Lock Out Tag Out (LOTO)
Outline
• Importance of Lock
Out/Tag Out (LOTO)
• OSHA’s Control of
Hazardous Energy
standard
Why is LOTO important?
• The Lock Out/Tag Out
procedure prevents
the unexpected start
up or release of stored
energy that could
cause injury to
employees by placing
a lock and/or warning
tag on an energy
isolation device.
LOTO Program Enforcement
• A violation of an employee's responsibility
must be reported to the employee's
immediate supervisor for appropriate action.
• A violation of a contractor’s responsibility
must be reported to the project manager (or
the person who hired the contractor) for
appropriate action.
Regulatory Agencies

• Federal: Occupational Safety and Health
Administration (OSHA)
• State: Montana Occupational Safety & Health
Bureau (MOSHB)
Hazardous Energy Sources
• Electrical
• Mechanical (i.e.
motors, drive belts)
• Chemical (i.e. natural
gas, propane)
• Thermal
• Pneumatic
• Hydraulic
OSHA’s LOTO Standard
29 CFR 1910.147
• Requires a written energy control program
that includes defined energy control
procedures
• Requires documented employee training
• Requires periodic inspections at least
annually
• Requires certain equipment specifics
LOTO Program - Responsibilities
• Coordinate the LOTO
program;
• Training & assistance with
annual inspections;
• Maintain copies of
equipment specific lock out
procedures, annual
inspections & training
records; and
• Update & evaluate the LOTO
program annually.
LOTO Program - Responsibilities
• Notify contractors to bring
their LOTO program to
preconstruction meeting;
and
• Include LOTO as an
agenda item & allow
contractors & Employees
to discuss
LOTO Program
Employers Responsibilities
•
•
•
•
•

Complete equipment specific LOTO procedures;
Conduct annual & periodic inspections;
Keep a list of authorized employees;
Issue LOTO devices to employees;
Ensure all affected employees are properly
trained on LOTO procedures;
• Enforce compliance with LOTO program; and
• Provide employees with copies of the LOTO
Program upon request.
LOTO Program
Authorized Employee Responsibilities
• Attend required training;
• Follow all LOTO procedures;
• Assist supervisor’s in completing equipment
specific LOTO procedures;
• Consult supervisors when questions or
concerns arise; and
• Notify all affected employees of LOTO
activities.
LOTO Program - Contractors
• Contractor & on-site
employer must
exchange LOTO info
• On-site employees
must understand &
comply with the
contractor’s rules.
• Employees must be
alert & aware of any
new types of LOTO
devices.
LOTO Program - Equipment
• Must be singularly
identified;
• Must be the ONLY
devices for
controlling energy;
and
• Must NOT be used
for any other
purposes.
LOTO Program - Equipment

• Lock Out devices must be durable & withstand the
environment to which they are exposed. Tag out devices
must be constructed & printed so they do not deteriorate
or become illegible;
• LO/TO devices must be standardized by color, shape or
size;
• LO/TO devices must be substantial enough to prevent
early or accidental removal and removal without
excessive force.
LOTO Program - Equipment
• Lock out will be
accomplished
using a lock and
key. Chains, or
other hardware,
may be used in
conjunction with
the lock to isolate
the energy source.
LOTO Program - Equipment
• One key will be issued
to the authorized
employee applying the
lock.
LOTO Program - Equipment
• Tag Out devices must
include a legend such
as: DO NOT START,
DO NOT OPEN, DO
NOT CLOSE, DO
NOT ENERGIZE, DO
NOT OPERATE, etc.
• Tag Out devices must
have standardized
print and format.
LOTO Program
Required Tag Out Device Information
• Name of authorized employee who locked
out equipment;
• Authorized employee’s radio or phone
number, including contractors;
• Date and time of lockout; and
• Brief description of work being performed.
LOTO Program - Equipment
• An approved warning tag
should accompany all
lockouts.
• The warning tag should
be attached directly to
the lockout device by a
nylon tie.
LOTO Program - Procedures
• Preparation for shutdown
• Shutting down the
equipment
• Equipment isolation
• Application of LOTO devices
• Release of stored energy
• Verifying equipment isolation
LOTO Program
Prep For Shutdown
• Know the types and amounts of
energy that power specific
equipment
• Know the hazards of that energy
• Know how the energy can be
controlled – review equipment
specific procedures if necessary
• Direct any questions to
immediate supervisor
LOTO Program
Shutting Down Equipment
• Notify ALL affected employees that a LOTO
procedure is being used and why.
• Shut the equipment down using operating
controls.
• Follow proper procedure for the equipment
to avoid endangering anyone during the
shutdown.
LOTO Program - Energy Isolation
• Lock Out / Tag Out energy isolating sources with
assigned locks and tags. Usually requires locking
out electrical disconnect.
• Be sure to isolate ALL energy sources (secondary
as well as primary).
LOTO Program
Application of Devices
• Use valve covers, plug
locks, etc. if the lock can’t
be placed directly on the
energy control.
• When Lock Out is used,
every employee in the work
crew must attach their own
personal lock.
LOTO Program
Application of Devices
• A Tag Out system alone is not acceptable at any
time unless the equipment is not capable of
being locked out.
• The tag must be placed at the same location that
the lockout device would have been attached,
and additional measures must be taken to
ensure the level of safety is equivalent to that
obtained by using a lock.
• This includes: blocking of a controlling switch,
removal of an isolating circuit element, opening
of an extra disconnect device, or removal of a
valve handle ONLY.
LOTO Program
Release of Stored Energy
• Inspect the system to make
sure all parts have stopped
moving.
• Disperse stored energy
(springs, hydraulic systems,
air, gas, water pressure, or
steam).
• If stored energy can build up
again, monitor it to make
certain it stays below
hazardous levels.
LOTO Program
Verifying Equipment Isolation
• Make certain all dangerous
areas are clear of personnel.
• Verify that the equipment
cannot be turned to the “on”
position.
• Press all “start” buttons and
activating controls on the
equipment.
• Return all controls to the “off”
position after certain that Lock
Out is effective.
LOTO Program
Removing LOTO Devices / Restoring
Equipment

• Safeguard all employees by making certain
everyone is clear of the equipment. Also
notify affected employees of impending reenergization.
• Verify that all tools have been removed and
all guards reinstalled.
• Remove LOTO devices. Each device must
be removed by the person who put it on.
• Energize equipment.
LOTO Program - Troubleshooting
• Remove all tools & personnel from the area.
• Notify affected employees of impending reenergization.
• Authorized employees remove the Lock Out
device but MUST leave tag in place.
• Energize equipment.
• When finished, de-energize & reapply Lock
Out device.
LOTO Program - Shift Changes
• If servicing lasts more than one shift, LOTO
protection CANNOT be interrupted.
• The original authorized employee will
remove their lock & the incoming employee
will place theirs on the isolating device.
• The incoming authorized employee MUST
VERIFY that ALL energy sources are
locked out prior to beginning work.
LOTO Program
Abandoned Lock Procedure
• Verify authorized employee has left the worksite &
notify them that their lock is being removed.
• LOTO devices may ONLY be removed if supervisor
is present & authorizes removal.
• After all communication attempts are complete & the
equipment has been inspected, lock can be removed
and new lock installed.
• Notify employee their lock was removed prior to
starting new shift.
LOTO Program - Exceptions
• Work on cord & plug equipment
IF it is unplugged, the plug
remains within arms reach during
servicing and authorized
employee has exclusive control
of the plug.
• If guards aren’t removed or
bypassed & are effective in
preventing worker exposure to
hazards created by the
unexpected energization or start
up of machines or equipment, or
the release of energy.
LOTO Program
Equipment Specific LOTO
• Equipment Specific LOTO forms must be
completed by the supervisor and / or the
authorized employee.
• All equipment specific procedures should be
easily accessible or posted directly on the
equipment.
LOTO Program
Equipment Specific Procedures
Procedures must be updated when:
• New equipment is installed; or
• New energy sources are added to a facility
or individual equipment; or
• Magnitude of an energy source changes; or
• Designated isolation points change.
LOTO Program - Training
• Supervisors
• Authorized
Employees
• All Employees
LOTO Program - Re-Training
• Change in authorized employee’s job assignments
or job area that contains sources of hazardous
energy;
• Change in machines, equipment or process that
presents a new hazard;
• Change in energy control procedures;
• Need for refresher training found during periodic
inspections; and/or
• Employer believes there are deviations from, or
inadequacies in, the employee’s knowledge or use
of LOTO procedures.
LOTO Program
Periodic Inspections
• An inspection will be conducted at least annually
by an authorized employee not involved in the
procedure being inspected.
• The inspection will identify any deficiencies in or
deviations from the program.
• The supervisor must certify that the inspections
have been performed.
LOTO Program
Periodic Inspections
• Where Lock Out is used, the inspector must review
each authorized employee's responsibilities under
the procedure with that employee (group meetings
are acceptable).
• Where Tag Out is used, the inspector must review
BOTH the authorized and affected employee's
responsibilities with those employees for the energy
control procedure being inspected.
LOTO Program - Assistance
• Our bureau will provide assistance with;
o
o
o
o

Programs
Facility inspections
Specific procedures,
Training.

• Contact 406-444-6401 to schedule a free
on-site consultation.
More Information
www.osha.gov
Occupational Safety and Health Administration
www.montanasafety.com
Montana Occupational Safety and Health Bureau

More Related Content

What's hot

What's hot (20)

ONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag OutONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag Out
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
 
Lockout/Tagout Training (Contractor Version)
Lockout/Tagout Training (Contractor Version)Lockout/Tagout Training (Contractor Version)
Lockout/Tagout Training (Contractor Version)
 
Lockout tagout refresher training
Lockout tagout refresher trainingLockout tagout refresher training
Lockout tagout refresher training
 
Lock Out Tag Out
Lock Out Tag OutLock Out Tag Out
Lock Out Tag Out
 
LOTO
LOTO LOTO
LOTO
 
Lockout Tagout by CTDOL
Lockout Tagout by CTDOLLockout Tagout by CTDOL
Lockout Tagout by CTDOL
 
Mewp training
Mewp training Mewp training
Mewp training
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
LOTO Training.ppt
LOTO Training.pptLOTO Training.ppt
LOTO Training.ppt
 
PPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie EPPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie E
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Lockout/Tagout
Lockout/TagoutLockout/Tagout
Lockout/Tagout
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009
 
NGI-Permit to Work
NGI-Permit to WorkNGI-Permit to Work
NGI-Permit to Work
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Line Of Fire Presentation.ppt
Line Of Fire Presentation.pptLine Of Fire Presentation.ppt
Line Of Fire Presentation.ppt
 
Loto training
Loto trainingLoto training
Loto training
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
 
Man and machine interface
Man and machine interfaceMan and machine interface
Man and machine interface
 

Viewers also liked

Lock Out Tag Out Safe Work Procedure
Lock Out Tag Out Safe Work Procedure Lock Out Tag Out Safe Work Procedure
Lock Out Tag Out Safe Work Procedure Julian Kalac P.Eng
 
Catalogue khoa LOTO (Lockout Tagout)_TIFACO
Catalogue khoa LOTO (Lockout Tagout)_TIFACOCatalogue khoa LOTO (Lockout Tagout)_TIFACO
Catalogue khoa LOTO (Lockout Tagout)_TIFACOTIFACO VIET NAM
 
Safe Isolation Procedure
Safe Isolation ProcedureSafe Isolation Procedure
Safe Isolation Proceduretotalpeople
 
Lockout Tag Out
Lockout Tag OutLockout Tag Out
Lockout Tag Outsspuent
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009txn4_8
 
8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagoutCreative Safety Supply
 

Viewers also liked (8)

Lock Out Tag Out Safe Work Procedure
Lock Out Tag Out Safe Work Procedure Lock Out Tag Out Safe Work Procedure
Lock Out Tag Out Safe Work Procedure
 
Catalogue khoa LOTO (Lockout Tagout)_TIFACO
Catalogue khoa LOTO (Lockout Tagout)_TIFACOCatalogue khoa LOTO (Lockout Tagout)_TIFACO
Catalogue khoa LOTO (Lockout Tagout)_TIFACO
 
Loto online slides
Loto online slidesLoto online slides
Loto online slides
 
Safe Isolation Procedure
Safe Isolation ProcedureSafe Isolation Procedure
Safe Isolation Procedure
 
Lockout Tag Out
Lockout Tag OutLockout Tag Out
Lockout Tag Out
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009
 
Loto.ppt
Loto.pptLoto.ppt
Loto.ppt
 
8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout
 

Similar to Lockout tagout (20)

Lock Out Tag Out (LOTO)
Lock Out Tag Out (LOTO)Lock Out Tag Out (LOTO)
Lock Out Tag Out (LOTO)
 
Energy Control Program by MCIEAST
Energy Control Program by MCIEASTEnergy Control Program by MCIEAST
Energy Control Program by MCIEAST
 
LOTO 2
LOTO 2LOTO 2
LOTO 2
 
Lockout Tagout by SETON
Lockout Tagout by SETONLockout Tagout by SETON
Lockout Tagout by SETON
 
Lockout Tagout Training
Lockout Tagout TrainingLockout Tagout Training
Lockout Tagout Training
 
LOTO & ENERGY ISOLATION.pptx
LOTO & ENERGY ISOLATION.pptxLOTO & ENERGY ISOLATION.pptx
LOTO & ENERGY ISOLATION.pptx
 
Lock Out-Tag Out Training by Ryko
Lock Out-Tag Out Training by RykoLock Out-Tag Out Training by Ryko
Lock Out-Tag Out Training by Ryko
 
loto
lotoloto
loto
 
LOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptxLOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptx
 
LOTO Training.pdf
LOTO Training.pdfLOTO Training.pdf
LOTO Training.pdf
 
Lockout-Tagout 2023.ppt
Lockout-Tagout 2023.pptLockout-Tagout 2023.ppt
Lockout-Tagout 2023.ppt
 
Lock Out-Tag Out.ppt
Lock Out-Tag Out.pptLock Out-Tag Out.ppt
Lock Out-Tag Out.ppt
 
Lockout/Tag Out
Lockout/Tag OutLockout/Tag Out
Lockout/Tag Out
 
lockout-tagout-training.ppt
lockout-tagout-training.pptlockout-tagout-training.ppt
lockout-tagout-training.ppt
 
LOTO.pptx
LOTO.pptxLOTO.pptx
LOTO.pptx
 
Lockout Tagout by KU
Lockout Tagout by KULockout Tagout by KU
Lockout Tagout by KU
 
Lockout &tagout
Lockout &tagoutLockout &tagout
Lockout &tagout
 
Lock out tag out procedures
Lock out  tag out proceduresLock out  tag out procedures
Lock out tag out procedures
 
Lock out tag out procedures
Lock out  tag out proceduresLock out  tag out procedures
Lock out tag out procedures
 
Elearningtemplateppt
ElearningtemplatepptElearningtemplateppt
Elearningtemplateppt
 

Recently uploaded

Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
PANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxPANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxakanksha16arora
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111GangaMaiya1
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Pooja Bhuva
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxJisc
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
Simple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfSimple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfstareducators107
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Celine George
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use CasesTechSoup
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 

Recently uploaded (20)

Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
PANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxPANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Simple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfSimple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdf
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use Cases
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 

Lockout tagout

  • 1.
  • 2. Lock Out Tag Out (LOTO)
  • 3. Outline • Importance of Lock Out/Tag Out (LOTO) • OSHA’s Control of Hazardous Energy standard
  • 4. Why is LOTO important? • The Lock Out/Tag Out procedure prevents the unexpected start up or release of stored energy that could cause injury to employees by placing a lock and/or warning tag on an energy isolation device.
  • 5. LOTO Program Enforcement • A violation of an employee's responsibility must be reported to the employee's immediate supervisor for appropriate action. • A violation of a contractor’s responsibility must be reported to the project manager (or the person who hired the contractor) for appropriate action.
  • 6. Regulatory Agencies • Federal: Occupational Safety and Health Administration (OSHA) • State: Montana Occupational Safety & Health Bureau (MOSHB)
  • 7. Hazardous Energy Sources • Electrical • Mechanical (i.e. motors, drive belts) • Chemical (i.e. natural gas, propane) • Thermal • Pneumatic • Hydraulic
  • 8. OSHA’s LOTO Standard 29 CFR 1910.147 • Requires a written energy control program that includes defined energy control procedures • Requires documented employee training • Requires periodic inspections at least annually • Requires certain equipment specifics
  • 9. LOTO Program - Responsibilities • Coordinate the LOTO program; • Training & assistance with annual inspections; • Maintain copies of equipment specific lock out procedures, annual inspections & training records; and • Update & evaluate the LOTO program annually.
  • 10. LOTO Program - Responsibilities • Notify contractors to bring their LOTO program to preconstruction meeting; and • Include LOTO as an agenda item & allow contractors & Employees to discuss
  • 11. LOTO Program Employers Responsibilities • • • • • Complete equipment specific LOTO procedures; Conduct annual & periodic inspections; Keep a list of authorized employees; Issue LOTO devices to employees; Ensure all affected employees are properly trained on LOTO procedures; • Enforce compliance with LOTO program; and • Provide employees with copies of the LOTO Program upon request.
  • 12. LOTO Program Authorized Employee Responsibilities • Attend required training; • Follow all LOTO procedures; • Assist supervisor’s in completing equipment specific LOTO procedures; • Consult supervisors when questions or concerns arise; and • Notify all affected employees of LOTO activities.
  • 13. LOTO Program - Contractors • Contractor & on-site employer must exchange LOTO info • On-site employees must understand & comply with the contractor’s rules. • Employees must be alert & aware of any new types of LOTO devices.
  • 14. LOTO Program - Equipment • Must be singularly identified; • Must be the ONLY devices for controlling energy; and • Must NOT be used for any other purposes.
  • 15. LOTO Program - Equipment • Lock Out devices must be durable & withstand the environment to which they are exposed. Tag out devices must be constructed & printed so they do not deteriorate or become illegible; • LO/TO devices must be standardized by color, shape or size; • LO/TO devices must be substantial enough to prevent early or accidental removal and removal without excessive force.
  • 16. LOTO Program - Equipment • Lock out will be accomplished using a lock and key. Chains, or other hardware, may be used in conjunction with the lock to isolate the energy source.
  • 17. LOTO Program - Equipment • One key will be issued to the authorized employee applying the lock.
  • 18. LOTO Program - Equipment • Tag Out devices must include a legend such as: DO NOT START, DO NOT OPEN, DO NOT CLOSE, DO NOT ENERGIZE, DO NOT OPERATE, etc. • Tag Out devices must have standardized print and format.
  • 19. LOTO Program Required Tag Out Device Information • Name of authorized employee who locked out equipment; • Authorized employee’s radio or phone number, including contractors; • Date and time of lockout; and • Brief description of work being performed.
  • 20. LOTO Program - Equipment • An approved warning tag should accompany all lockouts. • The warning tag should be attached directly to the lockout device by a nylon tie.
  • 21. LOTO Program - Procedures • Preparation for shutdown • Shutting down the equipment • Equipment isolation • Application of LOTO devices • Release of stored energy • Verifying equipment isolation
  • 22. LOTO Program Prep For Shutdown • Know the types and amounts of energy that power specific equipment • Know the hazards of that energy • Know how the energy can be controlled – review equipment specific procedures if necessary • Direct any questions to immediate supervisor
  • 23. LOTO Program Shutting Down Equipment • Notify ALL affected employees that a LOTO procedure is being used and why. • Shut the equipment down using operating controls. • Follow proper procedure for the equipment to avoid endangering anyone during the shutdown.
  • 24. LOTO Program - Energy Isolation • Lock Out / Tag Out energy isolating sources with assigned locks and tags. Usually requires locking out electrical disconnect. • Be sure to isolate ALL energy sources (secondary as well as primary).
  • 25. LOTO Program Application of Devices • Use valve covers, plug locks, etc. if the lock can’t be placed directly on the energy control. • When Lock Out is used, every employee in the work crew must attach their own personal lock.
  • 26. LOTO Program Application of Devices • A Tag Out system alone is not acceptable at any time unless the equipment is not capable of being locked out. • The tag must be placed at the same location that the lockout device would have been attached, and additional measures must be taken to ensure the level of safety is equivalent to that obtained by using a lock. • This includes: blocking of a controlling switch, removal of an isolating circuit element, opening of an extra disconnect device, or removal of a valve handle ONLY.
  • 27. LOTO Program Release of Stored Energy • Inspect the system to make sure all parts have stopped moving. • Disperse stored energy (springs, hydraulic systems, air, gas, water pressure, or steam). • If stored energy can build up again, monitor it to make certain it stays below hazardous levels.
  • 28. LOTO Program Verifying Equipment Isolation • Make certain all dangerous areas are clear of personnel. • Verify that the equipment cannot be turned to the “on” position. • Press all “start” buttons and activating controls on the equipment. • Return all controls to the “off” position after certain that Lock Out is effective.
  • 29. LOTO Program Removing LOTO Devices / Restoring Equipment • Safeguard all employees by making certain everyone is clear of the equipment. Also notify affected employees of impending reenergization. • Verify that all tools have been removed and all guards reinstalled. • Remove LOTO devices. Each device must be removed by the person who put it on. • Energize equipment.
  • 30. LOTO Program - Troubleshooting • Remove all tools & personnel from the area. • Notify affected employees of impending reenergization. • Authorized employees remove the Lock Out device but MUST leave tag in place. • Energize equipment. • When finished, de-energize & reapply Lock Out device.
  • 31. LOTO Program - Shift Changes • If servicing lasts more than one shift, LOTO protection CANNOT be interrupted. • The original authorized employee will remove their lock & the incoming employee will place theirs on the isolating device. • The incoming authorized employee MUST VERIFY that ALL energy sources are locked out prior to beginning work.
  • 32. LOTO Program Abandoned Lock Procedure • Verify authorized employee has left the worksite & notify them that their lock is being removed. • LOTO devices may ONLY be removed if supervisor is present & authorizes removal. • After all communication attempts are complete & the equipment has been inspected, lock can be removed and new lock installed. • Notify employee their lock was removed prior to starting new shift.
  • 33. LOTO Program - Exceptions • Work on cord & plug equipment IF it is unplugged, the plug remains within arms reach during servicing and authorized employee has exclusive control of the plug. • If guards aren’t removed or bypassed & are effective in preventing worker exposure to hazards created by the unexpected energization or start up of machines or equipment, or the release of energy.
  • 34. LOTO Program Equipment Specific LOTO • Equipment Specific LOTO forms must be completed by the supervisor and / or the authorized employee. • All equipment specific procedures should be easily accessible or posted directly on the equipment.
  • 35. LOTO Program Equipment Specific Procedures Procedures must be updated when: • New equipment is installed; or • New energy sources are added to a facility or individual equipment; or • Magnitude of an energy source changes; or • Designated isolation points change.
  • 36. LOTO Program - Training • Supervisors • Authorized Employees • All Employees
  • 37. LOTO Program - Re-Training • Change in authorized employee’s job assignments or job area that contains sources of hazardous energy; • Change in machines, equipment or process that presents a new hazard; • Change in energy control procedures; • Need for refresher training found during periodic inspections; and/or • Employer believes there are deviations from, or inadequacies in, the employee’s knowledge or use of LOTO procedures.
  • 38. LOTO Program Periodic Inspections • An inspection will be conducted at least annually by an authorized employee not involved in the procedure being inspected. • The inspection will identify any deficiencies in or deviations from the program. • The supervisor must certify that the inspections have been performed.
  • 39. LOTO Program Periodic Inspections • Where Lock Out is used, the inspector must review each authorized employee's responsibilities under the procedure with that employee (group meetings are acceptable). • Where Tag Out is used, the inspector must review BOTH the authorized and affected employee's responsibilities with those employees for the energy control procedure being inspected.
  • 40. LOTO Program - Assistance • Our bureau will provide assistance with; o o o o Programs Facility inspections Specific procedures, Training. • Contact 406-444-6401 to schedule a free on-site consultation.
  • 41. More Information www.osha.gov Occupational Safety and Health Administration www.montanasafety.com Montana Occupational Safety and Health Bureau