SlideShare a Scribd company logo
1 of 34
Download to read offline
Cost Engineering
Dr. Nabil I El Sawalhi
Assistant Professor
Construction Management
CE - L8 1
Estimating Methods
CE - L8 2
CE - L8 3
CE - L8 4
Algorithms
• Algorithms are generally applied in a
sequential series of steps to estimate various
elements of the total estimate. In detail unit
cost estimating, the steps are usually:
• 1) estimate the direct field cost,
• 2) the field indirect cost,
• 3) the office costs, and finally,
• 4) the profit and contingency.
CE - L8 5
Estimate General Form
• The algorithm in effect transforms project
technical and programmatic descriptive
information into cost terms.
• These estimating algorithms are often referred
to as cost estimating relationships (CERs).
• In a very simple, but common form, a CER may
appear as:
CE - L8 6
Cost resource = factor x parameter
where:
• Factor = $ (total, labor, or material, etc.), or
time (labor hours, equipment rental hours,
etc.) a unit cost factor in terms of resource
unit of measure
• Parameter = units of measure of the estimate
item
CE - L8 7
Estimating Methods
CE - L8 8
1. Opinion
• In the absence of data and shortage of time,
there may be no way to evaluate designs rather
than opinion.
• The key to opinion estimating is human ware.
• The individual is selected to a job because of his
experience, common sense, and knowledge.
• Opinion estimating is done collectively in
conferences.
CE - L8 9
2. Conference
• Non quantitative technique which provides single
value.
• It is done in a round table fashion.
• A mediator provides a question “ what is the labor
and material cost for this design.
• A hidden card gambit(strategy, maneuver) has each
of the committee expert reveal a personal value to
question.
• This could provide a consensus.
CE - L8 10
• If agreement is not reached, discussion and
presentation are permitted ( called estimate-
talk- estimate or E-T-E).
• The hidden card idea prevent any
brainstorming session which generally gives
optimistic estimate.
• A ranking scheme along the “good- better-
best” approach can be applied.
CE - L8 11
2. Conference
2. Conference
• The lack of analysis and a trial of verifiable
facts leading from the estimate to the
governing situation are major drawback to the
conference method.
• Although there is little faith in the method
accuracy, these factors seldom prevent its use.
CE - L8 12
3. Comparison (similarity or analogy)
• It use formal logic in estimating.
• If we faced with difficult design estimate
we designate it as design a and construct a
simpler design problem for which an
estimate can be found.
CE - L8 13
• The simpler problem is b.
• Ca (Da) <= Cb (Db)
• Where Ca,b = value of the estimate for design a
& b dollars.
• Da,b = design a or b
CE - L8 14
• If we have additional known design Dc which
have lower estimate than Ca, then the logic can
be expanded to
• Cc (Dc) <= Ca (Da) <= Cb (Db)
• Assume that design b and c generally satisfy the
technical requirements as nearly as possible.
• Comparison apply to any complexity of design.
• The comparison method is some time called
similarity or analogy
CE - L8 15
Example
• Three exterior wall systems for residence are
given as shown in the following figure . The
design that has the unknown cost is a, while b
and c have been explored for costs and
standards are available, which indicate that for
a 10-ft-long section Cb= $5.16/ft2 and Cc =
$4.93/ft2.
CE - L8 16
• The inspectable judgment for this method
initially requires that the unknown design be
squeezed between two designs that are above
and below the unknown cost. Does the reader
believe that design a satisfies this
requirement? . If this initial premise is
accepted, then the cost is between these two
numbers.
CE - L8 17
CE - L8 18
4. Unit method
• The unit method use historical & quantitative
evidence and leads to a cost driver easily
understood.
• Other names of unit method are:
• -average, order of magnitude;
• -Lump sum
• -Function
• -Parameter.
• -Module estimating
CE - L8 19
Unit
continued..
• It involves various refinements.
• Extensions of this method lead to the factor
estimating method.
• Examples:
• Cost of house per square foot,
• Cost of electrical transmission per mile,
• Construction cost per hospital bed,
• Chemical plant cost per barrel of oil capacity.
CE - L8 20
• The most common unit cost estimate for
building is the cost per square meter.
• A similar one is the cost per cubic meter.
• Another types of unit cost estimate is:
• Cost per unit or trade unit estimate (the
building is broken down into basic trades and
cost and percentage factors are given.
• Ca = ∑ci/ ∑ni
CE - L8 21
• Ca = average dollar cost per unit of design
• Ci = value of design in dollars
• Ni = design i unit.
• Example:
• Consider the cost of field installed gate valve
with carbon steel piping system. There are
three historical observations of total material
and labor cost.
CE - L8 22
Design
Weight ,Ib
Ci
$
2 20
3 30
4 60
∑ 9 110
CE - L8 23
The cost per pound is Ca = ∑ci/ ∑ni =
110/9=$12.22
Example. For a concrete roadway:
• Given:
• A unit cost model of the roadway with a
modifying parametric algorithm: One all-in,
line-item algorithm (concrete) of many in the
given model is:
• $ of concrete = $500 per cubic meter x (N)
cubic meters
CE - L8 24
• Where the corresponding parametric algorithm for
quantity parameter N is:
• (N) = (road width in meters) x (road length in
meters) x (road loading in kg/cm2) x (1 cm/kg)/(
100 cm/m)
• and the following road design parameters are
given:
• Road width = 10 m , Road length = 100 m
• Road loading = 12 kg/cm2
• $ of concrete=$500x [(1O)x(lOO)x(12)x(1)/(1OO)]
• = $60,000
• plus remaining algorithms of all other part items of
the model.
CE - L8 25
Area Estimate
• This is prepared depending on the basis of the
area of building, the rate being deducted from
the cost of similar building having similar
specification, heights and construction in the
locality.
• It is calculated by finding the area of the
building and multiplying by the unit area rate.
The area is calculated from the covered area
by taking external dimension of the building at
the floor level.
CE - L8 26
• The method builds a sorely needed bridge
between nuts-and-bolts unit cost estimating
and esoteric (unclear) parametric analysis.
• This method is most heavily used in trade
specific or general commercial building
construction and plant applications. The
models and parametric relationships are
prebuilt in some systems and left to the user
in others.
CE - L8 27
• Courtyard and other open areas should not be
included in the area.
• For multistory buildings there are two
methods to use:
A) All floors including basement floor and roof
have an equal cost
B) Basement and roof have different cost.
CE - L8 28
Example 1.
• A building of size 20x35m consist of :
• Basement, g floor,1st floor, 2nd floor and roof.
And the total cost of building is 630,000 $.
Calulate the cost of m2 assuming that:
• A) all floors including basement and roof have
the same cost
• B) cost of basement is 60% of cost of the rest
of floors and cost of roof is 40% of cost of rest
floors.
CE - L8 29
a) Assumption 1
• Basement and other floor area = 700x5=3500m2
• Cost per m2 = 630,000/3500= 180$
b) Assumption 2
• basement area = 700 x .6 = 420m2
• Roof area = 700x.4 = 280m2
• Other floors = 700x 3 = 2100
• Total area = 2800m
• Cost of floor =630000/2800 =225$
• Cost of basement = 225x0.6 = 135$
• Cost of roof = 225x0.4 =$90
CE - L8 30
Cube Rate Estimate for Building
• It is an approximate estimate and it is
prepared based on cubical contents of the
building.
• The cube rate being deducted from the cost of
similar building having similar specifications
and construction, in the locality.
• Cubic rate is more accurate than the area
because it considers the height of the
building.
CE - L8 31
Cubic Method
Example (2)
• A building of size 40x60m and consist of basement,
g floor, 1st floor , 2nd floor. The height of the
buildings are :
• 2.8m for basement. 3.0m for all other floors. The
total cost is $2,250,000. estimate the cost of cubic
meter using the following two assumptions:
• A) the cost of all floors are the same
• B) the cost of cubic meter of basement is %60 of
other floors
CE - L8 32
a) assumption 1
• Volume of basement = 40x60x2.8 =
6720m3
• Volume of any other floor = 40x60x3 =
7200m3
• Total volume of all floors = 6720x1+7200x3=
28,320 m3
• Cost of cubic meter = 2,250,000/28320= $
79,450
CE - L8 33
b) assumption 2
• Volume of basement = 40x60x2.8x0.60=
4032m3
• Volume of any other floor = 40x60x3= 7200m3
• Total volume of all floors = 4032x1+7200x3 =
25,632 m3
• Cost of cubic meter 2,250,000/22,632= $ 87,780
CE - L8 34

More Related Content

Similar to Civil Estimating Methods.pdf

COCOMO Modal In Software Engineering By NADEEM AHMED
COCOMO Modal In Software Engineering By NADEEM AHMED COCOMO Modal In Software Engineering By NADEEM AHMED
COCOMO Modal In Software Engineering By NADEEM AHMED NA000000
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Muhammad Umar
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...Deepak37004
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Padmasinh Patil
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
How to implement complex policies on existing network infrastructure
How to implement complex policies on existing network infrastructure How to implement complex policies on existing network infrastructure
How to implement complex policies on existing network infrastructure AJAY KHARAT
 
Energy simulation & analysis of two residential buildings
Energy simulation & analysis of two residential buildingsEnergy simulation & analysis of two residential buildings
Energy simulation & analysis of two residential buildingschirag aggarwal
 
SOC Chip Basics
SOC Chip BasicsSOC Chip Basics
SOC Chip BasicsA B Shinde
 
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...Shashidhar Reddy
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lccamichaeljmack
 
Cost estimation using cocomo model
Cost estimation using cocomo modelCost estimation using cocomo model
Cost estimation using cocomo modelNitesh Bichwani
 
Term Project Building Energy audit-methodology.pptx
Term Project  Building Energy audit-methodology.pptxTerm Project  Building Energy audit-methodology.pptx
Term Project Building Energy audit-methodology.pptxAnishShah206945
 
Mathematical modelling
Mathematical modellingMathematical modelling
Mathematical modellingfic-uk
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptxSulemanAhmad21
 

Similar to Civil Estimating Methods.pdf (20)

COCOMO Modal In Software Engineering By NADEEM AHMED
COCOMO Modal In Software Engineering By NADEEM AHMED COCOMO Modal In Software Engineering By NADEEM AHMED
COCOMO Modal In Software Engineering By NADEEM AHMED
 
ECBC Training_08-Compliance
ECBC Training_08-ComplianceECBC Training_08-Compliance
ECBC Training_08-Compliance
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
 
Section 3-2.pptx
Section 3-2.pptxSection 3-2.pptx
Section 3-2.pptx
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Unit 1b
Unit 1bUnit 1b
Unit 1b
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
How to implement complex policies on existing network infrastructure
How to implement complex policies on existing network infrastructure How to implement complex policies on existing network infrastructure
How to implement complex policies on existing network infrastructure
 
Energy simulation & analysis of two residential buildings
Energy simulation & analysis of two residential buildingsEnergy simulation & analysis of two residential buildings
Energy simulation & analysis of two residential buildings
 
SOC Chip Basics
SOC Chip BasicsSOC Chip Basics
SOC Chip Basics
 
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...
Built In Self Testing(BIST) Architecture for Motin Estimation and Computing A...
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lcca
 
Cost estimation using cocomo model
Cost estimation using cocomo modelCost estimation using cocomo model
Cost estimation using cocomo model
 
Term Project Building Energy audit-methodology.pptx
Term Project  Building Energy audit-methodology.pptxTerm Project  Building Energy audit-methodology.pptx
Term Project Building Energy audit-methodology.pptx
 
Mathematical modelling
Mathematical modellingMathematical modelling
Mathematical modelling
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptx
 

More from hasan752746

Business Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdfBusiness Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdfhasan752746
 
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfPROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfhasan752746
 
EPC -v- EPCM.pdf
EPC -v- EPCM.pdfEPC -v- EPCM.pdf
EPC -v- EPCM.pdfhasan752746
 
77-22545-313436-91480.pdf
77-22545-313436-91480.pdf77-22545-313436-91480.pdf
77-22545-313436-91480.pdfhasan752746
 
TOWER CRANES.pdf
TOWER CRANES.pdfTOWER CRANES.pdf
TOWER CRANES.pdfhasan752746
 

More from hasan752746 (6)

Risk.pdf
Risk.pdfRisk.pdf
Risk.pdf
 
Business Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdfBusiness Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdf
 
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfPROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
 
EPC -v- EPCM.pdf
EPC -v- EPCM.pdfEPC -v- EPCM.pdf
EPC -v- EPCM.pdf
 
77-22545-313436-91480.pdf
77-22545-313436-91480.pdf77-22545-313436-91480.pdf
77-22545-313436-91480.pdf
 
TOWER CRANES.pdf
TOWER CRANES.pdfTOWER CRANES.pdf
TOWER CRANES.pdf
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Civil Estimating Methods.pdf

  • 1. Cost Engineering Dr. Nabil I El Sawalhi Assistant Professor Construction Management CE - L8 1
  • 5. Algorithms • Algorithms are generally applied in a sequential series of steps to estimate various elements of the total estimate. In detail unit cost estimating, the steps are usually: • 1) estimate the direct field cost, • 2) the field indirect cost, • 3) the office costs, and finally, • 4) the profit and contingency. CE - L8 5
  • 6. Estimate General Form • The algorithm in effect transforms project technical and programmatic descriptive information into cost terms. • These estimating algorithms are often referred to as cost estimating relationships (CERs). • In a very simple, but common form, a CER may appear as: CE - L8 6
  • 7. Cost resource = factor x parameter where: • Factor = $ (total, labor, or material, etc.), or time (labor hours, equipment rental hours, etc.) a unit cost factor in terms of resource unit of measure • Parameter = units of measure of the estimate item CE - L8 7
  • 9. 1. Opinion • In the absence of data and shortage of time, there may be no way to evaluate designs rather than opinion. • The key to opinion estimating is human ware. • The individual is selected to a job because of his experience, common sense, and knowledge. • Opinion estimating is done collectively in conferences. CE - L8 9
  • 10. 2. Conference • Non quantitative technique which provides single value. • It is done in a round table fashion. • A mediator provides a question “ what is the labor and material cost for this design. • A hidden card gambit(strategy, maneuver) has each of the committee expert reveal a personal value to question. • This could provide a consensus. CE - L8 10
  • 11. • If agreement is not reached, discussion and presentation are permitted ( called estimate- talk- estimate or E-T-E). • The hidden card idea prevent any brainstorming session which generally gives optimistic estimate. • A ranking scheme along the “good- better- best” approach can be applied. CE - L8 11 2. Conference
  • 12. 2. Conference • The lack of analysis and a trial of verifiable facts leading from the estimate to the governing situation are major drawback to the conference method. • Although there is little faith in the method accuracy, these factors seldom prevent its use. CE - L8 12
  • 13. 3. Comparison (similarity or analogy) • It use formal logic in estimating. • If we faced with difficult design estimate we designate it as design a and construct a simpler design problem for which an estimate can be found. CE - L8 13
  • 14. • The simpler problem is b. • Ca (Da) <= Cb (Db) • Where Ca,b = value of the estimate for design a & b dollars. • Da,b = design a or b CE - L8 14
  • 15. • If we have additional known design Dc which have lower estimate than Ca, then the logic can be expanded to • Cc (Dc) <= Ca (Da) <= Cb (Db) • Assume that design b and c generally satisfy the technical requirements as nearly as possible. • Comparison apply to any complexity of design. • The comparison method is some time called similarity or analogy CE - L8 15
  • 16. Example • Three exterior wall systems for residence are given as shown in the following figure . The design that has the unknown cost is a, while b and c have been explored for costs and standards are available, which indicate that for a 10-ft-long section Cb= $5.16/ft2 and Cc = $4.93/ft2. CE - L8 16
  • 17. • The inspectable judgment for this method initially requires that the unknown design be squeezed between two designs that are above and below the unknown cost. Does the reader believe that design a satisfies this requirement? . If this initial premise is accepted, then the cost is between these two numbers. CE - L8 17
  • 18. CE - L8 18
  • 19. 4. Unit method • The unit method use historical & quantitative evidence and leads to a cost driver easily understood. • Other names of unit method are: • -average, order of magnitude; • -Lump sum • -Function • -Parameter. • -Module estimating CE - L8 19
  • 20. Unit continued.. • It involves various refinements. • Extensions of this method lead to the factor estimating method. • Examples: • Cost of house per square foot, • Cost of electrical transmission per mile, • Construction cost per hospital bed, • Chemical plant cost per barrel of oil capacity. CE - L8 20
  • 21. • The most common unit cost estimate for building is the cost per square meter. • A similar one is the cost per cubic meter. • Another types of unit cost estimate is: • Cost per unit or trade unit estimate (the building is broken down into basic trades and cost and percentage factors are given. • Ca = ∑ci/ ∑ni CE - L8 21
  • 22. • Ca = average dollar cost per unit of design • Ci = value of design in dollars • Ni = design i unit. • Example: • Consider the cost of field installed gate valve with carbon steel piping system. There are three historical observations of total material and labor cost. CE - L8 22
  • 23. Design Weight ,Ib Ci $ 2 20 3 30 4 60 ∑ 9 110 CE - L8 23 The cost per pound is Ca = ∑ci/ ∑ni = 110/9=$12.22
  • 24. Example. For a concrete roadway: • Given: • A unit cost model of the roadway with a modifying parametric algorithm: One all-in, line-item algorithm (concrete) of many in the given model is: • $ of concrete = $500 per cubic meter x (N) cubic meters CE - L8 24
  • 25. • Where the corresponding parametric algorithm for quantity parameter N is: • (N) = (road width in meters) x (road length in meters) x (road loading in kg/cm2) x (1 cm/kg)/( 100 cm/m) • and the following road design parameters are given: • Road width = 10 m , Road length = 100 m • Road loading = 12 kg/cm2 • $ of concrete=$500x [(1O)x(lOO)x(12)x(1)/(1OO)] • = $60,000 • plus remaining algorithms of all other part items of the model. CE - L8 25
  • 26. Area Estimate • This is prepared depending on the basis of the area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction in the locality. • It is calculated by finding the area of the building and multiplying by the unit area rate. The area is calculated from the covered area by taking external dimension of the building at the floor level. CE - L8 26
  • 27. • The method builds a sorely needed bridge between nuts-and-bolts unit cost estimating and esoteric (unclear) parametric analysis. • This method is most heavily used in trade specific or general commercial building construction and plant applications. The models and parametric relationships are prebuilt in some systems and left to the user in others. CE - L8 27
  • 28. • Courtyard and other open areas should not be included in the area. • For multistory buildings there are two methods to use: A) All floors including basement floor and roof have an equal cost B) Basement and roof have different cost. CE - L8 28
  • 29. Example 1. • A building of size 20x35m consist of : • Basement, g floor,1st floor, 2nd floor and roof. And the total cost of building is 630,000 $. Calulate the cost of m2 assuming that: • A) all floors including basement and roof have the same cost • B) cost of basement is 60% of cost of the rest of floors and cost of roof is 40% of cost of rest floors. CE - L8 29
  • 30. a) Assumption 1 • Basement and other floor area = 700x5=3500m2 • Cost per m2 = 630,000/3500= 180$ b) Assumption 2 • basement area = 700 x .6 = 420m2 • Roof area = 700x.4 = 280m2 • Other floors = 700x 3 = 2100 • Total area = 2800m • Cost of floor =630000/2800 =225$ • Cost of basement = 225x0.6 = 135$ • Cost of roof = 225x0.4 =$90 CE - L8 30
  • 31. Cube Rate Estimate for Building • It is an approximate estimate and it is prepared based on cubical contents of the building. • The cube rate being deducted from the cost of similar building having similar specifications and construction, in the locality. • Cubic rate is more accurate than the area because it considers the height of the building. CE - L8 31
  • 32. Cubic Method Example (2) • A building of size 40x60m and consist of basement, g floor, 1st floor , 2nd floor. The height of the buildings are : • 2.8m for basement. 3.0m for all other floors. The total cost is $2,250,000. estimate the cost of cubic meter using the following two assumptions: • A) the cost of all floors are the same • B) the cost of cubic meter of basement is %60 of other floors CE - L8 32
  • 33. a) assumption 1 • Volume of basement = 40x60x2.8 = 6720m3 • Volume of any other floor = 40x60x3 = 7200m3 • Total volume of all floors = 6720x1+7200x3= 28,320 m3 • Cost of cubic meter = 2,250,000/28320= $ 79,450 CE - L8 33
  • 34. b) assumption 2 • Volume of basement = 40x60x2.8x0.60= 4032m3 • Volume of any other floor = 40x60x3= 7200m3 • Total volume of all floors = 4032x1+7200x3 = 25,632 m3 • Cost of cubic meter 2,250,000/22,632= $ 87,780 CE - L8 34