Concrete Work
data Price
Materuial cost
Lean concrete G15 (already mixed) RM185.00/m3
G25 Concrete (already mixed ) RM195.00/m3
G30 Concrete (already mixed ) RM210.00/m3
Shrinkage, concsolidation and wasteage 50%
Labour cost
Two unskilled worker (8Hours per day) RM52.50/person
Placing of concrete 0.6h/m3
Cost of vibrator for reinfoced concrete, 1.2m3/h, incluidng fuel RM360.00/day
Additional labour for working around reinforcement at 0.55hour/m³ RM52.50/day
Allow 15% profit including overhead
Calculation for lean concrete G15
material cost
Add shrinkage, concsolidation and wasteage 50%
RM185.00 x 1.5 = RM277.50/m3
Labour cost
Two unskilled worker per hour RM52.50/8x2 = RM13.13/h
placing concrete RM13.13 x 0.6 = RM7.88/m3
Total Cost for lean concrete G15
RM277.50+RM7.88=RM285.38
Allow 15% profit including overhead RM285.38 x 1.15= RM328.19/m3
RM328.19/m3 x 0.05(thk) = RM16.41/m2
Calculation for reinforced concrete G25
material cost
Add shrinkage, concsolidation and wasteage 50%
RM195.00 x 1.5 = RM292.50/m3
Plant cost
Vibrator per day RM360.00/8 = RM45.00/h
per m3 RM45.00 / 1.2 = RM37.5/m3
Labour cost
Two unskilled worker per hour RM52.50/8x2 = RM13.13/h
placing concrete RM13.13 x 0.6 = RM7.88/m3
Reinforcement work labour cost per m3 RM52.50/8=RM6.56/h
RM6.56 x 0.55 = RM3.61/m3
Total cost for reinforced concrete G25
RM292.50 + RM37.5 + RM7.88 + RM3.61 = RM341.49/m3
Allow 15% profit including overhead RM341.49 x 1.15= RM392.71/m3
Calculation for reinforced concrete G30
material cost
Add shrinkage, concsolidation and wasteage 50%
RM210.00 x 1.5 = RM315.00/m3
Plant cost
Vibrator per day RM360.00/8 = RM45.00/h
per m3 RM45.00 / 1.2 = RM37.5/m3
Labour cost
Two unskilled worker per hour RM52.50/8x2 = RM13.13/h
placing concrete RM13.13 x 0.6 = RM7.88/m3
Reinforcement work labour cost per m3 RM52.50/8=RM6.56/hRM6.56 x 0.55 = RM3.61/m3
Total cost for reinforced concrete G30
RM315.00 + RM37.5 + RM7.88 + RM3.61 = RM363.99/m3
Allow 15% profit including overhead RM363.99 x 1.15= RM418.59/m3
Hardcore
Data Price
material cost
hardcore material RM7.5/m2
Allow 10% compaction
Labour cost
One unskilled worker, 8hours per day
Allow 15% profir including overhead RM52.50/person
Placing hardcore at 8m2/h
Calculation for hardcore
Material cost
Allow 10% compaction RM7.50 x 1.10 = RM8.25/m2
Labour cost
One unskilled worker per hour RM52.50/8 = RM6.56/h
Placing hardcore RM6.56/1.2 = RM5.47/m2
Total cost for hardcore
RM8.25 + RM5.47 = RM13.72/m2
Allow 15% profit including overhead RM13.72 x 1.15= RM15.78/m2
10mm dia high tensile Reinforcement Bar Cost
Data Price
material cost
10mm diameter bar delivered to site RM2700/tonne
Allow labour stacking and loading RM7/tonne
Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne
Allow spacers for rebar RM6/tonne
Allow 7% waste
Allow margin RM22/tonne
Allow 15% profit including overhead
Labour cost
One skilled labour, 8hours/day RM125/person
one unskilled worker, 8hours/day RM52.50/person
Allow 10% idling time
Select 28 minutes
Cut 32 minutes
Bend 35 minutes
Fix 23 minutes
Hoist Twice 7 minutes
calculation for 10mm h.t bar
material cost
10mm diameter h.t bar RM2700/tonne
Allow labour stacking and loading RM7/tonne
Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne
Spacer RM6/tonne
Allow 7% waste RM2700 x 0.07 = RM189/tonne
Margin RM22/tonne
Total RM2927.3/tonne
Labour cost
Skilled worker per hour Rm125/8 = RM15.63/h
One unskilled worker per hour RM52.50/8 = RM6.56/h
total RM15.63 + RM6.56 = RM22.19/h
Allow 10% idling time RM22.19 x 1.10 = RM24.41/h
Time required for
Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes
Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne
Total cost for 10mm h.t bar
RM2927.3 + RM508.54 = RM3435.84/tonne
Allow 15% profit including overhead RM3435.84 x 1.15= RM3951.22/tonne
12mm dia high tensile Reinforcement Bar Cost
Data Price
material cost
12mm diameter bar delivered to site RM2700/tonne
Allow labour stacking and loading RM7/tonne
Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne
Allow spacers for rebar RM6/tonne
Allow 7% waste
Allow margin RM22/tonne
Allow 15% profit including overhead
Labour cost
One skilled labour, 8hours/day RM125/person
one unskilled worker, 8hours/day RM52.50/person
Allow 10% idling time
Select 28 minutes
Cut 32 minutes
Bend 35 minutes
Fix 23 minutes
Hoist Twice 7 minutes
calculation for 12mm h.t bar
material cost
12mm diameter h.t bar RM2700/tonne
Allow labour stacking and loading RM7/tonne
Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne
Spacer RM6/tonne
Allow 7% waste RM2700 x 0.07 = RM189/tonne
Margin RM22/tonne
Total RM2927.3/tonne
Labour cost
Skilled worker per hour Rm125/8 = RM15.63/h
One unskilled worker per hour RM52.50/8 = RM6.56/h
total RM15.63 + RM6.56 = RM22.19/h
Allow 10% idling time RM22.19 x 1.10 = RM24.41/h
Time required for
Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes
Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne
Total cost for 12mm h.t bar
RM2927.3 + RM508.54 = RM3435.84/tonne
Allow 15% profit including overhead RM3435.84 x 1.15= RM3951.22/tonne
16mm dia high tensile Reinforcement Bar Cost
Data Price
material cost
16mm diameter bar delivered to site RM2650/tonne
Allow labour stacking and loading RM7/tonne
Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne
Allow spacers for rebar RM6/tonne
Allow 7% waste
Allow margin RM22/tonne
Allow 15% profit including overhead
Labour cost
One skilled labour, 8hours/day RM125/person
one unskilled worker, 8hours/day RM52.50/person
Allow 10% idling time
Select 28 minutes
Cut 32 minutes
Bend 35 minutes
Fix 23 minutes
Hoist Twice 7 minutes
calculation for 16mm h.t bar
material cost
16mm diameter h.t bar RM2650/tonne
Allow labour stacking and loading RM7/tonne
Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne
Spacer RM6/tonne
Allow 7% waste RM2650 x 0.07 = RM185.5/tonne
Margin RM22/tonne
Total RM2873.8/tonne
Labour cost
Skilled worker per hour Rm125/8 = RM15.63/h
One unskilled worker per hour RM52.50/8 = RM6.56/h
total RM15.63 + RM6.56 = RM22.19/h
Allow 10% idling time RM22.19 x 1.10 = RM24.41/h
Time required for
Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes
Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne
Total cost for 16mm h.t bar
RM2873.8 + RM508.54 = RM3382.34/tonne
Allow 15% profit including overhead RM3382.34 x 1.15= RM3889.69/tonne
8mm dia mild steel Reinforcement Bar Cost
Data Price
material cost
8mm diameter bar delivered to site RM 1250/ 800kg
Allow labour stacking and loading RM7/tonne
Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne
Allow spacers for rebar RM6/tonne
Allow 7% waste
Allow margin RM22/tonne
Allow 15% profit including overhead
Labour cost
One skilled labour, 8hours/day RM125/person
one unskilled worker, 8hours/day RM52.50/person
Allow 10% idling time
Select 28 minutes
Cut 32 minutes
Bend 35 minutes
Fix 23 minutes
Hoist Twice 7 minutes
calculation for 8mm m.s bar
material cost
8mm diameter h.t bar 1250/800 x 1000 RM1562.5/tonne
Allow labour stacking and loading RM7/tonne
Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne
Spacer RM6/tonne
Allow 7% waste RM1562.5 x 0.07 = RM109.38/tonne
Margin RM22/tonne
Total RM1710.18/tonne
Labour cost
Skilled worker per hour Rm125/8 = RM15.63/h
One unskilled worker per hour RM52.50/8 = RM6.56/h
total RM15.63 + RM6.56 = RM22.19/h
Allow 10% idling time RM22.19 x 1.10 = RM24.41/h
Time required for
Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes
Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne
Total cost for 8mm m.s bar
RM1710.18 + RM508.54 = RM2218.72/tonne
Allow 15% profit including overhead RM2218.72 x 1.15= RM2551.53/tonne
10mm dia mild steel Reinforcement Bar Cost
Data Price
material cost RM1802 /tonne
10mm diameter bar delivered to site RM/tonne
Allow labour stacking and loading RM7/tonne
Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne
Allow spacers for rebar RM6/tonne
Allow 7% waste
Allow margin RM22/tonne
Allow 15% profit including overhead
Labour cost
One skilled labour, 8hours/day RM125/person
one unskilled worker, 8hours/day RM52.50/person
Allow 10% idling time
Select 28 minutes
Cut 32 minutes
Bend 35 minutes
Fix 23 minutes
Hoist Twice 7 minutes
calculation for 10mm m.s bar
material cost
10mm diameter h.t bar RM1802/tonne
Allow labour stacking and loading RM7/tonne
Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne
Spacer RM6/tonne
Allow 7% waste RM1802 x 0.07 = RM126.14/tonne
Margin RM22/tonne
Total RM1966.44/tonne
Labour cost
Skilled worker per hour Rm125/8 = RM15.63/h
One unskilled worker per hour RM52.50/8 = RM6.56/h
total RM15.63 + RM6.56 = RM22.19/h
Allow 10% idling time RM22.19 x 1.10 = RM24.41/h
Time required for
Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes
Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne
Total cost for 10mm m.s bar
RM1966.44 + RM508.54 = RM2474.98/tonne
Allow 15% profit including overhead RM2474.98 x 1.15= RM2846.23/tonne
A6:2.61kg/m2 layer of Steel Fabric Reinforcement Cost
Data Price
A6:2.61kg/m2 RM10.00/m2
Allow 5% wastage
Lablour cost
2 unskilled labour, 8hoours/day RM52.50/person
allow 10% idling time
Allow 15% profit including overhead
Calculation for BRC A6:2.61kg/m2
material cost
Allow 5% wastage RM10 x 1.05 = RM10.5
Labour cost
Two unskilled worker per hour RM52.50/8x2 = RM13.13/h
allow 10% idling time RM13.13 x 1.10 = RM14.14/h
total cost
RM10.5 + RM14.14 = RM24.64/m2
Allow 15% profit including overhead RM24.63 x 1.15% = RM28.34/m2
A8:3.01kg/m2 layer of Steel Fabric Reinforcement Cost
Data Price
A8:3.01kg/m2 RM12.10/m2
Allow 5% wastage
Lablour cost
2 unskilled labour, 8hoours/day RM52.50/person
allow 10% idling time
Allow 15% profit including overhead
Calculation for BRC A8:3.01kg/m2
material cost
Allow 5% wastage RM12.10 x 1.05% = RM12.71/m2
Labour cost
Two unskilled worker per hour RM52.50/8x2 = RM13.13/h
allow 10% idling time RM13.13 x 1.10 = RM14.14/h
total cost
RM12.71 + RM14.14 = RM26.85
Allow 15% profit including overhead RM26.85 x 1.15% = RM30.88/m2

More Related Content

What's hot

Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compileTimun Loh
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof coveringEst
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)Yee Len Wan
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary ReportNatalie Reid
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Anne Allan
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysisfareezsham
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list Jeanne Hoo
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report마 이환
 

What's hot (20)

Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Bq floor
Bq floorBq floor
Bq floor
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof covering
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)
 
ECA form
ECA formECA form
ECA form
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report
 

Viewers also liked

Η εργασία του Κωστή
Η εργασία του ΚωστήΗ εργασία του Κωστή
Η εργασία του ΚωστήMartaki Fani
 
Adv & Adj Comp
Adv & Adj CompAdv & Adj Comp
Adv & Adj CompAlkin
 
Hamid sain's course record of philosophy and the sciences: introduction to th...
Hamid sain's course record of philosophy and the sciences: introduction to th...Hamid sain's course record of philosophy and the sciences: introduction to th...
Hamid sain's course record of philosophy and the sciences: introduction to th...Dr Hamid Sain MBBS(Ad.)FRCSEd
 
αφισα-θεατρικές δημιουργίες
αφισα-θεατρικές δημιουργίεςαφισα-θεατρικές δημιουργίες
αφισα-θεατρικές δημιουργίεςvasilikiarvan
 
Η εργασία του Αλέξανδρου
Η εργασία του ΑλέξανδρουΗ εργασία του Αλέξανδρου
Η εργασία του ΑλέξανδρουMartaki Fani
 
Teollisuustuotanto elpyy – kansantalous uuteen nousuun
Teollisuustuotanto elpyy – kansantalous uuteen nousuunTeollisuustuotanto elpyy – kansantalous uuteen nousuun
Teollisuustuotanto elpyy – kansantalous uuteen nousuunPalkansaajien tutkimuslaitos
 
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...Pierre-Majorique Léger
 
Οι Βαλκανικοί πόλεμοι με το λογισμικό Centennia
Οι Βαλκανικοί πόλεμοι με το λογισμικό CentenniaΟι Βαλκανικοί πόλεμοι με το λογισμικό Centennia
Οι Βαλκανικοί πόλεμοι με το λογισμικό CentenniaEvi Kousidou
 
Introduction to Graph Theory
Introduction to Graph TheoryIntroduction to Graph Theory
Introduction to Graph Theory Kazi Md. Saidul
 
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)Πηνελόπη Ρασιδάκη
 
software assignment
software assignmentsoftware assignment
software assignmentseenyeeyong
 
CoolTool NeuroLab Eye Tracking testing
CoolTool NeuroLab Eye Tracking testingCoolTool NeuroLab Eye Tracking testing
CoolTool NeuroLab Eye Tracking testingKateryna Khozroshyna
 

Viewers also liked (20)

Η εργασία του Κωστή
Η εργασία του ΚωστήΗ εργασία του Κωστή
Η εργασία του Κωστή
 
пуртова
пуртовапуртова
пуртова
 
Adv & Adj Comp
Adv & Adj CompAdv & Adj Comp
Adv & Adj Comp
 
Hamid sain's course record of philosophy and the sciences: introduction to th...
Hamid sain's course record of philosophy and the sciences: introduction to th...Hamid sain's course record of philosophy and the sciences: introduction to th...
Hamid sain's course record of philosophy and the sciences: introduction to th...
 
αφισα-θεατρικές δημιουργίες
αφισα-θεατρικές δημιουργίεςαφισα-θεατρικές δημιουργίες
αφισα-θεατρικές δημιουργίες
 
Btec Certificate
Btec CertificateBtec Certificate
Btec Certificate
 
Η εργασία του Αλέξανδρου
Η εργασία του ΑλέξανδρουΗ εργασία του Αλέξανδρου
Η εργασία του Αλέξανδρου
 
Teollisuustuotanto elpyy – kansantalous uuteen nousuun
Teollisuustuotanto elpyy – kansantalous uuteen nousuunTeollisuustuotanto elpyy – kansantalous uuteen nousuun
Teollisuustuotanto elpyy – kansantalous uuteen nousuun
 
WHISHWORKS - Company Profile
WHISHWORKS - Company ProfileWHISHWORKS - Company Profile
WHISHWORKS - Company Profile
 
Wordpress SEO and Security - AAC2016
Wordpress SEO and Security - AAC2016Wordpress SEO and Security - AAC2016
Wordpress SEO and Security - AAC2016
 
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...
YPO/WPO Conferrence @ HEC Montréal : Designing and Assessing Customer & Emplo...
 
Οι Βαλκανικοί πόλεμοι με το λογισμικό Centennia
Οι Βαλκανικοί πόλεμοι με το λογισμικό CentenniaΟι Βαλκανικοί πόλεμοι με το λογισμικό Centennia
Οι Βαλκανικοί πόλεμοι με το λογισμικό Centennia
 
Introduction to Graph Theory
Introduction to Graph TheoryIntroduction to Graph Theory
Introduction to Graph Theory
 
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)
β 1. η ακμη της ευρωπαϊκης αποικιοκρατιας (1871 1914)
 
software assignment
software assignmentsoftware assignment
software assignment
 
Els paisatges
Els paisatgesEls paisatges
Els paisatges
 
Paisatjes del mon
Paisatjes del monPaisatjes del mon
Paisatjes del mon
 
CoolTool NeuroLab Eye Tracking testing
CoolTool NeuroLab Eye Tracking testingCoolTool NeuroLab Eye Tracking testing
CoolTool NeuroLab Eye Tracking testing
 
Webdesign, UX et UCD #3
Webdesign, UX et UCD #3Webdesign, UX et UCD #3
Webdesign, UX et UCD #3
 
Content creation 101
Content creation 101Content creation 101
Content creation 101
 

Similar to Estimating

Spin plan for 80s combed yarn
Spin plan for 80s combed yarnSpin plan for 80s combed yarn
Spin plan for 80s combed yarnSwaraz Mollick
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answerDoreen Yeo
 
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Appendix 11   analysis of rates - balsio shp phase ii - 28032014Appendix 11   analysis of rates - balsio shp phase ii - 28032014
Appendix 11 analysis of rates - balsio shp phase ii - 28032014Nikhil Jaipurkar
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 

Similar to Estimating (10)

Excavation
ExcavationExcavation
Excavation
 
Spin plan for 80s combed yarn
Spin plan for 80s combed yarnSpin plan for 80s combed yarn
Spin plan for 80s combed yarn
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answer
 
MANAGEMENT ACCOUNTING
MANAGEMENT ACCOUNTING MANAGEMENT ACCOUNTING
MANAGEMENT ACCOUNTING
 
Sato
SatoSato
Sato
 
Sato
SatoSato
Sato
 
Sato
SatoSato
Sato
 
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Appendix 11   analysis of rates - balsio shp phase ii - 28032014Appendix 11   analysis of rates - balsio shp phase ii - 28032014
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 

More from Enoch Wong

BE workshop presentation
BE workshop presentation BE workshop presentation
BE workshop presentation Enoch Wong
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Measurement 4
Measurement 4 Measurement 4
Measurement 4 Enoch Wong
 
Management Science
Management Science Management Science
Management Science Enoch Wong
 
Building services
Building services Building services
Building services Enoch Wong
 
Strategy management group assignment
Strategy management group assignment Strategy management group assignment
Strategy management group assignment Enoch Wong
 
Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Enoch Wong
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Enoch Wong
 

More from Enoch Wong (9)

BE workshop presentation
BE workshop presentation BE workshop presentation
BE workshop presentation
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
Measurement 4
Measurement 4 Measurement 4
Measurement 4
 
Management Science
Management Science Management Science
Management Science
 
Building services
Building services Building services
Building services
 
Strategy management group assignment
Strategy management group assignment Strategy management group assignment
Strategy management group assignment
 
Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Fieldwork 1 (leveling)
Fieldwork 1 (leveling)
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)
 
Site report
Site reportSite report
Site report
 

Recently uploaded

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Estimating

  • 1. Concrete Work data Price Materuial cost Lean concrete G15 (already mixed) RM185.00/m3 G25 Concrete (already mixed ) RM195.00/m3 G30 Concrete (already mixed ) RM210.00/m3 Shrinkage, concsolidation and wasteage 50% Labour cost Two unskilled worker (8Hours per day) RM52.50/person Placing of concrete 0.6h/m3 Cost of vibrator for reinfoced concrete, 1.2m3/h, incluidng fuel RM360.00/day Additional labour for working around reinforcement at 0.55hour/m³ RM52.50/day Allow 15% profit including overhead Calculation for lean concrete G15 material cost Add shrinkage, concsolidation and wasteage 50% RM185.00 x 1.5 = RM277.50/m3 Labour cost Two unskilled worker per hour RM52.50/8x2 = RM13.13/h placing concrete RM13.13 x 0.6 = RM7.88/m3 Total Cost for lean concrete G15 RM277.50+RM7.88=RM285.38 Allow 15% profit including overhead RM285.38 x 1.15= RM328.19/m3 RM328.19/m3 x 0.05(thk) = RM16.41/m2
  • 2. Calculation for reinforced concrete G25 material cost Add shrinkage, concsolidation and wasteage 50% RM195.00 x 1.5 = RM292.50/m3 Plant cost Vibrator per day RM360.00/8 = RM45.00/h per m3 RM45.00 / 1.2 = RM37.5/m3 Labour cost Two unskilled worker per hour RM52.50/8x2 = RM13.13/h placing concrete RM13.13 x 0.6 = RM7.88/m3 Reinforcement work labour cost per m3 RM52.50/8=RM6.56/h RM6.56 x 0.55 = RM3.61/m3 Total cost for reinforced concrete G25 RM292.50 + RM37.5 + RM7.88 + RM3.61 = RM341.49/m3 Allow 15% profit including overhead RM341.49 x 1.15= RM392.71/m3 Calculation for reinforced concrete G30 material cost Add shrinkage, concsolidation and wasteage 50% RM210.00 x 1.5 = RM315.00/m3 Plant cost Vibrator per day RM360.00/8 = RM45.00/h per m3 RM45.00 / 1.2 = RM37.5/m3 Labour cost Two unskilled worker per hour RM52.50/8x2 = RM13.13/h placing concrete RM13.13 x 0.6 = RM7.88/m3 Reinforcement work labour cost per m3 RM52.50/8=RM6.56/hRM6.56 x 0.55 = RM3.61/m3 Total cost for reinforced concrete G30 RM315.00 + RM37.5 + RM7.88 + RM3.61 = RM363.99/m3 Allow 15% profit including overhead RM363.99 x 1.15= RM418.59/m3
  • 3. Hardcore Data Price material cost hardcore material RM7.5/m2 Allow 10% compaction Labour cost One unskilled worker, 8hours per day Allow 15% profir including overhead RM52.50/person Placing hardcore at 8m2/h Calculation for hardcore Material cost Allow 10% compaction RM7.50 x 1.10 = RM8.25/m2 Labour cost One unskilled worker per hour RM52.50/8 = RM6.56/h Placing hardcore RM6.56/1.2 = RM5.47/m2 Total cost for hardcore RM8.25 + RM5.47 = RM13.72/m2 Allow 15% profit including overhead RM13.72 x 1.15= RM15.78/m2
  • 4. 10mm dia high tensile Reinforcement Bar Cost Data Price material cost 10mm diameter bar delivered to site RM2700/tonne Allow labour stacking and loading RM7/tonne Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne Allow spacers for rebar RM6/tonne Allow 7% waste Allow margin RM22/tonne Allow 15% profit including overhead Labour cost One skilled labour, 8hours/day RM125/person one unskilled worker, 8hours/day RM52.50/person Allow 10% idling time Select 28 minutes Cut 32 minutes Bend 35 minutes Fix 23 minutes Hoist Twice 7 minutes calculation for 10mm h.t bar material cost 10mm diameter h.t bar RM2700/tonne Allow labour stacking and loading RM7/tonne Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne Spacer RM6/tonne Allow 7% waste RM2700 x 0.07 = RM189/tonne Margin RM22/tonne Total RM2927.3/tonne Labour cost Skilled worker per hour Rm125/8 = RM15.63/h One unskilled worker per hour RM52.50/8 = RM6.56/h total RM15.63 + RM6.56 = RM22.19/h Allow 10% idling time RM22.19 x 1.10 = RM24.41/h Time required for Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne Total cost for 10mm h.t bar RM2927.3 + RM508.54 = RM3435.84/tonne Allow 15% profit including overhead RM3435.84 x 1.15= RM3951.22/tonne
  • 5. 12mm dia high tensile Reinforcement Bar Cost Data Price material cost 12mm diameter bar delivered to site RM2700/tonne Allow labour stacking and loading RM7/tonne Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne Allow spacers for rebar RM6/tonne Allow 7% waste Allow margin RM22/tonne Allow 15% profit including overhead Labour cost One skilled labour, 8hours/day RM125/person one unskilled worker, 8hours/day RM52.50/person Allow 10% idling time Select 28 minutes Cut 32 minutes Bend 35 minutes Fix 23 minutes Hoist Twice 7 minutes calculation for 12mm h.t bar material cost 12mm diameter h.t bar RM2700/tonne Allow labour stacking and loading RM7/tonne Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne Spacer RM6/tonne Allow 7% waste RM2700 x 0.07 = RM189/tonne Margin RM22/tonne Total RM2927.3/tonne Labour cost Skilled worker per hour Rm125/8 = RM15.63/h One unskilled worker per hour RM52.50/8 = RM6.56/h total RM15.63 + RM6.56 = RM22.19/h Allow 10% idling time RM22.19 x 1.10 = RM24.41/h Time required for Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne Total cost for 12mm h.t bar RM2927.3 + RM508.54 = RM3435.84/tonne Allow 15% profit including overhead RM3435.84 x 1.15= RM3951.22/tonne
  • 6. 16mm dia high tensile Reinforcement Bar Cost Data Price material cost 16mm diameter bar delivered to site RM2650/tonne Allow labour stacking and loading RM7/tonne Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne Allow spacers for rebar RM6/tonne Allow 7% waste Allow margin RM22/tonne Allow 15% profit including overhead Labour cost One skilled labour, 8hours/day RM125/person one unskilled worker, 8hours/day RM52.50/person Allow 10% idling time Select 28 minutes Cut 32 minutes Bend 35 minutes Fix 23 minutes Hoist Twice 7 minutes calculation for 16mm h.t bar material cost 16mm diameter h.t bar RM2650/tonne Allow labour stacking and loading RM7/tonne Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne Spacer RM6/tonne Allow 7% waste RM2650 x 0.07 = RM185.5/tonne Margin RM22/tonne Total RM2873.8/tonne Labour cost Skilled worker per hour Rm125/8 = RM15.63/h One unskilled worker per hour RM52.50/8 = RM6.56/h total RM15.63 + RM6.56 = RM22.19/h Allow 10% idling time RM22.19 x 1.10 = RM24.41/h Time required for Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne Total cost for 16mm h.t bar RM2873.8 + RM508.54 = RM3382.34/tonne Allow 15% profit including overhead RM3382.34 x 1.15= RM3889.69/tonne
  • 7. 8mm dia mild steel Reinforcement Bar Cost Data Price material cost 8mm diameter bar delivered to site RM 1250/ 800kg Allow labour stacking and loading RM7/tonne Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne Allow spacers for rebar RM6/tonne Allow 7% waste Allow margin RM22/tonne Allow 15% profit including overhead Labour cost One skilled labour, 8hours/day RM125/person one unskilled worker, 8hours/day RM52.50/person Allow 10% idling time Select 28 minutes Cut 32 minutes Bend 35 minutes Fix 23 minutes Hoist Twice 7 minutes calculation for 8mm m.s bar material cost 8mm diameter h.t bar 1250/800 x 1000 RM1562.5/tonne Allow labour stacking and loading RM7/tonne Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne Spacer RM6/tonne Allow 7% waste RM1562.5 x 0.07 = RM109.38/tonne Margin RM22/tonne Total RM1710.18/tonne Labour cost Skilled worker per hour Rm125/8 = RM15.63/h One unskilled worker per hour RM52.50/8 = RM6.56/h total RM15.63 + RM6.56 = RM22.19/h Allow 10% idling time RM22.19 x 1.10 = RM24.41/h Time required for Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne Total cost for 8mm m.s bar RM1710.18 + RM508.54 = RM2218.72/tonne Allow 15% profit including overhead RM2218.72 x 1.15= RM2551.53/tonne
  • 8. 10mm dia mild steel Reinforcement Bar Cost Data Price material cost RM1802 /tonne 10mm diameter bar delivered to site RM/tonne Allow labour stacking and loading RM7/tonne Tie wire at 0.66kg/100kg of reinforcement bar RM500/tonne Allow spacers for rebar RM6/tonne Allow 7% waste Allow margin RM22/tonne Allow 15% profit including overhead Labour cost One skilled labour, 8hours/day RM125/person one unskilled worker, 8hours/day RM52.50/person Allow 10% idling time Select 28 minutes Cut 32 minutes Bend 35 minutes Fix 23 minutes Hoist Twice 7 minutes calculation for 10mm m.s bar material cost 10mm diameter h.t bar RM1802/tonne Allow labour stacking and loading RM7/tonne Tie wire (0.66kg/100kg) x 1000 x (500/1000) = RM3.3/tonne Spacer RM6/tonne Allow 7% waste RM1802 x 0.07 = RM126.14/tonne Margin RM22/tonne Total RM1966.44/tonne Labour cost Skilled worker per hour Rm125/8 = RM15.63/h One unskilled worker per hour RM52.50/8 = RM6.56/h total RM15.63 + RM6.56 = RM22.19/h Allow 10% idling time RM22.19 x 1.10 = RM24.41/h Time required for Select, cut, bend, fix and hoist twice (28+32+35+23+7)minutes = 125minutes Labour cost (125minutes / 60) x RM24.41 = RM50.85/kg = RM508.54/tonne Total cost for 10mm m.s bar RM1966.44 + RM508.54 = RM2474.98/tonne Allow 15% profit including overhead RM2474.98 x 1.15= RM2846.23/tonne
  • 9. A6:2.61kg/m2 layer of Steel Fabric Reinforcement Cost Data Price A6:2.61kg/m2 RM10.00/m2 Allow 5% wastage Lablour cost 2 unskilled labour, 8hoours/day RM52.50/person allow 10% idling time Allow 15% profit including overhead Calculation for BRC A6:2.61kg/m2 material cost Allow 5% wastage RM10 x 1.05 = RM10.5 Labour cost Two unskilled worker per hour RM52.50/8x2 = RM13.13/h allow 10% idling time RM13.13 x 1.10 = RM14.14/h total cost RM10.5 + RM14.14 = RM24.64/m2 Allow 15% profit including overhead RM24.63 x 1.15% = RM28.34/m2 A8:3.01kg/m2 layer of Steel Fabric Reinforcement Cost Data Price A8:3.01kg/m2 RM12.10/m2 Allow 5% wastage Lablour cost 2 unskilled labour, 8hoours/day RM52.50/person allow 10% idling time Allow 15% profit including overhead Calculation for BRC A8:3.01kg/m2 material cost Allow 5% wastage RM12.10 x 1.05% = RM12.71/m2 Labour cost Two unskilled worker per hour RM52.50/8x2 = RM13.13/h allow 10% idling time RM13.13 x 1.10 = RM14.14/h total cost RM12.71 + RM14.14 = RM26.85 Allow 15% profit including overhead RM26.85 x 1.15% = RM30.88/m2