SlideShare a Scribd company logo
1 of 50
MGT150. PROJECT MANAGEMENT (MGT150) > TAKE
ASSESSMENT: FINAL EXAM
Take Assessment: Final Exam
Top of Form
Name
Final Exam
Instructions
The final exam contains 40 multiple-choice questions and 20
true/false questions. Please study the materials available to you
before taking the test. For multiple-choice questions, identify
the answer that is most correct. For ture/false questions,
identify whether the statement is true or false. Make sure you
have thought through your answers carefully before submitting
the final exam.
Multiple Attempts
Not allowed. This Test can only be taken once.
Force Completion
This Test can be saved and resumed later.
Question Completion Status:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Question 1
1 points
Save
Which of the following is an example of a project?
a. Maintaining e-mail addresses
b. Capacity planning
c. Submitting travel and expense reports
d. Sending monthly reports to top management
Question 2
1 points
Save
An effective project manager must:
a. Tell his team members what to do
b. Be the most capable person on the team technically
c. Be focused on achieving results
d. Not trust his team members to achieve results without his
personal attention to detail
Question 3
1 points
Save
A key characteristic of an effective project team is that:
a. Members have graduate degrees in project management
b. Members come from the same professional background
c. Members see themselves as stakeholders in the project
d. Members adhere to a prescribed pecking order
Question 4
1 points
Save
A challenge of the matrix project organization is that:
a. Team members are full of ego
b. Team members are selected from the same functional area
c. Team members have divided loyalties
d. It enables functional managers to provide career guidance to
their workers
Question 5
1 points
Save
A key weakness of the Benefit-Cost ratio project selection
mechanism is that:
a. It only focuses on things that can be measured
b. It takes time frame into consideration
c. It is too much based on subjective judgment
d. It does not entail prioritizing
Question 6
1 points
Save
A major strength of task Gantt charts is that they can:
a. Offer a sophisticated model of a project
b. Show how many resources will be used on the project
c. Show the interdependencies of tasks
d. Show actual versus planned schedule status
Question 7
1 points
Save
If you want to shorten the length of a project, you must:
a. Shorten the critical path
b. Shorten the free float
c. Spend more money
d. Cut back on the features you plan to deliver
Question 8
1 points
Save
The critical path:
a. Provides the duration of a project
b. Has the shortest duration on a project
c. Is the most expensive path to implement
d. Contains the project's most significant tasks
Question 9
1 points
Save
A tool that graphically shows cost variance is:
a. A chart of accounts
b. A code of accounts
c. A histogram (also called a resource loading chart)
d. A cumulative cost curve (also called S-curve)
Question 10
1 points
Save
Which of the following methods involves performing tasks in
parallel?
a. Crashing
b. Fast tracking
c. Leveling
d. Hammocking
Question 11
1 points
Save
Top-down estimates (also called parametric estimates):
a. Are based on historical trends
b. Can be derived from the WBS
c. Can be determined by analyzing work packages
d. Provide accurate assessments of project costs
Question 12
1 points
Save
Bottom-up estimates:
a. Are based on historical trends
b. Can be derived from the WBS
c. Must employ Monte Carlo simulation
d. a and c
Question 13
1 points
Save
Definitive estimates are generally derived from:
a. Bottom-up estimates
b. Top-down estimates
c. Expert judgment cost estimates
d. Order of magnitude estimates
Question 14
1 points
Save
The resource planning tool that enables us to identify who we
need to carry out what tasks is called:
a. A resource Gantt chart
b. A resource matrix (also called the responsibility chart)
c. A resource ogive
d. A resource loading chart (also called a resource histogram)
Question 15
1 points
Save
Which of the following shows resource allocation over time?
a. Resource Gantt chart
b. Resource matrix
c. S-Curve
d. Resource leveling
Question 16
1 points
Save
What is the function of a change control board (CCB) in
configuration management?
a. To assess the management impacts of change requests
b. To initiate changes needed on the project
c. To focus on the technical implication of change requests
d. To approve change requests coming from senior management
Question 17
1 points
Save
Good functional requirements
a. Describe how the deliverable should be developed
b. Provide detailed technical insights into what the deliverable
will do
c. Describe what the deliverable looks like and what it should
do
d. Are created after development of the technical specifications
Question 18
1 points
Save
The type of management whose focus is on activities whose
variances lie outside the acceptable range is:
a. Management by Objectives
b. Management by Exception
c. Management by Walking Around
d. Management by Control Limits
Question 19
1 points
Save
Which of the following is a characteristic of an effective
reporting system?
a. SMART
b. KISS
c. MBO
d. LOWBALLING
Question 20
1 points
Save
Which of the following is an elapsed time task?
a. Paint is drying
b. A painter paints the wall
c. Software is being written
d. A sandwich is being made
Question 21
1 points
Save
An autocratic management style:
a. Is effective in most project management situations
b. Is effective in highly routine efforts
c. Is effective in high flux, state-of-the-art projects
d. Will lead to the tyranny of the majority
Question 22
1 points
Save
A project team structure that closely reflects the physical
structure of the deliverable is known as:
a. Egoless
b. Specialty
c. Surgical
d. Isomorphic
Question 23
1 points
Save
The purpose of mid-project evaluation is:
a. Continual monitoring of budget and estimates
b. To focus on achievement of individual element of the project
plan
c. To determine whether the original objectives are still relevant
d. To re-baseline the project budget
Question 24
1 points
Save
If the latest time you can start a task is five hours into the
project, and the earliest time is three and a half hours into the
project, how much slack (also called float) does the task have?
a. 0.5 hours
b. 1.5 hours
c. 2.5 hours
d. 8.5 hours
Question 25
1 points
Save
In risk management, insurance is an example of:
a. Risk avoidance
b. Risk deflection
c. Risk acceptance
d. Contingency planning
Question 26
1 points
Save
A four step risk assessment process reflecting standard risk
management good practice consists of:
a. Risk identification, Risk deflection, Risk impact analysis,
Risk monitoring and control
b. Risk acceptance, Risk impact analysis, Risk response
planning, Risk monitoring and control
c. Risk deflection, Contingency planning, Risk impact analysis,
Risk monitoring and control
d. Risk identification, Risk impact analysis, Risk response
planning, Risk monitoring and control
Question 27
1 points
Save
Structured Walk-Through is a methodology used in:
a. PERT
b. GERT
c. VERT
d. Project Evaluation
Question 28
1 points
Save
If review of a project's status indicates that EV = $400, AC =
$400, and PV = $500, the project is:
a. On budget, behind schedule
b. On budget, ahead of schedule
c. Over budget, behind schedule
d. Over budget, ahead of schedule
Question 29
1 points
Save
The poor man's hierarchy is a method for:
a. Project estimation
b. Project scheduling
c. WBS construction
d. Project selection
Question 30
1 points
Save
According to PMI, a WBS should focus on
a. Tasks
b. Deliverables
c. Interrelationships among activities
d. Cost of the project
Question 31
1 points
Save
If EV = $300, AC = $400, and the project budget is $1,000,
what is the estimated final cost of the project (this is known as
EAC, estimate at complete)?
a. $750
b. $1,000
c. $1,250
d. $1,333
Question 32
1 points
Save
Which of the following is a scope planning tool?
a. Benefit/cost analysis
b. WBS
c. Earned Value analysis
d. Fast tracking
Question 33
1 points
Save
In resource planning, one of the issues that needs to be
considered is:
a. Staff empowerment
b. Technical requirements of the project
c. Theory X management principles
d. Theory Y management principles
Question 34
1 points
Save
The bottom-most level of the WBS -- the level at which project
budget and schedule data are captured -- is called:
a. Work package
b. Code of accounts
c. Budget baseline
d. Change control level
Question 35
1 points
Save
Scope creep means:
a. Needs emergence and identification
b. Uncontrolled changes to a project's requirements during
project execution
c. Migration of project needs to requirements
d. Imprecise scope statement
Question 36
1 points
Save
Configuration management is a:
a. Methodology for working closely with customers by
developing and updating requirements for faster response to
changing customer needs
b. Methodology for ensuring that requirements evolve with
evolving customer requirements
c. Methodology for specifying requirements at the outset and
for controlling very tightly any changes to them
d. Methodology for specifying requirements at the outset and
for facilitating any changes to them with minimum customer
input
Question 37
1 points
Save
Rapid prototyping is a methodology for:
a. Specifying requirements at the outset and for controlling very
tightly any changes to them
b. Specifying requirements at the outset and for facilitating later
changes to them with minimum customer in put
c. Triggering early warning of unauthorized changes to the
original prototype to enable project management to take
remedial actions
d. Working closely with customers by creating and updating
prototypes that respond to customer input
Question 38
1 points
Save
Ensuring a one-to-one correspondence between specification
items and general design items is a feature of:
a. Scope statement definition
b. WBS construction
c. Rapid prototyping
d. Configuration management
Question 39
1 points
Save
Under what conditions may a project manager accept a change
request?
a. If the request has no effect on project objectives, deadlines,
or resources
b. If the request has no effect on project objectives, although it
has effects on deadlines and resources
c. If the request is coming from a valued customer
d. If the request is from the Chief Executive Officer
Question 40
1 points
Save
Which of the following is not an activity carried out during
project closeout?
a. Reassignment of project staff
b. Preparation of the project's baseline
c. Reassignment of material resources
d. Preparation of user manuals
Question 41
1 points
Save
When crashing a project, we typically choose critical path tasks
whose costs of crashing are highest.
True
False
Question 42
1 points
Save
The astute project manager typically uses only one management
style in order not to confuse his/her teammates.
True
False
Question 43
1 points
Save
Concurrent engineering involves overlapping tasks and phases
to accelerate a project's schedule.
True
False
Question 44
1 points
Save
A work package is to be found at the summary level of the
WBS.
True
False
Question 45
1 points
Save
Milestones, like tasks, consume resources.
True
False
Question 46
1 points
Save
In project management, the level of uncertainty plays a major
role in determining the adequacy of a project plan.
True
False
Question 47
1 points
Save
Using working time or elapsed time to calculate the time it will
take to complete a task produces the same results.
True
False
Question 48
1 points
Save
Needs recognition is the first stage of the needs-requirement life
cycle.
True
False
Question 49
1 points
Save
Functional requirements provide us with detailed technical
specifications.
True
False
Question 50
1 points
Save
A key objective of change control in configuration management
is to keep track of actions taken in response to change requests.
True
False
Question 51
1 points
Save
Under rapid prototyping (also called application prototyping),
the customer actually sees and works with the deliverable as it
evolves.
True
False
Question 52
1 points
Save
There is a definite link between the level of risk an enterprise
encounters and project time frame.
True
False
Question 53
1 points
Save
When we have objective data on the probability of an event, we
are involved with decision making under certainty.
True
False
Question 54
1 points
Save
The Theory X approach to managing workers is a classic
example of a top-down view of how people should be managed.
True
False
Question 55
1 points
Save
A laissez-faire management style may lead to a ship without
rudder syndrome.
True
False
Question 56
1 points
Save
An objective of prototyping is to minimize life-cycle cost.
True
False
Question 57
1 points
Save
A modern view in Human Resource Management is that positive
motivation results from an opportunity to achieve and
experience self-actualization.
True
False
Question 58
1 points
Save
Confidence in the accuracy of a cost estimate increases when
top-down and bottom-up estimates converge.
True
False
Question 59
1 points
Save
Internal Rate of Return (IRR) is the discount rate that sets the
present value of cash outflow equal to the present value of cash
inflow.
True
False
Question 60
1 points
Save
A project can be terminated prematurely because the original
objectives may no longer be valid.
True
False
Bottom of Form
_75_1
_46825_1
null
_11393_1
qHide
true
_2072_1

More Related Content

Similar to MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx

Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project management
NMIMS ASSIGNMENTS HELP
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
Baskar El
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
IRESH3
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
bubyslyke
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
giquickly
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
ginistays
 
Qnt 561 qnt/561 final exam 100% correct answers
Qnt 561 qnt/561 final exam 100% correct answersQnt 561 qnt/561 final exam 100% correct answers
Qnt 561 qnt/561 final exam 100% correct answers
Gliven
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
ginistays
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
bubyslyke
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
giquickly
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
ginistays
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
bubyslyke
 
Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#
siliverseyr
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
giquickly
 
Ops 571 final exam view 369
Ops 571 final exam view 369Ops 571 final exam view 369
Ops 571 final exam view 369
forrest44
 
Ops 571 ops571 final exam correct 100%
Ops 571 ops571 final exam correct 100%Ops 571 ops571 final exam correct 100%
Ops 571 ops571 final exam correct 100%
sharing3444
 

Similar to MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx (20)

Examination paper of project management certification
Examination paper of project management certificationExamination paper of project management certification
Examination paper of project management certification
 
Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project management
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
 
Qnt 561 final exam
Qnt 561 final examQnt 561 final exam
Qnt 561 final exam
 
PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
Qnt 561 qnt/561 final exam 100% correct answers
Qnt 561 qnt/561 final exam 100% correct answersQnt 561 qnt/561 final exam 100% correct answers
Qnt 561 qnt/561 final exam 100% correct answers
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
 
Mkt 571 final exam
Mkt 571 final examMkt 571 final exam
Mkt 571 final exam
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
 
Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
 
Ops 571 final exam view 369
Ops 571 final exam view 369Ops 571 final exam view 369
Ops 571 final exam view 369
 
Ops 571 ops571 final exam correct 100%
Ops 571 ops571 final exam correct 100%Ops 571 ops571 final exam correct 100%
Ops 571 ops571 final exam correct 100%
 

More from annandleola

CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docxCASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
annandleola
 
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docxCASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
annandleola
 
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docxCase 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
annandleola
 
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docxCase 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
annandleola
 
CASE 5Business Performance Evaluation Approaches for Thoughtf.docx
CASE 5Business Performance Evaluation Approaches for Thoughtf.docxCASE 5Business Performance Evaluation Approaches for Thoughtf.docx
CASE 5Business Performance Evaluation Approaches for Thoughtf.docx
annandleola
 
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docxCase 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
annandleola
 
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docxCase 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
annandleola
 
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docxCase 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
annandleola
 
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docxCASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
annandleola
 
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docxCase 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
annandleola
 
Case 48 Sun Microsystems Done by Nour Abdulaziz Maryam .docx
Case 48 Sun Microsystems Done by Nour Abdulaziz  Maryam .docxCase 48 Sun Microsystems Done by Nour Abdulaziz  Maryam .docx
Case 48 Sun Microsystems Done by Nour Abdulaziz Maryam .docx
annandleola
 
CASE 42 Myasthenia Gravis The immune response turns agai.docx
CASE 42 Myasthenia Gravis The immune response turns agai.docxCASE 42 Myasthenia Gravis The immune response turns agai.docx
CASE 42 Myasthenia Gravis The immune response turns agai.docx
annandleola
 
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docxCase 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
annandleola
 
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docxCase 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
annandleola
 
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docxCASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
annandleola
 
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docxCase 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
annandleola
 
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docxCase 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
annandleola
 
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docxCASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
annandleola
 

More from annandleola (20)

CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docxCASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
CASE 6B – CHESTER & WAYNE Chester & Wayne is a regional .docx
 
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docxCASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
CASE 9 Bulimia Nervosa Table 9-1   Dx Checklist   Bulimia Nervos.docx
 
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docxCase 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
Case 9 Bulimia Nervosa in Gorenstein and Comer (2014)Rita was a.docx
 
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docxCase 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
Case 8.1 Pros and Cons of Balkan Intervention59Must the a.docx
 
CASE 5Business Performance Evaluation Approaches for Thoughtf.docx
CASE 5Business Performance Evaluation Approaches for Thoughtf.docxCASE 5Business Performance Evaluation Approaches for Thoughtf.docx
CASE 5Business Performance Evaluation Approaches for Thoughtf.docx
 
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docxCase 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
Case 6-2 Not Getting Face Time at Facebook—and Getting the Last La.docx
 
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docxCase 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
Case 6.4 The Case of the Poorly Performing SalespersonEd Markham.docx
 
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docxCase 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
Case 5.6Kelo v City of New London545 U.S. 469 (2005)Ye.docx
 
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docxCASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
CASE 5.10 FIBREBOARD PAPER PRODUCTS CORP. V. NLRB SUPREME COURT OF.docx
 
Case 4 The McDonald’s China Food Supplier Scandal1. What we.docx
Case 4 The McDonald’s China Food Supplier Scandal1. What we.docxCase 4 The McDonald’s China Food Supplier Scandal1. What we.docx
Case 4 The McDonald’s China Food Supplier Scandal1. What we.docx
 
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docxCase 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
Case 3 Neesha Wilson Phoenix Rising Risks, Protective Factors, and.docx
 
Case 48 Sun Microsystems Done by Nour Abdulaziz Maryam .docx
Case 48 Sun Microsystems Done by Nour Abdulaziz  Maryam .docxCase 48 Sun Microsystems Done by Nour Abdulaziz  Maryam .docx
Case 48 Sun Microsystems Done by Nour Abdulaziz Maryam .docx
 
CASE 42 Myasthenia Gravis The immune response turns agai.docx
CASE 42 Myasthenia Gravis The immune response turns agai.docxCASE 42 Myasthenia Gravis The immune response turns agai.docx
CASE 42 Myasthenia Gravis The immune response turns agai.docx
 
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docxCase 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
Case 4 JetBlue Delighting Customers Through Happy JettingIn the.docx
 
Case 4-2 Hardee TransportationThe Assignment Answer the four .docx
Case 4-2 Hardee TransportationThe Assignment Answer the four .docxCase 4-2 Hardee TransportationThe Assignment Answer the four .docx
Case 4-2 Hardee TransportationThe Assignment Answer the four .docx
 
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docxCase 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
Case 3-8 Accountant takes on Halliburton and Wins!1.      Descri.docx
 
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docxCASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
CASE 3.2 A Shift for Lieutenant Colonel AdamsEAM 751 Chapter.docx
 
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docxCase 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
Case 3 Ford’s Pinto Fires The Retrospective View of Ford’s Fiel.docx
 
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docxCase 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
Case 3Competition in the Craft Brewing Industry in 2017John D. Var.docx
 
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docxCASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
CASE 3.2 Ethics, Schmethics-Enrons Code of EthicsIn Jul.docx
 

Recently uploaded

Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
MateoGardella
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 

Recently uploaded (20)

Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 

MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx

  • 1. MGT150. PROJECT MANAGEMENT (MGT150) > TAKE ASSESSMENT: FINAL EXAM Take Assessment: Final Exam Top of Form Name Final Exam Instructions The final exam contains 40 multiple-choice questions and 20 true/false questions. Please study the materials available to you before taking the test. For multiple-choice questions, identify the answer that is most correct. For ture/false questions, identify whether the statement is true or false. Make sure you have thought through your answers carefully before submitting the final exam. Multiple Attempts Not allowed. This Test can only be taken once. Force Completion This Test can be saved and resumed later. Question Completion Status: 1 2 3 4 5 6 7
  • 4. Question 1 1 points Save Which of the following is an example of a project? a. Maintaining e-mail addresses b. Capacity planning c. Submitting travel and expense reports d. Sending monthly reports to top management Question 2 1 points Save
  • 5. An effective project manager must: a. Tell his team members what to do b. Be the most capable person on the team technically c. Be focused on achieving results d. Not trust his team members to achieve results without his personal attention to detail Question 3 1 points Save A key characteristic of an effective project team is that:
  • 6. a. Members have graduate degrees in project management b. Members come from the same professional background c. Members see themselves as stakeholders in the project d. Members adhere to a prescribed pecking order Question 4 1 points Save A challenge of the matrix project organization is that: a. Team members are full of ego b. Team members are selected from the same functional area
  • 7. c. Team members have divided loyalties d. It enables functional managers to provide career guidance to their workers Question 5 1 points Save A key weakness of the Benefit-Cost ratio project selection mechanism is that: a. It only focuses on things that can be measured b. It takes time frame into consideration c. It is too much based on subjective judgment
  • 8. d. It does not entail prioritizing Question 6 1 points Save A major strength of task Gantt charts is that they can: a. Offer a sophisticated model of a project b. Show how many resources will be used on the project c. Show the interdependencies of tasks d. Show actual versus planned schedule status
  • 9. Question 7 1 points Save If you want to shorten the length of a project, you must: a. Shorten the critical path b. Shorten the free float c. Spend more money d. Cut back on the features you plan to deliver Question 8 1 points Save The critical path:
  • 10. a. Provides the duration of a project b. Has the shortest duration on a project c. Is the most expensive path to implement d. Contains the project's most significant tasks Question 9 1 points Save A tool that graphically shows cost variance is: a. A chart of accounts
  • 11. b. A code of accounts c. A histogram (also called a resource loading chart) d. A cumulative cost curve (also called S-curve) Question 10 1 points Save Which of the following methods involves performing tasks in parallel? a. Crashing b. Fast tracking c. Leveling
  • 12. d. Hammocking Question 11 1 points Save Top-down estimates (also called parametric estimates): a. Are based on historical trends b. Can be derived from the WBS c. Can be determined by analyzing work packages d. Provide accurate assessments of project costs
  • 13. Question 12 1 points Save Bottom-up estimates: a. Are based on historical trends b. Can be derived from the WBS c. Must employ Monte Carlo simulation d. a and c Question 13 1 points Save Definitive estimates are generally derived from:
  • 14. a. Bottom-up estimates b. Top-down estimates c. Expert judgment cost estimates d. Order of magnitude estimates Question 14 1 points Save The resource planning tool that enables us to identify who we need to carry out what tasks is called:
  • 15. a. A resource Gantt chart b. A resource matrix (also called the responsibility chart) c. A resource ogive d. A resource loading chart (also called a resource histogram) Question 15 1 points Save Which of the following shows resource allocation over time? a. Resource Gantt chart b. Resource matrix
  • 16. c. S-Curve d. Resource leveling Question 16 1 points Save What is the function of a change control board (CCB) in configuration management? a. To assess the management impacts of change requests b. To initiate changes needed on the project c. To focus on the technical implication of change requests d. To approve change requests coming from senior management
  • 17. Question 17 1 points Save Good functional requirements a. Describe how the deliverable should be developed b. Provide detailed technical insights into what the deliverable will do c. Describe what the deliverable looks like and what it should do d. Are created after development of the technical specifications
  • 18. Question 18 1 points Save The type of management whose focus is on activities whose variances lie outside the acceptable range is: a. Management by Objectives b. Management by Exception c. Management by Walking Around d. Management by Control Limits Question 19 1 points Save Which of the following is a characteristic of an effective reporting system?
  • 19. a. SMART b. KISS c. MBO d. LOWBALLING Question 20 1 points Save Which of the following is an elapsed time task?
  • 20. a. Paint is drying b. A painter paints the wall c. Software is being written d. A sandwich is being made Question 21 1 points Save An autocratic management style: a. Is effective in most project management situations b. Is effective in highly routine efforts
  • 21. c. Is effective in high flux, state-of-the-art projects d. Will lead to the tyranny of the majority Question 22 1 points Save A project team structure that closely reflects the physical structure of the deliverable is known as: a. Egoless b. Specialty c. Surgical d. Isomorphic
  • 22. Question 23 1 points Save The purpose of mid-project evaluation is: a. Continual monitoring of budget and estimates b. To focus on achievement of individual element of the project plan c. To determine whether the original objectives are still relevant d. To re-baseline the project budget Question 24 1 points
  • 23. Save If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have? a. 0.5 hours b. 1.5 hours c. 2.5 hours d. 8.5 hours Question 25 1 points Save In risk management, insurance is an example of:
  • 24. a. Risk avoidance b. Risk deflection c. Risk acceptance d. Contingency planning Question 26 1 points Save A four step risk assessment process reflecting standard risk management good practice consists of:
  • 25. a. Risk identification, Risk deflection, Risk impact analysis, Risk monitoring and control b. Risk acceptance, Risk impact analysis, Risk response planning, Risk monitoring and control c. Risk deflection, Contingency planning, Risk impact analysis, Risk monitoring and control d. Risk identification, Risk impact analysis, Risk response planning, Risk monitoring and control Question 27 1 points Save Structured Walk-Through is a methodology used in: a. PERT
  • 26. b. GERT c. VERT d. Project Evaluation Question 28 1 points Save If review of a project's status indicates that EV = $400, AC = $400, and PV = $500, the project is: a. On budget, behind schedule b. On budget, ahead of schedule c. Over budget, behind schedule
  • 27. d. Over budget, ahead of schedule Question 29 1 points Save The poor man's hierarchy is a method for: a. Project estimation b. Project scheduling c. WBS construction d. Project selection
  • 28. Question 30 1 points Save According to PMI, a WBS should focus on a. Tasks b. Deliverables c. Interrelationships among activities d. Cost of the project Question 31 1 points Save If EV = $300, AC = $400, and the project budget is $1,000, what is the estimated final cost of the project (this is known as EAC, estimate at complete)?
  • 29. a. $750 b. $1,000 c. $1,250 d. $1,333 Question 32 1 points Save Which of the following is a scope planning tool?
  • 30. a. Benefit/cost analysis b. WBS c. Earned Value analysis d. Fast tracking Question 33 1 points Save In resource planning, one of the issues that needs to be considered is: a. Staff empowerment b. Technical requirements of the project
  • 31. c. Theory X management principles d. Theory Y management principles Question 34 1 points Save The bottom-most level of the WBS -- the level at which project budget and schedule data are captured -- is called: a. Work package b. Code of accounts c. Budget baseline d. Change control level
  • 32. Question 35 1 points Save Scope creep means: a. Needs emergence and identification b. Uncontrolled changes to a project's requirements during project execution c. Migration of project needs to requirements d. Imprecise scope statement Question 36
  • 33. 1 points Save Configuration management is a: a. Methodology for working closely with customers by developing and updating requirements for faster response to changing customer needs b. Methodology for ensuring that requirements evolve with evolving customer requirements c. Methodology for specifying requirements at the outset and for controlling very tightly any changes to them d. Methodology for specifying requirements at the outset and for facilitating any changes to them with minimum customer input Question 37 1 points
  • 34. Save Rapid prototyping is a methodology for: a. Specifying requirements at the outset and for controlling very tightly any changes to them b. Specifying requirements at the outset and for facilitating later changes to them with minimum customer in put c. Triggering early warning of unauthorized changes to the original prototype to enable project management to take remedial actions d. Working closely with customers by creating and updating prototypes that respond to customer input Question 38 1 points Save
  • 35. Ensuring a one-to-one correspondence between specification items and general design items is a feature of: a. Scope statement definition b. WBS construction c. Rapid prototyping d. Configuration management Question 39 1 points Save Under what conditions may a project manager accept a change request?
  • 36. a. If the request has no effect on project objectives, deadlines, or resources b. If the request has no effect on project objectives, although it has effects on deadlines and resources c. If the request is coming from a valued customer d. If the request is from the Chief Executive Officer Question 40 1 points Save Which of the following is not an activity carried out during project closeout?
  • 37. a. Reassignment of project staff b. Preparation of the project's baseline c. Reassignment of material resources d. Preparation of user manuals Question 41 1 points Save When crashing a project, we typically choose critical path tasks whose costs of crashing are highest. True False
  • 38. Question 42 1 points Save The astute project manager typically uses only one management style in order not to confuse his/her teammates. True False Question 43 1 points Save Concurrent engineering involves overlapping tasks and phases to accelerate a project's schedule.
  • 39. True False Question 44 1 points Save A work package is to be found at the summary level of the WBS. True False Question 45 1 points Save
  • 40. Milestones, like tasks, consume resources. True False Question 46 1 points Save In project management, the level of uncertainty plays a major role in determining the adequacy of a project plan. True False
  • 41. Question 47 1 points Save Using working time or elapsed time to calculate the time it will take to complete a task produces the same results. True False Question 48 1 points Save Needs recognition is the first stage of the needs-requirement life cycle.
  • 42. True False Question 49 1 points Save Functional requirements provide us with detailed technical specifications. True False Question 50 1 points Save
  • 43. A key objective of change control in configuration management is to keep track of actions taken in response to change requests. True False Question 51 1 points Save Under rapid prototyping (also called application prototyping), the customer actually sees and works with the deliverable as it evolves. True False
  • 44. Question 52 1 points Save There is a definite link between the level of risk an enterprise encounters and project time frame. True False Question 53 1 points Save When we have objective data on the probability of an event, we are involved with decision making under certainty.
  • 45. True False Question 54 1 points Save The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed. True False
  • 46. Question 55 1 points Save A laissez-faire management style may lead to a ship without rudder syndrome. True False Question 56 1 points Save An objective of prototyping is to minimize life-cycle cost. True
  • 47. False Question 57 1 points Save A modern view in Human Resource Management is that positive motivation results from an opportunity to achieve and experience self-actualization. True False Question 58 1 points Save Confidence in the accuracy of a cost estimate increases when top-down and bottom-up estimates converge.
  • 48. True False Question 59 1 points Save Internal Rate of Return (IRR) is the discount rate that sets the present value of cash outflow equal to the present value of cash inflow. True False
  • 49. Question 60 1 points Save A project can be terminated prematurely because the original objectives may no longer be valid. True False Bottom of Form _75_1 _46825_1 null _11393_1 qHide