of material (lbs) / ( 62.4 x specific gravity of material) Volume = Weight of material (lbs) / density of material (lbs/cf) Temporary Structures Construction Loads As per ASCE 37-02, Cp = Lo (.25 + 15/sqrt(AI))  Cp = reduced design uniformly distributed Personnel and Equipment load per sf, Lo = is the unreduced uniformly distributed P&E per sf; AI = is the influence area, sf P&E on slope roof; R = 1.2 –0.5F  where F = slope of the roof (in/ft); R = Reduction Factor (.6 < R < 1.0) Formwork Lateral pressure of concrete(p) = wh or ρgh  p = lateral pressure, lb/ft2 ; w = unit weight of concrete, lb/ft3 ; ρ = density of concrete (kg/m3 ); g = gravitational constant, 9.81 N/kg ; h = depth of fluid or plastic concrete from top of placement to point of consideration in form, ft(m). ACI Lateral pressure equations: Columns: For slump 7in or less to depth of 4ft or less: pmax = CwCc[150 + 9000 R/T] Walls: rate of placement (R) less than 7ft/h and height not exceeding 14 ft: pmax = CwCc[150 + 9000 R/T] Walls: R is 7ft/hr to 15ft/hr and height not exceeding 14 ft: pmax = CwCc[150 + 43,400/T +2800R/T] R = rate of placement(ft/hr), T = temperature of concrete during placing, o F, Cw = unit weight coefficient, Cc = chemistry coefficient
  • 7. Shoring and Reshoring Use ACI SP-4 Formwork for concrete Concrete maturity and early strength evaluation Bracing P = (H x h1 x L1) / (h2 x L2)  P = strut load per foot of form (lb/ft)(kN/m) ; H = lateral load at top of form ( lb/ft ) (kN/m) ; h1 = height of form (ft)(m) ; H2 = height of top of strut (ft)(m) ; L1 = length of strut (ft) (m) ; L2 = horizontal distance from form to bottom of strut (ft) (m) Pressure applied to wall due to wind ; P = .00256 Vc2  Vc = Wind Velocity Anchorage The force required to pull the concrete apart = Force (lbs) = material cohesion (lbs/in2 ) x Surface Area of failure Surface Area of a Cone = pi x r x sqrt (r2 + h2 ) Volume of the Cone = 1/3 (pi x r2 x h) Cofferdam (systems for temporary excavation support) F1 = wh1 2 / 2 ; F2 = wh2 2 / 2 ; w = unit weight of water ; h1 = outside water height ; h2 = inside water height F1 = outside hydrostatic force ; F2 = inside hydrostatic force ; F3 = water buoyancy force If h1 = 2 h2, then F1 = 4 F2 and F3 = ¾ F1
  • 8. Worker Health, Safety, and Environment Safety Statistics (e.g., incident rate, EMR) OSHA Incident Rate = (# of Injuries & Illness * 200,000) / Total hrs all employees Fatal Accident Rate = (# of Fatalities * 108 ) / Total hrs all employees Fatality Rate = (# of Fatalities / yr) / (Total # people exposed)