Management for Construction Materials and Control of
Construction Waste in Construction Industry: A Review
A. A. Gulghane1
, Prof P. V. Khandve2
1(Department of civil engineering, Prof Ram Meghe College of Engineering and Management, Sant Gadge
Baba Amravati University, Badnera, India)
2 (Department of civil engineering, Prof Ram Meghe College of Engineering and Management, Sant Gadge
Baba Amravati University, Badnera, India)
ABSTRACT
In recent treads a wide range of building materials is available for the construction of civil engineering
structures. The total cost of materials may be up to 60% or more of the total cost incurred in construction project
dependent upon the type of project. Effective construction materials management is a key to success for a
construction project. Construction waste is another serious problem in construction industry. A large and various
types of construction waste with different characteristics are created at all the stages of construction.
Construction industries have a larger part in contributing environmental problems. The economic and
environmental benefits must be gained from construction waste minimization. This paper presents a review on
systematically investigation of the management of construction materials and construction waste, material
management techniques, control of construction waste and existing situation of construction management and
construction waste in the industry.
Keywords - Material Management, Construction Waste, Management techniques, Economic relevance, Existing
Situation.
I. INTRODUCTION
Construction industry is largest economic
expenditure in India. According to eleventh five year
plan, it is the second largest economic activity after
agriculture. Materials management is an important
element in project management. Effective
construction materials management process is a key
to success of a construction project. For many years it
has evolved and changed with respect to the ever-
growing complexity of projects. It is very important
to understand the origin of materials management
procedures and how these procedures differ from
those of other industries. Materials constitute a major
cost component for construction Industry. The total
cost of materials may be 60% or more of the total
cost incurred in construction project dependent upon
the type of project and the extent of mechanisation
and plant used (K V. Patel et al. 2011). Such a large
investment requires considerable planning and
control so as to minimize wastage which invariably
affects the performance of the organization. Materials
management is a coordinating function responsible
for planning and controlling materials flow. One of
the major problems in delaying construction projects
is poor materials management. Ensuring a timely
flow of materials is an important concern of material
management. The management of procuring
materials is critical as any materials surpluses or
shortages will delay the project and put it at risk. This
then affects the maintenance of a consistent flow of
materials for production, thus affecting the overall
project. Materials Management is simply the process
by which an organization is supplied with the goods
and services that it needs to achieve its objectives of
buying, storage and movement of materials.
Basically, material management is concerned with
the planning, identification, procuring, storage,
receiving, and distribution of materials. The purpose
of material management is to assure that the right
materials are in the right place, in the right quantities
when needed. The increased economic growth as
well as urbanization has led into extensive
construction activities that generate large amounts of
construction wastes. All round the world construction
materials generate million tons of waste annually.
Waste is one of the serious problems in construction
industry. The term wastage refers to the variance, if
any between the estimated and actual consumption of
an individual item. Some hazardous materials may
not be moved, before the authorities have ascertained
that safety guidelines and restrictions have been
followed. Hence proper management of waste
materials from construction sites has now become
very crucial. Managing waste means that eliminating
waste wherever possible, minimizing waste wherever
feasible and reusing materials which could otherwise
become waste. A large and various types of waste
with different characteristics are created at all the
stages of construction right from site preparation,
demolition of existing structures to final product. The
exact quantity and composition of construction waste
RESEARCH ARTICLE OPEN ACCESS
A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64
www.ijera.com 60 | P a g e
generated throughout the projects are difficult to be
identified as they are keep on changing due to the
dynamic nature of the construction activities. A
different stage of construction generates different
types and composition of waste. However, the
generation of construction waste is predictable based
on the building design and procurement of the
building materials. The nature of waste composition
might be different at various construction stages.
Thus waste generation throughout the construction
stages needs to be identified and quantified to
minimize the wastage.
II. MANAGEMENT OF CONSTRUCTION
MATERIALS
An essential factor adversely affecting the
performance of construction projects is the improper
management of materials during site activities (N B.
Kasim. 2008). Material is the main component in any
of the construction projects. Therefore, if the material
management in construction projects is not managed
properly it will create a major project cost variance.
The total cost of the project can be well controlled by
taking corrective actions towards the cost variance
occur in the project. (T. Phani Madhavi et al. 2013,
Alin Veronika et al. 2006). Studies by the
Construction Industry Institute (CII) have shown that
materials and installed equipment can make up 50–
60%of the total project cost and impact 80%of its
schedule (C H. Caldas et al. 2014). During the last
few years, enormous growth in infrastructure has
been found, by wide range of diversity construction
organization (S V. Desale et al. 2013). Fundamental
Principles of Site Material Management enlightens
the factors considered during site layout and planning
for efficient material management. Ineffective
material management practices are evident on many
projects and cause considerable waste in time and
money. (H. Randolph et al. 2005, Pauline Jeruto
Keitany et al. 2014). For managing a productive and
cost efficient site efficient material management is
very essential. The materials management system in
any project insure that the right quality of material
and quantity of materials are appropriately selected,
effectively purchased, properly delivered and safely
handled on site in a timely manner and at a proper
reasonable cost. (G.Kanimozhi et al, 2014, S.
Donyavi et al. 2009). Any organizations need to put
their effects for proper materials management
techniques for the effectiveness of project execution.
Material management involves storage,
identification, retrieval, transport, and construction
methods. Each of above is indelibly linked to ensure
safety, productivity, and schedule performance.
According to Kini (1999), materials management is
an indispensable part of the project management
which can be integrated with engineering to provide
an end product that meets the client’s requirements
and is cost effective. Over the years, materials
management in any construction project has become
a critical component of successful project execution.
(Carlos H. Caldas et al, 2014, C.K.Georgekutty et al.
2012). There should be a centralised material
management team co-ordination between the site and
the organization so that effective material
management strategies can be applied and monitored.
Construction materials management may present
similarities at the conceptual level but the
implementation details vary. Material planning
considers materials in the order of requirement at site
(S V. Desale et al. 2013). Material procurement and
storage on construction sites need to be properly
planned and executed to avoid the negative impacts
of material shortage or excessive material inventory
on-site deficiencies in the supply and flow of
construction material were often cited as major
causes of productivity degradation and financial
losses (G.Kanimozhim et al. 2014). It is observed that
construction materials are less homogeneous, less
standardized, and more numerous than those of
manufacturing, and that the characteristics of demand
are different. Their should be awareness about
material planning & scheduling at every stage of
material management. (A R. Patil et al, 2013).
III. MATERIAL MANAGEMENT
TECHNIQUES
Materials management is categorized to 5
processes these processes are majorly followed on
construction site they are namely 1.Planning,
2.Procurement, 3.Logistics, 4.Handling 5.Waste
control processes. Materials planning include
quantifying, ordering and scheduling. Companies
may have two major levels in planning- micro and
macro level. Procurement is described as the
purchase of materials and services from outside
organizations. (N. Kasim. 2011, C H. Caldas et al.
2014). Purchasing procedure can be described as Step
1 – Material Indent, Step 2 – Enquiry to Vendors,
Step 3 – Vendor Comparison, Step 4 – Vendor
Selection and Negotiations, Step 5 – Purchase Order,
Step 6 – Vendor Evaluation. Receipt system can be
divided into 1.Receipt from outside suppliers
2.Receipts from internal divisions. Inspection can
happen in two ways 1. Pre- dispatch inspection 2.
inspection on the site. There are three methods of
inspection 1. Visual 2. Tactile 3. Statistical. Logistics
is a concept that emphasizes movement of materials.
Materials handling encompasses virtually all aspects
of all movements of raw materials, work in process,
or finished goods within a construction site. (G.
Kanimozhi et al. 2014, K V. Patel et al. 2011). For
effective material management the most important
materials management functions are (I) Primary
Functions is to meet the primary objectives, the
primary functions of the materials management are
A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64
www.ijera.com 61 | P a g e
given as materials requirements planning (MRP),
purchasing, inventory planning and control,
ascertaining and maintaining the flow and supply of
materials, quality control of materials, departmental
efficiency. (II) Secondary functions are
standardization and simplification, make and buy
decisions, coding and classification of materials,
forecasting and planning. (K V. Patel et al 2011).
Some other functions in context to material
management are: Project Acquisition Strategy,
Subcontracting, Expediting, Supplier Quality
Management .Site Materials Management, Materials
Management for Operations and Maintenance,
Implementing Materials Management Programs.
(Carlos H. Caldas et al. 2014). For effective
execution of material management following process
can be followed first of all material need generated
from site, then material ordered in store after that
indent is generated, then check availability in the
store after that check for the balance Items after that
vendor selection from the approved list then Material
Inspection from received stock at last issue of
material to the department. (Ashwini R. Patil et al.
2013). Implementation of IT in materials
management could facilitate the effective and
efficient control of materials on site reducing the
human efforts. Implementation of IT includes
construction materials planning system, material
handling equipment selection advisor, construction
materials exchange, and bar-code system (N.B.
Kasim et al.2005, 2014). Experimental
methodologies which can also be adopted for
management of construction materials are analysis of
site and management, analysis on inventory
controlling, analysis on purchasing procedures,
analysis on procurement and tracking, analysis on
costs. (T. Phani Madhavi et al. 2013.
IV. EXISTING SITUATION OF MATERIAL
MANAGEMENT
Research has shown that construction materials
and equipment may constitute more than 70% of the
total cost for a typical construction project (K V.
Patel et al. 2011, Pauline Jeruto Keitany et al. 2014).
In Indian construction industry currently manual
materials management practices and control
procedures are unsatisfactory as they are labour
intensive, inaccurate and error prone. All these
reasons leads to waste and surplus of construction
materials, delays in construction projects, decrease in
labour productivity and lack of up-to-date and real-
time information of the project. An initial assessment
of the tools and techniques currently in use in
materials management suggests that most of them are
under development with a few being used on a
commercial basis. (N.B. Kasim et al. 2012). New
emerging technologies such as wireless
communication system, bar-coding readers and Radio
Frequency Identification (RFID) are being adequately
used on site to overcome human error and are well
integrated with project management systems on
construction projects to make the tracking and
management of construction materials easier and
faster. (T. P. Madhavi et al. 2013, N. Kasim et al.
2013). It has found that scheduling delays occurred in
70%, 40% and 50% of government contracted
construction projects in the United Kingdom, India,
and United Arab Emirates (UAE) respectively due to
improper material management (G.Kanimozhi et al.
2014). Currently all over the globe the main reason in
cost variance and problematic management of
material are due to overstocked materials because of
improper planning, damaged materials due to
logistics, handling or in application, loss of materials
because of improper supervision, waiting of the
materials to arrive in location due to improper
tracking systems, frequent moving of materials due to
improper site layout, inflation, material changes in
buying/purchasing situation starting from the
prepared cost estimation, bulk construction material,
the shortages and changes of construction materials
quantity required, materials inefficiency on site,
stealing and loss of construction materials, material
shipment, work repairing, delay in updating/posting
storage system on site, inaccurate measurement of
work locationon construction projects, material off-
take, inaccurate estimation of shipment quantity of
materials, uneconomic order quantity of materials,
poor shipping time, inadequate tools/equipment
needed on site, increasing transportation cost of
materials, material over usage in location of project,
choosing the wrong materials for construction, the
increasing storage cost of materials, the poor buying
ability of managers, delay of payment for materials,
and the poor policy in purchasing the materials (Alin
Veronika et al. 2006, N. Kasim et al. 2013). It is
found out that administrative causes are 30% which
affects directly and 5% reasons due to unavailability
of material for faulty material management. “A”
category consists of 10% of total material involved in
construction but that cost 70% of the total cost. (T.
Phani Madhavi et al. 2013). Research has shown that
construction materials and handling equipment may
constitute more than 50% to 70% of the total cost for
a typical construction project. Firms employing
proper material management system are seen to have
increased their overall efficiency by 35%. (K V. Patel
et al. 2011).
V. CONSTRUCTION WASTE
MANAGEMENT
Construction waste consists of unwanted material
produced directly or incidentally by the construction
or industries. Construction and demolition waste is
generated whenever any construction/demolition
activity takes place (A.Harikumar et al. 2014).
A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64
www.ijera.com 62 | P a g e
Construction wastes in any project are in the form of
building debris form demolition process, rubble,
earth material, concrete waste, steel waste, timber
waste, and mixed site clearance construction
materials, arising from different construction
activities of project including land excavation or
formation on site, civil and building construction
materials, site clearance waste, demolition activities
waste, roadwork waste, and building renovation
waste. The management of construction wastes is a
global environmental issue experienced by countries
all over the world (L. Y. Shen et al. 2004, C. S. Poon
et al. 2013, Siti Akhtar Mahayuddin et al. 2013).
Vigorous literature review identified 81 factors for
causing construction waste and clustered in 7 groups
of factors namely design of project, handling of
construction materials and equipment, construction
workers, project management, site condition and
procurement of materials and external items (Ismail
Abdul Rahmana et al. 2013). The term “wastage”
refers to the variance if any between the estimated
and actual consumption of an individual item and
total factor consumption of all inputs in a
construction project. Material waste has been
recognized as a major problem in the construction
industry that has important implications both for the
efficiency of the industry and for the environmental
impact of construction projects. (S V. Desale et al.
2013, Jing Zhang et al. 2005). For managing the
waste their must be efficient waste management
system which can control the waste at source and
manage the waste at every stage or phase of
construction project (M D. Meghani et al. 2011, K R.
Kareem et al. 2013). Moreover, waste measurement
plays an important role in the management of
production systems since it is an effective way to
assess their performance. The increasing awareness
of environmental impacts from construction wastes
has led to the development of waste management as
an important function of construction project
management (Carlos T. Formoso et al. 2002). Waste
management in construction activities has been
promoted for the aim of protecting the environment
in line with the recognition that the wastes from
construction works contributes significantly to the
polluted environment (L. Y. Shen et al. 2004).
Various approaches for managing construction
wastes have been developed in the existing research
works and simultaneously practices, and these project
works can be grouped largely into three areas mainly
classification of waste, management strategies for
waste and disposal technologies for waste.
Construction activities generally have negative
effects on the environment, which includes the
exploitation of natural land and other resources for
development and the generation of waste and various
forms of pollution (Tam et al. 2005, 2006, Carlos T.
Formoso et al. 2002, S. Nagapan et al. 2012 ). Other
negative impacts to the environment are generation of
waste, ecological imbalance, changes in living
environment, sewage, reduction in environmental
resources and energy usage (Siti Akhtar Mahayuddin
et al. 2013). To reduce this impact on environment
construction practitioners need to determine
significant contributory factors of waste generation
before engaging with construction works (Ismail
Abdul Rahmana et al. 2013).
VI. CONTROL OF CONSTRUCTION WASTE
Reduction of waste can be done by practicing attitude
towards Zero wastage, proper decisions at design
stage, site management, proper standardization of
construction materials, and Codification of the same
(S. Sanmath 2011). Construction waste can also be
reduced by using waste management system on
project. The project activities are to be planned at
every stage by every construction personnel, who are
involved, in minimizing the overall waste generation
at project (J. Thomas et al. 2013). Waste rate
estimation method can be used to improve the
handling material, reduce the waste rate, and improve
productivity (A. Al-Hajj et al. 2011, M D. Meghani et
al. 2011). Concept of 3R and 4R can be also
beneficial to reduce the wastage of construction
materials, which includes reduce, reuse, recycle, and
recovery. These can be applied to the entire lifecycles
of products and services (K R. Kareem et al. 2013, J.
Thomas et al. 2013, Nitish Bagdi et al. 2013). The
free-flow mapping presentation technique can be
adopted in the study for investigating the waste flow
practice on construction sites. The technique has been
considered advantageous in presenting flows of
processes logically, clearly, and in the simplest way
(L. Y. Shen et al. 2004). The prediction of waste flow
can be modelled through the building elements at the
construction stages (Siti Akhtar Mahayuddin et al.
2013). For effective reduction of material waste
management strategy for construction waste can be
used such as reduce waste generation, maximize
reusing, and recycling, reduce the intake of mixed
construction waste at landfills. The use of
environmental friendly construction methods has
been encouraged, such as using a large panel system
on any project site, applying prefabrication
components for effectivity, and reducing the
application of wet trade (L. Y. Shen et al. 2004). A
management strategy for construction waste also
involves the maintenance of a well-managed public
filling programme with sufficient facilities and
access. Sort mixed construction waste and not just
dispose of it in any single place, reuse and recycle as
of materials as far as possible, design better and
construct more efficiently to minimize waste etc.
(A.Harikumar et al. 2014). Various strategies for
Construction and Demolition waste reduction also
include standardization of design, stock control for
A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64
www.ijera.com 63 | P a g e
minimization of over ordering, environmental
education to workforce etc. (N. Bagdi et al. 2013).
Government implemented construction waste
disposal charging scheme (CWDCS) can provide
financial incentives to C&D waste generators to
reduce waste and encourage reuse and recycling.
Government’s interventions like Landfill tax, higher
tax for using virgin construction materials, tax credits
for recycling etc can be used on construction site for
waste minimization (C. S. Poon et al. 2013, Mansi
Jain 2012).
VII. EXISTING SITUATION OF
CONSTRUCTION WASTE
Due to least priority given to appropriate site
waste minimization and management systems in
Indian construction industry leads to generation of
huge quantities of material waste every year.
Presently, awareness of resource-efficient
construction practices is lacking in most countries (J.
Thomas et al. 2013). Currently, existence of national
policies as well as the regional policies, laws and
regulations governing reuse and recycle principles for
construction waste is minimal as far as India is
consent (Mansi Jain. 2012). At present, private
contractors remove this waste to privately owned site,
low-lying land for a price purpose, or more
commonly dumping it in unauthorized manner along
roads or other public land or the region (A.Harikumar
et al. 2014). Central Pollution Control Board has
estimated current quantum of solid waste generation
in India to the tune of 48 million tons per annum of
which waste from Construction Industry accounts for
25% (A.Harikumar et al. 2014, B.Prakash Rao et al.
2014). Recent studies as in pointed out the waste
generated in China are around 40% and 39.27 million
tons in Spain. Malaysia and Singapore is facing the
problem of illegal dumping and the issue has become
more serious recently throughout the country.
According to government statistics, in Hong Kong,
soft inert materials (such as soil, earth, and slurry)
account for approximately 70% of all C&D waste,
which can only be reused as fill materials in
reclamation and earth filling works (C. S. Poon et al.
2013). Investment in construction accounts for nearly
11 per cent of India‟s Gross Domestic Product
(GDP) (Market, 2009). Technology Information,
Forecasting and Assessment Council (TIFAC) study
mentions that total construction work for five years
during 2006-2011 is equivalent to $847 billion.
Therefore material waste generation from
construction activity is also huge in monetary terms.
Statistical data shows, construction, and demolition
(C&D) debris frequently makes up to 30% of the
waste received at many landfill sites around the
world. (Mansi Jain, 2012). According to European
Topic Centre on Resource and Waste Management
(EIONET, 2006) construction and demolition waste
represents around 25% of all waste generated. Indian
buildings in 2013 must have generated more than 53
million tonnes. Demolitions of buildings generate
300-500 kg per sq meter (TIFAC. 2013).
Considerable research has been carried out in country
like United States of America, Japan, United
Kingdom, France, Germany, and Denmark etc. for
recycling of waste concrete from site, masonry, and
bricks, bituminous and other constituents of waste
from Construction Industry. These studies have
shown possibility of using construction waste to
substitute new materials of recycling. Today, in most
European countries, it is economically feasible to
recycle up to 80–90% of the total amount of
construction waste and most demolition and
recycling technologies are generally easy to
implement and control (J. Thomas et al. 2013, M.
Jain. 2012).
VIII. CONCLUSION
The systematic literature review identified that
Materials management processes require a
transformation to improve the overall in handling of
materials for more efficiency and effectiveness on the
construction site. This is because poor handling of
construction materials affects the overall performance
of construction projects in terms of cost, time,
quality, and productivity. From the literature review
it is understood that this area require further research
to find some feasible solutions to control the total
project cost. There is no proper system for
procurement of construction materials. This give light
to the fact that pre-planning and material
procurement are equally important in controlling the
total project cost. It reveals that the minimization of
materials wastage during the construction phases is
important in order to avoid loss of profits. It is
observed that considerable research has been
conducted to investigate individual construction
waste management strategies at a specific stage of a
construction project. Currently, the majority of
research efforts have been given to the material loss
in construction activities rather than the non-value-
adding work as an intangible waste. Waste
Generation Rate is an effective indicator for
measuring construction waste and benchmarking
construction waste management performance.
REFERENCES
Journal Papers:
[1] K.V. Patel, C.M. Vyas, Construction
Material Management on Project Sites,
National Conference on Recent Tends in
Engineering and Technology, 2011.
[2] M T. Phani, S V. Mathew and S. Roy,
Material Management in Construction – A
Case Study, International Journal of
A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64
www.ijera.com 64 | P a g e
Research in Engineering and Technology,
2013, pp. 400-403.
[3] K R. Kareem, R K. Pandey, Study of
Management and Control of Waste
Construction Materials in Civil Construction
Project, International Journal of Engineering
and Advance Technology, 2(3), 2013, pp.
345-350.
[4] A. Harikumar, M H.Shreejith, P A.Jacob
and S,Aiswarya, Minimizing Construction
Wastes By Efficient site practices,
International Journal of Education and
Applied Research, 4(2), 2014, PP. 46-48.
[5] G. Kanimozhi, P. Latha, Material
Management in Constuction Industry, Indian
Journal of Applied Research, 4(4), 2014, pp.
1-3 .
[6] S V. Desale, S V. Deodhar, Identification
And Eliminating Waste in Construction by
Using Lean and Six Sigma Principles,
International Journal of Innovative Research
in Science, Engineering and Technology,
3(4), 2014, pp. 285-296.
[7] A R. Patil, S V. Pataskar, Analyzing
Material Management Techniques on
Construction Project, International Journal
of Engineering and Innovative Technology.
3(4), 2013, pp. 96-100.

More Related Content

What's hot

IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkRicardo Magno Antunes
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET Journal
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET Journal
 
IRJET- Crisis Management in Constrution Projects
IRJET- Crisis Management in Constrution ProjectsIRJET- Crisis Management in Constrution Projects
IRJET- Crisis Management in Constrution ProjectsIRJET Journal
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET Journal
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial BuildingsIRJET Journal
 
IRJET- A Study on Productivity of Concreting Work in Building Construction in...
IRJET- A Study on Productivity of Concreting Work in Building Construction in...IRJET- A Study on Productivity of Concreting Work in Building Construction in...
IRJET- A Study on Productivity of Concreting Work in Building Construction in...IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Amit Kumbar
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET Journal
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regioneSAT Publishing House
 
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET Journal
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...IRJET Journal
 
022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)Dr Fereidoun Dejahang
 
Effect of ecodesign practices on the financial performance of manufacturing f...
Effect of ecodesign practices on the financial performance of manufacturing f...Effect of ecodesign practices on the financial performance of manufacturing f...
Effect of ecodesign practices on the financial performance of manufacturing f...Martin Otundo
 
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...IAEME Publication
 

What's hot (20)

IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction Projects
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
Labour productivity
Labour productivityLabour productivity
Labour productivity
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical Framework
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
IRJET- Crisis Management in Constrution Projects
IRJET- Crisis Management in Constrution ProjectsIRJET- Crisis Management in Constrution Projects
IRJET- Crisis Management in Constrution Projects
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial Buildings
 
IRJET- A Study on Productivity of Concreting Work in Building Construction in...
IRJET- A Study on Productivity of Concreting Work in Building Construction in...IRJET- A Study on Productivity of Concreting Work in Building Construction in...
IRJET- A Study on Productivity of Concreting Work in Building Construction in...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
 
022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)
 
Effect of ecodesign practices on the financial performance of manufacturing f...
Effect of ecodesign practices on the financial performance of manufacturing f...Effect of ecodesign practices on the financial performance of manufacturing f...
Effect of ecodesign practices on the financial performance of manufacturing f...
 
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...
BUILDING MATERIALS ASSESSMENT FOR SUSTAINABLE CONSTRUCTION BASED ON FIGURE OF...
 

Similar to Management for Construction Materials and Control of Construction Waste in Construction Industry: A Review

A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...IRJET Journal
 
IRJET- Efficient Techniques of Construction Material Management in Constr...
IRJET-  	  Efficient Techniques of Construction Material Management in Constr...IRJET-  	  Efficient Techniques of Construction Material Management in Constr...
IRJET- Efficient Techniques of Construction Material Management in Constr...IRJET Journal
 
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRYA REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRYIRJET Journal
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET Journal
 
Factors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction SiteFactors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction SiteIRJET Journal
 
Attitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials WastageAttitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials WastageIRJET Journal
 
Identification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIdentification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIRJET Journal
 
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET Journal
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfYohannesBizuneheWeld
 
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...Claire Webber
 
Evaluation of factors affecting residential building maintenance in nigeria u...
Evaluation of factors affecting residential building maintenance in nigeria u...Evaluation of factors affecting residential building maintenance in nigeria u...
Evaluation of factors affecting residential building maintenance in nigeria u...Alexander Decker
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET Journal
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET Journal
 
Application of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential BuildingApplication of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential BuildingIRJET Journal
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesIJERA Editor
 
An assessment of material management on building construction sites
An assessment of material management on building construction sitesAn assessment of material management on building construction sites
An assessment of material management on building construction sitesAlexander Decker
 

Similar to Management for Construction Materials and Control of Construction Waste in Construction Industry: A Review (20)

A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
 
IRJET- Efficient Techniques of Construction Material Management in Constr...
IRJET-  	  Efficient Techniques of Construction Material Management in Constr...IRJET-  	  Efficient Techniques of Construction Material Management in Constr...
IRJET- Efficient Techniques of Construction Material Management in Constr...
 
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRYA REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
Factors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction SiteFactors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction Site
 
Attitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials WastageAttitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials Wastage
 
Identification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIdentification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building Construction
 
D0482326
D0482326D0482326
D0482326
 
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
 
D013152126
D013152126D013152126
D013152126
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdf
 
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...
A Multi-Criteria Decision-Making Model To Choose The Best Option For Sustaina...
 
B1304021217
B1304021217B1304021217
B1304021217
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Evaluation of factors affecting residential building maintenance in nigeria u...
Evaluation of factors affecting residential building maintenance in nigeria u...Evaluation of factors affecting residential building maintenance in nigeria u...
Evaluation of factors affecting residential building maintenance in nigeria u...
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
Application of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential BuildingApplication of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential Building
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing Countries
 
An assessment of material management on building construction sites
An assessment of material management on building construction sitesAn assessment of material management on building construction sites
An assessment of material management on building construction sites
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 

Management for Construction Materials and Control of Construction Waste in Construction Industry: A Review

  • 1. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 59 | P a g e Management for Construction Materials and Control of Construction Waste in Construction Industry: A Review A. A. Gulghane1 , Prof P. V. Khandve2 1(Department of civil engineering, Prof Ram Meghe College of Engineering and Management, Sant Gadge Baba Amravati University, Badnera, India) 2 (Department of civil engineering, Prof Ram Meghe College of Engineering and Management, Sant Gadge Baba Amravati University, Badnera, India) ABSTRACT In recent treads a wide range of building materials is available for the construction of civil engineering structures. The total cost of materials may be up to 60% or more of the total cost incurred in construction project dependent upon the type of project. Effective construction materials management is a key to success for a construction project. Construction waste is another serious problem in construction industry. A large and various types of construction waste with different characteristics are created at all the stages of construction. Construction industries have a larger part in contributing environmental problems. The economic and environmental benefits must be gained from construction waste minimization. This paper presents a review on systematically investigation of the management of construction materials and construction waste, material management techniques, control of construction waste and existing situation of construction management and construction waste in the industry. Keywords - Material Management, Construction Waste, Management techniques, Economic relevance, Existing Situation. I. INTRODUCTION Construction industry is largest economic expenditure in India. According to eleventh five year plan, it is the second largest economic activity after agriculture. Materials management is an important element in project management. Effective construction materials management process is a key to success of a construction project. For many years it has evolved and changed with respect to the ever- growing complexity of projects. It is very important to understand the origin of materials management procedures and how these procedures differ from those of other industries. Materials constitute a major cost component for construction Industry. The total cost of materials may be 60% or more of the total cost incurred in construction project dependent upon the type of project and the extent of mechanisation and plant used (K V. Patel et al. 2011). Such a large investment requires considerable planning and control so as to minimize wastage which invariably affects the performance of the organization. Materials management is a coordinating function responsible for planning and controlling materials flow. One of the major problems in delaying construction projects is poor materials management. Ensuring a timely flow of materials is an important concern of material management. The management of procuring materials is critical as any materials surpluses or shortages will delay the project and put it at risk. This then affects the maintenance of a consistent flow of materials for production, thus affecting the overall project. Materials Management is simply the process by which an organization is supplied with the goods and services that it needs to achieve its objectives of buying, storage and movement of materials. Basically, material management is concerned with the planning, identification, procuring, storage, receiving, and distribution of materials. The purpose of material management is to assure that the right materials are in the right place, in the right quantities when needed. The increased economic growth as well as urbanization has led into extensive construction activities that generate large amounts of construction wastes. All round the world construction materials generate million tons of waste annually. Waste is one of the serious problems in construction industry. The term wastage refers to the variance, if any between the estimated and actual consumption of an individual item. Some hazardous materials may not be moved, before the authorities have ascertained that safety guidelines and restrictions have been followed. Hence proper management of waste materials from construction sites has now become very crucial. Managing waste means that eliminating waste wherever possible, minimizing waste wherever feasible and reusing materials which could otherwise become waste. A large and various types of waste with different characteristics are created at all the stages of construction right from site preparation, demolition of existing structures to final product. The exact quantity and composition of construction waste RESEARCH ARTICLE OPEN ACCESS
  • 2. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 60 | P a g e generated throughout the projects are difficult to be identified as they are keep on changing due to the dynamic nature of the construction activities. A different stage of construction generates different types and composition of waste. However, the generation of construction waste is predictable based on the building design and procurement of the building materials. The nature of waste composition might be different at various construction stages. Thus waste generation throughout the construction stages needs to be identified and quantified to minimize the wastage. II. MANAGEMENT OF CONSTRUCTION MATERIALS An essential factor adversely affecting the performance of construction projects is the improper management of materials during site activities (N B. Kasim. 2008). Material is the main component in any of the construction projects. Therefore, if the material management in construction projects is not managed properly it will create a major project cost variance. The total cost of the project can be well controlled by taking corrective actions towards the cost variance occur in the project. (T. Phani Madhavi et al. 2013, Alin Veronika et al. 2006). Studies by the Construction Industry Institute (CII) have shown that materials and installed equipment can make up 50– 60%of the total project cost and impact 80%of its schedule (C H. Caldas et al. 2014). During the last few years, enormous growth in infrastructure has been found, by wide range of diversity construction organization (S V. Desale et al. 2013). Fundamental Principles of Site Material Management enlightens the factors considered during site layout and planning for efficient material management. Ineffective material management practices are evident on many projects and cause considerable waste in time and money. (H. Randolph et al. 2005, Pauline Jeruto Keitany et al. 2014). For managing a productive and cost efficient site efficient material management is very essential. The materials management system in any project insure that the right quality of material and quantity of materials are appropriately selected, effectively purchased, properly delivered and safely handled on site in a timely manner and at a proper reasonable cost. (G.Kanimozhi et al, 2014, S. Donyavi et al. 2009). Any organizations need to put their effects for proper materials management techniques for the effectiveness of project execution. Material management involves storage, identification, retrieval, transport, and construction methods. Each of above is indelibly linked to ensure safety, productivity, and schedule performance. According to Kini (1999), materials management is an indispensable part of the project management which can be integrated with engineering to provide an end product that meets the client’s requirements and is cost effective. Over the years, materials management in any construction project has become a critical component of successful project execution. (Carlos H. Caldas et al, 2014, C.K.Georgekutty et al. 2012). There should be a centralised material management team co-ordination between the site and the organization so that effective material management strategies can be applied and monitored. Construction materials management may present similarities at the conceptual level but the implementation details vary. Material planning considers materials in the order of requirement at site (S V. Desale et al. 2013). Material procurement and storage on construction sites need to be properly planned and executed to avoid the negative impacts of material shortage or excessive material inventory on-site deficiencies in the supply and flow of construction material were often cited as major causes of productivity degradation and financial losses (G.Kanimozhim et al. 2014). It is observed that construction materials are less homogeneous, less standardized, and more numerous than those of manufacturing, and that the characteristics of demand are different. Their should be awareness about material planning & scheduling at every stage of material management. (A R. Patil et al, 2013). III. MATERIAL MANAGEMENT TECHNIQUES Materials management is categorized to 5 processes these processes are majorly followed on construction site they are namely 1.Planning, 2.Procurement, 3.Logistics, 4.Handling 5.Waste control processes. Materials planning include quantifying, ordering and scheduling. Companies may have two major levels in planning- micro and macro level. Procurement is described as the purchase of materials and services from outside organizations. (N. Kasim. 2011, C H. Caldas et al. 2014). Purchasing procedure can be described as Step 1 – Material Indent, Step 2 – Enquiry to Vendors, Step 3 – Vendor Comparison, Step 4 – Vendor Selection and Negotiations, Step 5 – Purchase Order, Step 6 – Vendor Evaluation. Receipt system can be divided into 1.Receipt from outside suppliers 2.Receipts from internal divisions. Inspection can happen in two ways 1. Pre- dispatch inspection 2. inspection on the site. There are three methods of inspection 1. Visual 2. Tactile 3. Statistical. Logistics is a concept that emphasizes movement of materials. Materials handling encompasses virtually all aspects of all movements of raw materials, work in process, or finished goods within a construction site. (G. Kanimozhi et al. 2014, K V. Patel et al. 2011). For effective material management the most important materials management functions are (I) Primary Functions is to meet the primary objectives, the primary functions of the materials management are
  • 3. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 61 | P a g e given as materials requirements planning (MRP), purchasing, inventory planning and control, ascertaining and maintaining the flow and supply of materials, quality control of materials, departmental efficiency. (II) Secondary functions are standardization and simplification, make and buy decisions, coding and classification of materials, forecasting and planning. (K V. Patel et al 2011). Some other functions in context to material management are: Project Acquisition Strategy, Subcontracting, Expediting, Supplier Quality Management .Site Materials Management, Materials Management for Operations and Maintenance, Implementing Materials Management Programs. (Carlos H. Caldas et al. 2014). For effective execution of material management following process can be followed first of all material need generated from site, then material ordered in store after that indent is generated, then check availability in the store after that check for the balance Items after that vendor selection from the approved list then Material Inspection from received stock at last issue of material to the department. (Ashwini R. Patil et al. 2013). Implementation of IT in materials management could facilitate the effective and efficient control of materials on site reducing the human efforts. Implementation of IT includes construction materials planning system, material handling equipment selection advisor, construction materials exchange, and bar-code system (N.B. Kasim et al.2005, 2014). Experimental methodologies which can also be adopted for management of construction materials are analysis of site and management, analysis on inventory controlling, analysis on purchasing procedures, analysis on procurement and tracking, analysis on costs. (T. Phani Madhavi et al. 2013. IV. EXISTING SITUATION OF MATERIAL MANAGEMENT Research has shown that construction materials and equipment may constitute more than 70% of the total cost for a typical construction project (K V. Patel et al. 2011, Pauline Jeruto Keitany et al. 2014). In Indian construction industry currently manual materials management practices and control procedures are unsatisfactory as they are labour intensive, inaccurate and error prone. All these reasons leads to waste and surplus of construction materials, delays in construction projects, decrease in labour productivity and lack of up-to-date and real- time information of the project. An initial assessment of the tools and techniques currently in use in materials management suggests that most of them are under development with a few being used on a commercial basis. (N.B. Kasim et al. 2012). New emerging technologies such as wireless communication system, bar-coding readers and Radio Frequency Identification (RFID) are being adequately used on site to overcome human error and are well integrated with project management systems on construction projects to make the tracking and management of construction materials easier and faster. (T. P. Madhavi et al. 2013, N. Kasim et al. 2013). It has found that scheduling delays occurred in 70%, 40% and 50% of government contracted construction projects in the United Kingdom, India, and United Arab Emirates (UAE) respectively due to improper material management (G.Kanimozhi et al. 2014). Currently all over the globe the main reason in cost variance and problematic management of material are due to overstocked materials because of improper planning, damaged materials due to logistics, handling or in application, loss of materials because of improper supervision, waiting of the materials to arrive in location due to improper tracking systems, frequent moving of materials due to improper site layout, inflation, material changes in buying/purchasing situation starting from the prepared cost estimation, bulk construction material, the shortages and changes of construction materials quantity required, materials inefficiency on site, stealing and loss of construction materials, material shipment, work repairing, delay in updating/posting storage system on site, inaccurate measurement of work locationon construction projects, material off- take, inaccurate estimation of shipment quantity of materials, uneconomic order quantity of materials, poor shipping time, inadequate tools/equipment needed on site, increasing transportation cost of materials, material over usage in location of project, choosing the wrong materials for construction, the increasing storage cost of materials, the poor buying ability of managers, delay of payment for materials, and the poor policy in purchasing the materials (Alin Veronika et al. 2006, N. Kasim et al. 2013). It is found out that administrative causes are 30% which affects directly and 5% reasons due to unavailability of material for faulty material management. “A” category consists of 10% of total material involved in construction but that cost 70% of the total cost. (T. Phani Madhavi et al. 2013). Research has shown that construction materials and handling equipment may constitute more than 50% to 70% of the total cost for a typical construction project. Firms employing proper material management system are seen to have increased their overall efficiency by 35%. (K V. Patel et al. 2011). V. CONSTRUCTION WASTE MANAGEMENT Construction waste consists of unwanted material produced directly or incidentally by the construction or industries. Construction and demolition waste is generated whenever any construction/demolition activity takes place (A.Harikumar et al. 2014).
  • 4. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 62 | P a g e Construction wastes in any project are in the form of building debris form demolition process, rubble, earth material, concrete waste, steel waste, timber waste, and mixed site clearance construction materials, arising from different construction activities of project including land excavation or formation on site, civil and building construction materials, site clearance waste, demolition activities waste, roadwork waste, and building renovation waste. The management of construction wastes is a global environmental issue experienced by countries all over the world (L. Y. Shen et al. 2004, C. S. Poon et al. 2013, Siti Akhtar Mahayuddin et al. 2013). Vigorous literature review identified 81 factors for causing construction waste and clustered in 7 groups of factors namely design of project, handling of construction materials and equipment, construction workers, project management, site condition and procurement of materials and external items (Ismail Abdul Rahmana et al. 2013). The term “wastage” refers to the variance if any between the estimated and actual consumption of an individual item and total factor consumption of all inputs in a construction project. Material waste has been recognized as a major problem in the construction industry that has important implications both for the efficiency of the industry and for the environmental impact of construction projects. (S V. Desale et al. 2013, Jing Zhang et al. 2005). For managing the waste their must be efficient waste management system which can control the waste at source and manage the waste at every stage or phase of construction project (M D. Meghani et al. 2011, K R. Kareem et al. 2013). Moreover, waste measurement plays an important role in the management of production systems since it is an effective way to assess their performance. The increasing awareness of environmental impacts from construction wastes has led to the development of waste management as an important function of construction project management (Carlos T. Formoso et al. 2002). Waste management in construction activities has been promoted for the aim of protecting the environment in line with the recognition that the wastes from construction works contributes significantly to the polluted environment (L. Y. Shen et al. 2004). Various approaches for managing construction wastes have been developed in the existing research works and simultaneously practices, and these project works can be grouped largely into three areas mainly classification of waste, management strategies for waste and disposal technologies for waste. Construction activities generally have negative effects on the environment, which includes the exploitation of natural land and other resources for development and the generation of waste and various forms of pollution (Tam et al. 2005, 2006, Carlos T. Formoso et al. 2002, S. Nagapan et al. 2012 ). Other negative impacts to the environment are generation of waste, ecological imbalance, changes in living environment, sewage, reduction in environmental resources and energy usage (Siti Akhtar Mahayuddin et al. 2013). To reduce this impact on environment construction practitioners need to determine significant contributory factors of waste generation before engaging with construction works (Ismail Abdul Rahmana et al. 2013). VI. CONTROL OF CONSTRUCTION WASTE Reduction of waste can be done by practicing attitude towards Zero wastage, proper decisions at design stage, site management, proper standardization of construction materials, and Codification of the same (S. Sanmath 2011). Construction waste can also be reduced by using waste management system on project. The project activities are to be planned at every stage by every construction personnel, who are involved, in minimizing the overall waste generation at project (J. Thomas et al. 2013). Waste rate estimation method can be used to improve the handling material, reduce the waste rate, and improve productivity (A. Al-Hajj et al. 2011, M D. Meghani et al. 2011). Concept of 3R and 4R can be also beneficial to reduce the wastage of construction materials, which includes reduce, reuse, recycle, and recovery. These can be applied to the entire lifecycles of products and services (K R. Kareem et al. 2013, J. Thomas et al. 2013, Nitish Bagdi et al. 2013). The free-flow mapping presentation technique can be adopted in the study for investigating the waste flow practice on construction sites. The technique has been considered advantageous in presenting flows of processes logically, clearly, and in the simplest way (L. Y. Shen et al. 2004). The prediction of waste flow can be modelled through the building elements at the construction stages (Siti Akhtar Mahayuddin et al. 2013). For effective reduction of material waste management strategy for construction waste can be used such as reduce waste generation, maximize reusing, and recycling, reduce the intake of mixed construction waste at landfills. The use of environmental friendly construction methods has been encouraged, such as using a large panel system on any project site, applying prefabrication components for effectivity, and reducing the application of wet trade (L. Y. Shen et al. 2004). A management strategy for construction waste also involves the maintenance of a well-managed public filling programme with sufficient facilities and access. Sort mixed construction waste and not just dispose of it in any single place, reuse and recycle as of materials as far as possible, design better and construct more efficiently to minimize waste etc. (A.Harikumar et al. 2014). Various strategies for Construction and Demolition waste reduction also include standardization of design, stock control for
  • 5. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 63 | P a g e minimization of over ordering, environmental education to workforce etc. (N. Bagdi et al. 2013). Government implemented construction waste disposal charging scheme (CWDCS) can provide financial incentives to C&D waste generators to reduce waste and encourage reuse and recycling. Government’s interventions like Landfill tax, higher tax for using virgin construction materials, tax credits for recycling etc can be used on construction site for waste minimization (C. S. Poon et al. 2013, Mansi Jain 2012). VII. EXISTING SITUATION OF CONSTRUCTION WASTE Due to least priority given to appropriate site waste minimization and management systems in Indian construction industry leads to generation of huge quantities of material waste every year. Presently, awareness of resource-efficient construction practices is lacking in most countries (J. Thomas et al. 2013). Currently, existence of national policies as well as the regional policies, laws and regulations governing reuse and recycle principles for construction waste is minimal as far as India is consent (Mansi Jain. 2012). At present, private contractors remove this waste to privately owned site, low-lying land for a price purpose, or more commonly dumping it in unauthorized manner along roads or other public land or the region (A.Harikumar et al. 2014). Central Pollution Control Board has estimated current quantum of solid waste generation in India to the tune of 48 million tons per annum of which waste from Construction Industry accounts for 25% (A.Harikumar et al. 2014, B.Prakash Rao et al. 2014). Recent studies as in pointed out the waste generated in China are around 40% and 39.27 million tons in Spain. Malaysia and Singapore is facing the problem of illegal dumping and the issue has become more serious recently throughout the country. According to government statistics, in Hong Kong, soft inert materials (such as soil, earth, and slurry) account for approximately 70% of all C&D waste, which can only be reused as fill materials in reclamation and earth filling works (C. S. Poon et al. 2013). Investment in construction accounts for nearly 11 per cent of India‟s Gross Domestic Product (GDP) (Market, 2009). Technology Information, Forecasting and Assessment Council (TIFAC) study mentions that total construction work for five years during 2006-2011 is equivalent to $847 billion. Therefore material waste generation from construction activity is also huge in monetary terms. Statistical data shows, construction, and demolition (C&D) debris frequently makes up to 30% of the waste received at many landfill sites around the world. (Mansi Jain, 2012). According to European Topic Centre on Resource and Waste Management (EIONET, 2006) construction and demolition waste represents around 25% of all waste generated. Indian buildings in 2013 must have generated more than 53 million tonnes. Demolitions of buildings generate 300-500 kg per sq meter (TIFAC. 2013). Considerable research has been carried out in country like United States of America, Japan, United Kingdom, France, Germany, and Denmark etc. for recycling of waste concrete from site, masonry, and bricks, bituminous and other constituents of waste from Construction Industry. These studies have shown possibility of using construction waste to substitute new materials of recycling. Today, in most European countries, it is economically feasible to recycle up to 80–90% of the total amount of construction waste and most demolition and recycling technologies are generally easy to implement and control (J. Thomas et al. 2013, M. Jain. 2012). VIII. CONCLUSION The systematic literature review identified that Materials management processes require a transformation to improve the overall in handling of materials for more efficiency and effectiveness on the construction site. This is because poor handling of construction materials affects the overall performance of construction projects in terms of cost, time, quality, and productivity. From the literature review it is understood that this area require further research to find some feasible solutions to control the total project cost. There is no proper system for procurement of construction materials. This give light to the fact that pre-planning and material procurement are equally important in controlling the total project cost. It reveals that the minimization of materials wastage during the construction phases is important in order to avoid loss of profits. It is observed that considerable research has been conducted to investigate individual construction waste management strategies at a specific stage of a construction project. Currently, the majority of research efforts have been given to the material loss in construction activities rather than the non-value- adding work as an intangible waste. Waste Generation Rate is an effective indicator for measuring construction waste and benchmarking construction waste management performance. REFERENCES Journal Papers: [1] K.V. Patel, C.M. Vyas, Construction Material Management on Project Sites, National Conference on Recent Tends in Engineering and Technology, 2011. [2] M T. Phani, S V. Mathew and S. Roy, Material Management in Construction – A Case Study, International Journal of
  • 6. A. A. Gulghane et al. Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64 www.ijera.com 64 | P a g e Research in Engineering and Technology, 2013, pp. 400-403. [3] K R. Kareem, R K. Pandey, Study of Management and Control of Waste Construction Materials in Civil Construction Project, International Journal of Engineering and Advance Technology, 2(3), 2013, pp. 345-350. [4] A. Harikumar, M H.Shreejith, P A.Jacob and S,Aiswarya, Minimizing Construction Wastes By Efficient site practices, International Journal of Education and Applied Research, 4(2), 2014, PP. 46-48. [5] G. Kanimozhi, P. Latha, Material Management in Constuction Industry, Indian Journal of Applied Research, 4(4), 2014, pp. 1-3 . [6] S V. Desale, S V. Deodhar, Identification And Eliminating Waste in Construction by Using Lean and Six Sigma Principles, International Journal of Innovative Research in Science, Engineering and Technology, 3(4), 2014, pp. 285-296. [7] A R. Patil, S V. Pataskar, Analyzing Material Management Techniques on Construction Project, International Journal of Engineering and Innovative Technology. 3(4), 2013, pp. 96-100.