SlideShare a Scribd company logo
1 of 10
Download to read offline
When trying to figure out Borrow Pit Problems you need to understand a few things.
1. Water can be added or removed from soil
2. The MASS of the SOLIDS CAN NOT be changed
3. Need to know phase relationships in soil….which I will show you next
Phase relationship in Soil
This represents the soil that you take from a
borrow pit. It is made up of AIR, WATER, and
SOLIDS.
So if you separated the soil into its components
it would look like this. It is referred to as a Soil
Phase Diagram.
When looking at a Soil Phase Diagram you
think of it two ways, 1. Volume, 2. Mass.
AIR
WATER
SOIL
AIR
WATER
SOIL
Volume
Va
Vw
Vs
Mass
Ma = 0
Mw
Ms
Va = Volume Air
Vw = Volume Water
Vs = Volume Solid
Ma = Mass Air = 0
Mw = Mass Water
Ms = Mass Solid
Vt = Volume Total = Va + Vw + Vs
Mt = Mass Total = Mw + Ms
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
Basic Terms/Formulas to know – Soil Phase relationship
Density of Water = γwater = Mw/Vw
English Units = 62.42 pounds per CF(pcf)
SI Units = 1,000 g/liter = 1,000kg/m3
Specific Gravity = Gs = γsolids /γwater
=Ms/(Vs * γwater )
Moisture Content (w) = Mw/Ms Porosity (n) = Vv/Vt
Vv = Volume of Voids = Vw + Va
Vt = Total Volume = Vs +Vw + Va
Degree of Saturation (S) = Vw/Vv
Vw = Volume of Water
Vv = Total Volume of Voids
Void Ratio (e) = Vv/Vs
Vv = Total Volume of Voids
Vs = Volume of Solid
Total or Wet Density of Soil (γwet) = M/V
M = Mw + Ms
V = Vw + Vs + Va
Dry Density of Soil (γdry) = Ms /V
V = Vw + Vs + Va
Density of Solids = Ms/Vs
Specific Gravity = the density of the solids divided by the density of Water
Moisture Content = Mass of Water divided by the Mass of Solids
Void Ratio = Volume of Voids divided by the Volume of Solids
Porosity = Volume of Voids divided by the Total Volume,
Higher porosity = higher permeability
Specific Gravity = S * e = Gs * w
Porosity (n) = e/(1+e)
Void Ratio (e) = n/(1-n)
Total or Wet Density of Soil (γwet) =
γwet = ((γwater * Gs ( 1+w))/(1+e)
Dry Density of Soil (γdry) = γwet /(1+w)
(γdry) = (γwater * Gs)/(1+(w/S)*Gs)
(γdry) = (γwater * Gs)/(1+e)
Relationships to know
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
Load and Shrinkage Factors
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
AIR
WATER
SOIL
AIR
WATER
SOIL
AIR
WATER
SOIL
1.0BCY
1.25LCY
.90CCY
VB
VL = VB (1+SWELL)
VL = VB x SWELL FACTOR(or Load factor)
VC = VB (1 - SHRINKAGE)
VC = VB x SHRINKAGE FACTOR
DL = Dry Loose Unit Weight (γDL)
DC = Dry Compacted Unit Weight (γDC)
DB = Dry Bank Unit Weight (γDB)
Important Volume Change Relationships:
In excavation, 1+Swell is called “Swell Factor”
LCY to CCY:
CCY to BCY:
Borrow-Pit Method
 Another important concept to know is the Borrow Pit Method in order to calculate the
volume of the borrow pit. It is also called the unit-area method.
 The Volume is determined based on a predetermined grid pattern. The site is divided
into equal squares of sides 20,50, or a 100 ft. Elevations are then measured at the corners
of the grid, which are given titles that correspond to the coordinates of the corner in the
grid, ex: 3-D, 4-A,..
 Then for simplicity of calculations, the points are connected to the corners
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
WWW.LEARNCIVILENGINEERING.COM
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
Question #1: After surveying a borrow pit, the surveyor produced the
following borrow pit grid below. If you consider 0.0, the elevation that you
can cut to. What is the total cut volume (cy) available?
a.  250 cy
b.  232 cy
c.  201 cy
d.  343 cy
A B
C D E
G
F
2.4
2.8
3.2
3.5
3.3
3.1
2.1
2.4
2.8
1.8
1.6
1.3
20 feet
20 feet
20 feet
20 feet
20 feet
Question # 2: 120cy of bank soil is excavated and stockpiled before being
trucked and then compacted. The soil has a swell of 25% and a shrinkage of
15%.
What is the final volume of the compacted soil?
a.  68 cy
b.  102 cy
c.  150 cy
d.  128 cy
Question #3. A 10 ft wide, 500 ft long, 2 ft thick road is being constructed. The soil
density after compaction was found to be 112.1 pcf at an optimum moisture content
of 10.5%. The soil from the borrow pit has a total density of 105pcf and a moisture
content of 8.5%
What is the total volume(cf) of soil that needs to be hauled from the borrow pit?
a.  45,395 cf
b.  12,856 cf
c.  11,584 cf
d.  5,260 cf
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
Question # 4. Soil borings at a proposed Borrow Pit indicate that the soil is
primarily a sandy clay. Cores taken of the soil in the pit indicates an average
dry density of 88pcf at a moisture content of 22%.
The volume of the contained soil in the fill when constructed is 20,000 cy.
Based on the average results of a Standard Proctor compaction test the soil
will be compacted to a density of 95 pcf at a moisture content of 25%.
Dump trucks with a capacity of 15cy will be used to transport the soil from the
borrow pit to the proposed road bed.
1. Assuming that the soil in the dump truck has a dry density of 69 pcf at a
moisture content of 22% estimate the number of loads that will be necessary.
2. Compute the volume of the hole at the borrow pit after the soil is removed
a.  68 trucks
b.  12,856 trucks
c.  658 trucks
d.  1,836 trucks
a.  36,568 cy
b.  21,591 cy
c.  24,564 cy
d.  19,836 cy
WWW.LEARNCIVILENGINEERING.COM
Answer #1:
Step 1: Setup a chart to get the volume under each square; Then sum up all
the volumes.
Step 2: Find Volume in Cubic yards
 Vtotal = 6260 cf / (27cf/cy) = 232 cy
EARTHWORK CONSTRUCTION AND LAYOUT
**BORROW PIT VOLUMES**
Grid Area (sf) Average depth (ft) Volume (cf)
A 400 (2.4+3.5+2.8+3.3)/4 = 3.0 1200
B 200 (3.5+3.3+2.1)/3 = 2.97 594
C 400 (2.8+3.3+3.2+3.1)/4 = 3.1 1240
D 400 (3.3+2.1+3.1+2.4)/4 = 2.7 1080
E 400 (2.1+1.8+2.4+1.6)/4 = 1.98 792
F 200 (3.1+2.4+2.8)/3 = 2.77 554
G 400 (2.4+2.8+1.6+1.3)/4 = 2.0 800
Vtotal = 6260cf
Answer #2:
The shrinkage factor is taken with respect to the bank volume condition.
- so, Vcompacted fill =(1-.15)(120cy) = 102cy
For your information the swell is taken with respect to the bank volume
condition too.
- so, Vstockpile =(1+.25)(120cy) = 150cy
Answer #3:
Step 1: Find the mass of solids (Ms) required for the controlled fill:
- Volume of Compacted soil = (500ft)(10ft)(2ft) = 10,000 cf
- dry density of the compacted soil is given = 112.1 pcf
- using Dry Density of Soil (γdry) = Ms /V = 112.1pcf = Ms /10,000cf, so Ms =
1,121,000 lbs
Step 2: Find total volume of soil that needs to be hauled from the borrow pit:
- using Moisture Content (w) = Mw/Ms , .085 = Mw/1,121,000lbs = Mw = 95,285
lbs
- Total Mass at borrow pit = 1,121,000lbs + 95,285lbs = 1,216,285 lbs
- using Total or Wet Density of Soil (γwet) =
M/V = 105pcf = 1,216,285 lbs/V, V = 11,583.7 cf
FYI ----to figure out the Mass of water in compacted soil
- Moisture content in compacted soil given at 10.5% = .105
- using Moisture Content (w) = Mw/Ms , .105 = Mw/1,121,000lbs = Mw =
117,705 lbs
Answer #4:
Step 1: Find the mass of solids (Ms) required for the controlled fill:
- Volume of Compacted soil = 20,000 cy * 27cf/cy = 540,000 cf
- dry density of the compacted soil is given = 95 pcf
- using Dry Density of Soil (γdry) = Ms /V = 95 pcf = Ms /540,000 cf, so Ms =
51,300,000 lbs
Step 2: Find the # of Trucks required to haul Soil.
- Ms = 51,300,000 lbs, and the dry density of the soil to be hauled is 69 pcf
- so, 51,300,000 lbs/69pcf = 743,478 cf / 27cf/cy = 27,536 cy
- so the number of trucks needed is 27,536cy/15cy/truck = 1836 trucks
Step 3: Find the Volume at the borrow pit
- dry density of the compacted soil is given = 88 pcf
- (γdry) = Ms /V, 88pcf = 51,300,000 lbs/V, V= 51,300,000lbs/88pcf = 582,955cf
- convert to cy, 582,955cf/(27cf/cy) = 21,591cy

More Related Content

What's hot

Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Muhammad Irfan
 
Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Latif Hyder Wadho
 
(Part ii)- open channels
(Part ii)- open channels(Part ii)- open channels
(Part ii)- open channelsMohsin Siddique
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Hossam Shafiq II
 
Solution.manual elementary.surveying-13edition
Solution.manual elementary.surveying-13editionSolution.manual elementary.surveying-13edition
Solution.manual elementary.surveying-13editionAwais Ahmad
 
Traverse Survey Part 2/2
Traverse Survey Part 2/2Traverse Survey Part 2/2
Traverse Survey Part 2/2Muhammad Zubair
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Hossam Shafiq II
 
Design of two way slabs(d.d.m.)
Design of two way slabs(d.d.m.)Design of two way slabs(d.d.m.)
Design of two way slabs(d.d.m.)Malika khalil
 
Shrinkage Limit Test
Shrinkage Limit TestShrinkage Limit Test
Shrinkage Limit TestSOURABH PAL
 
Material Testing Lab Equipments
Material Testing Lab EquipmentsMaterial Testing Lab Equipments
Material Testing Lab EquipmentsNaveed Hussain
 
Examples on effective stress
Examples on effective stressExamples on effective stress
Examples on effective stressMalika khalil
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound InterestHector Tibo
 
3_hydrostatic-force_tutorial-solution(1)
3_hydrostatic-force_tutorial-solution(1)3_hydrostatic-force_tutorial-solution(1)
3_hydrostatic-force_tutorial-solution(1)Diptesh Dash
 
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]Geotechnical Engineering-I [Lec #24: Soil Permeability - II]
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]Muhammad Irfan
 
Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Md. Shahadat Hossain
 

What's hot (20)

Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]
 
Homework 1 (solution )
Homework 1 (solution )Homework 1 (solution )
Homework 1 (solution )
 
Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)
 
(Part ii)- open channels
(Part ii)- open channels(Part ii)- open channels
(Part ii)- open channels
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
 
Solution.manual elementary.surveying-13edition
Solution.manual elementary.surveying-13editionSolution.manual elementary.surveying-13edition
Solution.manual elementary.surveying-13edition
 
Traverse Survey Part 2/2
Traverse Survey Part 2/2Traverse Survey Part 2/2
Traverse Survey Part 2/2
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
 
Design of two way slabs(d.d.m.)
Design of two way slabs(d.d.m.)Design of two way slabs(d.d.m.)
Design of two way slabs(d.d.m.)
 
Shrinkage Limit Test
Shrinkage Limit TestShrinkage Limit Test
Shrinkage Limit Test
 
Material Testing Lab Equipments
Material Testing Lab EquipmentsMaterial Testing Lab Equipments
Material Testing Lab Equipments
 
Examples on effective stress
Examples on effective stressExamples on effective stress
Examples on effective stress
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound Interest
 
3_hydrostatic-force_tutorial-solution(1)
3_hydrostatic-force_tutorial-solution(1)3_hydrostatic-force_tutorial-solution(1)
3_hydrostatic-force_tutorial-solution(1)
 
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]Geotechnical Engineering-I [Lec #24: Soil Permeability - II]
Geotechnical Engineering-I [Lec #24: Soil Permeability - II]
 
Phase relations
Phase relationsPhase relations
Phase relations
 
3) sampling
3) sampling3) sampling
3) sampling
 
stress distribution in soils
stress distribution in soilsstress distribution in soils
stress distribution in soils
 
Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)
 
Ge 105 lecture 3 (LEVELING ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 3 (LEVELING ADJUSTMENT) by: Broddett B. AbatayoGe 105 lecture 3 (LEVELING ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 3 (LEVELING ADJUSTMENT) by: Broddett B. Abatayo
 

Similar to Borrow pit-volumes

Geotechnical engineering numerical
Geotechnical engineering numerical Geotechnical engineering numerical
Geotechnical engineering numerical wasim shaikh
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Muhammad Irfan
 
Consolidation nec
Consolidation necConsolidation nec
Consolidation necGokul Saud
 
Solution to first semester soil 2015 16
Solution to first semester soil 2015 16Solution to first semester soil 2015 16
Solution to first semester soil 2015 16chener Qadr
 
Soil Mechanics-Index Properties and Solid,water,air relation.pdf
Soil Mechanics-Index Properties and Solid,water,air relation.pdfSoil Mechanics-Index Properties and Solid,water,air relation.pdf
Soil Mechanics-Index Properties and Solid,water,air relation.pdfBinita Kunwar
 
Geo technical properties of soil by sajid hussain
Geo technical properties of soil by sajid hussainGeo technical properties of soil by sajid hussain
Geo technical properties of soil by sajid hussainsajid hussain
 
Soil Compaction - Civil Engineering
Soil Compaction - Civil EngineeringSoil Compaction - Civil Engineering
Soil Compaction - Civil EngineeringLatif Hyder Wadho
 
Compaction tests
Compaction testsCompaction tests
Compaction testsAmi jasani
 
compaction test
compaction testcompaction test
compaction testBahzad5
 
Geo Technical Engineering (Compaction)
Geo Technical Engineering (Compaction)Geo Technical Engineering (Compaction)
Geo Technical Engineering (Compaction)Latif Hyder Wadho
 
Determination of in situ density of soil
Determination of in situ density of soilDetermination of in situ density of soil
Determination of in situ density of soilSumanHaldar8
 
Question bank of soil mechanics
Question bank of soil mechanicsQuestion bank of soil mechanics
Question bank of soil mechanicsPrashantha Tr
 
Lecture soil compaction
Lecture  soil compactionLecture  soil compaction
Lecture soil compactionPookodu
 
Lecture soil compaction
Lecture  soil compactionLecture  soil compaction
Lecture soil compactionPookodu
 

Similar to Borrow pit-volumes (20)

Unit 1 PPT.pptx
Unit 1 PPT.pptxUnit 1 PPT.pptx
Unit 1 PPT.pptx
 
Geotechnical engineering numerical
Geotechnical engineering numerical Geotechnical engineering numerical
Geotechnical engineering numerical
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]
 
Soil moisture
Soil moisture Soil moisture
Soil moisture
 
Settlement
SettlementSettlement
Settlement
 
Consolidation nec
Consolidation necConsolidation nec
Consolidation nec
 
Solution to first semester soil 2015 16
Solution to first semester soil 2015 16Solution to first semester soil 2015 16
Solution to first semester soil 2015 16
 
Introduction to Soil Mechanics
Introduction to Soil MechanicsIntroduction to Soil Mechanics
Introduction to Soil Mechanics
 
Soil Mechanics-Index Properties and Solid,water,air relation.pdf
Soil Mechanics-Index Properties and Solid,water,air relation.pdfSoil Mechanics-Index Properties and Solid,water,air relation.pdf
Soil Mechanics-Index Properties and Solid,water,air relation.pdf
 
Geo technical properties of soil by sajid hussain
Geo technical properties of soil by sajid hussainGeo technical properties of soil by sajid hussain
Geo technical properties of soil by sajid hussain
 
Mix design
Mix designMix design
Mix design
 
Soil Compaction - Civil Engineering
Soil Compaction - Civil EngineeringSoil Compaction - Civil Engineering
Soil Compaction - Civil Engineering
 
Compaction tests
Compaction testsCompaction tests
Compaction tests
 
compaction test
compaction testcompaction test
compaction test
 
Geo Technical Engineering (Compaction)
Geo Technical Engineering (Compaction)Geo Technical Engineering (Compaction)
Geo Technical Engineering (Compaction)
 
5 soil compaction
5 soil compaction5 soil compaction
5 soil compaction
 
Determination of in situ density of soil
Determination of in situ density of soilDetermination of in situ density of soil
Determination of in situ density of soil
 
Question bank of soil mechanics
Question bank of soil mechanicsQuestion bank of soil mechanics
Question bank of soil mechanics
 
Lecture soil compaction
Lecture  soil compactionLecture  soil compaction
Lecture soil compaction
 
Lecture soil compaction
Lecture  soil compactionLecture  soil compaction
Lecture soil compaction
 

More from Prionath Roy

Pile capacity equations
Pile capacity equationsPile capacity equations
Pile capacity equationsPrionath Roy
 
Marshal mix design
Marshal mix designMarshal mix design
Marshal mix designPrionath Roy
 
Load reduction factor_ǿ
Load reduction factor_ǿLoad reduction factor_ǿ
Load reduction factor_ǿPrionath Roy
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)Prionath Roy
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavelPrionath Roy
 
Document given by hassan
Document given by hassanDocument given by hassan
Document given by hassanPrionath Roy
 
Construction engineering formula sheet
Construction engineering formula sheetConstruction engineering formula sheet
Construction engineering formula sheetPrionath Roy
 
Civil engineering suggestions for wasa
Civil engineering suggestions for wasaCivil engineering suggestions for wasa
Civil engineering suggestions for wasaPrionath Roy
 
Civil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationCivil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationPrionath Roy
 
Bearing capaciy equations
Bearing capaciy equationsBearing capaciy equations
Bearing capaciy equationsPrionath Roy
 
সেনাবাহিনী
সেনাবাহিনীসেনাবাহিনী
সেনাবাহিনীPrionath Roy
 
~$Aring capaciy equations
~$Aring capaciy equations~$Aring capaciy equations
~$Aring capaciy equationsPrionath Roy
 
Why cod is greater than bod
Why cod is greater than bodWhy cod is greater than bod
Why cod is greater than bodPrionath Roy
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mistPrionath Roy
 
Suggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examSuggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examPrionath Roy
 
Suggestion done by me
Suggestion done by meSuggestion done by me
Suggestion done by mePrionath Roy
 

More from Prionath Roy (20)

Pile capacity equations
Pile capacity equationsPile capacity equations
Pile capacity equations
 
Marshal mix design
Marshal mix designMarshal mix design
Marshal mix design
 
Load reduction factor_ǿ
Load reduction factor_ǿLoad reduction factor_ǿ
Load reduction factor_ǿ
 
Influence linebeams (ce 311)
Influence linebeams (ce 311)Influence linebeams (ce 311)
Influence linebeams (ce 311)
 
Environmental engg. pavel
Environmental engg. pavelEnvironmental engg. pavel
Environmental engg. pavel
 
Document1
Document1Document1
Document1
 
Document given by hassan
Document given by hassanDocument given by hassan
Document given by hassan
 
Construction engineering formula sheet
Construction engineering formula sheetConstruction engineering formula sheet
Construction engineering formula sheet
 
Civil engineering suggestions for wasa
Civil engineering suggestions for wasaCivil engineering suggestions for wasa
Civil engineering suggestions for wasa
 
Civil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examinationCivil engineering suggestions for upcoming examination
Civil engineering suggestions for upcoming examination
 
Bearing capaciy equations
Bearing capaciy equationsBearing capaciy equations
Bearing capaciy equations
 
Ad exam
Ad examAd exam
Ad exam
 
Active tab
Active tabActive tab
Active tab
 
Active tab
Active tabActive tab
Active tab
 
সেনাবাহিনী
সেনাবাহিনীসেনাবাহিনী
সেনাবাহিনী
 
~$Aring capaciy equations
~$Aring capaciy equations~$Aring capaciy equations
~$Aring capaciy equations
 
Why cod is greater than bod
Why cod is greater than bodWhy cod is greater than bod
Why cod is greater than bod
 
Titas question of mist
Titas question of mistTitas question of mist
Titas question of mist
 
Suggestion for govt. job recruitment exam
Suggestion for govt. job recruitment examSuggestion for govt. job recruitment exam
Suggestion for govt. job recruitment exam
 
Suggestion done by me
Suggestion done by meSuggestion done by me
Suggestion done by me
 

Borrow pit-volumes

  • 1. When trying to figure out Borrow Pit Problems you need to understand a few things. 1. Water can be added or removed from soil 2. The MASS of the SOLIDS CAN NOT be changed 3. Need to know phase relationships in soil….which I will show you next Phase relationship in Soil This represents the soil that you take from a borrow pit. It is made up of AIR, WATER, and SOLIDS. So if you separated the soil into its components it would look like this. It is referred to as a Soil Phase Diagram. When looking at a Soil Phase Diagram you think of it two ways, 1. Volume, 2. Mass. AIR WATER SOIL AIR WATER SOIL Volume Va Vw Vs Mass Ma = 0 Mw Ms Va = Volume Air Vw = Volume Water Vs = Volume Solid Ma = Mass Air = 0 Mw = Mass Water Ms = Mass Solid Vt = Volume Total = Va + Vw + Vs Mt = Mass Total = Mw + Ms EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES**
  • 2. Basic Terms/Formulas to know – Soil Phase relationship Density of Water = γwater = Mw/Vw English Units = 62.42 pounds per CF(pcf) SI Units = 1,000 g/liter = 1,000kg/m3 Specific Gravity = Gs = γsolids /γwater =Ms/(Vs * γwater ) Moisture Content (w) = Mw/Ms Porosity (n) = Vv/Vt Vv = Volume of Voids = Vw + Va Vt = Total Volume = Vs +Vw + Va Degree of Saturation (S) = Vw/Vv Vw = Volume of Water Vv = Total Volume of Voids Void Ratio (e) = Vv/Vs Vv = Total Volume of Voids Vs = Volume of Solid Total or Wet Density of Soil (γwet) = M/V M = Mw + Ms V = Vw + Vs + Va Dry Density of Soil (γdry) = Ms /V V = Vw + Vs + Va Density of Solids = Ms/Vs Specific Gravity = the density of the solids divided by the density of Water Moisture Content = Mass of Water divided by the Mass of Solids Void Ratio = Volume of Voids divided by the Volume of Solids Porosity = Volume of Voids divided by the Total Volume, Higher porosity = higher permeability Specific Gravity = S * e = Gs * w Porosity (n) = e/(1+e) Void Ratio (e) = n/(1-n) Total or Wet Density of Soil (γwet) = γwet = ((γwater * Gs ( 1+w))/(1+e) Dry Density of Soil (γdry) = γwet /(1+w) (γdry) = (γwater * Gs)/(1+(w/S)*Gs) (γdry) = (γwater * Gs)/(1+e) Relationships to know EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES**
  • 3. Load and Shrinkage Factors EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES** AIR WATER SOIL AIR WATER SOIL AIR WATER SOIL 1.0BCY 1.25LCY .90CCY VB VL = VB (1+SWELL) VL = VB x SWELL FACTOR(or Load factor) VC = VB (1 - SHRINKAGE) VC = VB x SHRINKAGE FACTOR DL = Dry Loose Unit Weight (γDL) DC = Dry Compacted Unit Weight (γDC) DB = Dry Bank Unit Weight (γDB) Important Volume Change Relationships: In excavation, 1+Swell is called “Swell Factor” LCY to CCY: CCY to BCY:
  • 4. Borrow-Pit Method  Another important concept to know is the Borrow Pit Method in order to calculate the volume of the borrow pit. It is also called the unit-area method.  The Volume is determined based on a predetermined grid pattern. The site is divided into equal squares of sides 20,50, or a 100 ft. Elevations are then measured at the corners of the grid, which are given titles that correspond to the coordinates of the corner in the grid, ex: 3-D, 4-A,..  Then for simplicity of calculations, the points are connected to the corners EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES**
  • 5. WWW.LEARNCIVILENGINEERING.COM EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES** Question #1: After surveying a borrow pit, the surveyor produced the following borrow pit grid below. If you consider 0.0, the elevation that you can cut to. What is the total cut volume (cy) available? a.  250 cy b.  232 cy c.  201 cy d.  343 cy A B C D E G F 2.4 2.8 3.2 3.5 3.3 3.1 2.1 2.4 2.8 1.8 1.6 1.3 20 feet 20 feet 20 feet 20 feet 20 feet Question # 2: 120cy of bank soil is excavated and stockpiled before being trucked and then compacted. The soil has a swell of 25% and a shrinkage of 15%. What is the final volume of the compacted soil? a.  68 cy b.  102 cy c.  150 cy d.  128 cy
  • 6. Question #3. A 10 ft wide, 500 ft long, 2 ft thick road is being constructed. The soil density after compaction was found to be 112.1 pcf at an optimum moisture content of 10.5%. The soil from the borrow pit has a total density of 105pcf and a moisture content of 8.5% What is the total volume(cf) of soil that needs to be hauled from the borrow pit? a.  45,395 cf b.  12,856 cf c.  11,584 cf d.  5,260 cf EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES** Question # 4. Soil borings at a proposed Borrow Pit indicate that the soil is primarily a sandy clay. Cores taken of the soil in the pit indicates an average dry density of 88pcf at a moisture content of 22%. The volume of the contained soil in the fill when constructed is 20,000 cy. Based on the average results of a Standard Proctor compaction test the soil will be compacted to a density of 95 pcf at a moisture content of 25%. Dump trucks with a capacity of 15cy will be used to transport the soil from the borrow pit to the proposed road bed. 1. Assuming that the soil in the dump truck has a dry density of 69 pcf at a moisture content of 22% estimate the number of loads that will be necessary. 2. Compute the volume of the hole at the borrow pit after the soil is removed a.  68 trucks b.  12,856 trucks c.  658 trucks d.  1,836 trucks a.  36,568 cy b.  21,591 cy c.  24,564 cy d.  19,836 cy
  • 7. WWW.LEARNCIVILENGINEERING.COM Answer #1: Step 1: Setup a chart to get the volume under each square; Then sum up all the volumes. Step 2: Find Volume in Cubic yards  Vtotal = 6260 cf / (27cf/cy) = 232 cy EARTHWORK CONSTRUCTION AND LAYOUT **BORROW PIT VOLUMES** Grid Area (sf) Average depth (ft) Volume (cf) A 400 (2.4+3.5+2.8+3.3)/4 = 3.0 1200 B 200 (3.5+3.3+2.1)/3 = 2.97 594 C 400 (2.8+3.3+3.2+3.1)/4 = 3.1 1240 D 400 (3.3+2.1+3.1+2.4)/4 = 2.7 1080 E 400 (2.1+1.8+2.4+1.6)/4 = 1.98 792 F 200 (3.1+2.4+2.8)/3 = 2.77 554 G 400 (2.4+2.8+1.6+1.3)/4 = 2.0 800 Vtotal = 6260cf
  • 8. Answer #2: The shrinkage factor is taken with respect to the bank volume condition. - so, Vcompacted fill =(1-.15)(120cy) = 102cy For your information the swell is taken with respect to the bank volume condition too. - so, Vstockpile =(1+.25)(120cy) = 150cy
  • 9. Answer #3: Step 1: Find the mass of solids (Ms) required for the controlled fill: - Volume of Compacted soil = (500ft)(10ft)(2ft) = 10,000 cf - dry density of the compacted soil is given = 112.1 pcf - using Dry Density of Soil (γdry) = Ms /V = 112.1pcf = Ms /10,000cf, so Ms = 1,121,000 lbs Step 2: Find total volume of soil that needs to be hauled from the borrow pit: - using Moisture Content (w) = Mw/Ms , .085 = Mw/1,121,000lbs = Mw = 95,285 lbs - Total Mass at borrow pit = 1,121,000lbs + 95,285lbs = 1,216,285 lbs - using Total or Wet Density of Soil (γwet) = M/V = 105pcf = 1,216,285 lbs/V, V = 11,583.7 cf FYI ----to figure out the Mass of water in compacted soil - Moisture content in compacted soil given at 10.5% = .105 - using Moisture Content (w) = Mw/Ms , .105 = Mw/1,121,000lbs = Mw = 117,705 lbs
  • 10. Answer #4: Step 1: Find the mass of solids (Ms) required for the controlled fill: - Volume of Compacted soil = 20,000 cy * 27cf/cy = 540,000 cf - dry density of the compacted soil is given = 95 pcf - using Dry Density of Soil (γdry) = Ms /V = 95 pcf = Ms /540,000 cf, so Ms = 51,300,000 lbs Step 2: Find the # of Trucks required to haul Soil. - Ms = 51,300,000 lbs, and the dry density of the soil to be hauled is 69 pcf - so, 51,300,000 lbs/69pcf = 743,478 cf / 27cf/cy = 27,536 cy - so the number of trucks needed is 27,536cy/15cy/truck = 1836 trucks Step 3: Find the Volume at the borrow pit - dry density of the compacted soil is given = 88 pcf - (γdry) = Ms /V, 88pcf = 51,300,000 lbs/V, V= 51,300,000lbs/88pcf = 582,955cf - convert to cy, 582,955cf/(27cf/cy) = 21,591cy