SlideShare a Scribd company logo
1 of 9
Download to read offline
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
1 | P a g e  
   
EDITORS COMMENTS 
The UK is facing a second lockdown and it is 
not  clear  how  extreme  the  restrictions  the 
government  may  need  to  impose  will  be. 
Whilst  construction  sites  are  operating  the 
true financial impacts are still not known and 
delay and disruption claims are likely to form 
a  good  proportion  of  disputes  moving 
forward.  Whether  they  will  be  resolved 
amicably or not remains to be seen. 
What is clear that tight margins and historical 
issues  led  to  pressure  in  the  supply  chain 
which we believe has led to a significant rise 
in  adjudications  in  the  second  and  third 
quarters of this and is likely to continue into 
the new year. 
We  are  still  planning  on  holding  the  annual 
Edinburgh  and  London  conferences  for  2021 
though they may become virtual if necessary. 
We  have  a  range  of  articles  from  across  the 
globe and it is of real interest that New South 
Wales  has  removed  the  owner  occupier 
exemption. 
In  John  Doyle  Construction  Ltd  v  Erith 
Contractors Ltd [2020] EWHC 2451 (TCC), the 
first judgment from the High Court following 
the  Supreme  Court’s  decision  in  Bresco  v 
Lonsdale  [2020]  USKC  25,  Riaz  Hussain  QC, 
was successful in resisting enforcement of an 
adjudicator’s decision in favour of a company 
in  liquidation.  On  the  facts  it  was  held  that 
insufficient security was provided both for the 
sum of the adjudicator’s decision and for the 
costs  of  final  proceedings.  This  case  can  be 
contrasted  with  the  cases  where  a  Party  in 
liquidation  has  successfully  enforced  an 
adjudicator’s  decision  namely  Balfour  Beatty 
Civil  Engineering  Ltd  &  Anor  v  Astec  Projects 
Ltd  [2020]  EWHC  796  (TCC)  and  Styles  and 
Wood  v  GECIF  Trustees  Unreported  4 
September 2020. 
Despite  the  different  results  concerning 
enforcement  it  is  likely  that  parties  will 
adjudicate  and  enforce  despite  liquidation 
and  insolvency  where  they  have  access  to 
funds  to  provide  both  security  and  costs  for 
final proceedings. 
Sean Gibbs LLB(Hons) LLM MICE FCIOB FRICS 
FCIARB,  is  a  director  with  Hanscomb 
Intercontinental and is available to serve as an 
arbitrator,  adjudicator,  mediator,  quantum 
expert  and  dispute  board  member. 
sean.gibbs@hanscombintercontinental.co.uk 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
2 | P a g e  
   
IRDK  VENTURES  SDN  BHD  V. 
ECONPILE  (M)  SDN  BHD  (CIVIL 
APPEAL NO. W – 02 (C)(A) – 645 – 
04 / 2016) (Decision dated 9th July 
2020)  
Summary:  The  issue  before  the  Court  of 
Appeal was an application by the developer of 
a  project  ‘IRDK  Ventures  Sdn  Bhd’,  the 
Appellant,  against  the  decision  of  the  Kuala 
Lumpur High Court which held in favour of the 
Contractor  ‘Econpile  (M)  Sdn  Bhd’,  the 
Respondent,  and  allowed  the  Respondent’s 
Enforcement  Application  of  an  Adjudicator’s 
decision  dated  30th  October  2015,  while 
dismissing  the  Appellant’s  Setting  Aside 
Application.  
As  a  brief  background,  the  Adjudicator’s 
decision  was  due  on  15th  October  2015, 
which  was  subsequently  extended  to  30th 
October  2015  by  agreement  of  both  parties 
under  Section  12(2)(c)  of  the  Construction 
Industry  Payment  and  Adjudication  Act  2012 
(the “CIPAA”). The Adjudicator’s decision was 
delivered  to  the  parties  on  3rd  November 
2015,  after  confirmation  from  the  AIAC 
regarding  a  balance  payment  of  RM258.32 
(being  the  GST  to  be  deposited  with  AIAC). 
The Appellant’s solicitors had sent a scanned 
copy  of  the  cheque  on  29th  October  2015, 
which was physically delivered to the AIAC on 
30th  October  2015  (5:20  pm,  Friday),  and 
reached  the  AIAC’s  Case  Counsel  on  2nd 
November 2015 (at [11]‐[17]). “23.1 Whether 
an adjudication decision delivered within time 
but  released  to  the  parties  only  after  the 
payment  of  the  GST  for  KLRCA’s  fees  is  void 
and/or whether there is a delay in making and 
serving  the  Adjudication  decision  to  the 
Parties; and 23.2 Whether the Adjudicator has 
the  jurisdiction  to  decide  on  the  payment 
claims  when  the  contract  has  been 
terminated  and/or  whether  the  Respondent 
was  entitled  to  commence  an  adjudication 
proceeding  under  CIPAA  after  the  contract 
had been terminated” (at [23]). The Court of 
Appeal on 9th July 2020 dismissed the appeals 
with cost (at [57]). First, the Court of Appeal 
referring  to  sections  12(2)  and  19  of  CIPAA, 
and Regulations 7,9, and 12 under Schedule II 
of the AIAC’s Standard Terms of Appointment 
held  that  “…having  Newsletter  August  2020 
62  The  Federal  Court  of  Malaysia  amongst 
other  grounds  of  judgement  observed  as 
follows:  “[34]  The  award  of  the  arbitral 
tribunal  embodies  the  totality  of  the  case 
before  it  which  includes  inter‐alia,  the  relief 
sought,  the  issues  to  be  tired,  witness 
statements,  submissions,  summary  of 
findings,  costs  and  disposition.  By  analogy, 
this  is  similar  to  the  grounds  of  judgment 
delivered by the courts, which are distinct and 
separate  from  the  judgment  or  order  itself. 
The  dispositive  award  is  the  judgment 
whereas  the  entire  award  is  the  grounds  of 
judgment. It defies logic that the whole award 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
3 | P a g e  
   
containing  the  findings  and  analysis  of  the 
arbitral tribunal of the evidence, which is akin 
to the grounds of judgment be considered as 
forming  the  terms  of  judgment  to  be 
registered as a judgment of the High Court. An 
analogy  may  also  be  drawn  between  the 
approach taken by the courts in dealing with 
an  application  under  REJA  and  the  approach 
that the courts ought to take in an application 
under Section 38 of the Arbitration Act 2005. 
Both REJA and Section 38 provide an avenue 
for  the  successful  party  to  register  the 
judgment  in  Malaysia  as  a  judgment  of  the 
High  Court”  (at  [34]).  perused  the 
abovementioned  provisions  and  after  careful 
perusal of the chronology of facts, we were of 
the  view  that  the  act  of  withholding  the 
delivery  of  the  decision  by  the  Adjudicator 
was with a legitimate basis. It was clear to us 
there  was  still  an  outstanding  fee  [sic]  and 
payment  in  the  form  of  GST  that  was  still 
pending to be paid to the KLRCA” (at [41]). It 
further  observed  that  “the  cheque  was  sent 
on a late Friday afternoon and as such, it only 
natural  that  it  will  only  be  processed  on  the 
next working day (at [43]). Most importantly, 
the  Court  of  Appeal  held  that  “It  is  our 
unanimous  view  that  the  Adjudication’s 
decision  was  delivered  within  time  and  the 
same  was  released  to  the  parties  soon  after 
confirmation  that  the  GST  payment  to  the 
KLRCA  had  been  duly  paid  pursuant  to  the 
KLRCA Standard Terms of Appointment of the 
Adjudicator as provided under Schedule II of 
the KLRCA Adjudication Rules and Procedure, 
to which the parties had agreed to adhere to. 
Thus, it is our decision that the Adjudicator’s 
decision  was  valid”  (at  [48]).  Second,  the 
Court of Appeal referring to Sections 2 and 3 
of CIPAA, Clause 25.4(d) of the PAM 2006, and 
Section  17A  of  the  Interpretation  Acts  1948 
and  1967,  held  that  the  Respondent  had  a 
statutory  right  to  refer  to  adjudication  for 
recovery  of  payment  in  the  construction 
industry.  A  remedy  under  the  CIPAA  is  only 
intended  as  an  interim  measure,  and  the 
aggrieved  party  may  still  find  recourse  in  an 
arbitration  proceeding  and/or  in  Court  (at 
[52]‐[55]). Accordingly, it held that “we were 
of  the  unanimous  view  that  none  of  the 
requirements  under  section  15  of  CIPAA  has 
[sic]  been  established  by  the  Appellant  to 
convince  this  Court  to  set  aside  the 
Adjudicator’s decision. We were also mindful 
that  an  adjudication  decision  should  only  be 
set aside in a rare and extreme circumstances 
in  order  to  give  effect  to  the  provisional 
resolution  of  payment  disputes  in 
construction contracts” (at [56]). 
 
 
 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
4 | P a g e  
   
1155 NEPEAN HIGHWAY PTY LTD V 
PROMAX BUILDING PTY LTD [2020] 
VSCA 253  
Under s 16(2) of the Building and Construction 
Industry  Security  of  Payment  Act  2002  (the 
Act),  if  a  respondent  fails  to  provide  a 
payment  schedule  in  response  to  a  payment 
claim, and fails to pay the amount claimed by 
the  due  date  for  payment,  the  claimant  is 
faced with a choice.  It can either (a) recover 
the  unpaid  portion  of  the  claimed  amount 
from  the  respondent  as  a  debt  due  to  the 
claimant  or  (b)  make  an  adjudication 
application  under  section  18(1)(b)  of  the  Act 
in relation to the payment claim.  
 
In most cases, the claimant elects to recover 
the  unpaid  portion  of  the  claim  as  a  debt.  
This is not only more efficient – it avoids the 
need  for  an  adjudication  entirely  –  but 
applying  for  adjudication  introduces 
additional  risk.    Section  18(2)(b)  of  the  Act 
requires the claimant to give the respondent a 
second  opportunity  to  provide  a  payment 
schedule  before  making  any  adjudication 
application,  raising  the  possibility  that  the 
respondent may realize its error and cure it by 
providing a payment schedule.  Alternatively, 
the  adjudicator  may  stray  into  error,  giving 
rise  to  an  application  to  set  aside  the 
determination entirely. 
 
The  Court  of  Appeal’s  decision  in  1155 
Nepean  Highway  Pty  Ltd  v  Promax  Building 
Pty Ltd [2020] VSCA 253 highlights these risks.  
The  plaintiff,  Promax  Building  Pty  Ltd 
(Promax),  was  engaged  to  build  26 
apartments  for  a  lump  sum  price  of 
$8,595,000.  On 15 July 2019, it submitted a 
claim  under  s  14  the  Act  for  a  progress 
payment  of  $2,017,382.15.    No  payment 
schedule was issued by the respondent.   
 
Promax  then  notified  the  respondent  of  its 
intention  to  apply  for  adjudication  and  gave 
the respondent a further two business days in 
which  to  provide  a  payment  schedule  in 
accordance with s 18(2) of the Act.  Again, no 
payment  schedule  was  provided. 
Consequently,  s  21(2A) of  the  Act  prevented 
the  respondent  from  filing  an  adjudication 
response,  meaning  that  the  only  material 
before  the  adjudicator  was  Promax's 
adjudication application.   
 
Unsurprisingly,  the  adjudicator  issued  a 
determination  in  favour  of  Promax,  finding 
that  it  was  entitled  to  the  full  amount 
claimed, plus adjudicator’s fees and interest.  
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
5 | P a g e  
   
Notwithstanding  that  it  had  failed  to  file  a 
payment schedule, the respondent vigorously 
challenged the adjudicator’s determination in 
subsequent  judicial  review  proceedings.    It 
argued,  among  other  things,  that  the 
adjudicator  had  erred  in  inferring  from  its 
failure to provide a payment schedule that no 
credible challenge could be made to the value 
of Promax's claim; failed to properly value the 
works; and improperly relied on photos of the 
works without comparing those works to the 
contract drawings. 
 
None  of  these  arguments  were  accepted  by 
the Court, either at first instance or on appeal.  
Promax  was,  by  that  measure,  entirely 
successful  at  every  stage  of  the  proceeding.  
The  fact  that  Promax  had  to  obtain  a 
determination,  defend  it  at  trial,  and  then 
again on appeal, however, highlights the risks 
introduced by Promax’s decision to apply for 
adjudication.    In  contrast  to  proceedings 
brought to recover a debt – where s 16(4)(b) 
of the Act would have narrowed the grounds 
on which a determination could be challenged 
‐ the adjudicator’s determination provided an 
additional  source  of  potential  error  that  was 
beyond  Promax’s  control.    Given  that,  the 
case  is  a  useful  reminder  of  the  perils  of 
applying  for  adjudication  where  alternative 
options are available. 
 
 
Bill  Stephenson  Barrister  Melbourne  TEC 
Chambers (MTECC) 
Contact Details: 
Phone: (03) 9225 6792  
Mobile: 0418 352 047 
Email: bstephenson@vicbar.com.au  
 
 
 
 
 
 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
6 | P a g e  
   
SHOULD  THE  UK  FOLLOW  NEW 
SOUTH  WALES  AND  AMEND  THE 
CONSTRUCTION  ACT  TO  REMOVE 
THE  RESIDENTIAL  OCCUPIER 
EXCEPTION 
Should the UK follow New South Wales and 
amend  the  Construction  Act  to  remove  the   
“residential  occupier”  exception  to  the 
compulsory  adjudication  provisions  in 
section  106  of  the  Housing  Grants, 
Construction and Regeneration Act 1996 (the 
Construction Act)? 
In  the  United  Kingdom  the  exception  was 
intended to benefit only those who occupy or 
intended  to  occupy  a  property  as  their 
residence.  The  ambit  of  this  exception  was 
considered by the court in Westfields v. Lewis 
[2013] EWHC 376 (TCC) 27 February 2013. 
Section  106  of  the  1996  Act  provides  as 
follows: 
"106  Provisions  not  applicable  to  contract 
with residential occupier. 
(1) This Part does not apply— 
(a)  to  a  construction  contract  with  a 
residential occupier… 
(2) A construction contract with a residential 
occupier means a construction contract which 
principally relates to operations on a dwelling 
which  one  of  the  parties  to  the  contract 
occupies,  or  intends  to  occupy,  as  his 
residence. 
In this subsection 'dwelling' means a dwelling‐
house or a flat; and for this purpose— 
'dwelling‐house'  does  not  include  a  building 
containing a flat…". 
Turning  to  New  South  Wales  on  the  1 
September  2020,  the  Building  and 
Construction  Industry  Security  of  Payment 
Regulation  2020  (NSW)  entered  in  force  and 
repealed  the  existing  Building  and 
Construction  Industry  Security  of  Payment 
Regulation  2008  (NSW).  Previously,  owner 
occupier construction contracts were exempt 
from  the  NSW  Adjudication  scheme  under 
clause 4.1 of the Regulation and section 7(5) 
of the Act which specifically provided that the 
Act did not apply to these types of contracts. 
Under  the  NSW  Act,  an  owner  occupier 
construction  contract  means  a  construction 
contract  for  the  carrying  out  of  residential 
building  work  (within  the  meaning  of  the 
Home Building Act 1989 (NSW)) on such part 
of  any  premises  as  the  party  for  whom  the 
work  is  carried  out  resides  or  proposes  to 
reside  in.  It  bears  a  remarkable  similarity  to 
the UK position and definition. 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
7 | P a g e  
   
The consequences of the amendments in New 
South  Wales  are  thought  to  benefit  builders 
and  owner  occupiers  by  reducing  the  costs 
and  timeframes  to  recover  any  disputed 
amounts owed by owner occupiers. 
The  downside  being  that  owner  occupiers 
entering into building contracts to undertake 
residential building work at their premises or 
intended  premises  from  1  March  2021  will 
need  to become familiar with the Security of 
Payment  legislation  including  the 
consequences  of  failing  to  respond  to  a 
payment  claim  within  the  prescribed 
timeframes.    Further  if  they  wish  to  dispute 
the  amounts  claimed  by  a  builder  in  a 
payment claim, they will need to ensure that a 
payment  schedule  is  served  within  10 
business  days  after  the  payment  claim  is 
served. 
The position will be very similar in the United 
Kingdom in terms of benefits and detriments. 
Very  low  disputes  would  go  to  the  Small 
Claims  Court  and  it  is  arguable  that 
adjudication  would  be  better  than  the  long 
wait  for  a  decision.  Lord  Coulson  posed  the 
question  in  his  judgment  in    Westfields 
Construction  Ltd  v  Lewis,  Is  it  not  time  for 
s.106,  and  the  other  exceptions  to  statutory 
adjudication, to be done away with, so that all 
parties  to  a  construction  contract  can  enjoy 
the  benefits  of  adjudication?  I  would  answer 
the  question  that  it  is  time  and  overseas 
jurisdictions have recognised this. 
DRBF CONNECTIONS CONFERENCE
The DRBF Connections Conference takes place 
virtually  over  three  days  from  the  28  to  30 
October 2020. 
Global  speakers  include  Robert  Fenwick 
Elliott,  John  Papworth,  Jeremy  Glover  and 
Nicholas Gould. 
For  further  information  and  registration 
follow the link: 
https://matchboxvirtual.com/drbf‐
connections‐conference‐2020/  
 
 
 
 
 
 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
8 | P a g e  
   
TCC COURT JUDGEMENTS 
September 
 Daewoo  Shipbuilding  And  Marine 
Engineering  Company  Ltd  v  Songa 
Offshore  Equinox  Ltd  &  Anor [2020] 
EWHC  2353  (TCC) (01  September 
2020) 
 Dr  Jones  Yeovil  Ltd  v  The  Stepping 
Stone  Group  Ltd [2020]  EWHC  2308 
(TCC) (04 September 2020) 
 Energy  Works  (Hull)  Ltd  v  MW  High 
Tech  Projects  UK  Ltd  &  Ors [2020] 
EWHC  2537  (TCC) (24  September 
2020) 
 Essex  County  Council  v  UBB  Waste 
(Essex) Ltd (No. 3) [2020] EWHC 2387 
(TCC) (11 September 2020) 
 John  Doyle  Construction  Ltd  v  Erith 
Contractors  Ltd  (Rev  1) [2020]  EWHC 
2451 (TCC) (14 September 2020) 
 The Leicester Bakery (Holdings) Ltd v 
Ridge  And  Partners  LLP [2020]  EWHC 
2430 (TCC) (11 September 2020) 
 Municpio  De  Mariana  &  Ors  v  BHP 
Group Plc & Anor [2020] EWHC 2471 
(TCC) (18 September 2020) 
 
 Premier  Engineering  (Lincoln)  Ltd  v 
MW High Tech Projects UK Ltd [2020] 
EWHC  2484  (TCC) (18  September 
2020) 
 Pullman  Foods  Ltd  v  The  Welsh 
Ministers  &  Anor [2020]  EWHC  2521 
(TCC) (23 September 2020) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
WWW.UKADJUDICATORS.CO.UK 
OCTOBER 2020 NEWSLETTER 
 
9 | P a g e  
   
SCL  INTERNATIONAL  CONFERENCE 
2021 
 
The  Society  of  Construction  Law  9th
 
International Conference has been postponed 
till November 2021. 
The  Right  Honourable  Lord  Justice  Coulson 
will be a keynote speaker at the Conference. 
 
http://www.constructionlaw2021.com/scl21    

More Related Content

What's hot

CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
 
Article on IBC, 2016
Article on IBC, 2016Article on IBC, 2016
Article on IBC, 2016Alok Saksena
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct paymentsKheng Hoe Advocates
 
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...surrenderyourthrone
 
Remuneration Management System in Public Sector
Remuneration Management System in Public SectorRemuneration Management System in Public Sector
Remuneration Management System in Public SectorAventin Partners
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Recent important judgements feb 2015
Recent important judgements feb 2015Recent important judgements feb 2015
Recent important judgements feb 2015Ashok Seth
 
Litigation case law updates - tatva study circle session
Litigation case law updates - tatva study circle sessionLitigation case law updates - tatva study circle session
Litigation case law updates - tatva study circle sessionSai Chandra Haas Madhoor
 
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...GLC
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterSeanGibbs12
 
Newsletter sep 2015 - issue no.1
Newsletter   sep 2015 - issue no.1Newsletter   sep 2015 - issue no.1
Newsletter sep 2015 - issue no.1oswinfo
 
Newsletter november 2015 - - issue no.2
Newsletter   november 2015 - - issue no.2Newsletter   november 2015 - - issue no.2
Newsletter november 2015 - - issue no.2oswinfo
 
Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Resolution Institute
 
Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3Resolution Institute
 
Construction Service under GST
Construction Service under GSTConstruction Service under GST
Construction Service under GSTCA Nemish Shah
 
Real estate construction GST impact-great compilation by CA Shiv Ashish
Real estate construction GST impact-great compilation by CA Shiv AshishReal estate construction GST impact-great compilation by CA Shiv Ashish
Real estate construction GST impact-great compilation by CA Shiv AshishShakir Shaikh
 

What's hot (20)

CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
 
Article on IBC, 2016
Article on IBC, 2016Article on IBC, 2016
Article on IBC, 2016
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...
Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd v Dae Hanguru Infra Sdn Bhd and ...
 
Remuneration Management System in Public Sector
Remuneration Management System in Public SectorRemuneration Management System in Public Sector
Remuneration Management System in Public Sector
 
Report(1)
Report(1)Report(1)
Report(1)
 
UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Jbcc - out with the old
Jbcc - out with the oldJbcc - out with the old
Jbcc - out with the old
 
Recent important judgements feb 2015
Recent important judgements feb 2015Recent important judgements feb 2015
Recent important judgements feb 2015
 
Litigation case law updates - tatva study circle session
Litigation case law updates - tatva study circle sessionLitigation case law updates - tatva study circle session
Litigation case law updates - tatva study circle session
 
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...
Logistics Services Agreement Sample (Purchase this doc, Text: 08118887270 (Wh...
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
 
Newsletter sep 2015 - issue no.1
Newsletter   sep 2015 - issue no.1Newsletter   sep 2015 - issue no.1
Newsletter sep 2015 - issue no.1
 
Newsletter november 2015 - - issue no.2
Newsletter   november 2015 - - issue no.2Newsletter   november 2015 - - issue no.2
Newsletter november 2015 - - issue no.2
 
Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3
 
Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3
 
Construction Service under GST
Construction Service under GSTConstruction Service under GST
Construction Service under GST
 
Aictu vs uoi
Aictu vs uoiAictu vs uoi
Aictu vs uoi
 
Real estate construction GST impact-great compilation by CA Shiv Ashish
Real estate construction GST impact-great compilation by CA Shiv AshishReal estate construction GST impact-great compilation by CA Shiv Ashish
Real estate construction GST impact-great compilation by CA Shiv Ashish
 

Similar to UK Adjudicators October 2020 Newsletter

UKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfUKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfSeanGibbs12
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021SeanGibbs12
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 

Similar to UK Adjudicators October 2020 Newsletter (20)

UKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfUKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdf
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
 
UKA March 2020 newsletter
UKA March 2020 newsletterUKA March 2020 newsletter
UKA March 2020 newsletter
 
UK Adjudicators November 2018 newsletter
UK Adjudicators November 2018 newsletterUK Adjudicators November 2018 newsletter
UK Adjudicators November 2018 newsletter
 
UK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletterUK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletter
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
UK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletterUK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletter
 
UK Adjudicators February 2020 newsletter
UK Adjudicators February 2020 newsletterUK Adjudicators February 2020 newsletter
UK Adjudicators February 2020 newsletter
 
UKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdfUKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdf
 
UK Adjudicators January 2020 Newsletter
UK Adjudicators January 2020 NewsletterUK Adjudicators January 2020 Newsletter
UK Adjudicators January 2020 Newsletter
 
UK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 NewsletterUK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 Newsletter
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
January 2018 newsletter
 
February 2019 newsletter
February 2019 newsletterFebruary 2019 newsletter
February 2019 newsletter
 
UK Adjudicators May 2020 newsletter
UK Adjudicators May 2020 newsletterUK Adjudicators May 2020 newsletter
UK Adjudicators May 2020 newsletter
 
1622036407540
16220364075401622036407540
1622036407540
 
UK Adjudicators July 2018 newsletter
UK  Adjudicators July 2018 newsletterUK  Adjudicators July 2018 newsletter
UK Adjudicators July 2018 newsletter
 
May June 2018 newsletter
May June 2018 newsletterMay June 2018 newsletter
May June 2018 newsletter
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 

More from Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE

More from Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE (20)

UK Adjudicators September 2021 Newsletter
UK Adjudicators  September 2021 Newsletter UK Adjudicators  September 2021 Newsletter
UK Adjudicators September 2021 Newsletter
 
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference packUK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
 
UK Adjudicators 2021 London Conference pack
UK Adjudicators 2021 London Conference packUK Adjudicators 2021 London Conference pack
UK Adjudicators 2021 London Conference pack
 
UK Adjudicators London 2021 Conference pack
UK Adjudicators London 2021 Conference packUK Adjudicators London 2021 Conference pack
UK Adjudicators London 2021 Conference pack
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Glos CE - material shortages & fluctuations in standard forms of contr5act
Glos CE - material shortages & fluctuations in standard forms of contr5actGlos CE - material shortages & fluctuations in standard forms of contr5act
Glos CE - material shortages & fluctuations in standard forms of contr5act
 
UK Adjudicators Newsletter July 2021
UK Adjudicators Newsletter July 2021UK Adjudicators Newsletter July 2021
UK Adjudicators Newsletter July 2021
 
UK Adjudicators London 2021 Adjudication & Arbitration Conference
UK Adjudicators  London 2021 Adjudication & Arbitration ConferenceUK Adjudicators  London 2021 Adjudication & Arbitration Conference
UK Adjudicators London 2021 Adjudication & Arbitration Conference
 
UK Adjudicators Newsletter June 2021
UK Adjudicators  Newsletter June 2021UK Adjudicators  Newsletter June 2021
UK Adjudicators Newsletter June 2021
 
The need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projectsThe need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projects
 
JCT Dispute Adjudication Board 20221
JCT Dispute Adjudication  Board 20221JCT Dispute Adjudication  Board 20221
JCT Dispute Adjudication Board 20221
 
UK Adjudicators newsletter May 2021
UK Adjudicators newsletter May 2021UK Adjudicators newsletter May 2021
UK Adjudicators newsletter May 2021
 
UK Adjudicators panel members 14 March 2021
UK Adjudicators panel members 14 March 2021UK Adjudicators panel members 14 March 2021
UK Adjudicators panel members 14 March 2021
 
Vis East Moot Programme 2021
Vis East Moot Programme 2021Vis East Moot Programme 2021
Vis East Moot Programme 2021
 
UK Adjudicators Panel Members
UK Adjudicators Panel MembersUK Adjudicators Panel Members
UK Adjudicators Panel Members
 
Hanscomb Intercontinental brochure expert advisory & expert witness services
Hanscomb Intercontinental brochure expert advisory & expert witness servicesHanscomb Intercontinental brochure expert advisory & expert witness services
Hanscomb Intercontinental brochure expert advisory & expert witness services
 
Hanscomb Intercontinental expert advisory & expert witness services
Hanscomb Intercontinental expert advisory & expert witness servicesHanscomb Intercontinental expert advisory & expert witness services
Hanscomb Intercontinental expert advisory & expert witness services
 
UK Adjudicators panel members 7 August 2020
UK Adjudicators panel members 7 August 2020UK Adjudicators panel members 7 August 2020
UK Adjudicators panel members 7 August 2020
 
UK Adjudicators panellists 23 July 2020
UK Adjudicators panellists 23 July 2020UK Adjudicators panellists 23 July 2020
UK Adjudicators panellists 23 July 2020
 
UK Adjudicator panel members 5 July 2020
UK Adjudicator panel members 5 July 2020UK Adjudicator panel members 5 July 2020
UK Adjudicator panel members 5 July 2020
 

Recently uploaded

Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionNilamPadekar1
 
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书SD DS
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsAbdul-Hakim Shabazz
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书srst S
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceMichael Cicero
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书Fir L
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书SD DS
 
Good Governance Practices for protection of Human Rights (Discuss Transparen...
Good Governance Practices for protection  of Human Rights (Discuss Transparen...Good Governance Practices for protection  of Human Rights (Discuss Transparen...
Good Governance Practices for protection of Human Rights (Discuss Transparen...shubhuc963
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxsrikarna235
 
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书Fs Las
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书FS LS
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书SD DS
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementShubhiSharma858417
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaAbheet Mangleek
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 

Recently uploaded (20)

Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 sedition
 
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书
如何办理(ISU毕业证书)爱荷华州立大学毕业证学位证书
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
 
Good Governance Practices for protection of Human Rights (Discuss Transparen...
Good Governance Practices for protection  of Human Rights (Discuss Transparen...Good Governance Practices for protection  of Human Rights (Discuss Transparen...
Good Governance Practices for protection of Human Rights (Discuss Transparen...
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptx
 
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreement
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in India
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 

UK Adjudicators October 2020 Newsletter

  • 1.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    1 | P a g e       EDITORS COMMENTS  The UK is facing a second lockdown and it is  not  clear  how  extreme  the  restrictions  the  government  may  need  to  impose  will  be.  Whilst  construction  sites  are  operating  the  true financial impacts are still not known and  delay and disruption claims are likely to form  a  good  proportion  of  disputes  moving  forward.  Whether  they  will  be  resolved  amicably or not remains to be seen.  What is clear that tight margins and historical  issues  led  to  pressure  in  the  supply  chain  which we believe has led to a significant rise  in  adjudications  in  the  second  and  third  quarters of this and is likely to continue into  the new year.  We  are  still  planning  on  holding  the  annual  Edinburgh  and  London  conferences  for  2021  though they may become virtual if necessary.  We  have  a  range  of  articles  from  across  the  globe and it is of real interest that New South  Wales  has  removed  the  owner  occupier  exemption.  In  John  Doyle  Construction  Ltd  v  Erith  Contractors Ltd [2020] EWHC 2451 (TCC), the  first judgment from the High Court following  the  Supreme  Court’s  decision  in  Bresco  v  Lonsdale  [2020]  USKC  25,  Riaz  Hussain  QC,  was successful in resisting enforcement of an  adjudicator’s decision in favour of a company  in  liquidation.  On  the  facts  it  was  held  that  insufficient security was provided both for the  sum of the adjudicator’s decision and for the  costs  of  final  proceedings.  This  case  can  be  contrasted  with  the  cases  where  a  Party  in  liquidation  has  successfully  enforced  an  adjudicator’s  decision  namely  Balfour  Beatty  Civil  Engineering  Ltd  &  Anor  v  Astec  Projects  Ltd  [2020]  EWHC  796  (TCC)  and  Styles  and  Wood  v  GECIF  Trustees  Unreported  4  September 2020.  Despite  the  different  results  concerning  enforcement  it  is  likely  that  parties  will  adjudicate  and  enforce  despite  liquidation  and  insolvency  where  they  have  access  to  funds  to  provide  both  security  and  costs  for  final proceedings.  Sean Gibbs LLB(Hons) LLM MICE FCIOB FRICS  FCIARB,  is  a  director  with  Hanscomb  Intercontinental and is available to serve as an  arbitrator,  adjudicator,  mediator,  quantum  expert  and  dispute  board  member.  sean.gibbs@hanscombintercontinental.co.uk     
  • 2.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    2 | P a g e       IRDK  VENTURES  SDN  BHD  V.  ECONPILE  (M)  SDN  BHD  (CIVIL  APPEAL NO. W – 02 (C)(A) – 645 –  04 / 2016) (Decision dated 9th July  2020)   Summary:  The  issue  before  the  Court  of  Appeal was an application by the developer of  a  project  ‘IRDK  Ventures  Sdn  Bhd’,  the  Appellant,  against  the  decision  of  the  Kuala  Lumpur High Court which held in favour of the  Contractor  ‘Econpile  (M)  Sdn  Bhd’,  the  Respondent,  and  allowed  the  Respondent’s  Enforcement  Application  of  an  Adjudicator’s  decision  dated  30th  October  2015,  while  dismissing  the  Appellant’s  Setting  Aside  Application.   As  a  brief  background,  the  Adjudicator’s  decision  was  due  on  15th  October  2015,  which  was  subsequently  extended  to  30th  October  2015  by  agreement  of  both  parties  under  Section  12(2)(c)  of  the  Construction  Industry  Payment  and  Adjudication  Act  2012  (the “CIPAA”). The Adjudicator’s decision was  delivered  to  the  parties  on  3rd  November  2015,  after  confirmation  from  the  AIAC  regarding  a  balance  payment  of  RM258.32  (being  the  GST  to  be  deposited  with  AIAC).  The Appellant’s solicitors had sent a scanned  copy  of  the  cheque  on  29th  October  2015,  which was physically delivered to the AIAC on  30th  October  2015  (5:20  pm,  Friday),  and  reached  the  AIAC’s  Case  Counsel  on  2nd  November 2015 (at [11]‐[17]). “23.1 Whether  an adjudication decision delivered within time  but  released  to  the  parties  only  after  the  payment  of  the  GST  for  KLRCA’s  fees  is  void  and/or whether there is a delay in making and  serving  the  Adjudication  decision  to  the  Parties; and 23.2 Whether the Adjudicator has  the  jurisdiction  to  decide  on  the  payment  claims  when  the  contract  has  been  terminated  and/or  whether  the  Respondent  was  entitled  to  commence  an  adjudication  proceeding  under  CIPAA  after  the  contract  had been terminated” (at [23]). The Court of  Appeal on 9th July 2020 dismissed the appeals  with cost (at [57]). First, the Court of Appeal  referring  to  sections  12(2)  and  19  of  CIPAA,  and Regulations 7,9, and 12 under Schedule II  of the AIAC’s Standard Terms of Appointment  held  that  “…having  Newsletter  August  2020  62  The  Federal  Court  of  Malaysia  amongst  other  grounds  of  judgement  observed  as  follows:  “[34]  The  award  of  the  arbitral  tribunal  embodies  the  totality  of  the  case  before  it  which  includes  inter‐alia,  the  relief  sought,  the  issues  to  be  tired,  witness  statements,  submissions,  summary  of  findings,  costs  and  disposition.  By  analogy,  this  is  similar  to  the  grounds  of  judgment  delivered by the courts, which are distinct and  separate  from  the  judgment  or  order  itself.  The  dispositive  award  is  the  judgment  whereas  the  entire  award  is  the  grounds  of  judgment. It defies logic that the whole award 
  • 3.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    3 | P a g e       containing  the  findings  and  analysis  of  the  arbitral tribunal of the evidence, which is akin  to the grounds of judgment be considered as  forming  the  terms  of  judgment  to  be  registered as a judgment of the High Court. An  analogy  may  also  be  drawn  between  the  approach taken by the courts in dealing with  an  application  under  REJA  and  the  approach  that the courts ought to take in an application  under Section 38 of the Arbitration Act 2005.  Both REJA and Section 38 provide an avenue  for  the  successful  party  to  register  the  judgment  in  Malaysia  as  a  judgment  of  the  High  Court”  (at  [34]).  perused  the  abovementioned  provisions  and  after  careful  perusal of the chronology of facts, we were of  the  view  that  the  act  of  withholding  the  delivery  of  the  decision  by  the  Adjudicator  was with a legitimate basis. It was clear to us  there  was  still  an  outstanding  fee  [sic]  and  payment  in  the  form  of  GST  that  was  still  pending to be paid to the KLRCA” (at [41]). It  further  observed  that  “the  cheque  was  sent  on a late Friday afternoon and as such, it only  natural  that  it  will  only  be  processed  on  the  next working day (at [43]). Most importantly,  the  Court  of  Appeal  held  that  “It  is  our  unanimous  view  that  the  Adjudication’s  decision  was  delivered  within  time  and  the  same  was  released  to  the  parties  soon  after  confirmation  that  the  GST  payment  to  the  KLRCA  had  been  duly  paid  pursuant  to  the  KLRCA Standard Terms of Appointment of the  Adjudicator as provided under Schedule II of  the KLRCA Adjudication Rules and Procedure,  to which the parties had agreed to adhere to.  Thus, it is our decision that the Adjudicator’s  decision  was  valid”  (at  [48]).  Second,  the  Court of Appeal referring to Sections 2 and 3  of CIPAA, Clause 25.4(d) of the PAM 2006, and  Section  17A  of  the  Interpretation  Acts  1948  and  1967,  held  that  the  Respondent  had  a  statutory  right  to  refer  to  adjudication  for  recovery  of  payment  in  the  construction  industry.  A  remedy  under  the  CIPAA  is  only  intended  as  an  interim  measure,  and  the  aggrieved  party  may  still  find  recourse  in  an  arbitration  proceeding  and/or  in  Court  (at  [52]‐[55]). Accordingly, it held that “we were  of  the  unanimous  view  that  none  of  the  requirements  under  section  15  of  CIPAA  has  [sic]  been  established  by  the  Appellant  to  convince  this  Court  to  set  aside  the  Adjudicator’s decision. We were also mindful  that  an  adjudication  decision  should  only  be  set aside in a rare and extreme circumstances  in  order  to  give  effect  to  the  provisional  resolution  of  payment  disputes  in  construction contracts” (at [56]).           
  • 4.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    4 | P a g e       1155 NEPEAN HIGHWAY PTY LTD V  PROMAX BUILDING PTY LTD [2020]  VSCA 253   Under s 16(2) of the Building and Construction  Industry  Security  of  Payment  Act  2002  (the  Act),  if  a  respondent  fails  to  provide  a  payment  schedule  in  response  to  a  payment  claim, and fails to pay the amount claimed by  the  due  date  for  payment,  the  claimant  is  faced with a choice.  It can either (a) recover  the  unpaid  portion  of  the  claimed  amount  from  the  respondent  as  a  debt  due  to  the  claimant  or  (b)  make  an  adjudication  application  under  section  18(1)(b)  of  the  Act  in relation to the payment claim.     In most cases, the claimant elects to recover  the  unpaid  portion  of  the  claim  as  a  debt.   This is not only more efficient – it avoids the  need  for  an  adjudication  entirely  –  but  applying  for  adjudication  introduces  additional  risk.    Section  18(2)(b)  of  the  Act  requires the claimant to give the respondent a  second  opportunity  to  provide  a  payment  schedule  before  making  any  adjudication  application,  raising  the  possibility  that  the  respondent may realize its error and cure it by  providing a payment schedule.  Alternatively,  the  adjudicator  may  stray  into  error,  giving  rise  to  an  application  to  set  aside  the  determination entirely.    The  Court  of  Appeal’s  decision  in  1155  Nepean  Highway  Pty  Ltd  v  Promax  Building  Pty Ltd [2020] VSCA 253 highlights these risks.   The  plaintiff,  Promax  Building  Pty  Ltd  (Promax),  was  engaged  to  build  26  apartments  for  a  lump  sum  price  of  $8,595,000.  On 15 July 2019, it submitted a  claim  under  s  14  the  Act  for  a  progress  payment  of  $2,017,382.15.    No  payment  schedule was issued by the respondent.      Promax  then  notified  the  respondent  of  its  intention  to  apply  for  adjudication  and  gave  the respondent a further two business days in  which  to  provide  a  payment  schedule  in  accordance with s 18(2) of the Act.  Again, no  payment  schedule  was  provided.  Consequently,  s  21(2A) of  the  Act  prevented  the  respondent  from  filing  an  adjudication  response,  meaning  that  the  only  material  before  the  adjudicator  was  Promax's  adjudication application.      Unsurprisingly,  the  adjudicator  issued  a  determination  in  favour  of  Promax,  finding  that  it  was  entitled  to  the  full  amount  claimed, plus adjudicator’s fees and interest.    
  • 5.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    5 | P a g e       Notwithstanding  that  it  had  failed  to  file  a  payment schedule, the respondent vigorously  challenged the adjudicator’s determination in  subsequent  judicial  review  proceedings.    It  argued,  among  other  things,  that  the  adjudicator  had  erred  in  inferring  from  its  failure to provide a payment schedule that no  credible challenge could be made to the value  of Promax's claim; failed to properly value the  works; and improperly relied on photos of the  works without comparing those works to the  contract drawings.    None  of  these  arguments  were  accepted  by  the Court, either at first instance or on appeal.   Promax  was,  by  that  measure,  entirely  successful  at  every  stage  of  the  proceeding.   The  fact  that  Promax  had  to  obtain  a  determination,  defend  it  at  trial,  and  then  again on appeal, however, highlights the risks  introduced by Promax’s decision to apply for  adjudication.    In  contrast  to  proceedings  brought to recover a debt – where s 16(4)(b)  of the Act would have narrowed the grounds  on which a determination could be challenged  ‐ the adjudicator’s determination provided an  additional  source  of  potential  error  that  was  beyond  Promax’s  control.    Given  that,  the  case  is  a  useful  reminder  of  the  perils  of  applying  for  adjudication  where  alternative  options are available.      Bill  Stephenson  Barrister  Melbourne  TEC  Chambers (MTECC)  Contact Details:  Phone: (03) 9225 6792   Mobile: 0418 352 047  Email: bstephenson@vicbar.com.au                  
  • 6.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    6 | P a g e       SHOULD  THE  UK  FOLLOW  NEW  SOUTH  WALES  AND  AMEND  THE  CONSTRUCTION  ACT  TO  REMOVE  THE  RESIDENTIAL  OCCUPIER  EXCEPTION  Should the UK follow New South Wales and  amend  the  Construction  Act  to  remove  the    “residential  occupier”  exception  to  the  compulsory  adjudication  provisions  in  section  106  of  the  Housing  Grants,  Construction and Regeneration Act 1996 (the  Construction Act)?  In  the  United  Kingdom  the  exception  was  intended to benefit only those who occupy or  intended  to  occupy  a  property  as  their  residence.  The  ambit  of  this  exception  was  considered by the court in Westfields v. Lewis  [2013] EWHC 376 (TCC) 27 February 2013.  Section  106  of  the  1996  Act  provides  as  follows:  "106  Provisions  not  applicable  to  contract  with residential occupier.  (1) This Part does not apply—  (a)  to  a  construction  contract  with  a  residential occupier…  (2) A construction contract with a residential  occupier means a construction contract which  principally relates to operations on a dwelling  which  one  of  the  parties  to  the  contract  occupies,  or  intends  to  occupy,  as  his  residence.  In this subsection 'dwelling' means a dwelling‐ house or a flat; and for this purpose—  'dwelling‐house'  does  not  include  a  building  containing a flat…".  Turning  to  New  South  Wales  on  the  1  September  2020,  the  Building  and  Construction  Industry  Security  of  Payment  Regulation  2020  (NSW)  entered  in  force  and  repealed  the  existing  Building  and  Construction  Industry  Security  of  Payment  Regulation  2008  (NSW).  Previously,  owner  occupier construction contracts were exempt  from  the  NSW  Adjudication  scheme  under  clause 4.1 of the Regulation and section 7(5)  of the Act which specifically provided that the  Act did not apply to these types of contracts.  Under  the  NSW  Act,  an  owner  occupier  construction  contract  means  a  construction  contract  for  the  carrying  out  of  residential  building  work  (within  the  meaning  of  the  Home Building Act 1989 (NSW)) on such part  of  any  premises  as  the  party  for  whom  the  work  is  carried  out  resides  or  proposes  to  reside  in.  It  bears  a  remarkable  similarity  to  the UK position and definition.     
  • 7.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    7 | P a g e       The consequences of the amendments in New  South  Wales  are  thought  to  benefit  builders  and  owner  occupiers  by  reducing  the  costs  and  timeframes  to  recover  any  disputed  amounts owed by owner occupiers.  The  downside  being  that  owner  occupiers  entering into building contracts to undertake  residential building work at their premises or  intended  premises  from  1  March  2021  will  need  to become familiar with the Security of  Payment  legislation  including  the  consequences  of  failing  to  respond  to  a  payment  claim  within  the  prescribed  timeframes.    Further  if  they  wish  to  dispute  the  amounts  claimed  by  a  builder  in  a  payment claim, they will need to ensure that a  payment  schedule  is  served  within  10  business  days  after  the  payment  claim  is  served.  The position will be very similar in the United  Kingdom in terms of benefits and detriments.  Very  low  disputes  would  go  to  the  Small  Claims  Court  and  it  is  arguable  that  adjudication  would  be  better  than  the  long  wait  for  a  decision.  Lord  Coulson  posed  the  question  in  his  judgment  in    Westfields  Construction  Ltd  v  Lewis,  Is  it  not  time  for  s.106,  and  the  other  exceptions  to  statutory  adjudication, to be done away with, so that all  parties  to  a  construction  contract  can  enjoy  the  benefits  of  adjudication?  I  would  answer  the  question  that  it  is  time  and  overseas  jurisdictions have recognised this.  DRBF CONNECTIONS CONFERENCE The DRBF Connections Conference takes place  virtually  over  three  days  from  the  28  to  30  October 2020.  Global  speakers  include  Robert  Fenwick  Elliott,  John  Papworth,  Jeremy  Glover  and  Nicholas Gould.  For  further  information  and  registration  follow the link:  https://matchboxvirtual.com/drbf‐ connections‐conference‐2020/                  
  • 8.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    8 | P a g e       TCC COURT JUDGEMENTS  September   Daewoo  Shipbuilding  And  Marine  Engineering  Company  Ltd  v  Songa  Offshore  Equinox  Ltd  &  Anor [2020]  EWHC  2353  (TCC) (01  September  2020)   Dr  Jones  Yeovil  Ltd  v  The  Stepping  Stone  Group  Ltd [2020]  EWHC  2308  (TCC) (04 September 2020)   Energy  Works  (Hull)  Ltd  v  MW  High  Tech  Projects  UK  Ltd  &  Ors [2020]  EWHC  2537  (TCC) (24  September  2020)   Essex  County  Council  v  UBB  Waste  (Essex) Ltd (No. 3) [2020] EWHC 2387  (TCC) (11 September 2020)   John  Doyle  Construction  Ltd  v  Erith  Contractors  Ltd  (Rev  1) [2020]  EWHC  2451 (TCC) (14 September 2020)   The Leicester Bakery (Holdings) Ltd v  Ridge  And  Partners  LLP [2020]  EWHC  2430 (TCC) (11 September 2020)   Municpio  De  Mariana  &  Ors  v  BHP  Group Plc & Anor [2020] EWHC 2471  (TCC) (18 September 2020)     Premier  Engineering  (Lincoln)  Ltd  v  MW High Tech Projects UK Ltd [2020]  EWHC  2484  (TCC) (18  September  2020)   Pullman  Foods  Ltd  v  The  Welsh  Ministers  &  Anor [2020]  EWHC  2521  (TCC) (23 September 2020)                             
  • 9.   WWW.UKADJUDICATORS.CO.UK  OCTOBER 2020 NEWSLETTER    9 | P a g e       SCL  INTERNATIONAL  CONFERENCE  2021    The  Society  of  Construction  Law  9th   International Conference has been postponed  till November 2021.  The  Right  Honourable  Lord  Justice  Coulson  will be a keynote speaker at the Conference.    http://www.constructionlaw2021.com/scl21