The document summarizes Massachusetts' solid waste master plan and challenges. It discusses the state's shrinking disposal capacity and difficulties siting new facilities. It also provides details about the integrated solid waste management system in Bourne, including a landfill, recycling programs, and a proposed anaerobic digestion project. Recommendations include developing a state waste plan through the Executive Office of Energy and Environmental Affairs, improving interagency cooperation, and supporting new infrastructure development.
3. Solid Waste Master Plan
Massachusetts General Laws Chapter
16, Section 21, requires the Department
of Environmental Protection (MassDEP)
to develop and maintain a
comprehensive statewide master plan
for solid waste management, which the
agency updates on a ten-year planning
cycle.
4. Solid Waste Master Plan
(6) to the extent disposal is identified
as not taking place in any current or
future year at such sites, the options
available to local public bodies for
disposal at such sites or alternative
means …
5. Current Challenges
MA is facing a shrinking disposal capacity;
serious shortfall looming
Markets for recyclables are in flux; processors
struggling at both SSR and C&D facilities
Planning and building new facilities of all types
is a challenge
Financing
Siting
Community support
Permitting
6. Current Challenges
MA is essentially an island; increasing
export a reality
Rail haul to Ohio is growing
Not prepared for disruptions to the
system
Outages, fires, capacity choke points,
natural disasters
7. Key Questions
Do we want to control our own fate?
Who will build and operate facilities with local
and state governments deferring?
What if the private sector opts out?
What role can the state play from the cabinet
level on down?
Are we willing to rely on export?
Price increases, taxes, availability of railcars or
long haul trucking
9. Cons
Permitting pathway difficult for developers
Lack of coordination between agencies and media
(air, solid waste, water)
Policy doesn’t always translate into action
DEP doesn’t control all the factors
Extent of the need not always framed fully
Focus is mostly on household trash
Less on Ash, Non-MSW items, ICI wastes
Disaster debris
Data is incomplete
10. Bourne ISWM
Fully integrated solid waste management system, hence
the name “ISWM”
Residential recycling center (DPW collects at curbside weekly)
Composting
Landfilling (219,000 TPY potentially available until approximately 2035);
focused on managing ash currently, 30,000 TPY for MSW and soils
C&D transfer for processing
Single stream recyclables transfer station (formerly a baling facility)
Gross revenue for FY ‘16 ~ $12.75 million
Contributes approximately $2 million a year in savings and
cash to the General Fund
18. The Landfill will close. The “site” can be active forever.
{------limited life------} {--forever--}
19. Harvest Power Project
RFP led to a 25-year lease for AD, SSO, FOG, biosolids
HP to finance, build and operate
Purchase our LFG, make biogas, mix to make 4-5 mW
Town invested about $400,000
Town helped change carve-out for renewable energy
contracts at DOER to include mixed LFG and biogas
DEP grant for $30,000 for lease
DEP grant for $350,000 for infrastructure (rescinded)
20. Harvest Power Project
Conflicting emissions policies for LFG
and biogas
Increased risk and cost to HP
About $.07/kwh
Eversource rejected bid
HP terminated lease, no PPA
21. Current Status
Maximizing full use of the landfill up to
2035
Maximizing all of the site for potential
solid waste handling operations beyond
the life of the landfill
Looking at other technologies, including
enhanced composting
23. Lessons Learned
Start early with all the key stakeholders
Do it inside out; ask the tough questions now
Create a roadmap but be willing to adjust
Get commitments from various boards etc.
Budget- allow for 2-3 fiscal years
24. Lessons Learned
Think logistics and process, not just strategic goals
Expect obstacles and have support from leadership
Devote time to managing relationships – CRITICAL
Identify assets: land, permits, infrastructure, power/heat users
Identify what vendors need
Look for ways to help
25. Recommendations
Have a SWMP that is from the Executive
Office of Energy and Environmental
Affairs (EEA); cabinet level.
Include all relevant agencies in EEA and
outside too
DAR, DOER, DPU, DCAM, DOT
Clear understanding of pragmatic
realities, not just lofty goals
26. Recommendations
Intermedia cooperation on policy goals
Air, solid waste, water
Better data. Reinstate the Data Subcommittee and
coordinate with the DEP contractor
Mass balance approach for all materials matched
with disposal facilities, transfer facilities, processing
facilities
Plan in context of where our waste goes and could go
from Canada to Ohio to South Carolina and Virginia
Coordinate with other states at the cabinet level
27. Recommendations
Support those that build, own, operate infrastructure
Think like a developer and create a complete
pathway to success
Inside-out approach; start at goal and back out what
it will take
Legislators need to be better educated about facilities
Better prepare municipalities for changes and options
MA needs to improve leading by example
DOT glass, asphalt shingles, loam
DCAM recycling clean gypsum
29. It will take all of us
Regulators
Engineers
Educators
Politicians and local boards
Lawyers
Community liaisons and the general public
Business leaders
You can play a role
SWANA.org, Massrecycle.org
Recycling Committees, other local boards
30. We need infrastructure of all types
Recycling, re-purposing facilities, composting,
collection, energy generation, new technologies
Landfills will likely always be needed
Soils
Residuals (recycling, C&D)
Bulky, difficult-to-manage
Backup for outages
Storm debris
Special wastes
31. Edward M. Kennedy Institute for the United States Senate
Image source: Edward M. Kennedy Institute for the United States Senate
Built on an old dump. Soils from the excavation were
managed at the Bourne landfill.