Facts & Figures
INtelligent solutions 2ward the Development of Railway Energy and Asset Management Systems in Europe
Contract No. 777596
3
Project Partners
Contract No. 777596
• Predicted growth of transport, especially in European railway
infrastructures, is expected to introduce a dramatic increase in freight
and passenger services by the end of 2050.
• To support sustainable development of these infrastructures, novel data-
driven ICT solutions are required.
• These will enable monitoring, analysis and exploitation of energy and
asset information for the entire railway system including power grid,
stations, rolling stock and infrastructure.
• IN2DREAMS will address these challenges through two distinct work
streams: Work Stream 1 (WS1), focusing on the management of energy-
related data and Work Stream 2 (WS2), focusing on the management of
asset-related data
Challenge & Scope
4
Contract No. 777596
Work Stream 1 – Management of
Energy-related Data
WS1 aims to remove the current
and anticipated limitations of
REMS, by making these capable of
supporting a much wider array of
requirements than it is currently
the case.
Work Stream 2 – Management of
Asset-related Data
WS2 aims to improve efficiency and
sustainability of the railway asset
data management, by applying
research advances in machine
learning, data visualization and
decentralized architecture with
smart contracts.
High-level Objectives
5
Contract No. 777596
6
Project Structure
WP1: Project Management & Technical Coordination
WP6:UserApplication
WP4:SmartContractsforRailwayDataTransactions
WP2: Integrated Communication Platform
WP7: Dissemination, Exploitation & Cooperation with S2R
WP3 WP5
Sensing
Monitoring
Devices
Knowledge Extraction
from Railway Asset Data
Data
Management
Platform
WS1 WS2
Contract No. 777596
7
Links with Shift2Rail
WORK STREAM 1 OVERVIEW
GUILLAUME PELLETIER (DOTVISION) – TECHNICAL LEADER
InnoTrans Presentation - 20/09/2018
Contract No. 777596
WS 1 – Management of Energy-related Data. It aims to:
• Realize a non-intrusive Smart Metering sensor networks at Railway
System level.
• Setting up an open system and interface for data collection,
aggregation and analysis in an open source Operational Data
Management (ODM) Platform.
• Providing a set of User Applications design and specifications. The
Applications will exploit the energy analysis process with the aim of
enhancing the energy decision making and the line operation
patterns, as well as other possible improvements such as preventive
maintenance.
WS1- Management of Energy related data
9
Contract No. 777596
WS1 proposes a dynamically re-configurable ICT infrastructure to
facilitate both the operation and the services supported by the
railway network
• WP2 : A heterogeneous telecommunication platform, consisting of
both wireless and wireline systems converging energy and telecom
services.
• WP3 An IOT and ODM platform for data collection, aggregation and
analysis that scales with the railway operators needs.
• WP6: A set of users’ applications with emphasis on fault detection /
localisation and energy efficient optimization.
WS1- Work package
10
Contract No. 777596
WS1- Industrial IT Architecture
11
IP Capable
devices
Existing IOT
Devices
Low Power
devices
gateway
Gateway
Provisioning API
App Backend
Stream Processor
Data Store Data Analytics & Learning
Device data stores
Identity and Registry Stores
Device Connectivity Data Processing, Analytics and Management
Solution UX
Business Integration
Connectors and
Gateway(s)
Personal mobile
devices
Business
Systems
Presentation & Business Connectivity
Data Path
Standard cloud infrastructure
Optional solution component
Edge
Message
Broker
WP6WP2 WP3 WP3 WP6
Contract No. 777596
WP2:
• To date, the On-board
and train-to-ground
data transmission is
operational on Reims
POC and Bristol Based
LTE network.
• Ground to operations
is also supported using
a combination of
wireless and optical
technologies
• IOT connectivity is
completed
WS1- Status
12
WP3:
• Delivered the
Architectural overview
of the solution.
• Launched the Data
Management
Platform.
• Built the Monitoring
On Board Rugged
Gateway (ALOHA).
• Successfully passed
the first installation
and security test on
Reims Tramway
WP6:
• Architecture has been
deployed and QMiner
software has been
installed. Forecasting
models of energy
consumption for trains
• Sub-stations are under
development and will be
implemented
• Moreover, a task to
model energy data has
started
Contract No. 777596
WS1- POC
• WS1 has started a Proof of Concept in
Reims Tramway which encompass the WP2
WP3 physical devices and set of analysis
from WP6
• Work in progress presentation is available
at InnoTrans with AR support.
13
WORK STREAM 2 OVERVIEW
NADIA FABRIZIO (CEFRIEL) – WORK PACKAGE LEADER
InnoTrans Presentation - 20/09/2018
Contract No. 777596
WS 2 – Management of Asset-related Data. It aims to:
• Define the necessary IT solutions and related methodologies for business
security, economic sustainability and decision support in the field of data
processing and analytics in railway applications for asset management.
• This work is directly related to the Technical Demonstrator TD3.6: Dynamic
Railway Information Management System (DRIMS).
• Will address some of the challenges related to TD3.6 outlined in the S2R
MAAP. This TD focuses on interfaces with external systems, maintenance-
related data management as well as data mining and data analytics, asset
degradation modelling covering both degradation modelling driven by
data and domain knowledge and the enhancement of existing models
using data/new insights.
WS2- Management of asset related data
15
Contract No. 777596
Support data-driven methodologies applied in real world railway contexts
• Address fundamental topics of data and transactions security, safeguarding data ownership rights, railway specific
structural contract mechanisms for information and knowledge exchange
• Extend the work carried out in the framework of the IN2RAIL project by studying, designing and developing data-driven
IT tools and methodologies for explicit knowledge extraction, with particular reference to the derivation of data-driven
descriptive, diagnostic, and predictive models
• Design and develop visual analytics tools for the interpretation of data and models by human operators and decision
makers→ WP5
• Design, develop and test a reference software architecture for implementation of smart contracts in railway
ecosystem for data exchange. Address the legal aspects related to the adoption of smart contracts in the railway
ecosystem. →WP4
• Develop tools and metrics for the (statistical) assessment and validation of data-driven models performance. →WP4
• Design and develop visual analytics tools for the interpretation of data and models by human operators and decision
makers.
• Design and develop rule-based data analytics tools for the exploitation of the implicit knowledge stored in data-driven
models.
Objective of WS2
16
Contract No. 777596
SCOPE AND IMPACTS
Railway applications for asset
management.
• Focus is on
• interfaces with external
systems,
• maintenance-related data
management
• data mining and data analytics
(asset degradation modelling
covering both degradation
modelling driven by data and
domain knowledge
• enhancement of existing models
using data/new insights.
WS2- Management of asset related data
17
IMPACTS
Improvement of
capacity – a large
improvement in line
capacity due to a more
effective asset
maintenance
management
1. future Intelligent Asset Maintenance,
2. Data-driven methodologies
3. holistic approach to asset management and decision
support including diagnostics and prognostics
Improved Reliability:
failure modes of current
systems
will be
reduced/eliminated due
to the new “intelligent
asset management”
1. reduce unexpected maintenance interventions
2. thus increasing reliability and availability
Significant LCC savings 1. moving from reactive and preventive maintenance to
prescriptive maintenance based
2. nowcasting and forecasting of asset condition and
diagnosis
Improved safety 1. the number and magnitude of incidents will be reduced
Contract No. 777596
• Asset Maintenance-Manage the maintenance jobs workflow through the employment
of smart contracts, automatically enforcing the rules and clauses (like SLA) of the
maintenance contracts between the IM and the Contractor.
• Public Procurement-Employ the blockchain as a notarization platform for public
procurements, taking advantage of its immutability property.
• Data Monetisation-Monetize owned data creating an ecosystem able to manage the
access (and relative payments) to the data of the ecosystem’s participants, employing
smart contract to manage both the access rights and the payments.
• Train Path Allocation-Manage the international allocation of train path through the
employment of smart contracts and blockchain to automatize the adminstrative
workflow.
WP4 identified scenarios
18
The Asset Maintenance use case is the selected one for a
prototype implementation within IN2DREAMS
Contract No. 777596
• Cross-Scenario 1: Visualization in Control Center
• Cross-Scenario 2: Marketplace of Data and Data Monetization
• Specific-Scenario 1: Track Circuits
• Specific-Scenario 2: Train Delays and Penalties
• Specific-Scenario 3: Restoration Time
• Specific-Scenario 4: Switches
• Specific-Scenario 5: Train Energy Consumption
WP5 identified scenarios
19
Contract No. 777596
WP4 & WP5 links
20
Work of WP4 has been
organized in synergy with
WP5.
Restoration time, predicted
for each maintenance job as
part of one of the WP5 data
analytics scenarios, will be
stored on the blockchain, and
showed to RFI operators,
together with all the needed
data and alerts (i.e. delayed
maintenance) generated by
WP4 prototype. This specific
data visualization task will be
tackle inside WP5 data
visualization scenario
Contract No. 777596
WP4
Identified use cases
◦ “Asset Maintenance “ selected use
case
Select the appropriate DLT
◦ Hyperledger Fabric selected
platform
Draft a preliminary architecture
of the prototype
◦ Working prototype done In
Hyperledger Fabric (Composer)
WP5
Definition of the data analytics
scenario
Development and demonstration
of tools “Machine Learning &
Visualization” to demonstrate
the feasibility of extracting
knowledge from data
Study and develop POC
architecture
Status
21
Contract No. 777596
Together with CEFRIEL & UKON
we discussed the most suited subject of the POC and we observed that
◦ CEFRIEL has a scenario about handling maintenances with blockchain
◦ UNIGE has a scenario about predicting the maintenances restoration time
◦ UKON has a scenario about visualisation in the control center (visualisation for maintainers
and train dispatchers)
merging these three things together would be a good option
◦ CEFRIEL needs to ask to RFI information about 2-3 maintenances to use for the
demonstrator
◦ UNIGE will provide the interpretable model for the predictions of the restoration time, the
actual predictions, and the accuracy of the predictions
◦ UKON will implement three visualisations/monitors (1) for the maintainers, (2) for the
dispatchers, and (3) for the director of the maintenance
maybe we can also include something else from the WP5 like the train delay
predictions
22
POC
Contract No. 777596
The WS2 is developing a demonstrator on the selected scenarios
23
Demonstrator (PoC)
Demonstrator
WP5 Scenarios
• Restoration Time
• Train Delary Prediction
WP4 Scenarios
• Asset Maintenance
WP5 Scenario
• Visualization in Control Center
Contract No. 777596
Thank you for your Attention!
Any Questions?
Visit us at:
www.in2dreams.eu
24

More Related Content

What's hot

Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
Future Cities Project
 
Cost-Aware Virtual Machine Placement across Distributed Data Centers using Ba...
Cost-Aware Virtual Machine Placement acrossDistributed Data Centers using Ba...Cost-Aware Virtual Machine Placement acrossDistributed Data Centers using Ba...
Cost-Aware Virtual Machine Placement across Distributed Data Centers using Ba...
Soodeh Farokhi
 

What's hot (20)

Interoperable provision of geodata and services according to the INSPIRE Dire...
Interoperable provision of geodata and services according to the INSPIRE Dire...Interoperable provision of geodata and services according to the INSPIRE Dire...
Interoperable provision of geodata and services according to the INSPIRE Dire...
 
Bde sc3 2nd_workshop_2016_10_04_p03_efacec
Bde sc3 2nd_workshop_2016_10_04_p03_efacecBde sc3 2nd_workshop_2016_10_04_p03_efacec
Bde sc3 2nd_workshop_2016_10_04_p03_efacec
 
Information technology in power sectors
Information technology in power sectorsInformation technology in power sectors
Information technology in power sectors
 
SC1 Workshop 2 Pilot instantiations
SC1 Workshop 2 Pilot instantiationsSC1 Workshop 2 Pilot instantiations
SC1 Workshop 2 Pilot instantiations
 
Bde sc3 2nd_workshop_2016_10_04_p01_bde_introduction
Bde sc3 2nd_workshop_2016_10_04_p01_bde_introductionBde sc3 2nd_workshop_2016_10_04_p01_bde_introduction
Bde sc3 2nd_workshop_2016_10_04_p01_bde_introduction
 
mains
mainsmains
mains
 
Subject: Ex-post impact evaluations of energy efficiency policies in Europe
Subject:	Ex-post impact evaluations of energy efficiency policies in EuropeSubject:	Ex-post impact evaluations of energy efficiency policies in Europe
Subject: Ex-post impact evaluations of energy efficiency policies in Europe
 
FIWARE Global Summit - The View of the European Commission
FIWARE Global Summit - The View of the European CommissionFIWARE Global Summit - The View of the European Commission
FIWARE Global Summit - The View of the European Commission
 
Monet, an IoT Energy Management Platform based on MongoDB
Monet, an IoT Energy Management Platform based on MongoDBMonet, an IoT Energy Management Platform based on MongoDB
Monet, an IoT Energy Management Platform based on MongoDB
 
SUNSHINE Project: Bart delathouwer
SUNSHINE Project: Bart delathouwerSUNSHINE Project: Bart delathouwer
SUNSHINE Project: Bart delathouwer
 
BDE SC3.3 Workshop - Agenda
 BDE SC3.3 Workshop - Agenda BDE SC3.3 Workshop - Agenda
BDE SC3.3 Workshop - Agenda
 
BDE SC3.3 Workshop - BDE Pilot case for Wind Turbine condition monitoring re...
 BDE SC3.3 Workshop - BDE Pilot case for Wind Turbine condition monitoring re... BDE SC3.3 Workshop - BDE Pilot case for Wind Turbine condition monitoring re...
BDE SC3.3 Workshop - BDE Pilot case for Wind Turbine condition monitoring re...
 
[e-Government Program Action Plan : Warsaw, Poland]
[e-Government Program Action Plan : Warsaw, Poland][e-Government Program Action Plan : Warsaw, Poland]
[e-Government Program Action Plan : Warsaw, Poland]
 
Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
Workshop on Large-scale Sensing For Future Cities'13 / Jorge Sousa: "SMART2M"
 
Cost-Aware Virtual Machine Placement across Distributed Data Centers using Ba...
Cost-Aware Virtual Machine Placement acrossDistributed Data Centers using Ba...Cost-Aware Virtual Machine Placement acrossDistributed Data Centers using Ba...
Cost-Aware Virtual Machine Placement across Distributed Data Centers using Ba...
 
ICARUS @ 27th ACRIS Meeting (February 2020, London)
ICARUS @ 27th ACRIS Meeting (February 2020, London)ICARUS @ 27th ACRIS Meeting (February 2020, London)
ICARUS @ 27th ACRIS Meeting (February 2020, London)
 
DataPorts Project presentation
DataPorts Project presentationDataPorts Project presentation
DataPorts Project presentation
 
Development of GNSS receiver technologies for premium and general mass market...
Development of GNSS receiver technologies for premium and general mass market...Development of GNSS receiver technologies for premium and general mass market...
Development of GNSS receiver technologies for premium and general mass market...
 
The APIs4DGov study.
The APIs4DGov study. The APIs4DGov study.
The APIs4DGov study.
 
Cacti and Big Data at Orange France, OW2online, June 2020
Cacti and Big Data at Orange France, OW2online, June 2020Cacti and Big Data at Orange France, OW2online, June 2020
Cacti and Big Data at Orange France, OW2online, June 2020
 

Similar to In2 d t7.1-b-uni-043-01--_in2dreams_presentation_at_innotrans2018 (3)

Confluent Cloud inside the Digital Transformation of Autostrade per l’Italia
Confluent Cloud inside the Digital Transformation of Autostrade per l’ItaliaConfluent Cloud inside the Digital Transformation of Autostrade per l’Italia
Confluent Cloud inside the Digital Transformation of Autostrade per l’Italia
confluent
 
UNMESH 2015 modified Presentation
UNMESH 2015 modified PresentationUNMESH 2015 modified Presentation
UNMESH 2015 modified Presentation
Sayak Chakraborty
 

Similar to In2 d t7.1-b-uni-043-01--_in2dreams_presentation_at_innotrans2018 (3) (20)

Intelligent Infrastructure for Next-Generation Rail Systems
Intelligent Infrastructure for Next-Generation Rail SystemsIntelligent Infrastructure for Next-Generation Rail Systems
Intelligent Infrastructure for Next-Generation Rail Systems
 
Future Communication Scenarios for Next-generation Railways
Future Communication Scenarios for Next-generation RailwaysFuture Communication Scenarios for Next-generation Railways
Future Communication Scenarios for Next-generation Railways
 
Asset information and data management smart rail
Asset information and data management smart railAsset information and data management smart rail
Asset information and data management smart rail
 
RECAP at ETSI Experiential Network Intelligence (ENI) Meeting
RECAP at ETSI Experiential Network Intelligence (ENI) MeetingRECAP at ETSI Experiential Network Intelligence (ENI) Meeting
RECAP at ETSI Experiential Network Intelligence (ENI) Meeting
 
Confluent Cloud inside the Digital Transformation of Autostrade per l’Italia
Confluent Cloud inside the Digital Transformation of Autostrade per l’ItaliaConfluent Cloud inside the Digital Transformation of Autostrade per l’Italia
Confluent Cloud inside the Digital Transformation of Autostrade per l’Italia
 
5G Enablers and Use Cases, an European Pespective
5G Enablers and Use Cases, an European Pespective5G Enablers and Use Cases, an European Pespective
5G Enablers and Use Cases, an European Pespective
 
Grid and Cloud Computing Lecture-2a.pptx
Grid and Cloud Computing Lecture-2a.pptxGrid and Cloud Computing Lecture-2a.pptx
Grid and Cloud Computing Lecture-2a.pptx
 
Big Data in Shift2Rail: Connective and in2Stempo projects
Big Data in Shift2Rail: Connective and in2Stempo projectsBig Data in Shift2Rail: Connective and in2Stempo projects
Big Data in Shift2Rail: Connective and in2Stempo projects
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
 
Smart Networks and Services Joint Undertaking (SNS JU) Call Topics
Smart Networks and Services Joint Undertaking (SNS JU) Call TopicsSmart Networks and Services Joint Undertaking (SNS JU) Call Topics
Smart Networks and Services Joint Undertaking (SNS JU) Call Topics
 
5G implementation in the field of engineering
5G implementation in the field of engineering5G implementation in the field of engineering
5G implementation in the field of engineering
 
X internet
X internetX internet
X internet
 
UtiliAPP - Utility Analytics - Indigo Advisory Group
UtiliAPP  - Utility Analytics - Indigo Advisory GroupUtiliAPP  - Utility Analytics - Indigo Advisory Group
UtiliAPP - Utility Analytics - Indigo Advisory Group
 
Design of an Autonomous Management and Orchestration for Fog Computing
Design of an Autonomous Management and Orchestration for Fog ComputingDesign of an Autonomous Management and Orchestration for Fog Computing
Design of an Autonomous Management and Orchestration for Fog Computing
 
Evolution of Telecommunication
Evolution of Telecommunication Evolution of Telecommunication
Evolution of Telecommunication
 
UNMESH 2015 modified Presentation
UNMESH 2015 modified PresentationUNMESH 2015 modified Presentation
UNMESH 2015 modified Presentation
 
Demand Side management of smart grid using IoT
Demand Side management of smart grid using IoTDemand Side management of smart grid using IoT
Demand Side management of smart grid using IoT
 
First group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways CompetitionFirst group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways Competition
 
Webinar: Unlocking the potential of io t data
Webinar: Unlocking the potential of io t dataWebinar: Unlocking the potential of io t data
Webinar: Unlocking the potential of io t data
 
Sustainable Transportation System
Sustainable Transportation System Sustainable Transportation System
Sustainable Transportation System
 

More from Nadia Fabrizio (8)

D1.reader wallet p1nruuvdowld_1.0_final
D1.reader wallet p1nruuvdowld_1.0_finalD1.reader wallet p1nruuvdowld_1.0_final
D1.reader wallet p1nruuvdowld_1.0_final
 
20201111 kuppinger-qsn-final
20201111 kuppinger-qsn-final20201111 kuppinger-qsn-final
20201111 kuppinger-qsn-final
 
Smart c for re final 2
Smart c for re final 2Smart c for re final 2
Smart c for re final 2
 
Bedays2019 nadia fabrizio-short
Bedays2019 nadia fabrizio-shortBedays2019 nadia fabrizio-short
Bedays2019 nadia fabrizio-short
 
2019 bdva wg_dg
2019 bdva wg_dg2019 bdva wg_dg
2019 bdva wg_dg
 
Idsa, smau, milano, 2019 10-24
Idsa, smau, milano, 2019 10-24Idsa, smau, milano, 2019 10-24
Idsa, smau, milano, 2019 10-24
 
Eur par-fpdapp28082018 fn.fabrizio
Eur par-fpdapp28082018 fn.fabrizioEur par-fpdapp28082018 fn.fabrizio
Eur par-fpdapp28082018 fn.fabrizio
 
A4 i2018 blockchain_slideshare
A4 i2018 blockchain_slideshareA4 i2018 blockchain_slideshare
A4 i2018 blockchain_slideshare
 

Recently uploaded

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 

In2 d t7.1-b-uni-043-01--_in2dreams_presentation_at_innotrans2018 (3)

  • 1. GENERAL OVERVIEW STEFANOS GOGOS (UNIFE) – PROJECT COORDINATOR InnoTrans Presentation - 20/09/2018
  • 2. Contract No. 777596 2 Facts & Figures INtelligent solutions 2ward the Development of Railway Energy and Asset Management Systems in Europe
  • 4. Contract No. 777596 • Predicted growth of transport, especially in European railway infrastructures, is expected to introduce a dramatic increase in freight and passenger services by the end of 2050. • To support sustainable development of these infrastructures, novel data- driven ICT solutions are required. • These will enable monitoring, analysis and exploitation of energy and asset information for the entire railway system including power grid, stations, rolling stock and infrastructure. • IN2DREAMS will address these challenges through two distinct work streams: Work Stream 1 (WS1), focusing on the management of energy- related data and Work Stream 2 (WS2), focusing on the management of asset-related data Challenge & Scope 4
  • 5. Contract No. 777596 Work Stream 1 – Management of Energy-related Data WS1 aims to remove the current and anticipated limitations of REMS, by making these capable of supporting a much wider array of requirements than it is currently the case. Work Stream 2 – Management of Asset-related Data WS2 aims to improve efficiency and sustainability of the railway asset data management, by applying research advances in machine learning, data visualization and decentralized architecture with smart contracts. High-level Objectives 5
  • 6. Contract No. 777596 6 Project Structure WP1: Project Management & Technical Coordination WP6:UserApplication WP4:SmartContractsforRailwayDataTransactions WP2: Integrated Communication Platform WP7: Dissemination, Exploitation & Cooperation with S2R WP3 WP5 Sensing Monitoring Devices Knowledge Extraction from Railway Asset Data Data Management Platform WS1 WS2
  • 7. Contract No. 777596 7 Links with Shift2Rail
  • 8. WORK STREAM 1 OVERVIEW GUILLAUME PELLETIER (DOTVISION) – TECHNICAL LEADER InnoTrans Presentation - 20/09/2018
  • 9. Contract No. 777596 WS 1 – Management of Energy-related Data. It aims to: • Realize a non-intrusive Smart Metering sensor networks at Railway System level. • Setting up an open system and interface for data collection, aggregation and analysis in an open source Operational Data Management (ODM) Platform. • Providing a set of User Applications design and specifications. The Applications will exploit the energy analysis process with the aim of enhancing the energy decision making and the line operation patterns, as well as other possible improvements such as preventive maintenance. WS1- Management of Energy related data 9
  • 10. Contract No. 777596 WS1 proposes a dynamically re-configurable ICT infrastructure to facilitate both the operation and the services supported by the railway network • WP2 : A heterogeneous telecommunication platform, consisting of both wireless and wireline systems converging energy and telecom services. • WP3 An IOT and ODM platform for data collection, aggregation and analysis that scales with the railway operators needs. • WP6: A set of users’ applications with emphasis on fault detection / localisation and energy efficient optimization. WS1- Work package 10
  • 11. Contract No. 777596 WS1- Industrial IT Architecture 11 IP Capable devices Existing IOT Devices Low Power devices gateway Gateway Provisioning API App Backend Stream Processor Data Store Data Analytics & Learning Device data stores Identity and Registry Stores Device Connectivity Data Processing, Analytics and Management Solution UX Business Integration Connectors and Gateway(s) Personal mobile devices Business Systems Presentation & Business Connectivity Data Path Standard cloud infrastructure Optional solution component Edge Message Broker WP6WP2 WP3 WP3 WP6
  • 12. Contract No. 777596 WP2: • To date, the On-board and train-to-ground data transmission is operational on Reims POC and Bristol Based LTE network. • Ground to operations is also supported using a combination of wireless and optical technologies • IOT connectivity is completed WS1- Status 12 WP3: • Delivered the Architectural overview of the solution. • Launched the Data Management Platform. • Built the Monitoring On Board Rugged Gateway (ALOHA). • Successfully passed the first installation and security test on Reims Tramway WP6: • Architecture has been deployed and QMiner software has been installed. Forecasting models of energy consumption for trains • Sub-stations are under development and will be implemented • Moreover, a task to model energy data has started
  • 13. Contract No. 777596 WS1- POC • WS1 has started a Proof of Concept in Reims Tramway which encompass the WP2 WP3 physical devices and set of analysis from WP6 • Work in progress presentation is available at InnoTrans with AR support. 13
  • 14. WORK STREAM 2 OVERVIEW NADIA FABRIZIO (CEFRIEL) – WORK PACKAGE LEADER InnoTrans Presentation - 20/09/2018
  • 15. Contract No. 777596 WS 2 – Management of Asset-related Data. It aims to: • Define the necessary IT solutions and related methodologies for business security, economic sustainability and decision support in the field of data processing and analytics in railway applications for asset management. • This work is directly related to the Technical Demonstrator TD3.6: Dynamic Railway Information Management System (DRIMS). • Will address some of the challenges related to TD3.6 outlined in the S2R MAAP. This TD focuses on interfaces with external systems, maintenance- related data management as well as data mining and data analytics, asset degradation modelling covering both degradation modelling driven by data and domain knowledge and the enhancement of existing models using data/new insights. WS2- Management of asset related data 15
  • 16. Contract No. 777596 Support data-driven methodologies applied in real world railway contexts • Address fundamental topics of data and transactions security, safeguarding data ownership rights, railway specific structural contract mechanisms for information and knowledge exchange • Extend the work carried out in the framework of the IN2RAIL project by studying, designing and developing data-driven IT tools and methodologies for explicit knowledge extraction, with particular reference to the derivation of data-driven descriptive, diagnostic, and predictive models • Design and develop visual analytics tools for the interpretation of data and models by human operators and decision makers→ WP5 • Design, develop and test a reference software architecture for implementation of smart contracts in railway ecosystem for data exchange. Address the legal aspects related to the adoption of smart contracts in the railway ecosystem. →WP4 • Develop tools and metrics for the (statistical) assessment and validation of data-driven models performance. →WP4 • Design and develop visual analytics tools for the interpretation of data and models by human operators and decision makers. • Design and develop rule-based data analytics tools for the exploitation of the implicit knowledge stored in data-driven models. Objective of WS2 16
  • 17. Contract No. 777596 SCOPE AND IMPACTS Railway applications for asset management. • Focus is on • interfaces with external systems, • maintenance-related data management • data mining and data analytics (asset degradation modelling covering both degradation modelling driven by data and domain knowledge • enhancement of existing models using data/new insights. WS2- Management of asset related data 17 IMPACTS Improvement of capacity – a large improvement in line capacity due to a more effective asset maintenance management 1. future Intelligent Asset Maintenance, 2. Data-driven methodologies 3. holistic approach to asset management and decision support including diagnostics and prognostics Improved Reliability: failure modes of current systems will be reduced/eliminated due to the new “intelligent asset management” 1. reduce unexpected maintenance interventions 2. thus increasing reliability and availability Significant LCC savings 1. moving from reactive and preventive maintenance to prescriptive maintenance based 2. nowcasting and forecasting of asset condition and diagnosis Improved safety 1. the number and magnitude of incidents will be reduced
  • 18. Contract No. 777596 • Asset Maintenance-Manage the maintenance jobs workflow through the employment of smart contracts, automatically enforcing the rules and clauses (like SLA) of the maintenance contracts between the IM and the Contractor. • Public Procurement-Employ the blockchain as a notarization platform for public procurements, taking advantage of its immutability property. • Data Monetisation-Monetize owned data creating an ecosystem able to manage the access (and relative payments) to the data of the ecosystem’s participants, employing smart contract to manage both the access rights and the payments. • Train Path Allocation-Manage the international allocation of train path through the employment of smart contracts and blockchain to automatize the adminstrative workflow. WP4 identified scenarios 18 The Asset Maintenance use case is the selected one for a prototype implementation within IN2DREAMS
  • 19. Contract No. 777596 • Cross-Scenario 1: Visualization in Control Center • Cross-Scenario 2: Marketplace of Data and Data Monetization • Specific-Scenario 1: Track Circuits • Specific-Scenario 2: Train Delays and Penalties • Specific-Scenario 3: Restoration Time • Specific-Scenario 4: Switches • Specific-Scenario 5: Train Energy Consumption WP5 identified scenarios 19
  • 20. Contract No. 777596 WP4 & WP5 links 20 Work of WP4 has been organized in synergy with WP5. Restoration time, predicted for each maintenance job as part of one of the WP5 data analytics scenarios, will be stored on the blockchain, and showed to RFI operators, together with all the needed data and alerts (i.e. delayed maintenance) generated by WP4 prototype. This specific data visualization task will be tackle inside WP5 data visualization scenario
  • 21. Contract No. 777596 WP4 Identified use cases ◦ “Asset Maintenance “ selected use case Select the appropriate DLT ◦ Hyperledger Fabric selected platform Draft a preliminary architecture of the prototype ◦ Working prototype done In Hyperledger Fabric (Composer) WP5 Definition of the data analytics scenario Development and demonstration of tools “Machine Learning & Visualization” to demonstrate the feasibility of extracting knowledge from data Study and develop POC architecture Status 21
  • 22. Contract No. 777596 Together with CEFRIEL & UKON we discussed the most suited subject of the POC and we observed that ◦ CEFRIEL has a scenario about handling maintenances with blockchain ◦ UNIGE has a scenario about predicting the maintenances restoration time ◦ UKON has a scenario about visualisation in the control center (visualisation for maintainers and train dispatchers) merging these three things together would be a good option ◦ CEFRIEL needs to ask to RFI information about 2-3 maintenances to use for the demonstrator ◦ UNIGE will provide the interpretable model for the predictions of the restoration time, the actual predictions, and the accuracy of the predictions ◦ UKON will implement three visualisations/monitors (1) for the maintainers, (2) for the dispatchers, and (3) for the director of the maintenance maybe we can also include something else from the WP5 like the train delay predictions 22 POC
  • 23. Contract No. 777596 The WS2 is developing a demonstrator on the selected scenarios 23 Demonstrator (PoC) Demonstrator WP5 Scenarios • Restoration Time • Train Delary Prediction WP4 Scenarios • Asset Maintenance WP5 Scenario • Visualization in Control Center
  • 24. Contract No. 777596 Thank you for your Attention! Any Questions? Visit us at: www.in2dreams.eu 24