SlideShare a Scribd company logo
1 of 25
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
Chapter 2
EARTHMOVING
MATERIALS AND
OPERATIONS
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
INTRODUCTION TO
EARTHMOVING
• The Earthmoving Process
– Earthmoving is the process of moving soil
or rock from one location to another and
processing it so that it meets construction
requirements of location, elevation,
density, moisture content, and so on.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
INTRODUCTION TO
EARTHMOVING
• Equipment Selection
– The choice of equipment to be used on a
construction project has a major influence
on the efficiency and profitability of the
construction operation.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
INTRODUCTION TO
EARTHMOVING
• Production of Earthmoving
Equipment
– The basic relationship for estimating the
production of all earthmoving equipment is
as follows:
• Production = Volume per cycle * Cycles per
hour
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
INTRODUCTION TO
EARTHMOVING
Table 2-1. Job efficiency factors for earthmoving operations (From
TM 5-331B, U.S. Department of the Army)
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
EARTHMOVING MATERIALS
• Soil and Rock
• General Soil Characteristics
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
• Soil is considered to consist of five
fundamental material types: gravel,
sand, silt, clay, and organic material.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
• Soil Classification Systems
– Two principal soil classification systems are used
for design and construction in the United States.
– These are the Unified System and the AASHTO
[American Association of State Highway and
Transportation Officials, formerly known as the
American Association of State Highway Officials
(AASHO)] System.
– In both systems, soil particles 3 in. or larger in
diameter are removed before performing
classification tests.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
Table 2-2. Unified system of soil classification—field identification
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
FIGURE 2-1. Typical gradation curves for coarse-grained soils. (U.S. Army Engineer School)
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
Table 2-3. AASHTO system of soil classification (Courtesy of BOMAG Americas)
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
• Field Identification of Soil (Unified
System)
– Dry Strength Test
– Shaking Test
• Construction Characteristics of Soils
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL IDENTIFICATION AND
CLASSIFICATION
Table 2-4. Construction characteristics of soils (Unified System)
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL VOLUME-CHANGE
CHARACTERISTICS
• Soil Conditions
– Bank: Material in its natural state before
disturbance. Often referred to as “in-place” or “in
situ.”A unit volume is identified as a bank cubic
yard (BCY) or a bank cubic meter (BCM).
– Loose: Material that has been excavated or
loaded. A unit volume is identified as a loose cubic
yard (LCY) or loose cubic meter (LCM).
– Compacted: Material after compaction. A unit
volume is identified as a compacted cubic yard
(CCY) or compacted cubic meter (CCM).
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL VOLUME-CHANGE
CHARACTERISTICS
• Swell
• Shrinkage
• Load and Shrinkage Factors
FIGURE 2-2. Typical soil volume change during earthmoving.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SOIL VOLUME-CHANGE
CHARACTERISTICS
Table 2-5. Typical soil weight and volume change characteristics*
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SPOIL BANKS
• When planning and estimating
earthwork, it is frequently necessary to
determine the size of the pile of
material that will be created by the
material removed from the excavation.
– If the pile of material is long in relation to
its width, it is referred to as a spoil bank.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SPOIL BANKS
Table 2-6. Typical values of angle of repose of excavated soil
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
SPOIL BANKS
• Triangular Spoil Bank
• Conical Spoil Pile
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
ESTIMATING EARTHWORK
VOLUME
• When planning or estimating an earthmoving project,
it is often necessary to estimate the volume of
material to be excavated or placed as fill.
• The procedures to be followed can be divided into
three principal categories:
– (1) pit excavations (small, relatively deep excavations such
as those required for basements and foundations)
– (2) trench excavation for utility lines
– (3) excavating or grading relatively large areas
• Procedures suggested for each of these three cases
are described in the following sections.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
ESTIMATING EARTHWORK
VOLUME
• Pit Excavations
• Trench
Excavations
• Large Areas
FIGURE 2-3. Figure for Example 2-6.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
ESTIMATING EARTHWORK
VOLUME
FIGURE 2-4. Figure for Example 2-8.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
CONSTRUCTION USE OF THE
MASS DIAGRAM
FIGURE 2-5. A mass diagram.
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
CONSTRUCTION USE OF THE
MASS DIAGRAM
• Characteristics of a Mass Diagram
• Using the Mass Diagram
Copyright ©2011, 2006 by Pearson Education, Inc.
publishing as Pearson [imprint]
Construction Methods and Management, 8th
ed.
S. W. Nunnally
CONSTRUCTION USE OF THE
MASS DIAGRAM
FIGURE 2-6. Construction use of a mass diagram.

More Related Content

What's hot

Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibrationAnjana R Menon
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Granular subbase and equipments used for its construction
Granular subbase and equipments used for its constructionGranular subbase and equipments used for its construction
Granular subbase and equipments used for its constructionshubham shama
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.pptTarique048
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc roaddeepak athwal
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Pile foundation
Pile foundationPile foundation
Pile foundationaranjalisp
 

What's hot (20)

Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Granular subbase and equipments used for its construction
Granular subbase and equipments used for its constructionGranular subbase and equipments used for its construction
Granular subbase and equipments used for its construction
 
2.foundation
2.foundation2.foundation
2.foundation
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
0137033451 pp3
0137033451 pp30137033451 pp3
0137033451 pp3
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Shallowfoundations
ShallowfoundationsShallowfoundations
Shallowfoundations
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
 

Viewers also liked

Viewers also liked (20)

0137033451 pp14
0137033451 pp140137033451 pp14
0137033451 pp14
 
0137033451 pp1
0137033451 pp10137033451 pp1
0137033451 pp1
 
0137033451 pp17
0137033451 pp170137033451 pp17
0137033451 pp17
 
0137033451 pp20
0137033451 pp200137033451 pp20
0137033451 pp20
 
0137033451 pp10
0137033451 pp100137033451 pp10
0137033451 pp10
 
0137033451 pp7
0137033451 pp70137033451 pp7
0137033451 pp7
 
0137033451 pp15
0137033451 pp150137033451 pp15
0137033451 pp15
 
0137033451 pp13
0137033451 pp130137033451 pp13
0137033451 pp13
 
0137033451 pp12
0137033451 pp120137033451 pp12
0137033451 pp12
 
0137033451 pp15
0137033451 pp150137033451 pp15
0137033451 pp15
 
0137033451 pp6
0137033451 pp60137033451 pp6
0137033451 pp6
 
0137033451 pp5
0137033451 pp50137033451 pp5
0137033451 pp5
 
0137033451 pp4
0137033451 pp40137033451 pp4
0137033451 pp4
 
Captive Services Brochure_FINAL_April 2016
Captive Services Brochure_FINAL_April 2016Captive Services Brochure_FINAL_April 2016
Captive Services Brochure_FINAL_April 2016
 
CARWEB2 salgsprosess BRUKERMANUAL, V-3, april 2015
CARWEB2 salgsprosess BRUKERMANUAL, V-3, april 2015CARWEB2 salgsprosess BRUKERMANUAL, V-3, april 2015
CARWEB2 salgsprosess BRUKERMANUAL, V-3, april 2015
 
Pennsylvanian 1-24-79
Pennsylvanian 1-24-79Pennsylvanian 1-24-79
Pennsylvanian 1-24-79
 
House of Nerds Intro-presentation
House of Nerds Intro-presentationHouse of Nerds Intro-presentation
House of Nerds Intro-presentation
 
Technology So Easy Your Lawyer Could Do It (OSCON 5/18)
Technology So Easy Your Lawyer Could Do It (OSCON 5/18)Technology So Easy Your Lawyer Could Do It (OSCON 5/18)
Technology So Easy Your Lawyer Could Do It (OSCON 5/18)
 
CompilersAndLibraries
CompilersAndLibrariesCompilersAndLibraries
CompilersAndLibraries
 
Cryo_app._note
Cryo_app._noteCryo_app._note
Cryo_app._note
 

Similar to 0137033451 pp2

Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored pilesSahl Buhary
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation reviewRajankumar416
 
L01 Ground Improvement - Introduction & Need for GI.pdf
L01 Ground Improvement - Introduction & Need for GI.pdfL01 Ground Improvement - Introduction & Need for GI.pdf
L01 Ground Improvement - Introduction & Need for GI.pdfSeanCassar1
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
Chapter-1 Introduction to Construction Equipments (1).pptx
Chapter-1 Introduction to Construction Equipments (1).pptxChapter-1 Introduction to Construction Equipments (1).pptx
Chapter-1 Introduction to Construction Equipments (1).pptxMubarekTeshome1
 
Unit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.pptUnit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.pptSylvesterRakgate1
 
Geological investigation.pptx
Geological investigation.pptxGeological investigation.pptx
Geological investigation.pptxUmesh Yadav
 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONIRJET Journal
 
F0373040048
F0373040048F0373040048
F0373040048theijes
 
IRJET- Seismic Behavior of Tall Building using Piled Raft Foundation
IRJET-  	  Seismic Behavior of Tall Building using Piled Raft FoundationIRJET-  	  Seismic Behavior of Tall Building using Piled Raft Foundation
IRJET- Seismic Behavior of Tall Building using Piled Raft FoundationIRJET Journal
 
Geotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdfGeotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdfXise1
 
Navarro a#1 introduction to foundation engineering_2014-2015
Navarro a#1 introduction to foundation engineering_2014-2015Navarro a#1 introduction to foundation engineering_2014-2015
Navarro a#1 introduction to foundation engineering_2014-2015Brylle Navarro
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface InvestigationAkram Suleiman
 

Similar to 0137033451 pp2 (20)

Chapter-1.ppt
Chapter-1.pptChapter-1.ppt
Chapter-1.ppt
 
Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored piles
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation review
 
L01 Ground Improvement - Introduction & Need for GI.pdf
L01 Ground Improvement - Introduction & Need for GI.pdfL01 Ground Improvement - Introduction & Need for GI.pdf
L01 Ground Improvement - Introduction & Need for GI.pdf
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Chapter-1 Introduction to Construction Equipments (1).pptx
Chapter-1 Introduction to Construction Equipments (1).pptxChapter-1 Introduction to Construction Equipments (1).pptx
Chapter-1 Introduction to Construction Equipments (1).pptx
 
site investigation
 site investigation site investigation
site investigation
 
Unit1 hbn
Unit1 hbnUnit1 hbn
Unit1 hbn
 
Unit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.pptUnit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.ppt
 
Geological investigation.pptx
Geological investigation.pptxGeological investigation.pptx
Geological investigation.pptx
 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
 
245 147849546912-16
245 147849546912-16245 147849546912-16
245 147849546912-16
 
Foundation
FoundationFoundation
Foundation
 
LECT 4 UPDATE.pdf
LECT 4 UPDATE.pdfLECT 4 UPDATE.pdf
LECT 4 UPDATE.pdf
 
F0373040048
F0373040048F0373040048
F0373040048
 
IRJET- Seismic Behavior of Tall Building using Piled Raft Foundation
IRJET-  	  Seismic Behavior of Tall Building using Piled Raft FoundationIRJET-  	  Seismic Behavior of Tall Building using Piled Raft Foundation
IRJET- Seismic Behavior of Tall Building using Piled Raft Foundation
 
Geotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdfGeotechnical-Engineering (1).pdf
Geotechnical-Engineering (1).pdf
 
Types of Foundation and Site Investigation.pdf
Types of Foundation and Site Investigation.pdfTypes of Foundation and Site Investigation.pdf
Types of Foundation and Site Investigation.pdf
 
Navarro a#1 introduction to foundation engineering_2014-2015
Navarro a#1 introduction to foundation engineering_2014-2015Navarro a#1 introduction to foundation engineering_2014-2015
Navarro a#1 introduction to foundation engineering_2014-2015
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface Investigation
 

0137033451 pp2

  • 1. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally Chapter 2 EARTHMOVING MATERIALS AND OPERATIONS
  • 2. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally INTRODUCTION TO EARTHMOVING • The Earthmoving Process – Earthmoving is the process of moving soil or rock from one location to another and processing it so that it meets construction requirements of location, elevation, density, moisture content, and so on.
  • 3. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally INTRODUCTION TO EARTHMOVING • Equipment Selection – The choice of equipment to be used on a construction project has a major influence on the efficiency and profitability of the construction operation.
  • 4. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally INTRODUCTION TO EARTHMOVING • Production of Earthmoving Equipment – The basic relationship for estimating the production of all earthmoving equipment is as follows: • Production = Volume per cycle * Cycles per hour
  • 5. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally INTRODUCTION TO EARTHMOVING Table 2-1. Job efficiency factors for earthmoving operations (From TM 5-331B, U.S. Department of the Army)
  • 6. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally EARTHMOVING MATERIALS • Soil and Rock • General Soil Characteristics
  • 7. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION • Soil is considered to consist of five fundamental material types: gravel, sand, silt, clay, and organic material.
  • 8. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION • Soil Classification Systems – Two principal soil classification systems are used for design and construction in the United States. – These are the Unified System and the AASHTO [American Association of State Highway and Transportation Officials, formerly known as the American Association of State Highway Officials (AASHO)] System. – In both systems, soil particles 3 in. or larger in diameter are removed before performing classification tests.
  • 9. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION Table 2-2. Unified system of soil classification—field identification
  • 10. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION FIGURE 2-1. Typical gradation curves for coarse-grained soils. (U.S. Army Engineer School)
  • 11. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION Table 2-3. AASHTO system of soil classification (Courtesy of BOMAG Americas)
  • 12. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION • Field Identification of Soil (Unified System) – Dry Strength Test – Shaking Test • Construction Characteristics of Soils
  • 13. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL IDENTIFICATION AND CLASSIFICATION Table 2-4. Construction characteristics of soils (Unified System)
  • 14. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL VOLUME-CHANGE CHARACTERISTICS • Soil Conditions – Bank: Material in its natural state before disturbance. Often referred to as “in-place” or “in situ.”A unit volume is identified as a bank cubic yard (BCY) or a bank cubic meter (BCM). – Loose: Material that has been excavated or loaded. A unit volume is identified as a loose cubic yard (LCY) or loose cubic meter (LCM). – Compacted: Material after compaction. A unit volume is identified as a compacted cubic yard (CCY) or compacted cubic meter (CCM).
  • 15. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL VOLUME-CHANGE CHARACTERISTICS • Swell • Shrinkage • Load and Shrinkage Factors FIGURE 2-2. Typical soil volume change during earthmoving.
  • 16. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SOIL VOLUME-CHANGE CHARACTERISTICS Table 2-5. Typical soil weight and volume change characteristics*
  • 17. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SPOIL BANKS • When planning and estimating earthwork, it is frequently necessary to determine the size of the pile of material that will be created by the material removed from the excavation. – If the pile of material is long in relation to its width, it is referred to as a spoil bank.
  • 18. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SPOIL BANKS Table 2-6. Typical values of angle of repose of excavated soil
  • 19. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally SPOIL BANKS • Triangular Spoil Bank • Conical Spoil Pile
  • 20. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally ESTIMATING EARTHWORK VOLUME • When planning or estimating an earthmoving project, it is often necessary to estimate the volume of material to be excavated or placed as fill. • The procedures to be followed can be divided into three principal categories: – (1) pit excavations (small, relatively deep excavations such as those required for basements and foundations) – (2) trench excavation for utility lines – (3) excavating or grading relatively large areas • Procedures suggested for each of these three cases are described in the following sections.
  • 21. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally ESTIMATING EARTHWORK VOLUME • Pit Excavations • Trench Excavations • Large Areas FIGURE 2-3. Figure for Example 2-6.
  • 22. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally ESTIMATING EARTHWORK VOLUME FIGURE 2-4. Figure for Example 2-8.
  • 23. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally CONSTRUCTION USE OF THE MASS DIAGRAM FIGURE 2-5. A mass diagram.
  • 24. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally CONSTRUCTION USE OF THE MASS DIAGRAM • Characteristics of a Mass Diagram • Using the Mass Diagram
  • 25. Copyright ©2011, 2006 by Pearson Education, Inc. publishing as Pearson [imprint] Construction Methods and Management, 8th ed. S. W. Nunnally CONSTRUCTION USE OF THE MASS DIAGRAM FIGURE 2-6. Construction use of a mass diagram.