Syllabus
∗ Roads constructed in mountainous region is called Hill roads.
∗ There are different considerations while designing hill roads as
compare to plain area roads.
∗ Types of curve used in hill roads is of different than plain road.
∗ All Geometric parameters will gets changes while designing hill roads
such as- Curves , Superelevation,SSD,OSD,Extra Widening etc.
3
5.1 Introduction
4
5.2 Components parts of Hill Roads
∗ Road Bed
∗ Side Drain
∗ Parapet wall
∗ Catch Water Drains
∗ Brest wall
∗ Retaining wall
∗ Cross Drains
A) Road Bed:-
The pavement potion of hill road is called Road bed.
Function: To Resist stresses developed due to moving traffic.
B) Side Drain :-
-Drain Provided on the sides of road is called side drain
- Side Drains Runs Parallel to the length of road.
Function: To collect and drain off rain water collected from camber o of road.
5
Continue.
C) Parapet Wall:
wall which is provided above the formation level in the down side slope is called
parapet wall.
Function: Protection to the traffic against falling down the hill slope.
D) Catch Water Drain:
It is drain provided on higher slope running parallel to the length of road.
Function : To make intercept for runoff coming from top of hill and divert water in to
near by cross drains.
E) Brest wall :
The wall constructed to up side slope is called Brest wall.
Function: Protect road from sliding of up side slope.
F) Retaining Wall:
The wall constructed to down side slope of road is called retaining wall.
Function: -To Protect down side slope from sliding.
-To Resist pressure of earth fill .
6
Continue.
G) Cross Drains:
The drains which is laid along width of road is called cross drains.
Function: To drain off rain water collected in side drains and catch drains.
7
Continue.
1.Length of Road:
Alignment of road should be short as possible bcoz cost will be increased as length of
road increases.
2.Geometrical Standards:
-Alignment of road should have proper geometrical standards such as
Gradient,Curves,SD,Radious of curves.
- Min. Radius of curve for hill road is allowed to 50m.
3.Existing Saddle or Pass:
Alignment of road should not pass through ridge line of hill to avoid extra cutting and
filling.
Alignment should passes through series of hills through existing saddle points.
8
Factors controlling Alignment of Hill Road .
4.Drainage Line:
Alignment of road should be parallel to drainage line to avoid no of cross
drainage drains.
5. Stability:
Alignment of road should passes along the stable and side having mild slope of
hill road.
6.Altitude:
-Altitude of road should not be passes through high altitude as well as low
altitude .
-High Altitude causes problem of snow falling and low altitude will increase no.
of cross drains.
-Alignment of road passes through altitude between 900 to 1500m.
-Alignment of road should faces sun and not located in windward side of hill
9
Factors controlling Alignment of Hill Road .
7.Cutting through Rocks:
Alignment of road should not passes through solid rocks to avoid cost of
cutting.
10
Factors controlling Alignment of Hill Road .
Alignment of Hill roads is fixed in three stages:
1. Reconnaissance
2. Trace out
3. Detailed Survey.
1.1.Reconnaissance:Reconnaissance:
-The temporary alignment of road is fixed during reconnaissance
survey by studying topographical, geographical and metrological
maps of the area .
-Arial survey is carried out for remote area.
2.Trace out :.Trace out :
-The route selected during reconnaissance survey is translated on
ground so as to collect details from actual site.
11
Alignment Survey Of Hill Road:-
- 1 to 1.5 m wide track is constructed so as to collect details.
3.Detailed Survey:3.Detailed Survey:
--During Detailed survey BM are fixed on ground.
-Prepare c/s Along length and along width.
-Mark the center line and boundary line of highway.
-Hydrological and soil investigation is carried out.
12
Cont.
1.Rock Cutting
2. Vertical Cutting (Precipice work)
3.Retaining wall
4. Foundation of Retaining wall
5.Revetment wall
6.Pavement Construction
13
Construction procedure of Hill Road
There are main three types of cures used in hill road curvesThere are main three types of cures used in hill road curves
1.1.Hair Pin CurveHair Pin Curve
2.2.Salient curvesSalient curves
3.3.Re-entrant curvesRe-entrant curves
Hair Pin Curve:Hair Pin Curve:
The curve on hill road which changes its direction through 180 deg.The curve on hill road which changes its direction through 180 deg.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
14
Types of Hill Road CurvesTypes of Hill Road Curves
 Salient curves:Salient curves:
Curve having their convexity on the outer edge of hill road .Curve having their convexity on the outer edge of hill road .
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
15
Re-entrant curves:Re-entrant curves:
Curve having convexity on the inner edge of hill road.Curve having convexity on the inner edge of hill road.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
16
∗ Formation of hill road done in following situation
1.Wholly in cutting
2.Partially in cutting and partially in embankment.
3.Wholly in embankment.
Wholly in cutting:Wholly in cutting:
Formation width of pavement of hill road is constructed fully inFormation width of pavement of hill road is constructed fully in
cutting .cutting .
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
17
Formation of Hill RoadFormation of Hill Road
 Partially in cutting and partially in embankment.Partially in cutting and partially in embankment.
Formation width of hill road is constructed partly in cutting andFormation width of hill road is constructed partly in cutting and
partly in embankment .partly in embankment .
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
18
Wholly in embankment:Wholly in embankment:
Formation width of hill road constructed fully inFormation width of hill road constructed fully in
filling(embankment)filling(embankment)
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
19
Definition:
The Downward movement of soil mass or rock along the slope due to gravity isThe Downward movement of soil mass or rock along the slope due to gravity is
called landslide.called landslide.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
20
LandslideLandslide
 Free Fall Landslide
 Toppled Landslide
 Slide Landslide
 Flow Landslide
 Complex Landslides
1.Free Fall Landslide:1.Free Fall Landslide:
When there is free fall or rolling of rocks and soil mass alongWhen there is free fall or rolling of rocks and soil mass along
the slope then it is called free fall landslide.the slope then it is called free fall landslide.
Types of LandslideTypes of Landslide
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
21
2.Toppled Landslide:2.Toppled Landslide:
Topples are nothing but overturning or forward rotation of rockTopples are nothing but overturning or forward rotation of rock
bed along slope .bed along slope .
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
22
3.Slide Landslide:3.Slide Landslide:
The downward movement of soil mass or rock along failureThe downward movement of soil mass or rock along failure
plane of downward slope.plane of downward slope.
1.Rotational landslide1.Rotational landslide
Rotational landslide is theRotational landslide is the
downward and outward movementdownward and outward movement
of a mass on top of a concaveof a mass on top of a concave
upward failure surfaceupward failure surface
2.Translational landslide2.Translational landslide
Movement of soil in translationalMovement of soil in translational
form along inclined failure plane dueform along inclined failure plane due
to less shear stress between twoto less shear stress between two
surfacesurface
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
23
4.Complex Landslide:4.Complex Landslide:
When there is combined effect of two or more landslideWhen there is combined effect of two or more landslide
then it is called as complex landslide.then it is called as complex landslide.
- It is the combonination of two or more landslide- It is the combonination of two or more landslide
mentioned above.mentioned above.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
24
Natural Causes of Landslides
Climate- Heavy Rainfall.
Geology and topography
Earthquakes
Weathering of rock
Erosion of soil and rock
Volcanoes
Forest fires
Human causes of landslides
Mining
Blasting
Increase in traffic load.
Causes of LandslideCauses of Landslide
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
25
Lead to economic declination or loss
Damage of infrastructure
Loss of life
Affects beauty of landscapes
Impacts on river ecosystems
Effect of LandslideEffect of Landslide
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
26
 Provide benching on side slope
 By providing proper drainage system.
 By constructing retaining wall and breast wall.
 By Soil stabilization techniques.
 By cement grouting or concrete lining.
 By rock nailing.
 By increasing vegetation on side slope.
 By fixing geosynthetic net on sloping side.
Prevention of LandslidePrevention of Landslide
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
27
Retaining wall
Constructed to prevent falling of soil
mass or rock on road surface or low
laying area.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
28
Vegetation on steep
slope
It helps to protect soil erosion.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
29
Rock nailing
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
30
Short -Crete technique
In this technique the cement mortar
is applied on unstable slope with high
pressure by using concrete Gun.
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
31
Grouting
In this method of prevention of
landslide the pressure chemical grout
is pressed in to cracks to make stable
Copyright © 2013 The McGraw-Hill Companies, Inc. Permission
required for reproduction or display.
32

More Related Content

What's hot

11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layoutsMani Vel
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway linesMani Vel
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component Sumit Kumar
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the trackT.Naga Anusha
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry DesignNachiketa Mithaiwala
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdfEr. Bam Bhandari
 
Transportation and highway engineering part 1
Transportation and highway engineering part 1 Transportation and highway engineering part 1
Transportation and highway engineering part 1 GEOMIND
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanencekrishnacp
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Hill road construction
Hill road constructionHill road construction
Hill road constructionGeet KH
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 

What's hot (20)

Hill roads
Hill roadsHill roads
Hill roads
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
5. Hill Roads.pdf
5. Hill Roads.pdf5. Hill Roads.pdf
5. Hill Roads.pdf
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry Design
 
Intersection,types
Intersection,typesIntersection,types
Intersection,types
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdf
 
Transportation and highway engineering part 1
Transportation and highway engineering part 1 Transportation and highway engineering part 1
Transportation and highway engineering part 1
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Hill road construction
Hill road constructionHill road construction
Hill road construction
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Road construction
Road constructionRoad construction
Road construction
 

Similar to Hill roads and Drainage

Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptswaongniyogi
 
CEN530_SlopeStability_Chapter1_Introduction.pdf
CEN530_SlopeStability_Chapter1_Introduction.pdfCEN530_SlopeStability_Chapter1_Introduction.pdf
CEN530_SlopeStability_Chapter1_Introduction.pdfDaliaAbdelMassih1
 
R16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesR16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesPoorna Nagidi
 
Hill road ppt
Hill road pptHill road ppt
Hill road pptPadduS
 
hillroads-200131051526.pptx
hillroads-200131051526.pptxhillroads-200131051526.pptx
hillroads-200131051526.pptxDESHANTAGGARWAL1
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highwayholegajendra
 
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxDESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxSamirsinh Parmar
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnelspartha sharma
 
Embankment dam by sitaram saini
Embankment dam by sitaram sainiEmbankment dam by sitaram saini
Embankment dam by sitaram sainiSitaramSaini11
 
316823403-5-Hill-Roads-073-old-pptx (1).pptx
316823403-5-Hill-Roads-073-old-pptx (1).pptx316823403-5-Hill-Roads-073-old-pptx (1).pptx
316823403-5-Hill-Roads-073-old-pptx (1).pptxecep nurali
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisationselvem
 

Similar to Hill roads and Drainage (20)

chapter 8.pptx
chapter 8.pptxchapter 8.pptx
chapter 8.pptx
 
chapter 8.pptx
chapter 8.pptxchapter 8.pptx
chapter 8.pptx
 
chapter 8.pptx
chapter 8.pptxchapter 8.pptx
chapter 8.pptx
 
Geology presentation
Geology presentationGeology presentation
Geology presentation
 
Geology presentation Nutech
Geology presentation NutechGeology presentation Nutech
Geology presentation Nutech
 
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
 
Highway pdf
Highway pdfHighway pdf
Highway pdf
 
CEN530_SlopeStability_Chapter1_Introduction.pdf
CEN530_SlopeStability_Chapter1_Introduction.pdfCEN530_SlopeStability_Chapter1_Introduction.pdf
CEN530_SlopeStability_Chapter1_Introduction.pdf
 
R16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopesR16 41013.2 stability analysis of slopes
R16 41013.2 stability analysis of slopes
 
Hill road ppt
Hill road pptHill road ppt
Hill road ppt
 
hillroads-200131051526.pptx
hillroads-200131051526.pptxhillroads-200131051526.pptx
hillroads-200131051526.pptx
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxDESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
 
Slopestability
SlopestabilitySlopestability
Slopestability
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
 
Embankment dam by sitaram saini
Embankment dam by sitaram sainiEmbankment dam by sitaram saini
Embankment dam by sitaram saini
 
316823403-5-Hill-Roads-073-old-pptx (1).pptx
316823403-5-Hill-Roads-073-old-pptx (1).pptx316823403-5-Hill-Roads-073-old-pptx (1).pptx
316823403-5-Hill-Roads-073-old-pptx (1).pptx
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisation
 

More from holegajendra

PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxholegajendra
 
4. traffic engineering
4. traffic engineering4. traffic engineering
4. traffic engineeringholegajendra
 
Introduction to Hydrology
Introduction to HydrologyIntroduction to Hydrology
Introduction to Hydrologyholegajendra
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)holegajendra
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineeringholegajendra
 
Application of GIS and RS in Watershed Management
Application of GIS and RS in Watershed ManagementApplication of GIS and RS in Watershed Management
Application of GIS and RS in Watershed Managementholegajendra
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gatesholegajendra
 
Diversion Headwork in Canal
 Diversion Headwork in Canal  Diversion Headwork in Canal
Diversion Headwork in Canal holegajendra
 
Maintenence of road
Maintenence of roadMaintenence of road
Maintenence of roadholegajendra
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work holegajendra
 

More from holegajendra (11)

PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
 
4. traffic engineering
4. traffic engineering4. traffic engineering
4. traffic engineering
 
Introduction to Hydrology
Introduction to HydrologyIntroduction to Hydrology
Introduction to Hydrology
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineering
 
Application of GIS and RS in Watershed Management
Application of GIS and RS in Watershed ManagementApplication of GIS and RS in Watershed Management
Application of GIS and RS in Watershed Management
 
Dam engineering
Dam engineeringDam engineering
Dam engineering
 
Spillway and gates
Spillway and gatesSpillway and gates
Spillway and gates
 
Diversion Headwork in Canal
 Diversion Headwork in Canal  Diversion Headwork in Canal
Diversion Headwork in Canal
 
Maintenence of road
Maintenence of roadMaintenence of road
Maintenence of road
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 

Hill roads and Drainage

  • 1. Unit-IVUnit-IV Hill Roads And DrainageHill Roads And Drainage ByBy Mr. Hole G.R.Mr. Hole G.R. (Lecturer in Civil Department)(Lecturer in Civil Department) Jayawantrao Sawant PolytechnicJayawantrao Sawant Polytechnic 1
  • 2. Unit-IV Hill Roads And DrainageHill Roads And Drainage Total Hrs.:-06 Hrs. Total Marks=10 Marks 2 Syllabus
  • 3. ∗ Roads constructed in mountainous region is called Hill roads. ∗ There are different considerations while designing hill roads as compare to plain area roads. ∗ Types of curve used in hill roads is of different than plain road. ∗ All Geometric parameters will gets changes while designing hill roads such as- Curves , Superelevation,SSD,OSD,Extra Widening etc. 3 5.1 Introduction
  • 4. 4 5.2 Components parts of Hill Roads
  • 5. ∗ Road Bed ∗ Side Drain ∗ Parapet wall ∗ Catch Water Drains ∗ Brest wall ∗ Retaining wall ∗ Cross Drains A) Road Bed:- The pavement potion of hill road is called Road bed. Function: To Resist stresses developed due to moving traffic. B) Side Drain :- -Drain Provided on the sides of road is called side drain - Side Drains Runs Parallel to the length of road. Function: To collect and drain off rain water collected from camber o of road. 5 Continue.
  • 6. C) Parapet Wall: wall which is provided above the formation level in the down side slope is called parapet wall. Function: Protection to the traffic against falling down the hill slope. D) Catch Water Drain: It is drain provided on higher slope running parallel to the length of road. Function : To make intercept for runoff coming from top of hill and divert water in to near by cross drains. E) Brest wall : The wall constructed to up side slope is called Brest wall. Function: Protect road from sliding of up side slope. F) Retaining Wall: The wall constructed to down side slope of road is called retaining wall. Function: -To Protect down side slope from sliding. -To Resist pressure of earth fill . 6 Continue.
  • 7. G) Cross Drains: The drains which is laid along width of road is called cross drains. Function: To drain off rain water collected in side drains and catch drains. 7 Continue.
  • 8. 1.Length of Road: Alignment of road should be short as possible bcoz cost will be increased as length of road increases. 2.Geometrical Standards: -Alignment of road should have proper geometrical standards such as Gradient,Curves,SD,Radious of curves. - Min. Radius of curve for hill road is allowed to 50m. 3.Existing Saddle or Pass: Alignment of road should not pass through ridge line of hill to avoid extra cutting and filling. Alignment should passes through series of hills through existing saddle points. 8 Factors controlling Alignment of Hill Road .
  • 9. 4.Drainage Line: Alignment of road should be parallel to drainage line to avoid no of cross drainage drains. 5. Stability: Alignment of road should passes along the stable and side having mild slope of hill road. 6.Altitude: -Altitude of road should not be passes through high altitude as well as low altitude . -High Altitude causes problem of snow falling and low altitude will increase no. of cross drains. -Alignment of road passes through altitude between 900 to 1500m. -Alignment of road should faces sun and not located in windward side of hill 9 Factors controlling Alignment of Hill Road .
  • 10. 7.Cutting through Rocks: Alignment of road should not passes through solid rocks to avoid cost of cutting. 10 Factors controlling Alignment of Hill Road .
  • 11. Alignment of Hill roads is fixed in three stages: 1. Reconnaissance 2. Trace out 3. Detailed Survey. 1.1.Reconnaissance:Reconnaissance: -The temporary alignment of road is fixed during reconnaissance survey by studying topographical, geographical and metrological maps of the area . -Arial survey is carried out for remote area. 2.Trace out :.Trace out : -The route selected during reconnaissance survey is translated on ground so as to collect details from actual site. 11 Alignment Survey Of Hill Road:-
  • 12. - 1 to 1.5 m wide track is constructed so as to collect details. 3.Detailed Survey:3.Detailed Survey: --During Detailed survey BM are fixed on ground. -Prepare c/s Along length and along width. -Mark the center line and boundary line of highway. -Hydrological and soil investigation is carried out. 12 Cont.
  • 13. 1.Rock Cutting 2. Vertical Cutting (Precipice work) 3.Retaining wall 4. Foundation of Retaining wall 5.Revetment wall 6.Pavement Construction 13 Construction procedure of Hill Road
  • 14. There are main three types of cures used in hill road curvesThere are main three types of cures used in hill road curves 1.1.Hair Pin CurveHair Pin Curve 2.2.Salient curvesSalient curves 3.3.Re-entrant curvesRe-entrant curves Hair Pin Curve:Hair Pin Curve: The curve on hill road which changes its direction through 180 deg.The curve on hill road which changes its direction through 180 deg. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 14 Types of Hill Road CurvesTypes of Hill Road Curves
  • 15.  Salient curves:Salient curves: Curve having their convexity on the outer edge of hill road .Curve having their convexity on the outer edge of hill road . Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 15
  • 16. Re-entrant curves:Re-entrant curves: Curve having convexity on the inner edge of hill road.Curve having convexity on the inner edge of hill road. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 16
  • 17. ∗ Formation of hill road done in following situation 1.Wholly in cutting 2.Partially in cutting and partially in embankment. 3.Wholly in embankment. Wholly in cutting:Wholly in cutting: Formation width of pavement of hill road is constructed fully inFormation width of pavement of hill road is constructed fully in cutting .cutting . Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 17 Formation of Hill RoadFormation of Hill Road
  • 18.  Partially in cutting and partially in embankment.Partially in cutting and partially in embankment. Formation width of hill road is constructed partly in cutting andFormation width of hill road is constructed partly in cutting and partly in embankment .partly in embankment . Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 18
  • 19. Wholly in embankment:Wholly in embankment: Formation width of hill road constructed fully inFormation width of hill road constructed fully in filling(embankment)filling(embankment) Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 19
  • 20. Definition: The Downward movement of soil mass or rock along the slope due to gravity isThe Downward movement of soil mass or rock along the slope due to gravity is called landslide.called landslide. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 20 LandslideLandslide
  • 21.  Free Fall Landslide  Toppled Landslide  Slide Landslide  Flow Landslide  Complex Landslides 1.Free Fall Landslide:1.Free Fall Landslide: When there is free fall or rolling of rocks and soil mass alongWhen there is free fall or rolling of rocks and soil mass along the slope then it is called free fall landslide.the slope then it is called free fall landslide. Types of LandslideTypes of Landslide Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 21
  • 22. 2.Toppled Landslide:2.Toppled Landslide: Topples are nothing but overturning or forward rotation of rockTopples are nothing but overturning or forward rotation of rock bed along slope .bed along slope . Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 22
  • 23. 3.Slide Landslide:3.Slide Landslide: The downward movement of soil mass or rock along failureThe downward movement of soil mass or rock along failure plane of downward slope.plane of downward slope. 1.Rotational landslide1.Rotational landslide Rotational landslide is theRotational landslide is the downward and outward movementdownward and outward movement of a mass on top of a concaveof a mass on top of a concave upward failure surfaceupward failure surface 2.Translational landslide2.Translational landslide Movement of soil in translationalMovement of soil in translational form along inclined failure plane dueform along inclined failure plane due to less shear stress between twoto less shear stress between two surfacesurface Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 23
  • 24. 4.Complex Landslide:4.Complex Landslide: When there is combined effect of two or more landslideWhen there is combined effect of two or more landslide then it is called as complex landslide.then it is called as complex landslide. - It is the combonination of two or more landslide- It is the combonination of two or more landslide mentioned above.mentioned above. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 24
  • 25. Natural Causes of Landslides Climate- Heavy Rainfall. Geology and topography Earthquakes Weathering of rock Erosion of soil and rock Volcanoes Forest fires Human causes of landslides Mining Blasting Increase in traffic load. Causes of LandslideCauses of Landslide Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 25
  • 26. Lead to economic declination or loss Damage of infrastructure Loss of life Affects beauty of landscapes Impacts on river ecosystems Effect of LandslideEffect of Landslide Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 26
  • 27.  Provide benching on side slope  By providing proper drainage system.  By constructing retaining wall and breast wall.  By Soil stabilization techniques.  By cement grouting or concrete lining.  By rock nailing.  By increasing vegetation on side slope.  By fixing geosynthetic net on sloping side. Prevention of LandslidePrevention of Landslide Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 27
  • 28. Retaining wall Constructed to prevent falling of soil mass or rock on road surface or low laying area. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 28
  • 29. Vegetation on steep slope It helps to protect soil erosion. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 29
  • 30. Rock nailing Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 30
  • 31. Short -Crete technique In this technique the cement mortar is applied on unstable slope with high pressure by using concrete Gun. Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 31
  • 32. Grouting In this method of prevention of landslide the pressure chemical grout is pressed in to cracks to make stable Copyright © 2013 The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 32