SlideShare a Scribd company logo
1 of 42
TURKEY 
ANATOLIA WATERSHED 
REHABILITATION 
PROJECT 
Sedat Kadioglu 
Ministry of Environment 
Abdulmecit Yesil 
Ministry of Agriculture and 
Rural Affairs
• PROJECT TITLE : 
Anatolia Watershed 
Rehabilitation Project 
• PROJECT BENEFICIARIES 
: 
• MMiinniissttrryy ooff EEnnvviirroonnmmeenntt ,, 
MMiinniissttrryy ooff FFoorreessttrryy,, MMiinniissttrryy 
ooff AAggrriiccuullttuurree aanndd RRuurraall 
AAffffaaiirrss aanndd GGeenneerraall DDiirreeccttrraattee 
ooff RRuurraall SSeerrvviicceess 
• PROJECT DURATION : 7 
Years 
• ( starting in 2003)
• THE PROJECT BUDGET 
The total cost of the project is 
around 50.000.000 US Dollars. 
6.000.000 US Dollars of this 
amount is provided by the GEF 
and the major portion is provided 
by the World Bank. The fund to be 
used for the rehabilitation works is 
a loan and the fund to be used for 
the pollution reduction works is a 
donation.
PROJECT AREA 
• The project will be carried out at 
totally 5 basins and 13 provinces. 
( Seyhan, Ceyhan, Göksu, Kızılırmak, 
and Yeşilırmak). Only rehabilitation 
works will be performed at Seyhan, 
Ceyhan and Göksu Basins while both 
rehabilitation and the GEF related 
pollution decrease works will be 
performed at Kızılırmak and Yeşilırmak 
Basins. 
4 provinces have been selected for the 
GEF. The provinces of Amasya , Çorum 
and Tokat are at Yeşilırmak Basin and 
Samsun is at Kızılırmak Basin.
River basins in Turkey
Rehabilitation works are being 
executed by the Ministry of Forestry, 
Ministry of Agriculture and Rural 
Affairs (TUGEM) and General 
Directorate Of Rural Services. 
Financing of the works regarding this 
step of the project will be covered by 
the World Bank loan. 
Reduction works of the pollution 
arising from agriculture in the Black 
Sea will be performed by the donation 
to be granted by the GEF.
JUSTIFICATION OF THE 
PROJECT 
The total area of the 13 provinces is 
about 19 million ha (24% of the 
country total). It is estimated that in 
these provinces, 70 MCs will cover an 
area of about 650,000 ha out of which 
250,000 ha will be the physical 
implementation area. Erosion (both 
sheet and gully) in forest, range and 
agricultural land, land degradation 
and soil and water pollution are 
important problems in the project 
area
A baseline survey conducted in early 
2002 in these watersheds indicated that 
34% of the livestock producers leave the 
wastes on open fields as manure, 22% 
dump the wastes into the streams, and 
11% leave it outside of the house. In 
77% of the households, the distance 
between the dwellings and the dump 
area varies between 2-100 meters. Some 
34% of the households have their water 
resources located at a distance of 0-10 
meters to livestock shelter.
The majority of the large livestock 
owners are not using the wastes as 
manure, but they are giving it free, in 
case of demand. Therefore, these wastes 
are mostly dumped in open areas, 
streams, and fields without any 
treatment. 
About half of the respondents have 
feverish diseases which is followed by 
goiter and diarrhea. On the other hand, 
waste water from agro-processing 
plants, i.e. sugar factory, paper mills, are 
discharged into streams without any 
treatment. Some factories have some 
primitive treatment facilities but either 
these are not operated, or if operated are 
not efficiently done so.
Additionally, Agricultural pollution is a 
serious problem. Concentrated poultry 
production in Çorum and beef fattening 
and dairy production in Amasya, Tokat 
and Bafra together with over-use of 
inorganic fertilizers are polluting the 
surface and ground waters, causing 
disease problems, unbearable odor, and 
visual pollution. Wells in the residential 
areas are susceptible to seepages 
threatening the public health. Untreated 
waste water from agro-processing plants 
is discharged into the streams, ultimately 
entering the Black Sea. Proper fertilizer 
use is another issue. Some efforts have 
been made to introduce soil analysis for 
better fertilizer application, but the 
impact is limited.
The Black Sea Transboundary 
Diagnostic Analysis identified 
nutrient pollution as the most serious 
problem that has lead to the 
ecological breakdown experienced in 
the Black Sea over the past few 
decades. The GEF Strategic 
Partnership was established in 2001 
in order to encourage public and 
private sector investments in nutrient 
reduction, notably industrial and 
urban wastewater treatment, 
agricultural nutrient pollution 
control and wetland restoration in the 
Black Sea and Danube Basin.
PROJECT OBJECTIVE 
• The overall objective of the 
project is to reduce the 
discharges of nutrients (nitrogen 
and phosphorus), and other 
agricultural pollution into the 
Yeşilırmak and Kızılırmak 
Rivers. The project will be 
implemented in the micro 
catchments that are in the 
provinces of Amasya , Çorum, 
Tokat and Samsun
PROJECT GLOBAL 
ENVIRONMENTAL 
OBJECTIVES 
• The project will fully integrate 
environmental concerns into agricultural 
practices to make them more sustainable, 
including the storage, management and 
application of manure and ensure 
ecologically sustainable use of natural 
resources to reduce the discharge of the 
nutrient load into the Turkish ground and 
surface waters as well as into the Black Sea. 
• The project will also promote appropriate 
policies and policy reforms in order to 
create an enabling environment for 
realizing the project objectives. It will 
develop capacity of private small holders 
and commercial farmers to use 
environment- friendly agricultural 
practices and resource management.
NUTRIENT MANAGEMENT 
In order to meet food production for 
increasing population requirements, 
increasing agricultural export, and to 
meet raw materials requirements for 
industry, agricultural production should 
be increased. But while aiming to 
increase agricultural production, 
natural sources such as soil and water 
which are main inputs of agriculture, 
should be protected.
Because of the different altitudes of our 
country, there are different climatic 
conditions. As the great mountain ranges 
are placed on the Black Sea and 
Mediterranean coasts, most of the rest of 
the country has a semi-dry climate with 
low precipitation. In almost all of the 
country there is drought and need to the 
water in summer times. Topography and 
climate specifications caused the use of 
different nutrients as fertilizers. One of 
the most important inputs for increasing 
agricultural production is nutrients as 
chemical and organic fertilizers.
In order to benefit from utilization of 
fertilizers at the utmost level, they have to 
be applied at the most suitable times and 
appropriately to the land. For this 
purpose, soil analysis will show us which 
nutrients have to be applied to the land 
for productivity. 
The objective of the GEF Project, that is 
still at the preparation stage and will 
begin in the year 2003, is the reduction 
of nutrients into Black Sea. In the 
determined micro-catchments and 
selected provinces, vegetal and livestock 
activities are very intensive.
• Solid and liquid wastes coming from 
beef, dairy and poultry production 
enterprises are polluting the ground 
and surface waters, and these 
circumstances are threatening human 
and environmental health and also 
causing pollution in the Black Sea. 
• This project’s objective is also the 
reduction of pollution by using 
chemical fertilizers based on soil 
testing
Vegetable production will be 
naturalized by using manures for 
vegetable production and demand for 
chemical fertilizers will be reduced. 
Within that scope, measures will be 
taken for the liquid and solid waste 
contaminants to the surface and ground 
waters in the determined micro-catchments 
and they will be collected. 
Manures will be used in vegetable 
production lands and range lands as 
organic fertilizers.
With that purpose, establishing a system 
for creating supply – demand balance 
between vegetable producers and 
livestock producers, causing farmers to 
try to use fertilizers consciously based on 
good agricultural practices and soil 
analysis by leading farmers, training of 
farmers by local agricultural agencies, 
awareness of the local population, and 
monitoring of the surface and ground 
waters for observing the results of these 
activities, and replication of these 
activities at national at regional levels 
is the objective.
• Nutrient reduction: 
The Project will reduce, over the long-term, 
the discharge of nutrients 
(nitrogen and phosphorus) and other 
agricultural pollutants into the surface 
and ground waters of Turkey and the 
Black Sea through integrated land and 
water management and promote 
ecologically sustainable use of natural 
resources.
This component is being 
prepared under the umbrella of 
the Black Sea/Danube Strategic 
Partnership-Nutrient Reduction 
Investment Fund under which 
riparian countries would be 
eligible for Global Environment 
Facility (GEF) funding for 
projects that would control or 
mitigate nutrient inflow to the 
Black Sea. The Project activities 
are directly linked to "Strategic 
Action Plan for the Protection 
and Rehabilitation of the Black 
Sea" (BSSAP), formulated with 
the assistance of the GEF.
• Within the framework of the 
project, the following steps will 
be taken : 
a) strengthening national policy 
and local regulatory capacity to 
meet European Union (EU) 
standards for agricultural 
nutrient pollution control, 
b) increasing the use of 
environmentally friendly 
agricultural practices and 
thereby reducing nutrient 
discharge particularly from 
agricultural sources to the Black 
Sea, 
c) capacity building and promoting a 
broad public awareness program 
and replication strategy.
Global Operational Strategy/Program 
objective addressed by the Project 
: 
The Project will implement priority 
actions identified in the Black Sea 
Strategic Action Plan. The Project will 
provide an opportunity for the GEF to 
be a catalyst for the actions to bring 
about the successful integration of 
improved land and water resource 
management practices. The GEF 
support will reduce costs and barriers to 
farmers, adopting improved and 
sustainable agricultural practices. It will 
help develop mechanisms to move from 
demonstration level activities to 
operational projects that reduce non-point 
source agricultural pollution to Black Sea.
THE MAIN COMPONENTS OF THE 
PROJECT : 
1) Manure management system and 
pollution from Agro-Industry 
2 ) Water and Soil Quality Monitoring 
Program 
3) National Level Strenthening Policy 
&Regulatory Capacity Building 
4) Public Awareness
Manure Management 
• The project will initially fund pilot 
actions to test the options for 
improving the storage and handling 
of livestock waste. Following a 
review of the different livestock 
husbandry practices in the project 
provinces, three types of enterprises 
were selected for the pilot activities: 
i) commercial beef and dairy farms 
in peri-urban areas that are 
frequently discharging solid and 
liquid wastes directly into the water 
body; ii) small livestock farms in 
the MC areas; and iii) poultry units 
(each with about 45,000 birds) in the 
Corum area where there is a high 
concentration of poultry production.
• In the case of the peri-urban cattle 
farmers and the small livestock farms 
in the MCs, the project will provide 
funds for construction of on-farm and 
central storage as well as equipment 
for waste collection and application to 
agricultural land. The arrangements 
for the organization and management 
of the investment and implementation 
phases, as well as the participation of 
the local administrations and 
beneficiaries, still have to be worked 
out in the course of further project 
preparation. With regard to the 
poultry units, primarily technical 
assistance will be provided for 
enforcing compliance with existing 
legislation and to develop a more 
efficient system for handling the 
collection and utilization of poultry 
manure.
• MARA’s and MOE’s staff, visited 
the sites selected for manure 
management pilot activities at: (a) 
Turhal - beef feed-lots on the Dazya 
Stream that drains into the 
Yesilirmak, Tokat Province; (b) 
Suluova - beef feed lots on the 
Tersakan Stream, draining into the 
Yesilirmak, Amasya Province; and 
(c) Bafra - small farmer milk and 
beef production in Ilyasu MC on the 
Ilyasu Stream draining into the 
Kizilirmak, Samsun Province (d) 
Chicken units lots on the Derinçay 
Stream draining into the Yeşilırmak , 
Çorum Province.
While the Turhal and Bafra sites 
were found to justify further 
investigation, the Suluova area was 
subject to serious pollution from 
household wastes, as well as from 
agro-industry and it would be 
difficult to measure the impact of 
project actions on nutrient discharge. 
Therefore Suluova was excluded 
from the project. Instead of Suluova, 
a new area will be determined.
Three pilot manure management facilities 
will be implemented in the first eighteen 
months of the project. At the same time 
the public awareness activities will be 
launched to sensitize the rural population 
to need to improve the handling of 
livestock waste. Following the evaluation 
of the impact of the pilot facilities against 
environmental, economic and social 
criteria, the project actions will be 
extended to other sites in the project years 
3 - 6. The Regional Environmental 
Assessment will be done for the liquid and 
solid manure storage structures.
Use of the field demonstration program 
will be realized in order to show the 
importance of organic manures and to 
improve good relations between the 
livestock producers who are without 
land for cultivation, and the arable 
farmers, horticulturists, orchard owners 
and rangeland users who are the 
potential market for organic manure
Fertilizer Use in the Project 
Provinces 
Although some efforts have been made 
to introduce soil analysis for better 
fertilizer application, the impact is 
limited. The “annual provincial 
extension programs” include nutrient 
management but due to problems 
regarding resource allocation, the 
effectiveness of these efforts are 
questionable. Therefore, inorganic 
fertilizer application is another source 
of non-point pollution in Kizilirmak and 
Yesilirmak watersheds. A baseline 
survey conducted in early 2002 in these 
watersheds indicated that only 15% of 
the farmers follows the advice given by 
the extension staff, traditional practices 
and “learning from the neighbor” is still 
dominant.
Around 17 % of the farmers who 
produce cash crops and own medium 
sized land made their soils analyzed. 
There is no such practice among small 
farmers producing cereals. The data 
indicated that about 33% of the farmers 
who had their soils analyzed were 
applying high amounts and in turn 
reduced the fertilizer rates. Introduction 
of improved storage and application of 
livestock wastes together with nutrient 
management programs should have a 
significant impact on reducing nutrient 
discharge into the water body.
Soil and water quality monitoring: 
The project will provide for the 
incremental equipment, staff 
training and operating costs for 
monitoring the impact of 
environment-friendly practices on 
the discharge of nutrients (N & P) 
into the water body. Measurements 
of BOD and suspended solids will 
also be made. MARA will be 
responsible for monitoring at the 
level of the MC, while MOE will be 
responsible for monitoring water 
quality upstream and downstream in 
the main river. The central MOE 
laboratory in Ankara will be used to 
calibrate samples taken by MARA.
In the micro catchments soil and water 
quality monitoring points have been 
selected, sampling procedures have 
been prepared, organizational 
arrangements with responsibilities of 
MOE and MARA have been agreed 
upon and investment and operational 
costs have been prepared.
National Level Strenthening of Policy 
&Regulatory Capacity: 
• Ministry of Environment (MOE) and 
Ministry of Agriculture and Rural 
Services (MARA) prepared their 
initial review of the status of 
environmental legislation covering, 
the Nitrate Directive legislation and 
certification standards for organic 
farming. The GEF funding could 
support work on application of the 
Nitrates Directive, the development 
of a Code of Good Agricultural 
Practices and measures required to 
promote the development of Organic 
Farming. With regard to Integrated 
Pest Management, this would be 
covered by the World Bank funding.
Within the framework of the project, 
the Turkish Nitrate Directive which is 
the equivalent of the EU Nitrate 
Directive (91/676/EEC) will be 
constituted. The Nitrates Directive 
adoption studies have been carried out 
by MOE and MARA. It is aimed that 
these studies will be completed by the 
end of 2002.
Public Awareness and Replication 
Strategy 
The program related to Public 
Awareness has been prepared by 
the authorities of MOE , MARA 
and the World Bank. Public 
awareness, capacity building and 
replication strategy activities will 
be conducted in all provinces 
covered by the project. Public 
awareness program will be applied 
at the local, national and 
international levels.
At the local level (Amasya, 
Çorum,Tokat and Samsun ), the 
following works will be carried out: 
(a) Villages will be visited in selected 
micro-catchments to find out about the 
level of public awareness, the interest 
and need for better knowledge of 
environmental matters and the issues it 
deals with. 
(b) Appropriate structures and 
instruments will be designed for the 
campaign ( Radio, TV, Publications) 
and the cost for each instrument will be 
determined. 
(c) The scope and specific objectives for 
each step will be defined in the 
campaign. 
(d) Proposals will be presented to local 
communities to test their receptivity to 
the approach and the instrument 
proposed .
e) Environment-friendly agricultural 
and manure management practices will 
be adopted. 
(f) Environmental awareness will be 
increased through enhanced school 
and NGO’s participation. 
(g) The problems caused by pollution 
and waste disposal will be explained.
At the national level the following 
works will be carried out: 
(a) The experiences gained at the local level 
will be reflected on the national level. 
(b) A broad nationwide public information 
campaign will be undertaken to 
disseminate the benefits of proposed 
project activities. 
(c) Efforts will be concentrated on 
institutions and groups that may 
influence the replication of the project in 
other areas. 
(d) A national media campaign will be 
launched to introduce the project to the 
people better . 
(e) The problems caused by pollution and 
waste disposal will be explained .
At the international level the following 
works will be carried out : 
• The project will provide for the 
organization of regional 
workshops, field trips, training, 
publication in international 
agriculture and environment 
journals and other activities to 
promote replication of project 
activities in other Black Sea 
riparian countries. The pilot 
activity will aim to serve as a 
model to be replicated in these 
countries which will help 
contribute to significant 
reductions in the nutrient loads 
entering the Black Sea.
ORGANIZATIONAL ISSUES FOR 
AGENCIES 
At the central level, there are three 
units i) Project Management Group 
(PMG), ii) Central Coordination Unit 
(CCU), and iii) Project Management 
Units (PMUs). At the field level 
(provincial) there are two units i) 
Local Project Management Teams 
(LPMT) ii) Micro Catchment 
Implemantation Teams (MCIT)

More Related Content

What's hot

Soil Carbon & its Sequestration for Better Soil Health
Soil Carbon & its Sequestration for Better Soil HealthSoil Carbon & its Sequestration for Better Soil Health
Soil Carbon & its Sequestration for Better Soil HealthBiswajitPramanick4
 
Agricultural drainage from waterlogged soils and indian experiences
Agricultural drainage from waterlogged soils and indian experiencesAgricultural drainage from waterlogged soils and indian experiences
Agricultural drainage from waterlogged soils and indian experiencesSuyog Khose
 
Evolution of watershed management in nepal
Evolution of watershed management in nepalEvolution of watershed management in nepal
Evolution of watershed management in nepalManoj Neupane
 
Soil fertility management in bangladesh
Soil fertility management in bangladeshSoil fertility management in bangladesh
Soil fertility management in bangladeshDr. Md. Altaf Hossain
 
Sustainable Management and Carbon Sequestration in Soils of Africa
Sustainable Management and Carbon Sequestration in Soils of AfricaSustainable Management and Carbon Sequestration in Soils of Africa
Sustainable Management and Carbon Sequestration in Soils of AfricaICARDA
 
International Network on Salt-Affected Soils (INSAS) and salinity mapping
International Network on Salt-Affected Soils (INSAS) and salinity mappingInternational Network on Salt-Affected Soils (INSAS) and salinity mapping
International Network on Salt-Affected Soils (INSAS) and salinity mappingWASAG
 
Cn 2 th14_inida_assessment of land degradation_baptista
Cn 2 th14_inida_assessment of land degradation_baptistaCn 2 th14_inida_assessment of land degradation_baptista
Cn 2 th14_inida_assessment of land degradation_baptistaErik van den Elsen
 
Global climate change phenomena, impacts and adaptations
Global climate  change phenomena, impacts and adaptationsGlobal climate  change phenomena, impacts and adaptations
Global climate change phenomena, impacts and adaptationsDevegowda S R
 
Climate Smart Agriculture and Soil-Carbon Sequestration
Climate Smart Agriculture and Soil-Carbon SequestrationClimate Smart Agriculture and Soil-Carbon Sequestration
Climate Smart Agriculture and Soil-Carbon SequestrationSIANI
 
Economic Valuation of water resources
Economic Valuation of water resources Economic Valuation of water resources
Economic Valuation of water resources virgo_az
 
Shankaraiah N :Watershed Program Present
Shankaraiah N :Watershed Program  PresentShankaraiah N :Watershed Program  Present
Shankaraiah N :Watershed Program Presentshankaraiah, N
 
Global Soil Partnership
Global Soil PartnershipGlobal Soil Partnership
Global Soil PartnershipFAO
 
NAP Expo 2015 Session III, II Ecosystem based adaptation Namibia
NAP Expo 2015 Session III, II Ecosystem based adaptation NamibiaNAP Expo 2015 Session III, II Ecosystem based adaptation Namibia
NAP Expo 2015 Session III, II Ecosystem based adaptation NamibiaNAP Events
 
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...Credit seSoil Health Management Through Carbon Sequestration Under Changing C...
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...munishsharma0255
 

What's hot (20)

Soil Carbon & its Sequestration for Better Soil Health
Soil Carbon & its Sequestration for Better Soil HealthSoil Carbon & its Sequestration for Better Soil Health
Soil Carbon & its Sequestration for Better Soil Health
 
Agricultural drainage from waterlogged soils and indian experiences
Agricultural drainage from waterlogged soils and indian experiencesAgricultural drainage from waterlogged soils and indian experiences
Agricultural drainage from waterlogged soils and indian experiences
 
Evolution of watershed management in nepal
Evolution of watershed management in nepalEvolution of watershed management in nepal
Evolution of watershed management in nepal
 
Soil fertility management in bangladesh
Soil fertility management in bangladeshSoil fertility management in bangladesh
Soil fertility management in bangladesh
 
Sustainable Management and Carbon Sequestration in Soils of Africa
Sustainable Management and Carbon Sequestration in Soils of AfricaSustainable Management and Carbon Sequestration in Soils of Africa
Sustainable Management and Carbon Sequestration in Soils of Africa
 
Files15 file2289
Files15 file2289Files15 file2289
Files15 file2289
 
Aesr 9.2
Aesr 9.2Aesr 9.2
Aesr 9.2
 
International Network on Salt-Affected Soils (INSAS) and salinity mapping
International Network on Salt-Affected Soils (INSAS) and salinity mappingInternational Network on Salt-Affected Soils (INSAS) and salinity mapping
International Network on Salt-Affected Soils (INSAS) and salinity mapping
 
Cn 2 th14_inida_assessment of land degradation_baptista
Cn 2 th14_inida_assessment of land degradation_baptistaCn 2 th14_inida_assessment of land degradation_baptista
Cn 2 th14_inida_assessment of land degradation_baptista
 
Global climate change phenomena, impacts and adaptations
Global climate  change phenomena, impacts and adaptationsGlobal climate  change phenomena, impacts and adaptations
Global climate change phenomena, impacts and adaptations
 
Climate Smart Agriculture and Soil-Carbon Sequestration
Climate Smart Agriculture and Soil-Carbon SequestrationClimate Smart Agriculture and Soil-Carbon Sequestration
Climate Smart Agriculture and Soil-Carbon Sequestration
 
Experiences of MERET Project of Ministry of Agriculture in integrated watersh...
Experiences of MERET Project of Ministry of Agriculture in integrated watersh...Experiences of MERET Project of Ministry of Agriculture in integrated watersh...
Experiences of MERET Project of Ministry of Agriculture in integrated watersh...
 
Birch Bay Watershed Characterization
Birch Bay Watershed CharacterizationBirch Bay Watershed Characterization
Birch Bay Watershed Characterization
 
Southeast Asia Conference 08
Southeast Asia Conference 08Southeast Asia Conference 08
Southeast Asia Conference 08
 
The Watershed Approach by Matthew Lacroix
The Watershed Approach by Matthew Lacroix The Watershed Approach by Matthew Lacroix
The Watershed Approach by Matthew Lacroix
 
Economic Valuation of water resources
Economic Valuation of water resources Economic Valuation of water resources
Economic Valuation of water resources
 
Shankaraiah N :Watershed Program Present
Shankaraiah N :Watershed Program  PresentShankaraiah N :Watershed Program  Present
Shankaraiah N :Watershed Program Present
 
Global Soil Partnership
Global Soil PartnershipGlobal Soil Partnership
Global Soil Partnership
 
NAP Expo 2015 Session III, II Ecosystem based adaptation Namibia
NAP Expo 2015 Session III, II Ecosystem based adaptation NamibiaNAP Expo 2015 Session III, II Ecosystem based adaptation Namibia
NAP Expo 2015 Session III, II Ecosystem based adaptation Namibia
 
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...Credit seSoil Health Management Through Carbon Sequestration Under Changing C...
Credit seSoil Health Management Through Carbon Sequestration Under Changing C...
 

Similar to Anatolia Watershed Rehabilitation Project Reduces Nutrient Pollution

REGIONAL SLURRY TECHNICAL TEAM REPORT.pdf
REGIONAL SLURRY TECHNICAL TEAM REPORT.pdfREGIONAL SLURRY TECHNICAL TEAM REPORT.pdf
REGIONAL SLURRY TECHNICAL TEAM REPORT.pdfGalfato Gabiso
 
Project Presentation in 2006
Project Presentation in 2006Project Presentation in 2006
Project Presentation in 2006Iwl Pcu
 
The Condition o the Philippine Environment and Natural Resources. Environment...
The Condition o the Philippine Environment and Natural Resources. Environment...The Condition o the Philippine Environment and Natural Resources. Environment...
The Condition o the Philippine Environment and Natural Resources. Environment...Rexther Solis
 
World Bank Experiences with Agricultural Non Point Source Pollution Control P...
World Bank Experiences with Agricultural Non Point Source Pollution Control P...World Bank Experiences with Agricultural Non Point Source Pollution Control P...
World Bank Experiences with Agricultural Non Point Source Pollution Control P...Iwl Pcu
 
T2 shaden abdel gawad cs operational drainage water reuse guidelines exec su...
T2 shaden abdel gawad cs operational drainage water reuse guidelines  exec su...T2 shaden abdel gawad cs operational drainage water reuse guidelines  exec su...
T2 shaden abdel gawad cs operational drainage water reuse guidelines exec su...NENAwaterscarcity
 
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011India Water Portal
 
Operational Drainage Water Reuse Guidelines
Operational Drainage Water Reuse GuidelinesOperational Drainage Water Reuse Guidelines
Operational Drainage Water Reuse GuidelinesFAO
 
Black Sea and Danube Basin Projects Presentation
Black Sea and Danube Basin Projects PresentationBlack Sea and Danube Basin Projects Presentation
Black Sea and Danube Basin Projects PresentationIwl Pcu
 
Irrigation scheduling practice at Tana Bales Sugar project by Hunda Tolina
Irrigation scheduling practice  at Tana Bales Sugar project by Hunda TolinaIrrigation scheduling practice  at Tana Bales Sugar project by Hunda Tolina
Irrigation scheduling practice at Tana Bales Sugar project by Hunda TolinaTana Bales sugar Factory
 
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...Journal of Agriculture and Crops
 
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003IWRS Society
 
Conservation of water in agriculture and industrial sectors
Conservation of water in agriculture and industrial sectorsConservation of water in agriculture and industrial sectors
Conservation of water in agriculture and industrial sectorsIWRS Society
 
Georgia ARET Project: Environment Pollution Control Program
Georgia ARET Project: Environment Pollution Control ProgramGeorgia ARET Project: Environment Pollution Control Program
Georgia ARET Project: Environment Pollution Control ProgramIwl Pcu
 
Current Status of Soil Researches in Turkey - Bülent Sönmez
Current Status of Soil Researches in Turkey - Bülent Sönmez Current Status of Soil Researches in Turkey - Bülent Sönmez
Current Status of Soil Researches in Turkey - Bülent Sönmez FAO
 
Niger food security
Niger food securityNiger food security
Niger food securityPatrickTanz
 
Drought Management in Iran, Masoud Bagherzadeh Karimi
Drought Management in Iran, Masoud Bagherzadeh KarimiDrought Management in Iran, Masoud Bagherzadeh Karimi
Drought Management in Iran, Masoud Bagherzadeh KarimiNENAwaterscarcity
 
GEF Romania Agricultural Pollution Control Project
GEF Romania Agricultural Pollution Control ProjectGEF Romania Agricultural Pollution Control Project
GEF Romania Agricultural Pollution Control ProjectIwl Pcu
 
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...NAP Events
 

Similar to Anatolia Watershed Rehabilitation Project Reduces Nutrient Pollution (20)

REGIONAL SLURRY TECHNICAL TEAM REPORT.pdf
REGIONAL SLURRY TECHNICAL TEAM REPORT.pdfREGIONAL SLURRY TECHNICAL TEAM REPORT.pdf
REGIONAL SLURRY TECHNICAL TEAM REPORT.pdf
 
Project Presentation in 2006
Project Presentation in 2006Project Presentation in 2006
Project Presentation in 2006
 
The Condition o the Philippine Environment and Natural Resources. Environment...
The Condition o the Philippine Environment and Natural Resources. Environment...The Condition o the Philippine Environment and Natural Resources. Environment...
The Condition o the Philippine Environment and Natural Resources. Environment...
 
World Bank Experiences with Agricultural Non Point Source Pollution Control P...
World Bank Experiences with Agricultural Non Point Source Pollution Control P...World Bank Experiences with Agricultural Non Point Source Pollution Control P...
World Bank Experiences with Agricultural Non Point Source Pollution Control P...
 
T2 shaden abdel gawad cs operational drainage water reuse guidelines exec su...
T2 shaden abdel gawad cs operational drainage water reuse guidelines  exec su...T2 shaden abdel gawad cs operational drainage water reuse guidelines  exec su...
T2 shaden abdel gawad cs operational drainage water reuse guidelines exec su...
 
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011
Environmental and social impacts of water projects_Pradeep Kumar (NWA)_2011
 
Operational Drainage Water Reuse Guidelines
Operational Drainage Water Reuse GuidelinesOperational Drainage Water Reuse Guidelines
Operational Drainage Water Reuse Guidelines
 
IFPRI - NAES Conference on Sustainable & Resilient Agriculture - Zahurul Kari...
IFPRI - NAES Conference on Sustainable & Resilient Agriculture - Zahurul Kari...IFPRI - NAES Conference on Sustainable & Resilient Agriculture - Zahurul Kari...
IFPRI - NAES Conference on Sustainable & Resilient Agriculture - Zahurul Kari...
 
Black Sea and Danube Basin Projects Presentation
Black Sea and Danube Basin Projects PresentationBlack Sea and Danube Basin Projects Presentation
Black Sea and Danube Basin Projects Presentation
 
Irrigation scheduling practice at Tana Bales Sugar project by Hunda Tolina
Irrigation scheduling practice  at Tana Bales Sugar project by Hunda TolinaIrrigation scheduling practice  at Tana Bales Sugar project by Hunda Tolina
Irrigation scheduling practice at Tana Bales Sugar project by Hunda Tolina
 
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...
Pre-Extension Demonstration of Integration of Both Mechanical and Biological ...
 
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003
CONSERVATION OF WATER IN AGRICULTURE AND INDUSTRIAL SECTORS - 2003
 
Conservation of water in agriculture and industrial sectors
Conservation of water in agriculture and industrial sectorsConservation of water in agriculture and industrial sectors
Conservation of water in agriculture and industrial sectors
 
Georgia ARET Project: Environment Pollution Control Program
Georgia ARET Project: Environment Pollution Control ProgramGeorgia ARET Project: Environment Pollution Control Program
Georgia ARET Project: Environment Pollution Control Program
 
Current Status of Soil Researches in Turkey - Bülent Sönmez
Current Status of Soil Researches in Turkey - Bülent Sönmez Current Status of Soil Researches in Turkey - Bülent Sönmez
Current Status of Soil Researches in Turkey - Bülent Sönmez
 
Niger food security
Niger food securityNiger food security
Niger food security
 
Olaguer
OlaguerOlaguer
Olaguer
 
Drought Management in Iran, Masoud Bagherzadeh Karimi
Drought Management in Iran, Masoud Bagherzadeh KarimiDrought Management in Iran, Masoud Bagherzadeh Karimi
Drought Management in Iran, Masoud Bagherzadeh Karimi
 
GEF Romania Agricultural Pollution Control Project
GEF Romania Agricultural Pollution Control ProjectGEF Romania Agricultural Pollution Control Project
GEF Romania Agricultural Pollution Control Project
 
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...
Uganda Country Experience Ecosystem-based Approaches to Climate Change Adapta...
 

More from Iwl Pcu

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Iwl Pcu
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Iwl Pcu
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Iwl Pcu
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)Iwl Pcu
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designingIwl Pcu
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)Iwl Pcu
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs PublicationIwl Pcu
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Iwl Pcu
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 

More from Iwl Pcu (20)

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designing
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs Publication
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 

Anatolia Watershed Rehabilitation Project Reduces Nutrient Pollution

  • 1. TURKEY ANATOLIA WATERSHED REHABILITATION PROJECT Sedat Kadioglu Ministry of Environment Abdulmecit Yesil Ministry of Agriculture and Rural Affairs
  • 2. • PROJECT TITLE : Anatolia Watershed Rehabilitation Project • PROJECT BENEFICIARIES : • MMiinniissttrryy ooff EEnnvviirroonnmmeenntt ,, MMiinniissttrryy ooff FFoorreessttrryy,, MMiinniissttrryy ooff AAggrriiccuullttuurree aanndd RRuurraall AAffffaaiirrss aanndd GGeenneerraall DDiirreeccttrraattee ooff RRuurraall SSeerrvviicceess • PROJECT DURATION : 7 Years • ( starting in 2003)
  • 3. • THE PROJECT BUDGET The total cost of the project is around 50.000.000 US Dollars. 6.000.000 US Dollars of this amount is provided by the GEF and the major portion is provided by the World Bank. The fund to be used for the rehabilitation works is a loan and the fund to be used for the pollution reduction works is a donation.
  • 4. PROJECT AREA • The project will be carried out at totally 5 basins and 13 provinces. ( Seyhan, Ceyhan, Göksu, Kızılırmak, and Yeşilırmak). Only rehabilitation works will be performed at Seyhan, Ceyhan and Göksu Basins while both rehabilitation and the GEF related pollution decrease works will be performed at Kızılırmak and Yeşilırmak Basins. 4 provinces have been selected for the GEF. The provinces of Amasya , Çorum and Tokat are at Yeşilırmak Basin and Samsun is at Kızılırmak Basin.
  • 6. Rehabilitation works are being executed by the Ministry of Forestry, Ministry of Agriculture and Rural Affairs (TUGEM) and General Directorate Of Rural Services. Financing of the works regarding this step of the project will be covered by the World Bank loan. Reduction works of the pollution arising from agriculture in the Black Sea will be performed by the donation to be granted by the GEF.
  • 7. JUSTIFICATION OF THE PROJECT The total area of the 13 provinces is about 19 million ha (24% of the country total). It is estimated that in these provinces, 70 MCs will cover an area of about 650,000 ha out of which 250,000 ha will be the physical implementation area. Erosion (both sheet and gully) in forest, range and agricultural land, land degradation and soil and water pollution are important problems in the project area
  • 8. A baseline survey conducted in early 2002 in these watersheds indicated that 34% of the livestock producers leave the wastes on open fields as manure, 22% dump the wastes into the streams, and 11% leave it outside of the house. In 77% of the households, the distance between the dwellings and the dump area varies between 2-100 meters. Some 34% of the households have their water resources located at a distance of 0-10 meters to livestock shelter.
  • 9. The majority of the large livestock owners are not using the wastes as manure, but they are giving it free, in case of demand. Therefore, these wastes are mostly dumped in open areas, streams, and fields without any treatment. About half of the respondents have feverish diseases which is followed by goiter and diarrhea. On the other hand, waste water from agro-processing plants, i.e. sugar factory, paper mills, are discharged into streams without any treatment. Some factories have some primitive treatment facilities but either these are not operated, or if operated are not efficiently done so.
  • 10. Additionally, Agricultural pollution is a serious problem. Concentrated poultry production in Çorum and beef fattening and dairy production in Amasya, Tokat and Bafra together with over-use of inorganic fertilizers are polluting the surface and ground waters, causing disease problems, unbearable odor, and visual pollution. Wells in the residential areas are susceptible to seepages threatening the public health. Untreated waste water from agro-processing plants is discharged into the streams, ultimately entering the Black Sea. Proper fertilizer use is another issue. Some efforts have been made to introduce soil analysis for better fertilizer application, but the impact is limited.
  • 11. The Black Sea Transboundary Diagnostic Analysis identified nutrient pollution as the most serious problem that has lead to the ecological breakdown experienced in the Black Sea over the past few decades. The GEF Strategic Partnership was established in 2001 in order to encourage public and private sector investments in nutrient reduction, notably industrial and urban wastewater treatment, agricultural nutrient pollution control and wetland restoration in the Black Sea and Danube Basin.
  • 12. PROJECT OBJECTIVE • The overall objective of the project is to reduce the discharges of nutrients (nitrogen and phosphorus), and other agricultural pollution into the Yeşilırmak and Kızılırmak Rivers. The project will be implemented in the micro catchments that are in the provinces of Amasya , Çorum, Tokat and Samsun
  • 13. PROJECT GLOBAL ENVIRONMENTAL OBJECTIVES • The project will fully integrate environmental concerns into agricultural practices to make them more sustainable, including the storage, management and application of manure and ensure ecologically sustainable use of natural resources to reduce the discharge of the nutrient load into the Turkish ground and surface waters as well as into the Black Sea. • The project will also promote appropriate policies and policy reforms in order to create an enabling environment for realizing the project objectives. It will develop capacity of private small holders and commercial farmers to use environment- friendly agricultural practices and resource management.
  • 14. NUTRIENT MANAGEMENT In order to meet food production for increasing population requirements, increasing agricultural export, and to meet raw materials requirements for industry, agricultural production should be increased. But while aiming to increase agricultural production, natural sources such as soil and water which are main inputs of agriculture, should be protected.
  • 15. Because of the different altitudes of our country, there are different climatic conditions. As the great mountain ranges are placed on the Black Sea and Mediterranean coasts, most of the rest of the country has a semi-dry climate with low precipitation. In almost all of the country there is drought and need to the water in summer times. Topography and climate specifications caused the use of different nutrients as fertilizers. One of the most important inputs for increasing agricultural production is nutrients as chemical and organic fertilizers.
  • 16. In order to benefit from utilization of fertilizers at the utmost level, they have to be applied at the most suitable times and appropriately to the land. For this purpose, soil analysis will show us which nutrients have to be applied to the land for productivity. The objective of the GEF Project, that is still at the preparation stage and will begin in the year 2003, is the reduction of nutrients into Black Sea. In the determined micro-catchments and selected provinces, vegetal and livestock activities are very intensive.
  • 17. • Solid and liquid wastes coming from beef, dairy and poultry production enterprises are polluting the ground and surface waters, and these circumstances are threatening human and environmental health and also causing pollution in the Black Sea. • This project’s objective is also the reduction of pollution by using chemical fertilizers based on soil testing
  • 18. Vegetable production will be naturalized by using manures for vegetable production and demand for chemical fertilizers will be reduced. Within that scope, measures will be taken for the liquid and solid waste contaminants to the surface and ground waters in the determined micro-catchments and they will be collected. Manures will be used in vegetable production lands and range lands as organic fertilizers.
  • 19. With that purpose, establishing a system for creating supply – demand balance between vegetable producers and livestock producers, causing farmers to try to use fertilizers consciously based on good agricultural practices and soil analysis by leading farmers, training of farmers by local agricultural agencies, awareness of the local population, and monitoring of the surface and ground waters for observing the results of these activities, and replication of these activities at national at regional levels is the objective.
  • 20. • Nutrient reduction: The Project will reduce, over the long-term, the discharge of nutrients (nitrogen and phosphorus) and other agricultural pollutants into the surface and ground waters of Turkey and the Black Sea through integrated land and water management and promote ecologically sustainable use of natural resources.
  • 21. This component is being prepared under the umbrella of the Black Sea/Danube Strategic Partnership-Nutrient Reduction Investment Fund under which riparian countries would be eligible for Global Environment Facility (GEF) funding for projects that would control or mitigate nutrient inflow to the Black Sea. The Project activities are directly linked to "Strategic Action Plan for the Protection and Rehabilitation of the Black Sea" (BSSAP), formulated with the assistance of the GEF.
  • 22. • Within the framework of the project, the following steps will be taken : a) strengthening national policy and local regulatory capacity to meet European Union (EU) standards for agricultural nutrient pollution control, b) increasing the use of environmentally friendly agricultural practices and thereby reducing nutrient discharge particularly from agricultural sources to the Black Sea, c) capacity building and promoting a broad public awareness program and replication strategy.
  • 23. Global Operational Strategy/Program objective addressed by the Project : The Project will implement priority actions identified in the Black Sea Strategic Action Plan. The Project will provide an opportunity for the GEF to be a catalyst for the actions to bring about the successful integration of improved land and water resource management practices. The GEF support will reduce costs and barriers to farmers, adopting improved and sustainable agricultural practices. It will help develop mechanisms to move from demonstration level activities to operational projects that reduce non-point source agricultural pollution to Black Sea.
  • 24. THE MAIN COMPONENTS OF THE PROJECT : 1) Manure management system and pollution from Agro-Industry 2 ) Water and Soil Quality Monitoring Program 3) National Level Strenthening Policy &Regulatory Capacity Building 4) Public Awareness
  • 25. Manure Management • The project will initially fund pilot actions to test the options for improving the storage and handling of livestock waste. Following a review of the different livestock husbandry practices in the project provinces, three types of enterprises were selected for the pilot activities: i) commercial beef and dairy farms in peri-urban areas that are frequently discharging solid and liquid wastes directly into the water body; ii) small livestock farms in the MC areas; and iii) poultry units (each with about 45,000 birds) in the Corum area where there is a high concentration of poultry production.
  • 26. • In the case of the peri-urban cattle farmers and the small livestock farms in the MCs, the project will provide funds for construction of on-farm and central storage as well as equipment for waste collection and application to agricultural land. The arrangements for the organization and management of the investment and implementation phases, as well as the participation of the local administrations and beneficiaries, still have to be worked out in the course of further project preparation. With regard to the poultry units, primarily technical assistance will be provided for enforcing compliance with existing legislation and to develop a more efficient system for handling the collection and utilization of poultry manure.
  • 27. • MARA’s and MOE’s staff, visited the sites selected for manure management pilot activities at: (a) Turhal - beef feed-lots on the Dazya Stream that drains into the Yesilirmak, Tokat Province; (b) Suluova - beef feed lots on the Tersakan Stream, draining into the Yesilirmak, Amasya Province; and (c) Bafra - small farmer milk and beef production in Ilyasu MC on the Ilyasu Stream draining into the Kizilirmak, Samsun Province (d) Chicken units lots on the Derinçay Stream draining into the Yeşilırmak , Çorum Province.
  • 28. While the Turhal and Bafra sites were found to justify further investigation, the Suluova area was subject to serious pollution from household wastes, as well as from agro-industry and it would be difficult to measure the impact of project actions on nutrient discharge. Therefore Suluova was excluded from the project. Instead of Suluova, a new area will be determined.
  • 29. Three pilot manure management facilities will be implemented in the first eighteen months of the project. At the same time the public awareness activities will be launched to sensitize the rural population to need to improve the handling of livestock waste. Following the evaluation of the impact of the pilot facilities against environmental, economic and social criteria, the project actions will be extended to other sites in the project years 3 - 6. The Regional Environmental Assessment will be done for the liquid and solid manure storage structures.
  • 30. Use of the field demonstration program will be realized in order to show the importance of organic manures and to improve good relations between the livestock producers who are without land for cultivation, and the arable farmers, horticulturists, orchard owners and rangeland users who are the potential market for organic manure
  • 31. Fertilizer Use in the Project Provinces Although some efforts have been made to introduce soil analysis for better fertilizer application, the impact is limited. The “annual provincial extension programs” include nutrient management but due to problems regarding resource allocation, the effectiveness of these efforts are questionable. Therefore, inorganic fertilizer application is another source of non-point pollution in Kizilirmak and Yesilirmak watersheds. A baseline survey conducted in early 2002 in these watersheds indicated that only 15% of the farmers follows the advice given by the extension staff, traditional practices and “learning from the neighbor” is still dominant.
  • 32. Around 17 % of the farmers who produce cash crops and own medium sized land made their soils analyzed. There is no such practice among small farmers producing cereals. The data indicated that about 33% of the farmers who had their soils analyzed were applying high amounts and in turn reduced the fertilizer rates. Introduction of improved storage and application of livestock wastes together with nutrient management programs should have a significant impact on reducing nutrient discharge into the water body.
  • 33. Soil and water quality monitoring: The project will provide for the incremental equipment, staff training and operating costs for monitoring the impact of environment-friendly practices on the discharge of nutrients (N & P) into the water body. Measurements of BOD and suspended solids will also be made. MARA will be responsible for monitoring at the level of the MC, while MOE will be responsible for monitoring water quality upstream and downstream in the main river. The central MOE laboratory in Ankara will be used to calibrate samples taken by MARA.
  • 34. In the micro catchments soil and water quality monitoring points have been selected, sampling procedures have been prepared, organizational arrangements with responsibilities of MOE and MARA have been agreed upon and investment and operational costs have been prepared.
  • 35. National Level Strenthening of Policy &Regulatory Capacity: • Ministry of Environment (MOE) and Ministry of Agriculture and Rural Services (MARA) prepared their initial review of the status of environmental legislation covering, the Nitrate Directive legislation and certification standards for organic farming. The GEF funding could support work on application of the Nitrates Directive, the development of a Code of Good Agricultural Practices and measures required to promote the development of Organic Farming. With regard to Integrated Pest Management, this would be covered by the World Bank funding.
  • 36. Within the framework of the project, the Turkish Nitrate Directive which is the equivalent of the EU Nitrate Directive (91/676/EEC) will be constituted. The Nitrates Directive adoption studies have been carried out by MOE and MARA. It is aimed that these studies will be completed by the end of 2002.
  • 37. Public Awareness and Replication Strategy The program related to Public Awareness has been prepared by the authorities of MOE , MARA and the World Bank. Public awareness, capacity building and replication strategy activities will be conducted in all provinces covered by the project. Public awareness program will be applied at the local, national and international levels.
  • 38. At the local level (Amasya, Çorum,Tokat and Samsun ), the following works will be carried out: (a) Villages will be visited in selected micro-catchments to find out about the level of public awareness, the interest and need for better knowledge of environmental matters and the issues it deals with. (b) Appropriate structures and instruments will be designed for the campaign ( Radio, TV, Publications) and the cost for each instrument will be determined. (c) The scope and specific objectives for each step will be defined in the campaign. (d) Proposals will be presented to local communities to test their receptivity to the approach and the instrument proposed .
  • 39. e) Environment-friendly agricultural and manure management practices will be adopted. (f) Environmental awareness will be increased through enhanced school and NGO’s participation. (g) The problems caused by pollution and waste disposal will be explained.
  • 40. At the national level the following works will be carried out: (a) The experiences gained at the local level will be reflected on the national level. (b) A broad nationwide public information campaign will be undertaken to disseminate the benefits of proposed project activities. (c) Efforts will be concentrated on institutions and groups that may influence the replication of the project in other areas. (d) A national media campaign will be launched to introduce the project to the people better . (e) The problems caused by pollution and waste disposal will be explained .
  • 41. At the international level the following works will be carried out : • The project will provide for the organization of regional workshops, field trips, training, publication in international agriculture and environment journals and other activities to promote replication of project activities in other Black Sea riparian countries. The pilot activity will aim to serve as a model to be replicated in these countries which will help contribute to significant reductions in the nutrient loads entering the Black Sea.
  • 42. ORGANIZATIONAL ISSUES FOR AGENCIES At the central level, there are three units i) Project Management Group (PMG), ii) Central Coordination Unit (CCU), and iii) Project Management Units (PMUs). At the field level (provincial) there are two units i) Local Project Management Teams (LPMT) ii) Micro Catchment Implemantation Teams (MCIT)