CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
(Keshav) report file on kali sindh thermal power project, jhalawar
1. CHAPTER -1
1
INTRODUCTION OF K.S.T.P.P
Kali Sindh Thermal Power Project located near the Kalisindh river . Thermal
power station requires large quantity of water for formation of steam in steam tubes, it
also require water for cooling tower & for cooling of different accessories. For
generation of steam fuel ( Coal ) require it should be available from mines to power
plant through Rail/ Ship/ Road transportation. The nearby Rly station Jhalawar city is
only 8 KM from the Power Plant. The generated power to be fed in the transmission
line The 400 / 220 KV GSS is near the power plant .Huge land also available in near
area for ash disposal. These all factors make favor for site selection for Power Plant at
Jhalawar City. At present K.S.T.P.P. having 2 nos. units for generation of 1200 MW
as under:
Stage-I 2 x 600MW Date of C.O.D.. for Unit
#1
Stage-II 2 x 660 MW Proposed
Table no.1
The design of steam power station requires wide experience as the subsequent
operation and maintenance are greatly affected by its design. The most efficient
design consist of properly sized component designed to operate safely and
conveniently along with its auxiliaries and installation.
2. CHAPTER -2
GENERAL LAYOUT & BASIC IDEA:-
The Steam turbine converts thermal energy of steam into mechanical energy and
Generator converts this mechanical energy to Electrical energy. The operation of
steam turbine generator involves the expansion of steam through numerous stages in
turbine causing turbine rotor to rotate which in turn rotate Generator rotor. The
Generator rotor is manetised and its rotation generates the electric power in the
Generator Stator.
2.1 Basics of Steam Plant Cycle:
The Basics of Steam Plant is Rankine Cycle: See Plant Over view
(i) In Boiler heat addition takes place it is represented by Line 1-1’
( Sensible heat) & 1’-2 (Latent heat of water)
(ii) This Steam expands in turbine & causing turbine to rotate ,
(iii) this expansion is isentropic as entropy remain constant it is represented by
2
line 2-3
(iv) Steam is being condensed in condenser ,here heat rejection tooks place,
show by line 3-4
(v) This condensed steam completed the closed cycle through Boiler feed
pump as shown by Line 4-1
Fig. no. 2.1 Rankine Cycle
3. Power Station may be divided into four main circuits :
3
Fuel and Ash Circuit.
Air and Gas Circuit.
Feed water and Steam Circuit.
Cooling Water Circuit.
2.1.1 Fuel & Ash Circuit:-
Fuel from the storage is fed to the boiler through fuel handling device. The fuel used
in KSTPP is coal, which on combustion in the boiler produced the ash. This ash is
collected at the back of the boiler and removed to ash storage tank through ash
disposal equipment
2.1.2 Air and Gas Circuit:-
Air from the atmosphere is supplied to the combustion chamber of Boiler through the
action of forced draft fan and induced draft fan. The flue gas are first pass around the
boiler tubes and super heated tubes in the furnace, next through dust collector (ESP)
& then economizer. Finally, they are exhausted to the atmosphere through fans.
2.1.3 Feed Water and Steam Circuit:-
The condensate leaving the condenser is first heated in low pressure (LP) heaters
through extracted steam from the lower pressure extraction of the turbine. Then its
goes to deaerator where extra air and non-condensable gases are removed. From
deaerator it goes to boiler feed pump which increases the pressure of the water. From
the BFP it passes through the high pressure heaters. A small part of water and steam
is lost while passing through different components therefore water is added in hot
well. This water is called the make up water. Thereafter, feed water enters into the
boiler drum through economizer. In boiler tubes water circulates because of density
difference in lower and higher temperature section of the boiler. The wet steam passes
through superheater. From superheated it goes into the HP turbine after expanding in
the HP turbine. The low pressure steam called the cold reheat steam (CRH) goes to
the reheater (boiler). From reheater it goes to IP turbine and then to the LP turbine
and then exhausted through the condenser into hot well.
4. 2.1.4 Cooling Water Circuit:-
A large quantity of cooling water is required to condense the steam in condenser and
maintaining low pressure in it. The water is drawn from reservoir and after use it is
drained into the river
A complete Plant overview shown as under:
.
Fig. no. 2.2 plant overview
4
5. CHAPTER -3
COAL HANDLING PLANT OF K.S.T.P.P
We receive coal from Parsakanta Mines fromThe average distances of SECL, ECL &
BCCL are 800, 950 and 1350 Kms. Respectively
5
3.2 COAL HANDLING
It can be called the heart of thermal power plantbecause it provided the fuel for
combustion in boiler. The coal is brought to the KSTPP through rails there are
tracks in all for transportation of coal through rails. The Daily requirement of coal
remain approximately –
3000 Tons for Stage-I Thus approximately 16500 Tons coal is
5700 Tons for Stage-II required daily for Generation of 1045MW
At present everyday 2 to 3 Rakes of coal are to be unloaded at KSTPP. Each Rake
consists of 58 wagons and each wagons consists of app 55 tonnes of coal. The coal is
first unloaded from wagon by wagon triplers then crushed by crushers and send to
different Bunkers with the conveyor system.
The coal handling plant can broadly be divided into three sections :-
1) Wagon Unloading System.
2) Crushing System.
3) Conveying System.
3.2.1 WAGON UNLOADING SYSTEM:-
Wagon Tripler:-
It unloads the coal from wagon to hopper. In the hopper, Iron Jali is provided so that
pieces of only equal to and less than 250 mm. size pass through it. The bigger ones
are broken by the workers with the help of hammers
7. 7
3.2.2 CRUSHING SYSTEM:-
Crusher House:-
It consists of crushers which are used to crush the coal to 20 mm. size. There are
mainly two type of crushers
Primary Crushers i.e. i) Two roll crushers & ii) Rotary breaker.
Secondary Crushers. i.e. Ring granulators.
Primary Crushers:-
Primary crushers are provided in only CHP stage 3 system, while breaking of coal in
CHP Stage 1 & Stage 2 system is done at wagon tripler hopper jali up to the size (-)
250 mm.
Roll Crusher:-
Type : 80” 5 A breakers.
Capacity : 1350 TPH Rates/ 1500 TPH Design.
Feed material : Rom Coal.
Feed size. : (-) 1200 mm. (approx.)
End Product size : (-) 500 mm.
Motor rating. : 2 Nos. 125 KW, 100 rpm.
Rotary Breaker:-
Type : 12’ x 21’ Rotary Breaker.
Capacity : 800 TPH Rated/ 1000 TPH Design.
Secondary Crusher:-
Ring granulators crush by compressing accompanied by impact and shearing.The
unique feature of this granulator is the minimum power required for crushing per ton.
8. 8
Construction & Operation:-
Secondary crushers are ring type granulators crushing at the rate of 550 TPH / 750
TPH for input size of 250 mm. and output size of 20 mm. The crusher is coupled with
motor and gearbox by fluid coupling.
Main parts of granulator like breaker plates, cages , crushing rings and other internal
parts are made of tough manganese (Mn) steel.
The rotor consists of four rows of crushing rings each set having 20 Nos. of toothed
rings and 18 Nos. of plain rings.
Crushers of this type employ the centrifugal force of swinging rings stroking the coal
to produce the crushing action
3.2.3 CONVEYING SYSTEM:-
Stacker Reclaimer:-
The stacker re-claimer unit can stack the material in the form of pilein the coal stock
yard area& it may reclaim the stacked material and fed on to the bunker side
conveyors. While stacking material is being fed from the main line conveyor via
tripler unit and vibrating feeder on the intermediate conveyor which feds the material
on the boom conveyor of the stacker cum reclaimer. From this boom conveyor
material discharged on the coal stock yard area for Stacker reclaimer where it
properly stacked uniformely with the help of Travel Mechanism, Boom Luffing
mechanism, Boom Slewing Mechanism.
During reclaiming the material discharged on to the boom conveyor by the bucket
fitted to the bucket wheel body and boom conveyor feeds the material on the yard
conveyor running in the reverse direction.
Specification of Stacker / Reclaimer:-
Belt width. : 1400 mm..
Bucket wheel motor : 90 KW.
Boom Conveyor motor : 70 KW.
Intermediate Conveyor Motor : 90 KW.
Boom Luffing Motor : 22 KW.
Slewing assembly. : 10 KWx 2 nos.
9. Travel Motor : 7.5 KW x 6 nos.
Vibrating Feeder : 2x6 KW.
Fig. no. 3.3 Stacker
9
Conveyor Specification:-
Capacity of Conveyors
1. 1350 tons per hour. From Wagon Tipplers to Coal Stock Yard Area
2. 750 tons per hour from Stock YardTo Bunker side conveyors
.
10. No. of conveyors : more than 50
From Wagon
Tippler 1,2 to
Stacker Reclaimer-
1
10
From Wagon
Tippler 3,4 to
Stacker
Reclaimer-2
From
Wagon
Tippler -5
Conveyors for Bunker Side
Con 1A,1B Con 1C, 1D 6A,6B
Con-2A,2B,2C Con 2B,2C 7A,7B,7C,7D
Con 3A,3B,3C,4B Con 4C 8A,8B,8C,8D
Shuttle Conveyor Con 12 9A,9B,9C,9D 13A,13B
Telescopic Chute 14A,14B,19A,21A,21B,21C ,22A,22B
23A,24A,25A,25B,
Table no. 2
3.3 PLOW FEEDERS:-
From the Wagon Tippler No.1 & 2 the coal may be stock in the coal stock yard
below the shuttle conveyor , As through the shuttle conveyor the coal discharged on
the coal stock yard from a height of about 25 M so for minimizing the problem of
emission of dust in atmosphere the Telescopic chute is provided.
Below the coal Stock yard an Underground machines are installed known as plow
feeder machines. These machines collect the coal from stock yard and discharge it
on conveyor with the help plow feeder .This coal is takento Bunkers by different
conveyors.
11. CHAPTER -4
ASH HANDLING PLANT OF K.S.T.P.P
Ash produced as the result of combustion of coal is collected andremoved by ash
handling plant. Ash Handling Plant at KSTPP consists of specially designed bottom
ash and fly ash handling system
4.1 Ash Disposal & Dust Collection Plant:-
KSTPP has dry bottom furnace. Ash Handling Plant consists of especially designed
bottom and fly ash system for two path boiler. The system for both units is identical
and following description is applied to both the units the water compounded bottom
ash hopper receives the bottom ash from the furnace from where it is stores and
discharged through the clinker grinder. Two slurry pumps are provided which is
common to both units & used to make slurry and further transportation to ash dyke
11
through pipe line.
Dry free fly ash is collected in two number of 31 fly ash hoppers which are handled
by two independent fly ash system. The ash is removed from fly ash hoppers in dry
state is carried to the collecting equipment where it is mixed with water and resulting
slurry sump is discharged
Utilisation:- Utilisation of coal-ash is always practise than its disposal. There are
various methods of utilisation of coal-ash along with established engineering
technologies some of them are mentioned below:
1.. Manufacturing of building materials.
2.. Making of concrete.
3.. Manufacturing of pozzuolana cement.
4.. Road construction etc.
12. CHAPTER -5
ELECTRO-STATIC PRECIPITATOR
5.1 Scope & Principle of Operation:-
In an ESP the dust laden gas is passed through an intense electric field, which causes
ionization of the gases & they changed into ion while traveling towards opposite
charged electrodes it get deposited as particles and thus Fly ash is deposited on
electrode , this fly ash removed from the electrode with the help of agitating reapers
This Fly Ash collected in different hoppers from where it removes by Ash Handling
system. .
12
5.2 controller:-
Now a day micro-processor based intelligent controllers are used to regulate the
power fed to the HVR. The controls the firing / ignition angle of the thyristor
connected in parallel mode. The average power fed to ESP field can be controlled by
variation of the firing angle of thyristor. The output of controller with respect to time
is also controlled by microprocessor, so that ESP operation is smooth and efficient .
Controller also takes care of fault in KVR and gives a tripping - alarm
13. Fig no. 5.1 Controller
5.3 HIGH VOLTAGE RECTIFIER TRANSFORMER:-
HVR receives the regulated supply from controller. It steps upto high voltage rectifier.
The D.C. supply is fed to E.S.P. field through its negative bushing. The positive
bushing so connected to earth through small resistance which forms a current feed
13
back circuit
14. 14
5.4 E.S.P. FIELD:-
The field consists of emitting and collecting electrodes structure which are totally
isolated from each other and hanging with the top roof of field. The supply to these
electrodes is fed through support insulators. The collecting electrodes are of the shape
of flat plates. By several similar plates while the emitting electrodes are of the shape
of spring. The ash depositing on these electrode is rapped down by separate rapping
mechanism happens at the bottom of the field. From these hoppers ash is evacuated
by ash handling system and dispose to the disposal area. The rapping system is
automatically controlled with the help of the programmable metal controller, located
in the ESP auxiliaries control panels.
15. CHAPTER -6
15
BOILER:-
A boiler (or steam generator) is a closed vessel in which water, under pressure is
converted into steam. It is one of the major components of a thermal power plant. A
boiler is always designed to absorb maximum amount of heat released in process of
combustion. This is transferred to the boiler by all the three modes of heat transfer i.e.
conduction, convection and radiation.
6.1 Water tube boiler:-
In this type of boiler water flows inside the tubes and hot gases flow outside the
tubes. These tubes are interconnected to common water channels and to steam outlet.
In KSTPP, Natural circulation, tangentially fired, over hanged type, Water tube
boilers are used. Oil burners are provided between coal burners for initial start up and
flame stabilization. Firstly, light oil (diesel oil) is sprayed for initialization then heavy
oil (high speed diesel oil) is used for stabilization of flame. Pulverized coal is directly
fed from the coal mills to the burners at the four corners of the furnace through coal
pipes with the help of heated air coming from PA fan. Four nos. of ball mills of
34MT/hr. capacity each have been installed for each boiler. The pressure inside boiler
is -ive so as to minimized the pollution and looses & to prevent the accidents outside
the boiler.
16. Fig. no. 6.1 Boiler
For ensuring safe operation of boilers, furnace safe guard supervisory system (FSSS)
has been installed. This equipment systematically feed fuel to furnace as per load
requirement flame scanners installed to scan the flame conditions and in case of
unsafe working conditions trip the boiler and consequently the turbine. Turbine -
boiler interlocks safe guarding the boiler against possibility of furnace explosion
owing to flame failure.
16
17. 17
6.2 Furnace:-
Furnace is primary part of the boiler where the chemical energy available in the fuel is
converted into thermal energy by combustion.,
Fig. no. 6.2 Furnance
6.3 WATER:-
The source of water for power station is reservoir formed by Kota Barrage on the
Chambal River. In case of large capacity plants huge quantities of coal and water is
required.
18. 18
6.4 PULVERISED FUEL SYSTEM:-
The boiler fuel firing system is tangentially firing system in which the fuel is
introduced from wind nozzle located in the four corners inside the boiler.
The crushed coal from the coal crusher is transferred into the unit coalbunkers where
the coal is stored for feeding into pulverizing mill through rotary feeder
Fig. no. 6.3 Pulverised Fuel System
6.4.1 Fuel Oil System:-
The functional requirement of the fuel burning system is to supply a controllable and
uninterrupted flammable furnace input of fuel and air and to continuously ignite and
burn the fuel as rapidly as it is introduced into the furnace. The Fuel air (secondary
air) provided FD fan, surrounds the fuel nozzles. Dampers are provided so that
quantity of air can be controlled . Coal burners distribute the fuel and air evenly in the
furnace. Ignition takes place when the flammable furnace input is heated above the
ignition temperature..
6.5 Boiler Drum:-
The drum is a pressure vessel. Its function is to separate water and steam from the
mixture (of steam & water) generated in the furnace walls. It provides water storage
for preventing the saturation of tubes. It is made up of two halves of carbon steel
plates.
19. Fig. no. 6.4 Boiler Drum
Boiler drum is located at a height of 53m from ground.The drum form the part of
boiler circulating system i.e. movement of fluid from the drum to the combustion
zone and back to boiler drum. Feed water is supplied to the drum from the economizer
through feed nozzles. Water from the drum goes to water walls through six
downcomers.
19
6.6 Draft System:-
The combustion process in a furnace can take place only when it receives a steady
flow of air and has the combustion gases continuously removed. Theoretically
balanced draft means keeping furnace pressure equal to atmospheric pressure, but in
practice the furnace is kept slightly below atmospheric pressure. It ensures that there
is no egress of air or hot gas and ash into boiler house.
Primary air fan (P.A. fan) or Exhauster fan-
Pulverized coal is directly fed from coal mills to the burners at the four corners of the
furnace through coal pipes with the help of heated air coming from PA fan. Secondly,
this fan also dries the coal. Usually sized for 1500 RPM due to high pressure.
20. 20
Forced draught fan (F.D. fan):-
The combustion process in the furnace can take place only when it receives a steady
flow of air. This air is supplied by FD fan. Thus FD fan takes air from atmosphere at
ambient temperature & so provides additional draught. Its speed varies from 600-1500
RPM.
Induced draught fan (I.D. fan):-
The flue gases coming out of the boiler are passed to the ESP & then dust free gases
are discharged up by the chimney to the atmosphere through the ID fan.
Scanner Air Fan:-
Used to provide necessary cooling air to the flame scanners. Two air fans are usually
provided. One will run and other will remain as stand by. When F.D. fans trip the
scanner air fan will draw air from atmosphere through emergency damper. Typical
speed 3000 RPM.
6.7 Economizer:-
The flue gases coming out of the boiler carry lot of heat. An economiser extracts a
part of this heat from the flue gases and uses it for heating the feed water before it
enters into the steam drum. The use of economiser results in saving fuel consumption
and higher boiler efficiency but needs extra investment. In an economizer, a large
number of small diameter thin walled tubes are placed between two headers. Feed
water enters the tubes through the other. The flue gases flow outside the tubes
.
21. Fig.. No. 6.5 Economizer
21
Air preheaters:-
Air preheaters are employed to recover the heat from the flue gases leaving the
economiser and are used to heat the incoming air for combustion. This raises the
temperature of the furnace gases, improves combustion rates and efficiency and
lowers the stack (chimney) temperature, thus improving the overall efficiency of the
boiler.
Fig. no. 6.6 Air preheaters
Superheater:-
Superheated steam is that steam, which contains more heat than the saturated steam at
the same pressure i.e. it, has been heated above the temperature corresponding to its
pressure. This additional heat provides more energy to the turbine and thus the
22. electrical power output is more.The steam is superheated to the highest economical
temperature increase the efficiency–
22
Reheater:-
Reheaters are provided to raise the temperature of the steam from which part of
energy has already been extracted by HP turbine. This is done so that the steam
remains dry as far as possible through the last stage of the turbine.. From economizer
the water enters the drum and thus joins the circulation system through down covering
water wall tubes. In water wall tubes a part of the water is converted to steam due to
boiler and the mixture flows back to the drum. In the drum, the steam is separated out
through the steam separators and passed to the super heater. After the super heater
when the steam temperature becomes high and pressure upto 150 Kg./cm3 steam is
allowed to enter the turbine to convert potential energy to kinetic energy.
Soot Blower:-
The boiler tubes are cleaned with the help of steam by the process called soot
blowing.
6.8 TECHNICAL SPECIFICATION OF BOILER
1.Type : Direct fired, natural circulation
balance draft water tube boiler.
2. No. of Units. : Two.
3.Make : BHEL.
4.Capacity. : 375 tonnes per hour.
5.Steam Pressure. : 139 Kg./Cm2
6.Efficiency : 86.6 %.
7.No. of fans in service.
a) ID fans. : 2 Nos.
b) FD fans. : 2 Nos.
c) PA fans. : 2 Nos.
d) Seal Air fan. : 1 No.
23. e) Scanner Air fan. : 1 No.
f) Igniter fan. : 1 No.
8. Steam Temperature : 540oC.
9. No. of coal mills in : 3 Nos.service.
23
6.9 FUEL :-
a) COAL:-.
No. of chimney / stack. : 1 / 2.
Height of Chimney : 180 Meters
6.10 GENERAL DESCRIPTION:-
Boilers are tangentially fired, balance draft, natural circulation , radiant type, dry
bottom with direct fired pulverized coal from bowl mills. They are designed for
burning low grade coal with high ash content.
24. CHAPTER - 7
24
STEAM TURBINE
7.1 INTRODUCTION:-
Turbine is a machine in which a shaft is rotated steadily by impact or reaction of
current or stream of working substance ( steam , air , water, gases etc) upon blades of
a wheel. It converts the potential or kinetic energy of the working substance into
mechanical power by virtue of dynamic action of working substance. When the
working substance is steam it is called the steam turbine.
Fig. No. 7.1 Turbine
7.2 PRINCIPAL OF OPERATION OF STEAM TURBINE:-
Although the fundamental principles on which all steam turbine operate the same , yet
the methods where by these principles carried into effect very end as a result, certain
types of turbine have come into existence
25. 1. TECHNICAL DATA OF TURBINE :-
The main technical data of 110 MW turbine is given below:-
Rated output. 110 MW.
Rated speed. 3000 rpm
Rated steam pressure before 130 ata
stop valve.
Maximum steam pressure before 146 ata
stop valve.
Rated temperature of steam before stop valve 535oC.
Rated pressure of steam MP Casing 31.6 ata
Rated pressure of steam before MP Casing 35 ata
HP Cylinder 2 row carts wheel
25
+ 8 moving wheels.
MP Cylinder 2 moving wheels.
LP cylinder 4 moving wheels of
Double row design.
Single flow HP turbine with 25 reaction stages.
Double flow IP turbine with 20 reaction stages per flow.
Double flow LP turbinewith 8 reaction stages per flow.
2 main stop & control valves. & 2 steam check valve in CRH.
2 reheat stop & control valves. & 2 bypass stop & control valve.
7.2.1 Description of Steam Turbines:-
1) Steam flow:-
210 MW steam turbine is a tandem compound machine with HP, IP & LP parts. The
HP part is single flow cylinder and HP & LP parts are double flow cylinders. The
individual turbine rotors and generator rotor are rigidly coupled. The HP cylinder has
a throttle control. Main steam is admitted before blending by two combined main
stop and control valves. The HP turbine exhaust (CRH) leading to reheated have tow
swing check valves that prevent back flow of hot steam from reheated, into HP
turbine. The steam coming from reheated called HRH is passed to turbine via two
combined stop and control valves. The IP turbine exhausts directly goes to LP turbine
by cross ground pipes.
26. 2) HP Turbine:-
The HP casing is a barrel type casing without axial joint. Because of its rotation
symmetry the barrel type casing remain constant in shape and leak proof during quick
change in temperature. The inner casing too is cylinder in shape as horizontal joint
flange are relieved by higher pressure arising outside and this can kept small. Due to
this reason barrel type casing are especially suitable for quick start up and loading.The
HP turbine consists of 25 reaction stages. The moving and stationary blades are
inserted into appropriately shapes into inner casing and the shaft to reduce leakage
losses at blade tips.
3) IP Turbine:-
The IP turbine consists of 20 reaction stages per flow.
4) LP Turbine:-
The casing of double flow type LP turbine is of three shell design. Steam admitted to
LP turbine from IP turbine flows into the inner casing from both sides through steam
inlet nozzles.
26
27. CHAPTER - 8
27
TURBO GENERATOR
8.1 THEORY :-
TURBO GENERATOR manufactured by B.H.E.L. and incorporated with most
modern design concepts enclosing the stator windings, core and hydrogen coolers. .
The generator is driven by directly coupled steam turbine at a speed of 3000 r.p.m. the
Generator is designed for continuous operation at the rated output. The source of
excitation of rotor windings is thyristor controlled D.C. supply.
8.2 Main parts of generator:-
(A) STATOR:-
i. stator frame:-
The stator constructed in a single piece houses the core and windings. The
horizontally mounted water cooled gas coolers being so arranged that it may be
cleaned on the water side without opening the machine to atmosphere. All welded
joints exposed to hydrogen are specially made to prevent leakage. The complete
frame is subjected to hydraulic test at a pressure of 7 ATA.
ii. stator core:-
It is built up of special sheet laminations and whose assembly is supported by a
special guide bass. . Laminations are assembled on guide bass of group separated by
radial ducts to provide ventilation passage. plates. Use of non-magnetic steel reduces
considerably by heating of end iron clamping. special dampers are provided at either
ends of core.
28. Fig. No. 8.1 Stator Core
28
iii. stoter bars:-
Stoter bars dampers are provided to prevent hunting in ac machines.. Conductor
material is electrolytic copper connections brazed with free coating silver alloy to
obtain joints , which are both electrically & mechanically sound.
iv.stator windings:-
Stator windings are double star layers , lap wound, three phase, short pitch type.
Phases are connected to form a double star winding. The arrangement of complete
stator winding electrical circuit is viewed from turbine end of generator & rotor
windings.. The winding is designed to withstand short circuit stresses.
29. 29
v. terminal bushings:-
Six output leads (3 long,3 short) have been brought out of the coming on the exciter
side. casing. Gaskets are provided between the Flange of terminal bushings and
castings to make it absolutely gas tight.
vi. bearings:-
Generator bearings have electrical seats of consists of steel bodies with removable
steel pads. supplies oils to the turbine , bearings & governing gears. .
vii ventilation system:-
The machine is designed with ventilation system having 2 atm rated hydrogen
pressure. Two axial fans mounted on either side of the rotor to ensure circulation of
hydrogen.
8.3 HYDROGEN COOLERS:-
Three Hydrogen Coolers each comprising of two individual units are mounted inside
the stator frame.
(B) ROTOR :-
Rotor shaft consists of single piece alloy steel forging of high mechanical and
magnetic properties performance test includes :-
VIBRATION OF ROTOR:-
Fig. No. 8.2 Vibration of Roter
30. 30
rotor windings:-
Rotor winding is of direct coil type and consists of parallel strips of very high
conductivity Silver Bearing Copper,
bearings:-
The bearings are self-aligned & consist of slip steel shells linked with special bearing
metal having very low coefficient of friction.
slip rings:-
The slip rings are made of forged steel. They are located at either side of Generator
Shaft.
bush gear assembly:-
Generator bushes are made from the various compositions of natural graphite and
binding material. They have a low coefficient of friction and are self lubricating.
drying of winding:-
Generator stator bars are insulated with mica insulation , which is homogeneous in
nature and practically impervious to moisture, and reduce time required to draught.
8.4 TECHNICAL DATA:-
(A) Generator (110 MW):-
Continuous apparent power : 1,37,500 KVA.
Active power : 7,10,000 KW.
Power factor : 0.8 (lagging).
Rated voltage : 1000 + 5% rated.
Current : 7,220 A
Critical speed : 3000 r.p.m. at
Frequency : 50 Hz.
Phase connection : double star.
No. of terminals : 6.
Main diameter of slip rings : 420 mm.
31. Voltage regulation : 39%.
Reactance : Informative.
31
HYDROGEN COOLER:-
Nos. of elements : 6
Cooling medium : Water, H2 at 2 ATM
8.5COOLING SYSTEM:
In KSTPP hydrogen cooling system is employed for generator
cooling.
32. CHAPTER – 9
32
EXCITATION SYSTEM
The electric power Generators requires direct current excited magnets for its field
system. Exciter supply is given from transformer and then rectified.
(A) Function of excitation system:-
The main function of excitation system is to supply required excitation current at
rated load condition of turbo Generator The excitation system makes contribution
improving power system stability steady state condition. The excitation system that
are commonly termed quick response system and have following principal feature :-
Exciter of quick response & high voltage of not less than 1.4 times the rated filed
voltage and nominal exciter response of minimum 0.5.
(B)Type of Excitation System:-
There have been many developments in excitation system design. There has been
continuing reach among the design and the use alike from improving the excitation
system performance. The ultimate is to achieve stability; accuracy etc. the modern
excitation system adopted presently on BHEL makes turbo-generator I. Conventional
DC excitation system. Brushes excitation system.
9.1 STATIC EXCITATION SYSTEM :-
In KSTPP static excitation system is provided it mainly consists of the following:-
1) Rectifier transformer.
2) Nos. of thyristor converters.
3) An automatic voltage regulator (AVR).
4) Field suppression equipment.
5) Field flashing equipment.
9.2 GENERAL ARRANGEMENT:-
In the excitation system the power required for excitation of Generation are tapped
from 11 KV bus ducts through a step down rectifier transformer. After rectification in
thermistor, converter, the DC power is fed to the Generator field winding through a
field breaker. The AVR control the o/p
33. from thyristor converter by adjusting the firing angle depending upon Generator
voltages. The field flashing system facilitates initial built up of the Generator voltage
from the static AC or DC supply.
(I) RECTIFIER TRANSFORMER :-
This transformer steps down the bus voltage 11 KV to 640 V and has a rating of 1360
KVA. It is dry type, it is however provided with current relays and two temperature
sensors
(II) A THYRISTOR CONVERTOR :-
The thyristor panel and are intended for controlled rectification of AC Input power.
6. Thyristor converter are connected in parallel each rates for continuous current o/p
of 20 % of the rated capacity i.e. 20 % reserve. Each thyristor converter consists of 6
thyristor connected in 3-3 , full wave, 6-pulse bridge from and they are cooled by
fans provided with a fuse for protection against short circuit.
(III) AUTOMATIC VOLTAGE CONTROLS :-
The AVR is transistorized thyristor controlled equipment with very fast response.
The AVR is also having provision of stator and rotor currents limits and load angle
limits for optimum utilization of lagging and leading reactive capacities of generator.
(IV) FIELD SUPRESSION EQUIPMENT:-
The field equipment consists of a field breaker with discharge resistors. The field
breakers have 4 main breaking contacts and two discharge contacts, which close
before main contact break.
33
(a) A very fast response.
(b) Extremely reliable in view of static components.
(c) Low maintenance cost.
(d) High efficiency.
(e) Fast field suppression through field and discharge resistance as well as
through Thyristor Bridge, feeding the Generator field.
34. 34
9.3 OPERATION:-
After bringing the speed to operation speed say 3000 r.p.m. , the voltage is slowly
built up with the help of excitation system. This action is taken for synchronizing the
Generator.
(A) SYNCHRONIZING:-
For synchronizing the Generator to the grid system 5 condition of equality have to
be satisfied. These are
(I) Voltage
(II) Frequency
(III) Phase displacement
(IV) Phase sequence
(V) Wave form.
Wave form and phase sequence of the Generator are determined at the design of each
connection SYNCHRONIZING of the generator.
35. CHAPTER – 10
WATER TREATMENT PLANT
The principle problem in high pressure boiler is to control corrosion and steam
quality. Internal corrosion costs power station crores of rupees in repair without strict
control impurities in steam also form deposit over turbine blades and nozzles.
35
10.1 D.M. PLANT:-
Equipment for demineralization cum softening plant consists of two streams each
stream with activated carbon filter, weak acid , cation exchanger and mixed bed
exchanger. The filter water to DM plant through 250 dia. header from where a heater
top off has been taken to softening plant. Two filtered water booster pumps are
provided on filtered water line for meeting the pressure requirement in DM
Plant.SodiumSulphate solution of required strength is dosed into different filtered
water by mean of dosing pump to neutralize chlorine prior to activated carbon filter.
When water passed an activated carbon filter will remove residual chlorine from
water. Provision is made for back washing the activated carbon filter. When pressure
drop across filter exceeds a prescribed limit from the activated carbon filter the works
acid cation unit. The deception water the weak base anion exchanger unit water then
enters de-gasified unit where free CO2 is scrubbed out of water by upward counter
flow of low pr. air flow through degasified lower and degassed water is pumped to
strong base exchanger ( anion exchanger).Arrangement for dosing ammonia solution
into de-mineralized water after mixed bed unit has been provided p+1 correction
before water is taken in de-condensate transfer pump the DM water to unit condensor
as make up
36. CHAPTER – 11
C.W. PLANT & B.C.W. Pump House
Circulating water pump house has pumps for condensing the steam for condensor.
Five pumps are used for condensing Unit No.1 & 2 and after condensing this water
isdischarged back into the river.
Two pump for unit 1 & 2 with one stand by is used for supplying raw water to
chlrofied chemical dosing is tone between and chlorified water is taken through main
line. From main line water passes through filter bed to filter the water.
36
11.1 B.C.W. PUMP HOUSE:-
Filter water after demineralization is used for bearing cooling from BCW pump house
after passing through strainer and heat exchanger it enters at 30-32oC and leave
exchanger at 38oC. BCW here stand for water used for cooling oil used for cooling the
bearing. In CW pump house water is discharged from nozzle and impinged for
traveling water screens for cleaning it.
37. CHAPTER – 12
37
TRANSFORMER
Main transformers, which are necessary:
1. To step up the generated voltage.
2. To supply power to the auxiliaries from the generator.
3. To start the plant by taking the supply from the grid.
Are installed in a transformer yard. It is located in between the main plant and the
switchyard. The main transformers installed in the transformer yard are:
1. GENERATOR TRANSFORMER (GT – A):-
It steps up the voltage from 16.5 KV to 220 KV. It connects the plant
with the 220 KV switchyard.
2. GENERATOR TRANSFORMER (GT – B):-
It steps up the voltage from 16.5 KV to 400 KV. It connects the plant
with the 400 KV switchyard.
3. STATION TRANSFORMER (ST):-
It is a step down transformer with 50 MVA capacities. It is used to step
down 220 KV from the grid to 6.9 KV.
4. UNIT AUXILIARY TRANSFORMER (UAT):-
It is a step down transformer with 20 MVA capacities. It steps down
the voltage from 16.5 KV to 6.9 KV.
5. STATION SERVICE TRANSFORMER (SST):-
It is a step down transformer with 2MVA capacity. It is used to step
down from 6.6 KV to 0.4333 KV.
6. UNIT SERVICE TRANSFORMER (UST):-
It is a step down transformer with 2 MVA capacity. It is used to step
down from 6.6 kV to 0.4333 KV.
38. CHAPTER – 13
38
SWITCH YARD
220 KV SYSTEM :-
Two 220 KV bus bars have been provided in switch yard and are inter-connected
through a bus coupler. Each of the two 110 MW generator is connected to this system
through a step up of 125 MVA 240/ 11 KV yard generator transformer. There are two
step down transformer each feeding 6.6 KV system ( Station Switchyard ) viz. BS-IS
& SB-IB. four feeder take off from 220 switch yard, two to SKATPURA GSS and
other to HEERAPURA , Jaipur GSS.
39. CHAPTER -14
39
PROTECTION
1. Field Protection.
5. Negative Phase Sequence Protection.
6. Reverse Power Protection.
7. Forward Power Protection.
8. Under Frequency & Over Frequency Protection.
9. Generator Voltage Protection.
10. Rotor Earth Fault Protection.
14.1 General Protection:
It is most important electrical equipment of many generating station. Tripping of even
a generating unit may cause overloading of associated machines and even to system
un-stability . The basis function of protection applied to generator is to reduce
voltage to minimum by rapid discrimination clearance of faults. Unlike other
apparatus the opening of C.B. to isolate faulty generator is not sufficient to prevent
future damage.
40. CHAPTER -15
40
CONCLUSION
The first phase of practical training has proved to be quiet fruitful. It provided an
opportunity for encounter with such huge machines like wagon tippler .110 MW &
210 MW turbines and generators.
The architecture of the power plant the way various units are linked and the way
working of whole plant is controlled make the student realize that engineering is not
just learning the structured description and working of various machines, but the
greater part is of planning proper management.
It also provides an opportunities to lean low technology used at proper place and time
can cave a lot of labour e.g. wagon Tripler (CHP).But there are few factors that
require special mention. Training is not carried out into its tree sprit. It is
recommended that there should be some project specially meant for students where
presence of authorities should be ensured. There should be strict monitoring of the
performance of students and system of grading be improved on the basis of work
done.
However training has proved to be quite fruitful. It has allowed an opportunity to get
an exposure of the practical implementation to theoretical fundamentals.