SlideShare a Scribd company logo
1 of 19
Progress towards ResultsProgress towards Results
Overall Performance Study of the GEFOverall Performance Study of the GEF
Aaron ZazuetaAaron Zazueta
GEF Evaluation OfficeGEF Evaluation Office
IntroductionIntroduction
 OPS4 is an independent study to assess the extent to which the
GEF is achieving its objectives and to identify potential
improvements.
 OPS4 is a working document of the 5th
Replenishment of the GEF
and will be presented to the Assembly in May 2010.
 Final report was presented to the third replenishment meeting, 13-
14 October, 2009.
2
ScopeScope
 16 key questions identified in ToR (in: www.gefeo.org)
 All projects and project proposals until June 30, 2009 were studied:
• 2,389 finished, on-going and approved projects: $ 8,772 M.
• Project Terminal evaluations since OPS3: 215.
 OPS4 built on OPS3, 24 evaluation reports of the Evaluation Office,
and evidence from:
• 57 countries, visited after OPS3
• 9 special country case studies
• 10 additional project visits
• Literature and desk reviews, interviews, surveys
 Consultations with representatives of all stakeholders
3
LimitationsLimitations
 All 16 key questions answered, but varying degrees of depth;
 Need more work on:
• The involvement of civil society and the private sector in the
GEF
• Resources management in the GEF
• Cost-effectiveness
• Impact analysis – project oriented
 Two major evaluations of the Evaluation Office have led to on-going
reform processes:
• The reform of the project cycle; positive indications but it is too
soon for an evaluative judgments
• The reform of the RAF
 Impact evidence in the GEF is still limited to the 3 implementing
agencies: World Bank, UNDP and UNEP.
4
Report overviewReport overview
 GEF in a Changing World
• International Context
• Resource Mobilization
• Convention Guidance
• The Catalytic Nature of the GEF
• Programming Resources
 Progress toward Impact
• From Hypothesis to Evidence
• Focal Area and Multi Focal Area Progress
 Issues affecting Results
• Performance
• The GEF as a Learning Organization
• Resources Management
 Governance and Partnership
The full document, annexes, methodological and technical documents
related to OPS4 can be found in www.gefeo.org
5
OPS4 Main conclusions (1)OPS4 Main conclusions (1)
 Funding gap:
• International funding gap on global environmental problems
• GEF Replenishments led to less funds in real terms
• GEF now has more Focal Areas, more guidance, and more
countries
 The GEF contributed to progress toward impact
• 70% of finished projects see progress toward global
environmental benefits,
• further follow-up action from national partners is essential to
achieve global environmental benefits
 GEF project performance is satisfactory
• the GEF projects are effective in producing outcomes,
• the average score over the GEF-4 period of 80% exceeding the
international benchmark of 75%
6
OPS4 Main conclusions (2)OPS4 Main conclusions (2)
 The efficiency of the GEF can and should be further improved
• emphasis on programming,
• less time spent on project identification,
• enhanced fee structure,
• more integrated learning (look at lessons from IW Learn),
• results-based management framework that includes progress to
impact measurements (logframes, tracking tools, impact )
 “Inability to deliver” is a perception linked to pre-approval phase
• reform processes are underway and show promise
• GEF should move from focal area programming toward programming
on a national level
 The GEF partnership brings added value – its tensions need to be
resolved
 Governance is adequate but could improve
• Substantive role of Assembly / meet more often
• Clearer delineation of governance/management roles
7
OPS4 recommendationsOPS4 recommendations
 Interaction between the GEF and the conventions need to be
improved.
 Improvements in resource management should focus on
• developing a new system for reserving funds for project ideas
• reforming fiduciary standards and the fee system
 The GEF Council should address tensions within the GEF
partnership and provide guidance on roles and responsibilities.
 If the GEF-5 replenishment recommendations include strong
proposals concerning programming, efficiency and partnership,
OPS4 supports the highest level of replenishment for the GEF.
8
International Waters
Main conclusions and recommendations
from OPS4
9
BackgroundBackground
 Long-term objectives:
• Foster international, multi-state cooperation on priority
transboundary enbironmental concerns through more
comprehensive, ecosystem-based approaches to management.
• Play a catalytic role in addressing transboundary water concerns
by assisting countries to utilize the full range of technical
assistance, economic, financial, regulatory and institutional
reforms that are needed.
 No Convention
 Importance of diagnosis (TDA) and the strategic programming
(SAP)
 Foundation / Demonstration / investment
10
Conclusions (1)Conclusions (1)
 Rising challenges make GEFs IW work highly relevant.
 GEF has provided important support to new and existing
international agreements for the protection of
International Waters
• Helped set the stage for national policies that
reduce environmental stress.
11
Conclusions (2)Conclusions (2)
 GEF is contributing towards the reduction of pollution
and other stresses (such as overfishing) in international
water bodies.
 23 Terminal Evaluations were examined
• 8 demonstrated stress reduction
• 7 achieved promising intermediary stages and
outcomes
• 8 not designed for impacts (Global projects) or
where Foundational (too early to assess)
12
Review of Outcomes to Impacts (ROtI)Review of Outcomes to Impacts (ROtI)
 Based on 23 Terminal Evaluations.
13
.
state /
condition
Outputs
Reduced
Threat to
GEB
Enhance
dStatus
of GEB:
Outcomes
IMPACT
Assumption Assumption Assumption
state /
condition
ThreatsBasedAnalysisOutcomes-ImpactsTOCAnalysisProject LogFrame Analysis
Factors that affect progress towards impactFactors that affect progress towards impact
 Relevance to national priorities (sustainable financial support)
 Engagement with industrial and agricultural interests and other
sectors.
 Robust understanding of Ecosystem Services (scientifically sound
diagnostics such as TDAs)
 Projects in which not all important catchment countries participate
face more difficulties in moving towards GEB
 Absence of baselines and weak monitoring makes it more difficult to
determine long-term impacts
14
RecommendationsRecommendations
 IW impact analysis need to be done at the water body or catchment
level
• Need to examine combined effects of phased and concurrent
projects
 Focus on involving all countries in a catchment area before
investment stage, while continuing to support all participating
countries
 Other Focal Areas should consider IWs Phased Approach
(Foundation, Demonstration, Investment) when appropriate
15
Recommendations (2)Recommendations (2)
 GEF should draw lessons from the IW Learn Initiative when
developing a Knowledge Management approach across Agencies
and Focal Areas
 Continue to develop and integrate tools for RBM ( Logframes,
tracking tools and emerging evidence on impact drivers )
16
Issues for future considerationIssues for future consideration
 Ex-post catchment /cluster impact evaluations will be useful to more
fully gauge IW impacts
• GEF EO will undertake an IW Impact Evaluation in 2010.
• Criteria for selection of study:
 High levels of GEF funding at the catchment/basin level.
 Long-term GEF involvement in the area.
• GEF EO is looking to partner with the Evaluation Offices of
other Agencies.
 Looking you’re your input for the planning of the IW impact study
during discussion on Friday
17
Tentative Questions for the IW EvaluationTentative Questions for the IW Evaluation
 To what extent has the campaigns identified the critical
transboundary concerns and their root causes?
 To what extent has the GEF catalyzed agreements among riparian
countries to address the critical tansboundary concerns and their
root causes?
 What have been the accomplishments of the campaign so far?
• Better understanding of issues, capacities strengthened, laws and
regulations adopted and enforced, demonstrations, etc.
 To what extent do accomplishments signify progress towards
impact?
• Reduction of transboundary environmental stressed
• Improvement on the ecological status and human populations
 What are the factors that contribute or hinder progress towards
impacts?
• Lessons and recommendations
18
THANK YOU
DISCUSSION GROUP
TOMORROW
azazueta@theGEF.org
19

More Related Content

What's hot

Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9Mohamed Rafique
 
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...Tariq A. Deen
 
The sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesThe sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesNAP Events
 
The sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesThe sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesNAP Events
 
Climate Finance - National Adaptation Plans under the UNFCCC Process - Webinar
Climate Finance - National Adaptation Plans under the UNFCCC Process - WebinarClimate Finance - National Adaptation Plans under the UNFCCC Process - Webinar
Climate Finance - National Adaptation Plans under the UNFCCC Process - WebinarUNDP Climate
 
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 aug
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 augKnowledge and awareness WP7 and Capacity development WP6_steven downey_28 aug
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 augGlobal Water Partnership
 
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...UNDP Climate
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburDr. Md. Taibur Rahman
 
CCXG Forum, March 2022, Sindy Singh
CCXG Forum, March 2022, Sindy SinghCCXG Forum, March 2022, Sindy Singh
CCXG Forum, March 2022, Sindy SinghOECD Environment
 
Regional Development and RBM: Proposals for improvement
Regional Development and RBM: Proposals for improvementRegional Development and RBM: Proposals for improvement
Regional Development and RBM: Proposals for improvementGIZ Moldova
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceNAP Events
 
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...icgfmconference
 
Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Fbertrand
 
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...icgfmconference
 
The need for improvement in Public Expenditure and Financial Accountability (...
The need for improvement in Public Expenditure and Financial Accountability (...The need for improvement in Public Expenditure and Financial Accountability (...
The need for improvement in Public Expenditure and Financial Accountability (...John Leonardo
 
11.3.3 Experiencing on enhancing institutional arrangements and support for t...
11.3.3 Experiencing on enhancing institutional arrangements and support for t...11.3.3 Experiencing on enhancing institutional arrangements and support for t...
11.3.3 Experiencing on enhancing institutional arrangements and support for t...NAP Events
 
WCP measuring progress – indicators, milestones and targets ralph philip 27 aug
WCP measuring progress – indicators, milestones and targets ralph philip 27 augWCP measuring progress – indicators, milestones and targets ralph philip 27 aug
WCP measuring progress – indicators, milestones and targets ralph philip 27 augGlobal Water Partnership
 

What's hot (19)

Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9
 
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & G...
 
The sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesThe sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelines
 
The sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelinesThe sample NAP process based on the UNFCCC NAP technical guidelines
The sample NAP process based on the UNFCCC NAP technical guidelines
 
Climate Finance - National Adaptation Plans under the UNFCCC Process - Webinar
Climate Finance - National Adaptation Plans under the UNFCCC Process - WebinarClimate Finance - National Adaptation Plans under the UNFCCC Process - Webinar
Climate Finance - National Adaptation Plans under the UNFCCC Process - Webinar
 
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 aug
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 augKnowledge and awareness WP7 and Capacity development WP6_steven downey_28 aug
Knowledge and awareness WP7 and Capacity development WP6_steven downey_28 aug
 
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...
Country Experiences Malawi and Nepal - National Adaptation Plans under the UN...
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taibur
 
IWRM Planning
IWRM Planning IWRM Planning
IWRM Planning
 
CCXG Forum, March 2022, Sindy Singh
CCXG Forum, March 2022, Sindy SinghCCXG Forum, March 2022, Sindy Singh
CCXG Forum, March 2022, Sindy Singh
 
Regional Development and RBM: Proposals for improvement
Regional Development and RBM: Proposals for improvementRegional Development and RBM: Proposals for improvement
Regional Development and RBM: Proposals for improvement
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilience
 
PEG M&E Tool
PEG M&E ToolPEG M&E Tool
PEG M&E Tool
 
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...
Workshop Session I: Public Expenditure Financial Accountability (PEFA) Assess...
 
Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...
 
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...
Workshop Session II: Public Expenditure Financial Accountability (PEFA) Asses...
 
The need for improvement in Public Expenditure and Financial Accountability (...
The need for improvement in Public Expenditure and Financial Accountability (...The need for improvement in Public Expenditure and Financial Accountability (...
The need for improvement in Public Expenditure and Financial Accountability (...
 
11.3.3 Experiencing on enhancing institutional arrangements and support for t...
11.3.3 Experiencing on enhancing institutional arrangements and support for t...11.3.3 Experiencing on enhancing institutional arrangements and support for t...
11.3.3 Experiencing on enhancing institutional arrangements and support for t...
 
WCP measuring progress – indicators, milestones and targets ralph philip 27 aug
WCP measuring progress – indicators, milestones and targets ralph philip 27 augWCP measuring progress – indicators, milestones and targets ralph philip 27 aug
WCP measuring progress – indicators, milestones and targets ralph philip 27 aug
 

Viewers also liked

Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...
Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...
Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...Iwl Pcu
 
BSERP small grants programmes
BSERP small grants programmesBSERP small grants programmes
BSERP small grants programmesIwl Pcu
 
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5Iwl Pcu
 
Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...
 Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres... Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...
Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...Iwl Pcu
 
Outcomes of the institutional review of the Black Sea Commission: implementat...
Outcomes of the institutional review of the Black Sea Commission: implementat...Outcomes of the institutional review of the Black Sea Commission: implementat...
Outcomes of the institutional review of the Black Sea Commission: implementat...Iwl Pcu
 
Translating the UNECE Water Convention into Practise: Concluding Agreements ...
Translating the UNECE Water Convention into Practise:  Concluding Agreements ...Translating the UNECE Water Convention into Practise:  Concluding Agreements ...
Translating the UNECE Water Convention into Practise: Concluding Agreements ...Iwl Pcu
 
Guinea Current LME Strategic Action Programme (IWC5 Presentation)
Guinea Current LME  Strategic Action Programme (IWC5 Presentation)Guinea Current LME  Strategic Action Programme (IWC5 Presentation)
Guinea Current LME Strategic Action Programme (IWC5 Presentation)Iwl Pcu
 
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...Iwl Pcu
 
Joint Monitoring and Assessment in transboundary basins: obligations and expe...
Joint Monitoring and Assessment in transboundary basins: obligations and expe...Joint Monitoring and Assessment in transboundary basins: obligations and expe...
Joint Monitoring and Assessment in transboundary basins: obligations and expe...Iwl Pcu
 
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...Iwl Pcu
 
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)Iwl Pcu
 
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...Iwl Pcu
 
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASIN
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASININSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASIN
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASINIwl Pcu
 
BSERP exit strategy (Volovik)
BSERP exit strategy (Volovik)BSERP exit strategy (Volovik)
BSERP exit strategy (Volovik)Iwl Pcu
 
Danube Small Grants
Danube Small Grants Danube Small Grants
Danube Small Grants Iwl Pcu
 
Non-Market Valuation
Non-Market ValuationNon-Market Valuation
Non-Market ValuationIwl Pcu
 
Iran: Cost Assessment of Environmental Degradation
Iran: Cost Assessment of Environmental DegradationIran: Cost Assessment of Environmental Degradation
Iran: Cost Assessment of Environmental DegradationIwl Pcu
 

Viewers also liked (17)

Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...
Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...
Adaptive Management in the Danube River Basin (Weller/Zavadsky) [IWC4 Present...
 
BSERP small grants programmes
BSERP small grants programmesBSERP small grants programmes
BSERP small grants programmes
 
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5
The GEF IW Learning Portfolio of Projects: Combined Presentation at the IWC5
 
Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...
 Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres... Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...
Sustainable livelihoods in Milne Bay: Eco-tourism versus logging (IWC5 Pres...
 
Outcomes of the institutional review of the Black Sea Commission: implementat...
Outcomes of the institutional review of the Black Sea Commission: implementat...Outcomes of the institutional review of the Black Sea Commission: implementat...
Outcomes of the institutional review of the Black Sea Commission: implementat...
 
Translating the UNECE Water Convention into Practise: Concluding Agreements ...
Translating the UNECE Water Convention into Practise:  Concluding Agreements ...Translating the UNECE Water Convention into Practise:  Concluding Agreements ...
Translating the UNECE Water Convention into Practise: Concluding Agreements ...
 
Guinea Current LME Strategic Action Programme (IWC5 Presentation)
Guinea Current LME  Strategic Action Programme (IWC5 Presentation)Guinea Current LME  Strategic Action Programme (IWC5 Presentation)
Guinea Current LME Strategic Action Programme (IWC5 Presentation)
 
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...
Towards a Methodology for Assessment of Internationally Shared Aquifers (IWC5...
 
Joint Monitoring and Assessment in transboundary basins: obligations and expe...
Joint Monitoring and Assessment in transboundary basins: obligations and expe...Joint Monitoring and Assessment in transboundary basins: obligations and expe...
Joint Monitoring and Assessment in transboundary basins: obligations and expe...
 
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...
Guinea Current Large Marine Ecosystem Marine Management and Governance (IWC5 ...
 
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)
Monitoring Coral Reef Marine Protected Areas (IWC5 Presentation)
 
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...
Pacific Islands Oceanic Fisheries Management Project (OFM Project) (IWC5 Pres...
 
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASIN
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASININSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASIN
INSTITUTIONAL MAPPING OF THE SAN JUAN RIVER BASIN
 
BSERP exit strategy (Volovik)
BSERP exit strategy (Volovik)BSERP exit strategy (Volovik)
BSERP exit strategy (Volovik)
 
Danube Small Grants
Danube Small Grants Danube Small Grants
Danube Small Grants
 
Non-Market Valuation
Non-Market ValuationNon-Market Valuation
Non-Market Valuation
 
Iran: Cost Assessment of Environmental Degradation
Iran: Cost Assessment of Environmental DegradationIran: Cost Assessment of Environmental Degradation
Iran: Cost Assessment of Environmental Degradation
 

Similar to Progress towards Results: Overall Performance Study of the GEF (IWC5 Presentation)

Final outline plan for webinar evaluation and impact assessment mof 2004
Final outline plan for webinar evaluation and impact assessment mof 2004   Final outline plan for webinar evaluation and impact assessment mof 2004
Final outline plan for webinar evaluation and impact assessment mof 2004 EricaPackingtonIOD
 
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...OECD Environment
 
E-PASS Inception Project Management and Oversight
E-PASS Inception Project Management and OversightE-PASS Inception Project Management and Oversight
E-PASS Inception Project Management and Oversightepass2015
 
Regional Technical Dialogues on intended nationally determined contributions ...
Regional Technical Dialogues on intended nationally determined contributions ...Regional Technical Dialogues on intended nationally determined contributions ...
Regional Technical Dialogues on intended nationally determined contributions ...CIFOR-ICRAF
 
Key findings, lessons learned and next steps for TrackFin
Key findings, lessons learned and next steps for TrackFinKey findings, lessons learned and next steps for TrackFin
Key findings, lessons learned and next steps for TrackFinTrackFin
 
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...Iwl Pcu
 
3-OECD-Green-Budgeting-Survey-2021.pdf
3-OECD-Green-Budgeting-Survey-2021.pdf3-OECD-Green-Budgeting-Survey-2021.pdf
3-OECD-Green-Budgeting-Survey-2021.pdfOECD Governance
 
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...
 PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ... PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...NAP Events
 
Introduction to the NAP Global Network Webinar Series | Sector Integration in...
Introduction to the NAP Global Network Webinar Series | Sector Integration in...Introduction to the NAP Global Network Webinar Series | Sector Integration in...
Introduction to the NAP Global Network Webinar Series | Sector Integration in...NAP Global Network
 
The National Adaptation Plan
The National Adaptation PlanThe National Adaptation Plan
The National Adaptation PlanNAP Events
 
GF TADs Seminar On National Project Proposals
GF TADs Seminar On National Project ProposalsGF TADs Seminar On National Project Proposals
GF TADs Seminar On National Project ProposalsFAO
 
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...Soils FAO-GSP
 
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...OECD Environment
 
WRI's Measurement and Performance Tracking
WRI's Measurement and Performance TrackingWRI's Measurement and Performance Tracking
WRI's Measurement and Performance TrackingCIFOR-ICRAF
 
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...Iwl Pcu
 

Similar to Progress towards Results: Overall Performance Study of the GEF (IWC5 Presentation) (20)

Dhaka revpres160814
Dhaka revpres160814Dhaka revpres160814
Dhaka revpres160814
 
Final outline plan for webinar evaluation and impact assessment mof 2004
Final outline plan for webinar evaluation and impact assessment mof 2004   Final outline plan for webinar evaluation and impact assessment mof 2004
Final outline plan for webinar evaluation and impact assessment mof 2004
 
GEF policies
GEF  policies GEF  policies
GEF policies
 
Sandii lewin part_en
Sandii lewin part_enSandii lewin part_en
Sandii lewin part_en
 
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
 
E-PASS Inception Project Management and Oversight
E-PASS Inception Project Management and OversightE-PASS Inception Project Management and Oversight
E-PASS Inception Project Management and Oversight
 
Regional Technical Dialogues on intended nationally determined contributions ...
Regional Technical Dialogues on intended nationally determined contributions ...Regional Technical Dialogues on intended nationally determined contributions ...
Regional Technical Dialogues on intended nationally determined contributions ...
 
Key findings, lessons learned and next steps for TrackFin
Key findings, lessons learned and next steps for TrackFinKey findings, lessons learned and next steps for TrackFin
Key findings, lessons learned and next steps for TrackFin
 
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...
Thematic Breakout Session Two: Monitoring and Evaluation Results- Programme S...
 
PEG M&E Tool
PEG M&E ToolPEG M&E Tool
PEG M&E Tool
 
3-OECD-Green-Budgeting-Survey-2021.pdf
3-OECD-Green-Budgeting-Survey-2021.pdf3-OECD-Green-Budgeting-Survey-2021.pdf
3-OECD-Green-Budgeting-Survey-2021.pdf
 
Stocktaking of Integrated Approach Pilots (IAPs) Preparation
Stocktaking of Integrated Approach Pilots (IAPs) PreparationStocktaking of Integrated Approach Pilots (IAPs) Preparation
Stocktaking of Integrated Approach Pilots (IAPs) Preparation
 
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...
 PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ... PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...
PEG M&E tool: a tool for monitoring and reviewing Progress, Effectiveness & ...
 
Introduction to the NAP Global Network Webinar Series | Sector Integration in...
Introduction to the NAP Global Network Webinar Series | Sector Integration in...Introduction to the NAP Global Network Webinar Series | Sector Integration in...
Introduction to the NAP Global Network Webinar Series | Sector Integration in...
 
The National Adaptation Plan
The National Adaptation PlanThe National Adaptation Plan
The National Adaptation Plan
 
GF TADs Seminar On National Project Proposals
GF TADs Seminar On National Project ProposalsGF TADs Seminar On National Project Proposals
GF TADs Seminar On National Project Proposals
 
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...
Item 2: Global Soil Partnership - accomplishment, challenges and way forward:...
 
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
 
WRI's Measurement and Performance Tracking
WRI's Measurement and Performance TrackingWRI's Measurement and Performance Tracking
WRI's Measurement and Performance Tracking
 
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...
Role of Stakeholder Engagement in Integrated Water Management (A GEF Internat...
 

More from Iwl Pcu

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Iwl Pcu
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Iwl Pcu
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Iwl Pcu
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)Iwl Pcu
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designingIwl Pcu
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)Iwl Pcu
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs PublicationIwl Pcu
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Iwl Pcu
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5Iwl Pcu
 

More from Iwl Pcu (20)

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designing
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs Publication
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 

Progress towards Results: Overall Performance Study of the GEF (IWC5 Presentation)

  • 1. Progress towards ResultsProgress towards Results Overall Performance Study of the GEFOverall Performance Study of the GEF Aaron ZazuetaAaron Zazueta GEF Evaluation OfficeGEF Evaluation Office
  • 2. IntroductionIntroduction  OPS4 is an independent study to assess the extent to which the GEF is achieving its objectives and to identify potential improvements.  OPS4 is a working document of the 5th Replenishment of the GEF and will be presented to the Assembly in May 2010.  Final report was presented to the third replenishment meeting, 13- 14 October, 2009. 2
  • 3. ScopeScope  16 key questions identified in ToR (in: www.gefeo.org)  All projects and project proposals until June 30, 2009 were studied: • 2,389 finished, on-going and approved projects: $ 8,772 M. • Project Terminal evaluations since OPS3: 215.  OPS4 built on OPS3, 24 evaluation reports of the Evaluation Office, and evidence from: • 57 countries, visited after OPS3 • 9 special country case studies • 10 additional project visits • Literature and desk reviews, interviews, surveys  Consultations with representatives of all stakeholders 3
  • 4. LimitationsLimitations  All 16 key questions answered, but varying degrees of depth;  Need more work on: • The involvement of civil society and the private sector in the GEF • Resources management in the GEF • Cost-effectiveness • Impact analysis – project oriented  Two major evaluations of the Evaluation Office have led to on-going reform processes: • The reform of the project cycle; positive indications but it is too soon for an evaluative judgments • The reform of the RAF  Impact evidence in the GEF is still limited to the 3 implementing agencies: World Bank, UNDP and UNEP. 4
  • 5. Report overviewReport overview  GEF in a Changing World • International Context • Resource Mobilization • Convention Guidance • The Catalytic Nature of the GEF • Programming Resources  Progress toward Impact • From Hypothesis to Evidence • Focal Area and Multi Focal Area Progress  Issues affecting Results • Performance • The GEF as a Learning Organization • Resources Management  Governance and Partnership The full document, annexes, methodological and technical documents related to OPS4 can be found in www.gefeo.org 5
  • 6. OPS4 Main conclusions (1)OPS4 Main conclusions (1)  Funding gap: • International funding gap on global environmental problems • GEF Replenishments led to less funds in real terms • GEF now has more Focal Areas, more guidance, and more countries  The GEF contributed to progress toward impact • 70% of finished projects see progress toward global environmental benefits, • further follow-up action from national partners is essential to achieve global environmental benefits  GEF project performance is satisfactory • the GEF projects are effective in producing outcomes, • the average score over the GEF-4 period of 80% exceeding the international benchmark of 75% 6
  • 7. OPS4 Main conclusions (2)OPS4 Main conclusions (2)  The efficiency of the GEF can and should be further improved • emphasis on programming, • less time spent on project identification, • enhanced fee structure, • more integrated learning (look at lessons from IW Learn), • results-based management framework that includes progress to impact measurements (logframes, tracking tools, impact )  “Inability to deliver” is a perception linked to pre-approval phase • reform processes are underway and show promise • GEF should move from focal area programming toward programming on a national level  The GEF partnership brings added value – its tensions need to be resolved  Governance is adequate but could improve • Substantive role of Assembly / meet more often • Clearer delineation of governance/management roles 7
  • 8. OPS4 recommendationsOPS4 recommendations  Interaction between the GEF and the conventions need to be improved.  Improvements in resource management should focus on • developing a new system for reserving funds for project ideas • reforming fiduciary standards and the fee system  The GEF Council should address tensions within the GEF partnership and provide guidance on roles and responsibilities.  If the GEF-5 replenishment recommendations include strong proposals concerning programming, efficiency and partnership, OPS4 supports the highest level of replenishment for the GEF. 8
  • 9. International Waters Main conclusions and recommendations from OPS4 9
  • 10. BackgroundBackground  Long-term objectives: • Foster international, multi-state cooperation on priority transboundary enbironmental concerns through more comprehensive, ecosystem-based approaches to management. • Play a catalytic role in addressing transboundary water concerns by assisting countries to utilize the full range of technical assistance, economic, financial, regulatory and institutional reforms that are needed.  No Convention  Importance of diagnosis (TDA) and the strategic programming (SAP)  Foundation / Demonstration / investment 10
  • 11. Conclusions (1)Conclusions (1)  Rising challenges make GEFs IW work highly relevant.  GEF has provided important support to new and existing international agreements for the protection of International Waters • Helped set the stage for national policies that reduce environmental stress. 11
  • 12. Conclusions (2)Conclusions (2)  GEF is contributing towards the reduction of pollution and other stresses (such as overfishing) in international water bodies.  23 Terminal Evaluations were examined • 8 demonstrated stress reduction • 7 achieved promising intermediary stages and outcomes • 8 not designed for impacts (Global projects) or where Foundational (too early to assess) 12
  • 13. Review of Outcomes to Impacts (ROtI)Review of Outcomes to Impacts (ROtI)  Based on 23 Terminal Evaluations. 13 . state / condition Outputs Reduced Threat to GEB Enhance dStatus of GEB: Outcomes IMPACT Assumption Assumption Assumption state / condition ThreatsBasedAnalysisOutcomes-ImpactsTOCAnalysisProject LogFrame Analysis
  • 14. Factors that affect progress towards impactFactors that affect progress towards impact  Relevance to national priorities (sustainable financial support)  Engagement with industrial and agricultural interests and other sectors.  Robust understanding of Ecosystem Services (scientifically sound diagnostics such as TDAs)  Projects in which not all important catchment countries participate face more difficulties in moving towards GEB  Absence of baselines and weak monitoring makes it more difficult to determine long-term impacts 14
  • 15. RecommendationsRecommendations  IW impact analysis need to be done at the water body or catchment level • Need to examine combined effects of phased and concurrent projects  Focus on involving all countries in a catchment area before investment stage, while continuing to support all participating countries  Other Focal Areas should consider IWs Phased Approach (Foundation, Demonstration, Investment) when appropriate 15
  • 16. Recommendations (2)Recommendations (2)  GEF should draw lessons from the IW Learn Initiative when developing a Knowledge Management approach across Agencies and Focal Areas  Continue to develop and integrate tools for RBM ( Logframes, tracking tools and emerging evidence on impact drivers ) 16
  • 17. Issues for future considerationIssues for future consideration  Ex-post catchment /cluster impact evaluations will be useful to more fully gauge IW impacts • GEF EO will undertake an IW Impact Evaluation in 2010. • Criteria for selection of study:  High levels of GEF funding at the catchment/basin level.  Long-term GEF involvement in the area. • GEF EO is looking to partner with the Evaluation Offices of other Agencies.  Looking you’re your input for the planning of the IW impact study during discussion on Friday 17
  • 18. Tentative Questions for the IW EvaluationTentative Questions for the IW Evaluation  To what extent has the campaigns identified the critical transboundary concerns and their root causes?  To what extent has the GEF catalyzed agreements among riparian countries to address the critical tansboundary concerns and their root causes?  What have been the accomplishments of the campaign so far? • Better understanding of issues, capacities strengthened, laws and regulations adopted and enforced, demonstrations, etc.  To what extent do accomplishments signify progress towards impact? • Reduction of transboundary environmental stressed • Improvement on the ecological status and human populations  What are the factors that contribute or hinder progress towards impacts? • Lessons and recommendations 18