Mike Skaggs, Senior Vice President of Watts Bar Operations & Construction, discussed the completion of Watts Bar Unit 2 nuclear power plant. He summarized that the original project was delayed and over budget due to issues with leadership, cost estimating, project execution, and oversight. A revised estimate and schedule were developed based on lessons learned. Key priorities for completion included establishing experienced leadership, understanding the full scope of work, developing independent cost and schedule monitoring tools, and providing oversight of critical metrics. The project is now on track to be the first new nuclear plant of the 21st century in the United States.
2. Serving the 9 million people of
the Tennessee Valley region
through
– Energy that is safe, clean,
reliable
– Environmental stewardship of
natural resources
– Economic development that
brings good jobs to the region
and keeps them here
3.
4.
5. Fiscal Year 2014 Fuel Costs
0
6
31
43
58
68
0
10
20
30
40
50
60
70
80
Hydro Nuclear Coal Gas Purchased
Power
Off System
Wind
Purchases
$/MWh
Fuel Source
6.
7. Determined project would not meet in-service date of
October 2012 or budgeted cost estimate
Causes of schedule delays and cost overruns
‒ Leadership
‒ Estimate
‒ Execution
‒ Oversight
Revised estimate and schedule developed based on detailed
analysis and lessons learned
8. Establish a staffing strategy that employs a highly
experienced core leadership team with capabilities
aligned with unique project characteristics
Put right people in right jobs
Use appropriate staffing approach
Engage the workforce
9. Understand work to be done
Develop estimate based on detailed
analysis and lessons learned
Incorporate an independent
assessment of external
project risks into estimate
Ensure buy-in of cost and
schedule
10. Develop clear execution strategy at the start
Establish and use independent, integrated schedule and cost
monitoring tools
Establish a process to effectively control scope changes
Measure what needs to be achieved
11. Provide for independent verification of performance data
Implement cross-functional oversight to track critical key
performance indicators and risks
Assure active risk management processes are in place and
continually assess risk exposure and mitigation effectiveness
12. Safe and high quality
Design basis fidelity with Watts Bar
Unit 1 – the unit currently in operation
15. Over 30 million work-hours
without a lost-time incident
Greater than 97% Quality Control
Acceptance Rate
Meeting cost and schedule
expectations
16.
17. Open vessel testing successfully
completed
Cold and steam generator
hydrostatic testing successfully
completed
Hot functional
testing and
fuel load
preparations
in progress
18. Pilot for industry
Designs for modifications complete
New Flexible Equipment Storage
Building constructed
New water storage tank built
Required equipment onsite
19.
20. Protect safe, reliable operation
of Watts Bar Unit 1
Upcoming testing milestones
Emergent work during testing
Dual-unit operational readiness
Regulatory issues
21. Staffing and training
Demobilization plan
Outreach initiatives
22. Safety, quality, cost, and schedule targets
being met
Completing and readying systems, preparing
for dual-unit operations
Complex work and challenges remain
On track to be nation’s first new nuclear
generation of 21st century
Moving forward with diligence and using
lessons learned
Responsibility to complete the project
the right way – safely and with quality
Editor's Notes
TVA one of most reliable power providers 99.999% reliability for 14 years in a row
Reliability results from diverse generating resources . . . Diversity gives us flexibility to use assets that are most economical at the time . . . Helps us hold down costs
Currently 6 operating nuclear units in TVA’s generation fleet . . . Provide 1/3 of electricity TVA delivers. . . Lowest cost power we have except for hydro
Watts Bar Unit 2 will be TVA’s 7th unit and nation’s first new nuclear generation in 21st century . . . Watts Bar Unit 1 was nation’s last unit to come online in 20th century
A favorable addition to TVA’s generation fleet
Help control overall fuel costs, increase portfolio diversity, deliver safe, clean, and carbon-free energy